J213-MS for Reinforcement ,Formwork & Concrete Works
METHOD STATEMENT FOR CONCRETE WORKS
1.Scope of work:
2.References:
2
J213-MS for Reinforcement ,Formwork & Concrete Works
QA/QC : Quality Assurance and Quality Control Engineer
BS : British Standard
4. RESOURCES:
A) MATERIALS
All Applicable Form works
Reinforcement as per Approval & BRC Mesh as approved
Ready Mix concrete
Curing Water
Concrete Surface Hardener
Concrete Repair Material
Concrete Bonding Agent
Cement OPC / SRC where applicable.
Curing Compound
Water bars etc
As per Drawing All Structural Concrete –C30 Grade
Plain Cement Concrete – C15 Grade to be used after approval of Mix.
Site Mix concrete to be used for Minor works .Mix to be approved
before using.
List of Machineries:
Concrete truck mixer ● Concrete pump ● Emergency vehicle ● JCB
Boom Loader ● Mobile crane ● Needle vibrator 40mm & 60mm
Electrical vibrator ● Portable mixer machine ● Water pump
Stand wood cutting machine ● Hand wood cutting machine
Wood drilling machine ● Hand steel cutting machine
Steel cutting & bending machine ● Air compressor
List of Tools
Concrete bucket ● Hand tools ● Sprit level ● Thermo meter ● Trowel
3
J213-MS for Reinforcement ,Formwork & Concrete Works
Slump cone ● Concrete cube mould ● Straight edge ● Wheel barrow
Rubber boot ● Gloves ● Concrete rake ● Right-angle ● Hammer
Surveying Instrument( Auto Level and Total station) ● Floats
Measurement Tape ● Crow bar ● Hand shovel ● Nail puller
Wire cutter ● Hard brush ● lifting nylon slings ● Light fittings
Safety materials
B)MANPOWER
5.Responsibilities:
A) PROJECT MANAGER
Overall responsibility for all activities.
The management and coordination of project specification of CIVIL & MEP
and associated technical data, obtaining necessary approvals and ensuring
the distribution and availability of required in formats, documents where it
is needed.
Selection, sourcing and scheduling of all materials, obtaining necessary
approvals to procure and ensure availability of materials at site within the
planned time frame.
Monitoring of project in terms of cost and time, liaison with the client, and
obtaining approvals where ever necessary to reallocate or provide
additional resources.
Preparation of working program in terms of labor, plant / machineries and
time allocated.
B) CONSTRUCTION MANAGER
4
J213-MS for Reinforcement ,Formwork & Concrete Works
Assess manpower equipment and other resources required to achieve
milestone / target dates pertaining to their respective areas and inform
project manager team
Coordinate with sub ordinate staff and execute the work as per planned
schedules in conformance with applicable specifications.
Shall ensure that all activity are carried out as per the lay down procedures
Arrange the required Materials on time to site
Coordinate with Head office for required Manpower and Machinery
arrangements
C) PROJECT/SITE ENGINEER
D) QA/QC ENGINEER
Prepare and get approval of the Method statement based on spec and
drawing requirements
Approved Method Statement procedure communicate to Engineers and
training to be given the procedure to be followed.
Raised Inspection to be checked at site and make readiness to carryout
Consultant inspection.
Any consultant Comments /Rejection to be communicate to Execution
team and Get approval for Re inspection.
Responsible for maintenance of all records and other inspection testing
documents
E) SAFETY ENGINEER
5
J213-MS for Reinforcement ,Formwork & Concrete Works
Responsible for productive equipment if any illness happen at the time of
waterproofing on site
Toolbox talk is conducted prior to the start of the work in accordance of
procedure.
Maintaining all HSE records updated and in traceable manner.
Conducting on the job training to the workers on safe work equipment at
site.
Proper lighting arrangements shall be provided & checked periodically.
Timely report incidents/accidents to the project manager.
6.WORK PROCEDURE
6.1 Preparation checks
AHC shall ensure that all tools, materials for safety precautions, manpower
6
J213-MS for Reinforcement ,Formwork & Concrete Works
Reinforcement shall be delivered at project yard and then we start the cut
and bend by the approved shop drawing and bar bending it may be cold-
bent at the site. No re-bending allowed.
Storage of reinforcement shall be on suitable structures/supports above
the ground surface to prevent damage and accumulation of dirt, rust and
other deleterious matter & properly covered with tarpaulin or polythene
sheet reasonably.
The Contractor shall prepare the BBS schedules based on shop drawing,
approved by the Engineer.
Fabrication of reinforcement may be done on site or in the fabrication
shop. Depending upon the situation assembling of reinforcement cages
shall be done on site.
Reinforcement to be placed ,tied ,securely fixed in positions as per the
approved shop drawings .Comply the Tolerance limits as per ACI-110
Reinforcement shall be binded at all joints tightly to secure the rebar
alignment with approved binding wire Single wire for all joints or Double
wire at alternate joints.
The ends of all tying wires shall be turned into the main body of the
concrete and not allowed to project towards the surface.
All The lap length joint shall be 50 times bar diameter as noted in IFC
drawings
Approved spacers, chairs and other support shall be provided as necessary
to maintain the reinforcement on position and to maintain cover to
External environment. IFC Drawing Notes Typical cover details to be
followed.
7
J213-MS for Reinforcement ,Formwork & Concrete Works
Placing of all reinforcement steel bars will be checked and RFI to be raised
and approved by the Engineer and in no case is concrete to be placed
around any reinforcement that has not been approved by Engineer.
The reinforcement should be clean & free from loose rust, concrete mortar,
oil and or other substances.
