Etisalat - 273 Villas Percentage Sheet

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Project: 273 Villas

Bill No.
Percentage of Work Done Value of Work Done
Etisalat Works
Item Description Unit Qty. Unit Rate Amount Previous Current Cumulative Previous Current Cumulative
1 Etisalat Work

1.1 SUPPLY OF CAT6 CABLE- D link Villas 273 950.00 259350.00 37.00% 20.00% 57.00% 95959.50 51870.00 147829.50

SUPPLY OF RJ45 FOR FACEPLATE,RJ45 FOR PATCH


1.2 Villas 273 200.00 54600.00 0.00% 0.00% 0.00% 0.00 0.00 0.00
PANEL, 24 PORT PATCH PANEL

CABLE PULLING,INSTALLATION &


1.3 TERMINATION,TESTING & COMMISSIONING & Villas 273 100.00 27300.00 20.00% 10.00% 30.00% 5460.00 2730.00 8190.00
Etisalat NOC Certificate

Total 341250.00 29.72% 16.00% 45.72% 101419.50 54600.00 156019.50