Professional Documents
Culture Documents
A Two-Stage Scheduler of Distributed Energy Resources
A Two-Stage Scheduler of Distributed Energy Resources
A Two-Stage Scheduler of Distributed Energy Resources
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY ROORKEE. Downloaded on May 23,2022 at 09:46:18 UTC from IEEE Xplore. Restrictions apply.
2
integration is provided by including the network constrains, as unit belonging to h can be then defined as P jh ª¬ Pj1 " PjR º¼ .
t
the Matlab optimization software and the network model - integral constrains for storage units
implemented in the EMTP-RV environment [9-11]; Section Erj Erj 1 't Pjr1 r 2,!, R j S 1,!, S L
III shows the results obtained for the case study referring to
the IEEE 34-bus distribution system [12] and Section IV ERj 1 ERj 't PjR (3)
concludes the paper. E1
j E. 0
j
II. FORMULATION OF THE OPTIMIZATION PROBLEMS RELEVANT - constraints due to power limits P min and P max , and energy
TO THE DAY-AHEAD SCHEDULER AND INTRA-DAY ONE limit Emax
The basic idea is that the DSO tends to optimize its Pjmin d Pjr d Pjmax r , j
(4)
resources on both economical and technical requirements; the Ej d Ej max
j S 1,! , S L
DSO has two opportunities to supply customers: to get energy
from HV grid at market prices or to produce by its own - balance of thermal load Ploadth
generation. N C
what follows, both day-ahead scheduler and intra-day one are between electrical power and thermal production for CHP
described in details. units. The thermal load balance constraint assumes particular
A. Day-ahead scheduler importance for the case of CHP units that usually follow the
thermal load requests.
The day-ahead dispatcher calculates the optimal set-points
for each DER in terms of required energy (power for the B. Intra-day scheduler
assigned time interval) production. It performs the set point The developed intra-day scheduler acts each 15-minutes
optimization by using the following available information: (a) time intervals. It collects: (i) information of the network state
electrical and thermal load forecasts, (b) forecasts of RERs in terms of DER set points and voltage profile and (ii) short
production, (c) energy costs, (d) upper and lower limits for term forecasts of both RES mean production and load
generating units and (e) initial status of available storage units. requests. Then it calculates the three-phase power flows and,
The procedure considers both thermal and electric DERs if some technical constraints are violated or if the voltages
and both dispatchable and not-dispatchable DERs. The values are too far from the rated value Vset, it starts an
optimization problem is defined as the sum of costs of each optimization procedure that modifies the active and reactive
generation units (both electric and thermal) for all the time outputs P and Q of the N selected DERs that participate to the
intervals. network voltage control.
The optimization problem can be defined as follows: The optimization objective is the minimization of: (i) the
§ R N · square norm of both the voltage deviations, with respect the
min
r
¨ ¦¦ c j , r 't Pjr ¸ (1) rated value Vset, in the M selected network buses and (ii) the
Pj
©r 1 j 1 ¹
deviations of each j-th DER active power output, with respect
where the horizon time T is sub-divided into R intervals and
the corresponding value Pj,set, defined by the day-ahead
the individual interval is defined as 't = T/R, N are the scheduler. This last objective is taken into account by means
programmable generating units, Pjr is the output power for of a specific coefficient D as expressed by the following
the j-th unit at instant r, cj,r is the cost of the j-th unit at time r objective function.
in €/kWh. M N 2½
Assuming the presence of S electric production units, C min ®¦ Vi Vset ¦ D 2 Pj Pj , set ¾
P1 ... PN , Q1 ...QN
2
(6)
combined heat and power (CHP) units and L storage units, we ¯i 1 j 1 ¿
consider a vector of index h following the order The relationship between DER outputs and voltage
deviations is not linear. The problem is addressed by using a
h ^C , ( S C ), L, ( N S L)` , where (N–S–L) are the
constrained linear least-squares programming solver included
thermal production outputs. The vector of outputs of the j-th in an iterative procedure.
2169
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY ROORKEE. Downloaded on May 23,2022 at 09:46:18 UTC from IEEE Xplore. Restrictions apply.
3
In particular, at each algorithm iteration k, the matrix of the for their automatic set-point updates and power flow output
so-called sensitivity coefficients is calculated by means of a calculations.
power flow calculation. Each element of the matrix, namely
Ki,jp and Ki,jq, represents the linear relationship between the
voltage variation at bus i due to a small variation of the j-th
controlled-DER active or reactive outputs.
The constrained linear least-squares problem is formulated
as
2
min Cx d (7)
x
LF1
requirements. Concerning the power flow calculations, the 800
L Load_800
connection to the feeding network is considered as the slack
+
CP
bus. The limits on the P and Q variations of the controlled 802 Tr_2
+
1 2
G Gen_802
DERs take into account not only the unit production
CP
806
capabilities but also the convergence requirements of the
+
CP
814
two consecutive iterations is lower than a predefined small
V_reg_1
threshold.
