A Two-Stage Scheduler of Distributed Energy Resources

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

1

A Two-Stage Scheduler of Distributed Energy


Resources
Alberto Borghetti, Mauro Bosetti, Samuele Grillo, Andrea Morini, Mario Paolone, Federico Silvestro

 of an ERS that implements specific optimization functions:


Abstract — The paper presents a two-stage scheduler for the ƒ problems related to high variations in the steady state
optimal scheduling of distributed energy resources (DER) voltage profile of the network are often an obstacle for the
connected to a distribution network. The proposed approach integration of distributed generation (DG);
integrates a centralized day-ahead scheduler with an intra-day
ƒ the centralized ERS allows also for an higher DG
one. On the one hand, the day-ahead scheduler calculates the
active power set points during the following day taking into penetration, in terms of number and size of accepted
account both technical and economic objectives and constraints. DERs, by providing generation adjustment actions during
On the other hand, the intra-day scheduler takes into account the critical contingencies, particularly in islanded conditions;
results of the day-ahead one and updates every 15 minutes the ƒ the nowadays availability of commercial and dedicated
DERs set points for the optimization of the network voltage measurement/communication instrumentation provides
profiles.
adequate support for achieving monitoring and improved
The paper describes the implementation of the proposed two-
stage scheduler algorithm into a computer code based on a
state estimation of distribution networks;
JavaScript link between Matlab and EMTP-RV simulation ƒ the need of transmission networks expansion may be
environments and presents the results obtained for the case of a significantly reduced by improved control actions that
network configuration adapted from the IEEE 34-node test optimize the power flows in distribution systems in
distribution feeder. presence of DERs.
It is not possible, however, to directly transfer centralized
Index Terms — Distributed generation, active distribution transmission network operation concepts to distribution
networks, economic dispatching, optimal power-flow.
systems because of their specific characteristics. In particular,
I. INTRODUCTION i) typical distribution network topology (radial or weakly
meshed) and the reduced number of real-time
T HE coordinated operation and management of distribution
networks in presence of high penetration of Distributed
Energy Resources (DER), can be approached in several ways,
measurements, require the adoption of state estimation
techniques significantly different from those implemented
in transmission Energy Management Systems (EMS);
varying from a fully decentralized approach to a centralized ii) the contemporary presence in active distribution networks
one. Both approaches have peculiar characteristics and may be of renewable energy resources (RER) and loads
more or less appropriate depending on the specific situations characterized by reduced smoothing effect in time
[1-4]. variation, makes the management of energy balance more
Assuming that all the DERs are owned by the same complex;
distribution system operator (DSO), the implementation of a iii) the typical ratio between line resistances and reactance, in
coordinated integration of different DER [5-8] suggests the particular for the case of low voltage networks, is higher
adoption of a centralized approach. Such an approach, than that of transmission networks.
suitably integrated with local control systems to ensure system This paper describes an automatic ERS of the DERs set
security during fast transient dynamics (e.g. due to random points in order to achieve economic, reliability and power
load or configuration changes), is aimed to optimize the quality objectives. The proposed algorithm is composed by
system operation during its slow modifications (e.g. due to two stages: a day-ahead economic scheduler that calculates
daily, weekly and seasonal load variations). The optimization the active power set points during the following day in order
process is realized by means of an automatic Energy Resource to minimize the overall costs, and an intra-day scheduler that,
Scheduler (ERS). on the basis of measurements and short-term load and RERs
The following considerations further support the adoption production forecasts, updates the DERs set points for the
optimization of the network voltage profile every 15 minutes.
A. Borghetti, M. Bosetti and M. Paolone are with the Department of The need for 24-hour horizon function is justified by the
Electrical Engineering, University of Bologna, Italy. Email: requirement for an optimal use of the available energy storage
{alberto.borghetti;mauro.bosetti;mario.paolone}@mail.ing.unibo.it. facilities and by inter-temporal operation constraints.
S. Grillo, A. Morini, and F. Silvestro are with the Department of Electrical
Engineering, University of Genova, Italy. Email: {sgrillo;
In particular, the paper proposes an integration of the above
amorini;fsilvestro}@epsl.die.unige.it. mentioned day-ahead scheduler and intra-day one. The