Walking on reinforcement for access purposes will be avoided where
possible. Where it is unavoidable use planks for movement.
Chairs to be placed at required interval of min 1.5m between chairs.
Spacing between reinforcement In layers to be at least 30mm to be
followed for free flow of Max size aggregate.
BRC Mesh of approved Type to be used in Grade slabs wherever shown in
approved drawing.
Expansion Joint Dowel bar with PVC Sleeve to be placed as per drawing
Typical details
a.Preparatory works
9
J213-MS for Reinforcement ,Formwork & Concrete Works
Once all Reinforcement and MEP Inspections are done Plan concrete
activity well in advance.
Skilled and unskilled labor shall need to use safety requirements such as
safety helmet, safety shoes, goggles, gloves and QC and HSE trained for
concrete pouring.
All the concerned Site Engineer / Forman / Operators will be made
aware of the requirements of this method statement through tool box
talks by Construction manager/Project Engineer / HSE personnel, prior
to commencement of work.
Make sure that accesses and exit for the concrete mixtures was proper
from the pouring location.
Proper lighting must be available in case of night concreting.
Ensure that all the equipment’s required for testing such as
thermometer, slump cone, Concrete cube Mould etc are kept ready at
casting yard.
Checking of equipment/Vibrators should done and spare vibrators
should be maintained prior to start concreting..
Temperature should be monitored before ordering & concreting is not
allowed to pour if the ambient temperature is above 45°c
b. Concrete Pouring
Once the concrete will be reached at site will check the Fresh Concrete
test as per approved Grade / Type of Mix are used for the elements like
Footing, wall ,columns and slabs
The concrete mixer must be stopped at the check point for the
inspection of slump & Temperature test and to obtain sample cubes for
test.
10
J213-MS for Reinforcement ,Formwork & Concrete Works
Ensure concrete temperature is not exceeding 30 Deg C at the time of
concrete placement / as per the approved Mix design Limits.
One set of cubes (6 cubes) shall be taken First and every 50 cum and
addition .Each set consist of 6 cubes, 3 cubes to be tested on 7th days
and 3 cubes to be tested for 28th days.
Adding water is not allowed into concrete mixture after reach at site to
increase the workability Manufacturer written instruction can be
followed by adding Admixtures as per the Limit mentioned in Mix design
Concrete will be done in layers not exceeding 400 mm in single layer.
Unload the concrete within 2hrs of reaching the vehicle at site or within
the required workability is met.
Proper vibrator needles will be used as per the requirement and area of
usage. Compact the concrete properly and extra vibrator shall be
available in case of any shortage or mechanical problems
Footing and slab surface to finish level with straight edge and remove
the excess concrete from top. Type of finish should be followed from the
approved shop drawing to receive the compatibility to next finishes.
Concrete pour card shall be filled with all the placing details of Mixer
including concrete delivery notes, this task will be done whenever
required.
Concrete cube test report shall be submitted to the Engineer with
summary of cubes in test reports Submittal at regular interval monthly.
Immediate after completion of Structure Members and after initial set of
concrete Sprinkling of water to be done on the surface to minimize the
cracks development.
Curing shall be continued for Minimum 7 days .
11
J213-MS for Reinforcement ,Formwork & Concrete Works
Blinding concrete can be proceed with approved curing compound or
Potable water as per the approved Manufacturer recommendation in
the datasheet.
Major Blowholes / Repairs /Honey comp of concrete will show to QC &
Consultant for approved Repair method..
Concrete requirement in advance about one-week time will be notified
to Batching plant and QC engineer will be informed the laboratory
technician about one-day advance for field test /slump test/cube
testing.
Points to be consider Structure wise as below
Footings / Raft Mass concrete
Generally Rate of Pour will be 40 cum/ Hr/Pump
Vibrators 60 mm will be used
400mm Single Layer Concrete will be poured at on stretch
Beams
Generally Rate of Pour will be 20 Cum/ Hr/Pump
Vibrators 60mm,40mm, 20mm depends on Size and Reinforcement.
Max 400 mm Depth layer will be poured at a time
Columns & Walls
General Rate of Pour will be 20 cum /Hr/Pump
Max Free fall Height is 1.5meter to be ensured
If any Manual Poring of Column Max lift of Shutter allowed is 1.5 m
Vibrators 60mm & 40mm to be used.
Flexible hose to be lay inside the deep of column and uplift slower
evenly concrete to be filled up to minimize the free fall.
12
J213-MS for Reinforcement ,Formwork & Concrete Works
Ensure Waterbars in place where required like Underground Storage
Tanks
Slab/Grade Slab
General Rate of Pour will be 40 cum /Hr /Pump
3m width bay by bay pour will be planned to avoid cold joints
Vibrators 40mm & 25 mm will be used.
Filler board /Expansion Joint/Construction joint to be checked pre pour
and Dowel bar with Gap to be fixed as per drawing.
Concrete Surface Hardener to be applied wherever mentioned in
drawing as per Manufacturer and MAS recommendation.
6.5 Curing and Protection
13
J213-MS for Reinforcement ,Formwork & Concrete Works
6.6 Stripping of formwork shall be not being done before below criteria:
S.n Type of Formworks Minimum Period of Stripping
o
1 Beam sides, walls, and columns 1 Day
2 Soffits of slabs with back propping 4 days (Props Left under)
3 Soffits of beams with back 10 days (Props Left under)
propping
4 Removal of Props to slabs /beam 7 days upto 4.5m span , 14 days
morethan that
14
J213-MS for Reinforcement ,Formwork & Concrete Works