850
The optimization problems are solved by computer
+
CP
826
CP
L
CP
V_reg_2
+
856
EMTP-RV. For that purpose the Matlab code, aimed at
CP
1 2
L G
CP
(7) and (8), has been compiled as a COM (Component Object Load_856 Gen_856 860 Tr_6
1 2
Load_848
PV
838 862
control inside the developed JavaScript code. Moreover, Load_838 L
CP +
836
CP +
+
840
order (i) to simplify the development of the EMTP-RV models L Load_840
relevant to new network configurations and (ii) to provide an Fig. 2 Test network implemented in EMTP-RV, based on the IEEE 34-node
easy and direct access to all the EMTP-RV network-models test distribution feeder.
2170
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY ROORKEE. Downloaded on May 23,2022 at 09:46:18 UTC from IEEE Xplore. Restrictions apply.
4
during the day; such a result, illustrated also by Fig. 3b) also
Three different dispatchable electric power production shows the thermal load profile and the boiler output, is due to
units are considered to be connected to the network in the constrained thermal production. The thermal balance has
correspondence of nodes 802, 818 and 856 (see Fig. 2). The been defined as an inequality constraint in order to avoid the
system also includes a boiler. The relevant power limits and conflict between the electrical power production and the pure
costs are reported in Table I. Two not-dispatchable electric thermal load following.
power production units are also connected to the network, In Fig. 4, the market price and production costs are plotted
namely a photovoltaic (PV) array for a total peak power equal in order to show the algorithm procedure. Basically the
to 50 kW connected to the node 844 and a 750 kW wind algorithm tends to have the production units working only
generator connected to the node 826. during high peak market prices and to lower their production
Table I. Model parameters of the considered dispatchable DERs. during base low prices; except for the cogeneration plant
Dispatchable Symbol Rated output Pmin Cost
where it has to fulfill also the thermal constraint.
DER (kW) (kW) (€/kWh) 0.16
market clearing price
CHP gas- 1800 (electric) 720 (el.)
7000 diesel
grid
6000 renewable
In order to provide an example of the effectiveness of the
5000 intra-day scheduler action, we have first considered an high
4000 load period of the one-day horizon already considered in the
3000 previous section, namely the 39-th time period. Fig. 5 shows
2000
the voltage amplitudes at the various network buses for
1000
different operating conditions of dispatchable DERs of the
considered period, namely, (i) without available dispatchable
0
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85 89 93 DERs, (ii) with only Gen-856, and (iii) with all the DERs
15-minutes periods available. The voltage profiles in the presence of dispatchable
a)
DERs, namely the operating conditions (ii) and (iii), are
3000
obtained for two different Į-coefficient values of objective
2500
function (6), i.e. 0 and 50.
thermal load
boiler
Table II reports the load requests and the actual renewable
DERs thermal outputs (kW)
2000
CHP thermal
production levels in the considered period, with the
corresponding power factor pf values.
1500
Table II. Loads and RERs production levels, with the relevant power factor pf,
1000
in the 39-th period.
Power Powe
500
Symbol level Pf Symbol r level pf
(kW) (kW)
0
Load_800 3002.8 0.9 Load_848 200 0.95
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85 89 93
15-minutes periods Load_810 1290.7 0.9 Load_856 2000 0.95
b) Load_822 610 0.9 Load_864 141 0.9
Fig. 3 Day-ahead scheduling solution: a) electrical load balance and b) thermal Load_826 580 0.95 RERs
load balance. Load_838 120 0.9 PV 15.98 1
Load_840 160 0.95 Wind 300 0.9
Fig. 3a) shows the electrical load profile, the RERs
production and the electrical output of dispatchable DERs.
The electrical output of the CHP gas-turbine is rather constant
2171
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY ROORKEE. Downloaded on May 23,2022 at 09:46:18 UTC from IEEE Xplore. Restrictions apply.
5
1.01 deviation values are slightly worse than those obtained for the
case of Į=0 (in particular limited to few tens of volts), whilst,
1
as shown by Figs. 7a, the DERs active power output absolute
0.99 deviations can be very different from those provided by the
Voltage (p.u.)
0.98
day-ahead scheduler.
55
with all DERs (Į=0)
0.95 35
30
0.94
25
800
802
808
810
816
818
822
824
826
834
836
838
840
844
848
854
856
858
864
20
Bus
Fig. 5 Intraday scheduling solution: phase-a voltage profiles at various 15
2000
The results of Fig. 5 refer to phase-a of the system and, in GEN-802
GEN-856
view of the unbalanced line configuration of the considered GEN-818
1500
34-nodes IEEE radial distribution test feeder, Tables IV and V
show the values of the mean absolute deviation voltages for 1000
all the three phases and the DERs output deviations with
respect to the Pset values in correspondence of the considered 500
DERs operating conditions.
Table IV. Mean absolute deviation value of the voltages for all the three 0
phases and for the considered DERs operating conditions. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
hours
a)
DERs operating
voltage mean absolute deviation (V) 40
condition GEN-856
GEN-818
phase a phase b phase c 35
DERs output deviations (kW)
GEN-802
without DERs 874 844 852 30
Gen-856, Į=50 339 315 319
Gen-856, Į=0 185 164 167 25
2172
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY ROORKEE. Downloaded on May 23,2022 at 09:46:18 UTC from IEEE Xplore. Restrictions apply.