978-1-4244-2190-9/07/$25.00 ©2007 IEEE 2168 PowerTech 2007

Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY ROORKEE. Downloaded on May 23,2022 at 09:46:18 UTC from IEEE Xplore. Restrictions apply.
2

integration is provided by including the network constrains, as unit belonging to h can be then defined as P jh ª¬ Pj1 " PjR º¼ .
t

well as voltage profile optimization, in the day-ahead


scheduler. Moreover, the objective function of the intra-day Being NP the set of non-programmable (np) generation units
scheduler includes a penalization of deviations from the day- and E rj the level of the energy stored at time r by the j-th
ahead solution. storage unit, the technical constrains are expressed as follows:
The outline of the paper is the following: Section II - balance of electrical load Ploade
illustrates the optimization problems relevant to the day-ahead N
scheduler and the intra-day one as well as the implementation
of the scheduler by means of a developed interface between
¦Pj 1
j
r r
Ploade
 ¦ Pnpr k
kNP
r 1,!, R (2)

the Matlab optimization software and the network model - integral constrains for storage units
implemented in the EMTP-RV environment [9-11]; Section Erj Erj 1 't ˜ Pjr1 r 2,!, R j S 1,!, S  L
III shows the results obtained for the case study referring to
the IEEE 34-bus distribution system [12] and Section IV ERj 1 ERj 't ˜ PjR (3)
concludes the paper. E1
j E. 0
j

II. FORMULATION OF THE OPTIMIZATION PROBLEMS RELEVANT - constraints due to power limits P min and P max , and energy
TO THE DAY-AHEAD SCHEDULER AND INTRA-DAY ONE limit Emax
The basic idea is that the DSO tends to optimize its Pjmin d Pjr d Pjmax r , j
(4)
resources on both economical and technical requirements; the Ej d Ej max
j S  1,! , S  L
DSO has two opportunities to supply customers: to get energy
from HV grid at market prices or to produce by its own - balance of thermal load Ploadth
generation. N C

¦ Pjr  ¦ aj Pjr  bj t Pload


r
r 1,!, R (5)
The developed and implemented algorithm aims at better j S L1 j 1
th

exploiting the generation units on the basis of their


¦ a P  b j represents the coupling function
C r
availability, production costs and operation constraints. In where j 1 j j

what follows, both day-ahead scheduler and intra-day one are between electrical power and thermal production for CHP
described in details. units. The thermal load balance constraint assumes particular
A. Day-ahead scheduler importance for the case of CHP units that usually follow the
thermal load requests.
The day-ahead dispatcher calculates the optimal set-points
for each DER in terms of required energy (power for the B. Intra-day scheduler
assigned time interval) production. It performs the set point The developed intra-day scheduler acts each 15-minutes
optimization by using the following available information: (a) time intervals. It collects: (i) information of the network state
electrical and thermal load forecasts, (b) forecasts of RERs in terms of DER set points and voltage profile and (ii) short
production, (c) energy costs, (d) upper and lower limits for term forecasts of both RES mean production and load
generating units and (e) initial status of available storage units. requests. Then it calculates the three-phase power flows and,
The procedure considers both thermal and electric DERs if some technical constraints are violated or if the voltages
and both dispatchable and not-dispatchable DERs. The values are too far from the rated value Vset, it starts an
optimization problem is defined as the sum of costs of each optimization procedure that modifies the active and reactive
generation units (both electric and thermal) for all the time outputs P and Q of the N selected DERs that participate to the
intervals. network voltage control.
The optimization problem can be defined as follows: The optimization objective is the minimization of: (i) the
§ R N · square norm of both the voltage deviations, with respect the
min
r
¨ ¦¦ c j , r ˜ 't ˜ Pjr ¸ (1) rated value Vset, in the M selected network buses and (ii) the
Pj
©r 1 j 1 ¹
deviations of each j-th DER active power output, with respect
where the horizon time T is sub-divided into R intervals and
the corresponding value Pj,set, defined by the day-ahead
the individual interval is defined as 't = T/R, N are the scheduler. This last objective is taken into account by means
programmable generating units, Pjr is the output power for of a specific coefficient D as expressed by the following
the j-th unit at instant r, cj,r is the cost of the j-th unit at time r objective function.
in €/kWh. ­M N 2½
Assuming the presence of S electric production units, C min ®¦ Vi  Vset  ¦ D 2 Pj  Pj , set ¾
P1 ... PN , Q1 ...QN
2
(6)
combined heat and power (CHP) units and L storage units, we ¯i 1 j 1 ¿
consider a vector of index h following the order The relationship between DER outputs and voltage
deviations is not linear. The problem is addressed by using a
h ^C , ( S  C ), L, ( N  S  L)` , where (N–S–L) are the
constrained linear least-squares programming solver included
thermal production outputs. The vector of outputs of the j-th in an iterative procedure.

