PROJECT NAME QTY PROJECT START DATE END DATE

DURATION

Slurry 5 AND 2 TANK 42 29-Jun-2023 10-Aug-2023

JUNE JUL AUG REMARKS


SN

30-Jun-2023
29-Jun-2023
Activity Description QTY Task duration Start date End date

###
###
###

###
###

###
###
###

###
###
###

###
###
###

###
###
###

###
###

###
###

###
###
###

###
###

###
###
###

###
###

###
###

###
###

###
###

###
###

###
###
1 Excavation work
COMPLETE
2 Boulder soling work
COMPLETE
3 PCC WORK (1:4:8)
COMPLETE
4 Reinforcement work For Raft and
vertical Foundation COMPLETE
5
Centering and shuttering work COMPLETE
6 Raft Concreting Work
COMPLETE
7 Reinforcement work For 1st lift
shearwall COMPLETE
8 Centering and shuttering work For 1st 4 29-Jun-2023 1-Jul-2023

lift shearwall
9 concreting work for 1st lift shearwall 1 2-Jul-2023 2-Jul-2023

10 Reinforcement work For 2nd lift 7 4-Jul-2023 10-Jul-2023

shearwall
11 Centering and shuttering work For 2nd 8 8-Jul-2023 15-Jul-2023

lift shearwall
12 concreting work For 2nd lift shearwall 1
16-Jul-2023 16-Jul-2023

13 Reinforcement work For 3rd lift 6


17-Jul-2023 22-Jul-2023

shearwall
14 Centering and shuttering work For 3rd 6
21-Jul-2023 25-Jul-2023

lift shearwall
15 Centering and shuttering work For 7 24-Jul-2023 29-Jul-2023

beam,slab
16 Reinforcement work For beam,slab 12 28-Jul-2023 8-Aug-2023

with SM plate fixing


17 Concreting work For beam,slab 1 10-Aug-2023 10-Aug-2023

18 Tiles Work To be started later on as


per instruction of Client

** Note :
Civil working schedule shall be considered as the working day/period excluding national festival holiday's and natural abstraction from date commencement of the work.