6
environment allows one to incorporate distributed resources [5] R. Lasseter, A. Akhil, C. Marnay, J. Stevens, J. Dagle, R. Guttromson,
A. S. Meliopoulous, R. Yinger, J. Eto, “White Paper on Integration of
different from those present in the considered test system, Distributed Energy Resources—The MicroGrid Concept”. Available at:
such as on-load tap changer and power electronic components http://certs.lbl.gov/pdf/50829-app.pdf, 2002.
(SVC, DFACTS, etc.). [6] European Research Project MicroGrids. Available at:
http://microgrids.power.ece.ntua.gr/.
Further developments of the scheduler, however, will also
[7] A.Bertani, A.Borghetti, C.Bossi, L.De Biase, O.Lamquet, S.Massucco,
investigate the opportunity to introduce the load flow A.Morini, C.A.Nucci, M.Paolone, E.Quaia, F.Silvestro, “Management of
equations into a non-linear mathematical programming model Low Voltage Grids with High Penetration of Distributed Generation:
in order to improve computational performance and to obtain concepts, implementations and experiments”, Proc. of CIGRE general
session, Paris, 2006.
a more compact code. [8] A. Borghetti, M. Bosetti, C. Bossi, S. Massucco, E. Micolano, A.
Morini, C.A. Nucci, M. Paolone, F. Silvestro, “An Energy Resource
V. APPENDIX Scheduler Implemented in the Automatic Management System of a
Microgrid Test Facility”, Proc. Int. Conf. on Clean Electrical Power,
The IEEE 34-node test feeder is composed by branches Capri, Italy, 21-23 May 2007.
characterized by different conductor configurations. In order [9] J. Mahseredjian, S. Lefebvre and X.-D. Do, “A new method for time-
domain modelling of nonlinear circuits in large linear networks”, Proc.
to simplify the simulation results, the following assumptions of 11th Power Systems Computation Conference PSCC, August 1993.
have been made: (i) all the branches of the network are [10] J. Mahseredjian, L. Dubé, L. Gérin-Lajoie, “New Advances in the
composed by overhead lines which conductor configuration is Simulation of Transients with EMTP: Computation and Visualization
Techniques”, Proc. of 7th International Conference on Modeling and
the “ID #500” reported in the figure 1 of [12], where the phase
Simulation of Electric Machines, Converters and Systems, Montreal,
sequence a, b and c refers to the line conductors from left to August 2002.
right; (ii) the network loads are assumed located in [11] J. Mahseredjian, S. Dennetière, L. Dubé, B. Khodabakhchian “On a new
correspondence of the line terminations and (iii) the DERs are approach for the simulation of transients in power systems” Proc. of the
International Conference on Power Systems Transients IPST’2005,
assumed connected to the network via distribution power Montreal, June 2005.
transformers (see Fig. 2). All the transformers are represented [12] IEEE Distribution Planning Working Group, “Radial Distribution Test
by means of a 50 Hz standard model and the relevant Feeders”, IEEE Trans. on Power Systems Vol. 6, No. 3, August 1991, pp
975-985.
parameters are reported in Table A1.
Table A1 Data of the DERs power transformers.
Rated
Short circuit
Rated power dividing
Transformer name voltage
(MVA) ratio
(%)
(kV/kV)
Tr_1 25 150/24.9 9
V_reg_1; V_reg_2 15 24.9/24.9 8
Tr_2; Tr_3;Tr_5 10 24.9/6 6
Tr_4 2 24.9/0.69 6
Tr_6 5 24.9/0.69 6
VI. ACKNOWLEDGEMENTS
The authors thankfully acknowledge C. Bossi and A.
Bertani for their precious collaboration and Prof. S. Massucco
and Prof. C.A. Nucci for their helpful comments. A
preliminary version of the scheduler has been developed in the
framework of the Italian Electrical Power System Research
Program.
VII. REFERENCES
[1] J.H. Choi and J.C. Kim, “Advanced voltage regulation method of power
distribution systems interconnected with dispersed storage and
generation systems”, IEEE Trans. on PWRD, vol.16, no.2, April 2001,
pp.329-334.
[2] S. Repo, H. Laaksonen, P. Järventausta, O. Huhtala, M. Mickelsson, “A
case study of voltage rise problem due to a large amount of distributed
generation on a weak distribution network”, in Proc. of. 2003 IEEE
Bologna PowerTech Conference, vol.4.
[3] N.D. Hatziargyriou, A. Dimeas, A.G. Tsikalakis, J.A. Pecas Lopes, G.
Kariniotakis, J. Oyarzabal, , “Management of Microgrids in Market
Environment”, Proc. of 2005 International Conference on Future Power
Systems, 16-18 Nov. 2005.
[4] A. L. Dimeas, N. D. Hatziargyriou, “Operation of a Multiagent System
for Microgrid Control”, IEEE Transactions on Power Systems, vol. 20,
NO. 3, August 2005.
2173
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY ROORKEE. Downloaded on May 23,2022 at 09:46:18 UTC from IEEE Xplore. Restrictions apply.