2169

Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY ROORKEE. Downloaded on May 23,2022 at 09:46:18 UTC from IEEE Xplore. Restrictions apply.
3

In particular, at each algorithm iteration k, the matrix of the for their automatic set-point updates and power flow output
so-called sensitivity coefficients is calculated by means of a calculations.
power flow calculation. Each element of the matrix, namely
Ki,jp and Ki,jq, represents the linear relationship between the
voltage variation at bus i due to a small variation of the j-th
controlled-DER active or reactive outputs.
The constrained linear least-squares problem is formulated
as
2
min Cx  d (7)
x

The results of the power flow calculation at previous k-1


iteration, allows to determine both deviations of the M
voltages 'Vi =Vik-1-Vset and of the DER active power outputs
'Pj =Pjk-1-Pj,set. Therefore, we can write
ª K1,1P
... K1,PN Q
K1,1 ... K1,QN º ª 'P1 º ª 'V 1 º
« »« » « »
« # ... # # ... # » « ... » « ... » Fig. 1. Structure of the intra-day scheduler.
« »
« K MP ,1 ... K MP , N K MQ ,1 ... K MQ , N » « 'PN » « 'V M » (8)
Cx  d « »« » 
«D ... 0 0 ... 0 » « 'Q1 » « D ˜ 'P » III. APPLICATION EXAMPLE
« 0 « 1 »
% 0 0 ... 0 » « ... » « ... » An extensive analysis has been carried out to investigate
« »« »
¬« 0 ... D 0 ... 0 ¼» ¬« 'QN ¼» ««D ˜ 'P »» the proposed optimization strategies. In particular, we show
¬ N ¼
here the results obtained for the case of a test network adapted
where ǻP1. … ǻPN and ǻQ1. … ǻQN are the optimal on the basis of the 34-nodes IEEE radial distribution test
variations of active and reactive power operating levels at feeder [12]. The network structure is illustrated in Fig. 2 and
iteration k. its data and implementation details in the EMTP-RV code are
The problem is completed by the linear constraints given reported in the Appendix.
Tr_1
by the generators capability limits and the security reserves LF
1 2

LF1
requirements. Concerning the power flow calculations, the 800
L Load_800
connection to the feeding network is considered as the slack
+
CP

bus. The limits on the P and Q variations of the controlled 802 Tr_2
+

1 2
G Gen_802
DERs take into account not only the unit production
CP

806
capabilities but also the convergence requirements of the
+
CP

iterative process. If the optimal variations are sufficiently 810


808
Load_810 L
CP +

small, the iterative process will converge to the optimal


+
CP

solution of (6). The iterative procedure is terminated when the 812


+

difference between the objective function values calculated at


CP

814
two consecutive iterations is lower than a predefined small
V_reg_1
threshold.
850
The optimization problems are solved by computer
+

programs implemented in the Matlab environment and,


CP

818 820 822


816
concerning the power flow calculation of the intra-day CP + CP + CP +
L Load_822
+
CP

scheduler, are carried out by within the EMTP-RV 828 824


Tr_3
1 2
G Gen_818
environment [9-11]. The algorithm of the intra-day scheduler
CP +
+
+

CP

826
CP

has been implemented by means of an interface between 830


Tr_4
1 2
G Wind
Matlab and EMTP-RV. Such an interface, whose structure is Load_826
+

L
CP

852 858 864


illustrated in Fig. 1, is realized by means of the JavaScript 854 832
L Load_864
CP + CP + CP +
+

modelling programming environment that is part of the


CP

V_reg_2
+

856
EMTP-RV. For that purpose the Matlab code, aimed at
CP

842 844 846 848


834
Tr_5
solving the constrained minimization problem described by CP + CP + CP + CP +
L
+

1 2
L G
CP

(7) and (8), has been compiled as a COM (Component Object Load_856 Gen_856 860 Tr_6
1 2
Load_848

Model) object and included as ActiveX (Active eXtension) G


+
CP

PV
838 862
control inside the developed JavaScript code. Moreover, Load_838 L
CP +
836
CP +
+

specific JavaScript procedures have been also developed in


CP

840
order (i) to simplify the development of the EMTP-RV models L Load_840
relevant to new network configurations and (ii) to provide an Fig. 2 Test network implemented in EMTP-RV, based on the IEEE 34-node
easy and direct access to all the EMTP-RV network-models test distribution feeder.

2170

Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY ROORKEE. Downloaded on May 23,2022 at 09:46:18 UTC from IEEE Xplore. Restrictions apply.
4

during the day; such a result, illustrated also by Fig. 3b) also
Three different dispatchable electric power production shows the thermal load profile and the boiler output, is due to
units are considered to be connected to the network in the constrained thermal production. The thermal balance has
correspondence of nodes 802, 818 and 856 (see Fig. 2). The been defined as an inequality constraint in order to avoid the
system also includes a boiler. The relevant power limits and conflict between the electrical power production and the pure
costs are reported in Table I. Two not-dispatchable electric thermal load following.
power production units are also connected to the network, In Fig. 4, the market price and production costs are plotted
namely a photovoltaic (PV) array for a total peak power equal in order to show the algorithm procedure. Basically the
to 50 kW connected to the node 844 and a 750 kW wind algorithm tends to have the production units working only
generator connected to the node 826. during high peak market prices and to lower their production
Table I. Model parameters of the considered dispatchable DERs. during base low prices; except for the cogeneration plant
Dispatchable Symbol Rated output Pmin Cost
where it has to fulfill also the thermal constraint.
DER (kW) (kW) (€/kWh) 0.16
market clearing price
CHP gas- 1800 (electric) 720 (el.)

Market price and DERs costs (€/kWh)


Gen_818 0.0890 0.14 diesel
turbine 2819 (thermal) 1342 (th.)
CHP
Boiler 2000 0.03856 0.12
gas turbine
Diesel Gen_856 2000 800 0.1000
0.1
Gas turbine Gen_802 4000 1600 0.0810
0.08
A. Day-ahead scheduler solution
0.06
Fig. 3 illustrates a typical day-ahead scheduling solution
over a one-day horizon with 15-minute time intervals. The 0.04

considered thermal and electrical load profiles have been 0.02


derived from historical data, whereas the market prices have
0
been taken from the Italian spot market. Typical PV and wind 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85 89 93
production profiles are also considered. 15-minutes periods
9000 Fig. 4 Day-ahead scheduling solution: considered market prices and electrical
load
8000 gas turbine production costs.
CHP
B. Intra-day scheduler solution
DERs electrical outputs (kW)

7000 diesel
grid
6000 renewable
In order to provide an example of the effectiveness of the
5000 intra-day scheduler action, we have first considered an high
4000 load period of the one-day horizon already considered in the
3000 previous section, namely the 39-th time period. Fig. 5 shows
2000
the voltage amplitudes at the various network buses for
1000
different operating conditions of dispatchable DERs of the
considered period, namely, (i) without available dispatchable
0
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85 89 93 DERs, (ii) with only Gen-856, and (iii) with all the DERs
15-minutes periods available. The voltage profiles in the presence of dispatchable
a)
DERs, namely the operating conditions (ii) and (iii), are
3000
obtained for two different Į-coefficient values of objective
2500
function (6), i.e. 0 and 50.
thermal load
boiler
Table II reports the load requests and the actual renewable
DERs thermal outputs (kW)

2000
CHP thermal
production levels in the considered period, with the
corresponding power factor pf values.
1500
Table II. Loads and RERs production levels, with the relevant power factor pf,
1000
in the 39-th period.

Power Powe
500
Symbol level Pf Symbol r level pf
(kW) (kW)
0
Load_800 3002.8 0.9 Load_848 200 0.95
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85 89 93
15-minutes periods Load_810 1290.7 0.9 Load_856 2000 0.95
b) Load_822 610 0.9 Load_864 141 0.9
Fig. 3 Day-ahead scheduling solution: a) electrical load balance and b) thermal Load_826 580 0.95 RERs
load balance. Load_838 120 0.9 PV 15.98 1
Load_840 160 0.95 Wind 300 0.9
Fig. 3a) shows the electrical load profile, the RERs
production and the electrical output of dispatchable DERs.
The electrical output of the CHP gas-turbine is rather constant

2171

Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY ROORKEE. Downloaded on May 23,2022 at 09:46:18 UTC from IEEE Xplore. Restrictions apply.
5

1.01 deviation values are slightly worse than those obtained for the
case of Į=0 (in particular limited to few tens of volts), whilst,
1
as shown by Figs. 7a, the DERs active power output absolute
0.99 deviations can be very different from those provided by the
Voltage (p.u.)

0.98
day-ahead scheduler.
55
with all DERs (Į=0)

Mean absolute voltage deviations (V)


0.97 with all DERs (Į=50) 50
with only Gen-856 (Į=0)
with only Gen-856 (Į=50) 45
0.96
without dispatchable DERs 40

0.95 35

30
0.94
25
800

802

808

810

816

818

822

824

826

834

836

838

840

844

848

854

856

858

864
20
Bus
Fig. 5 Intraday scheduling solution: phase-a voltage profiles at various 15

network buses for different operating conditions of dispatchable DERs at 10


period 39 (namely, without available dispatchable DERs, with only Gen-856 5 phase a - Į=1 phase b - Į=1 phase c - Į=1
phase a - Į=0 phase b - Į=0 phase c - Į=0
and with all the DERs available) for two different Į-coefficient values of 0
scheduler objective function (0 and 50). 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
hours
For the case of Į=0, only the voltage deviations are Fig. 6 Intraday scheduling solution: mean absolute phase voltage deviations
minimized; for the case of Į equal to a large number (namely for two different Į-coefficient values: Į = 0 and Į = 1. The voltage deviations
values refer to the phase-to-ground voltage maximum value.
50), the output of each DER j is equal to the corresponding
value Pj,set defined by the day-ahead scheduler. The Pset values
2500
in the considered period are 1800 kW (Gen-818), 1647 kW
(Gen-856), and 4000 kW (Gen-802).
DERs output deviations (kW)

2000
The results of Fig. 5 refer to phase-a of the system and, in GEN-802
GEN-856
view of the unbalanced line configuration of the considered GEN-818
1500
34-nodes IEEE radial distribution test feeder, Tables IV and V
show the values of the mean absolute deviation voltages for 1000
all the three phases and the DERs output deviations with
respect to the Pset values in correspondence of the considered 500
DERs operating conditions.
Table IV. Mean absolute deviation value of the voltages for all the three 0
phases and for the considered DERs operating conditions. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
hours
a)
DERs operating
voltage mean absolute deviation (V) 40
condition GEN-856
GEN-818
phase a phase b phase c 35
DERs output deviations (kW)

GEN-802
without DERs 874 844 852 30
Gen-856, Į=50 339 315 319
Gen-856, Į=0 185 164 167 25

all DERs, Į=50 42 30 33 20


all DERs, Į=0 40 29 32
15
Table V. DERs output deviations with respect to the Pset values, for the
10
considered DERs operating conditions.
5
DERs operating DERs output deviations
condition (kW) 0
Gen-818 Gen-856 Gen-802 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
hours
Gen-856, Į=50 - 0.8 - b)
Gen-856, Į=0 - 353 - Fig. 7 Intraday scheduling solution: DERs active power output deviations with
all DERs, Į=50 0 0 0 respect Pset for two different Į-coefficient values: a) Į = 0, b) Į = 1.
all DERs, Į=0 0 353 0
IV. CONCLUSIONS
In order to provide the overall behavior of the intra-day The two stage scheduler described in the paper appears to
scheduler, it has been applied for the first 15-minutes interval be a useful tool for the correct management of distribution
of each of the 24 hours, considered in the day-ahead network with high penetration of DERs. The preliminary
optimization. In particular, Fig. 6 shows the mean absolute simulation tests have shown indeed that it is able to tackle
phase voltage deviations and Fig. 7 the DERs output absolute both economical and technical objectives with computational
deviations. The results presented in these figures refer to two time compatible for online applications.
different values of the Į-coefficient, namely 0 and 1. Fig. 6 The network representation within the EMTP-RV
shows that even for the case of Į=1, the mean absolute voltage

2172

Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY ROORKEE. Downloaded on May 23,2022 at 09:46:18 UTC from IEEE Xplore. Restrictions apply.
6

environment allows one to incorporate distributed resources [5] R. Lasseter, A. Akhil, C. Marnay, J. Stevens, J. Dagle, R. Guttromson,
A. S. Meliopoulous, R. Yinger, J. Eto, “White Paper on Integration of
different from those present in the considered test system, Distributed Energy Resources—The MicroGrid Concept”. Available at:
such as on-load tap changer and power electronic components http://certs.lbl.gov/pdf/50829-app.pdf, 2002.
(SVC, DFACTS, etc.). [6] European Research Project MicroGrids. Available at:
http://microgrids.power.ece.ntua.gr/.
Further developments of the scheduler, however, will also
[7] A.Bertani, A.Borghetti, C.Bossi, L.De Biase, O.Lamquet, S.Massucco,
investigate the opportunity to introduce the load flow A.Morini, C.A.Nucci, M.Paolone, E.Quaia, F.Silvestro, “Management of
equations into a non-linear mathematical programming model Low Voltage Grids with High Penetration of Distributed Generation:
in order to improve computational performance and to obtain concepts, implementations and experiments”, Proc. of CIGRE general
session, Paris, 2006.
a more compact code. [8] A. Borghetti, M. Bosetti, C. Bossi, S. Massucco, E. Micolano, A.
Morini, C.A. Nucci, M. Paolone, F. Silvestro, “An Energy Resource
V. APPENDIX Scheduler Implemented in the Automatic Management System of a
Microgrid Test Facility”, Proc. Int. Conf. on Clean Electrical Power,
The IEEE 34-node test feeder is composed by branches Capri, Italy, 21-23 May 2007.
characterized by different conductor configurations. In order [9] J. Mahseredjian, S. Lefebvre and X.-D. Do, “A new method for time-
domain modelling of nonlinear circuits in large linear networks”, Proc.
to simplify the simulation results, the following assumptions of 11th Power Systems Computation Conference PSCC, August 1993.
have been made: (i) all the branches of the network are [10] J. Mahseredjian, L. Dubé, L. Gérin-Lajoie, “New Advances in the
composed by overhead lines which conductor configuration is Simulation of Transients with EMTP: Computation and Visualization
Techniques”, Proc. of 7th International Conference on Modeling and
the “ID #500” reported in the figure 1 of [12], where the phase
Simulation of Electric Machines, Converters and Systems, Montreal,
sequence a, b and c refers to the line conductors from left to August 2002.
right; (ii) the network loads are assumed located in [11] J. Mahseredjian, S. Dennetière, L. Dubé, B. Khodabakhchian “On a new
correspondence of the line terminations and (iii) the DERs are approach for the simulation of transients in power systems” Proc. of the
International Conference on Power Systems Transients IPST’2005,
assumed connected to the network via distribution power Montreal, June 2005.
transformers (see Fig. 2). All the transformers are represented [12] IEEE Distribution Planning Working Group, “Radial Distribution Test
by means of a 50 Hz standard model and the relevant Feeders”, IEEE Trans. on Power Systems Vol. 6, No. 3, August 1991, pp
975-985.
parameters are reported in Table A1.
Table A1 Data of the DERs power transformers.

Rated
Short circuit
Rated power dividing
Transformer name voltage
(MVA) ratio
(%)
(kV/kV)
Tr_1 25 150/24.9 9
V_reg_1; V_reg_2 15 24.9/24.9 8
Tr_2; Tr_3;Tr_5 10 24.9/6 6
Tr_4 2 24.9/0.69 6
Tr_6 5 24.9/0.69 6

VI. ACKNOWLEDGEMENTS
The authors thankfully acknowledge C. Bossi and A.
Bertani for their precious collaboration and Prof. S. Massucco
and Prof. C.A. Nucci for their helpful comments. A
preliminary version of the scheduler has been developed in the
framework of the Italian Electrical Power System Research
Program.

VII. REFERENCES
[1] J.H. Choi and J.C. Kim, “Advanced voltage regulation method of power
distribution systems interconnected with dispersed storage and
generation systems”, IEEE Trans. on PWRD, vol.16, no.2, April 2001,
pp.329-334.
[2] S. Repo, H. Laaksonen, P. Järventausta, O. Huhtala, M. Mickelsson, “A
case study of voltage rise problem due to a large amount of distributed
generation on a weak distribution network”, in Proc. of. 2003 IEEE
Bologna PowerTech Conference, vol.4.
[3] N.D. Hatziargyriou, A. Dimeas, A.G. Tsikalakis, J.A. Pecas Lopes, G.
Kariniotakis, J. Oyarzabal, , “Management of Microgrids in Market
Environment”, Proc. of 2005 International Conference on Future Power
Systems, 16-18 Nov. 2005.
[4] A. L. Dimeas, N. D. Hatziargyriou, “Operation of a Multiagent System
for Microgrid Control”, IEEE Transactions on Power Systems, vol. 20,
NO. 3, August 2005.

2173

Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY ROORKEE. Downloaded on May 23,2022 at 09:46:18 UTC from IEEE Xplore. Restrictions apply.

You might also like