HARGA UPAH DAN BAHAN

JUMLAH HARGA
NO JENIS MATERIAL / BAHAN SATUAN
( Rp )

01 02 04 05

I UPAH
1 Mandor Lapangan HARI 92,500.00
2 Kepala Tukang HARI 90,000.00
3 Tukang Besi/Kayu HARI 85,000.00
4 Tukang Batu/Cat HARI 85,000.00
5 Tukang Pipa/anyam HARI 85,000.00
6 Pekerja HARI 72,500.00

II BAHAN
1 Kaso 5/7 sengon m3 3,000,000.00
2 Kayu papan 3/20 sengon m3 2,500,000.00
3 tanah urug m3 150,000.00
4 sirtu m3 200,000.00
5 pasir m3 240,000.00
6 Pasir Beton Kg 156.00
7 Kerikil (maksimum 30 mm) Kg 172.00
8 Air ltr 50.00
9 Paku Biasa 2" - 5" Kg 20,000.00
10 Minyak Bekisting Ltr 2,000.00
11 Besi beton m3 12,650.00
12 Kawat beton Kg 20,000.00
13 Besi beton kg 15,000.00
14 Kawat beton kg 20,000.00
15 Semen portland kg 1,250.00
16 Pasir beton m3 240,000.00
17 Kerikil beton m3 300,000.00
18 Almunium powder coated 4" m' 75,000.00
19 Tatapan almunium powder coated m' 12,500.00
20 Spigot m' 9,000.00
21 Skrup Fixer 7 cm bh 4,500.00
22 Skrup 1 cm duz 67,500.00
23 karet tatapan pintu m' 5,000.00
24 Sealent tube 40,000.00
25 Casement 3 profil powder coated m' 112,500.00
26 Spigot m' 9,000.00
27 Kaca bening 5mm m2 135,000.00
28 karet kaca m' 2,250.00
29 Multiplex 18mm Lbr 250,000.00
30 Multiplex 9mm Lbr 125,000.00
31 HPL Taco Lbr 250,000.00
32 Aksesoris kunci & engsel Ls 550,000.00
33 Lem Kuning Prima D Kg 75,000.00
34 Lem Kayu Kg 35,000.00
35 Sekrup 3cm Dus 135,000.00
36 Sekrup 5cm Dus 190,000.00
37 Fisher S6 Dus 10,000.00
38 Paku tembak Dus 45,000.00
39 Dempul sampolak Kg 70,000.00
40 Ampelas 80 Lbr 7,500.00
41 Ampelas 100 Lbr 7,500.00
42 Isolasi kertas Bh 6,000.00
43 Sealent Tube 45,000.00
44 Thiner Ltr 35,000.00
45 Kain Bal Kg 27,500.00
46 Wallpaper M2 50,000.00
47 Lem wallpaper Kg 25,000.00
48 Gypsum board 9 mm lbr 80,000.00
49 Cotton Plaster roll 10,000.00
50 Compound zak 75,000.00
51 Skrup gypsum kg 75,000.00
52 Rangka hollow galvalum 2/4 btg 25,000.00
53 Rangka hollow galvalum 4/4 btg 35,000.00
54 Dinabolt Bh 2,500.00
55 Rangka Metalfuring Btg 37,500.00
56 Keramik polos 30x30 m2 70,000.00
57 Semen putih Kg 15,000.00
58 Keramik polos 10x30 bh 5,000.00
59 Bata merah bh 900.00
60 Truss 95X33 Z10 m' 28,100.25
61 Truss 95X33 Z08 m' 21,204.40
62 Web 65X26 C08 m' 15,219.07
63 Reng 45X27 B50 m' 10,583.46
64 Top Plate 75x40 W08 m' 19,060.60
65 Screw pcs 278.51
66 Dynabolt pcs 2,080.00
67 Multi Grip pcs 3,503.50
68 Bracing m' 10,583.46
69 Aluminium foil m' 7,000.00
70 Gentel metal Tebal 0.30 mm m2 75,000.00
71 Screw Cteks 12-4 x 50 bh 1,200.00
72 Screw Cteks 10 x 16 - 16 bh 750.00
73 Wood plank m' 85,000.00
74 Plamir tembok kg 30,000.00
75 Cat dasar kg 25,000.00
76 Cat catylac interior kg 40,000.00
77 Cat alkali resisting primer kg 40,000.00
78 Cat Eksterior Weathershield kg 70,000.00
ANALISA HARGA SATUAN PEKERJAAN

HARGA JUMLAH HARGA


NO. URAIAN
( Rp. ) ( Rp. )

1 2 3 4

1 1M' Pengukuran dan pemasangan bouwplank 78,152.50


Over head 10% 7,140.00
a. Bahan 53,900.00
0.0120 m3 Kaso 5/7 sengon 3,000,000.00 36,000.00
0.0200 kg Paku 20,000.00 400.00
0.0070 m3 Kayu papan 3/20 sengon 2,500,000.00 17,500.00
b. Tenaga 17,112.50
0.100 Oh Pekerja 72,500.00 7,250.00
0.100 Oh Tukang kayu 85,000.00 8,500.00
0.010 Oh Kepala Tukang 90,000.00 900.00
0.005 Oh Mandor 92,500.00 462.50

2 1M3 Galian tanah biasa sedalam 1m 62,356.25


Over head 10% 5,668.75
a. Bahan -

b. Tenaga 56,687.50
0.750 Oh Pekerja 72,500.00 54,375.00
0.025 Oh Mandor 92,500.00 2,312.50

3 1M3 Pemadatan Tanah 44,962.50


Over head 10% 4,087.50
a. Bahan -

b. Tenaga 40,875.00
0.500 Oh Pekerja 72,500.00 36,250.00
0.050 Oh Mandor 92,500.00 4,625.00

4 1M3 Urugan tanah kembali 44,962.50


Over head 10% 4,087.50
a. Bahan -

b. Tenaga 40,875.00
0.500 Oh Pekerja 72,500.00 36,250.00
0.050 Oh Mandor 92,500.00 4,625.00

5 1M3 Urugan tanah didatangkan 209,962.50


Over head 10% 19,087.50
a. Bahan 150,000.00
1.2000 m3 tanah urug 125,000.00 150,000.00

b. Tenaga 40,875.00
0.500 Oh Pekerja 72,500.00 36,250.00
0.050 Oh Mandor 92,500.00 4,625.00

5 1M3 Buang tanah keluar site 31,405.00


Over head 10% 2,855.00
a. Bahan -
-

b. Tenaga 28,550.00
ANALISA HARGA SATUAN PEKERJAAN
0.330 Oh Pekerja 72,500.00 23,925.00
0.050 Oh Mandor 92,500.00 4,625.00

6 1M3 Urugan sirtu padat 253,481.25


Over head 10% 23,043.75
a. Bahan 210,000.00
1.2000 m3 sirtu 175,000.00 210,000.00

b. Tenaga 20,437.50
0.250 Oh Pekerja 72,500.00 18,125.00
0.025 Oh Mandor 92,500.00 2,312.50

7 1M3 Urugan pasir 255,942.50


Over head 10% 23,267.50
a. Bahan 210,000.00
1.2000 m3 pasir 175,000.00 210,000.00

b. Tenaga 22,675.00
0.300 Oh Pekerja 72,500.00 21,750.00
0.010 Oh Mandor 92,500.00 925.00

8 1M3 Pondasi batu kali ad. 1SP : 4 PP 856,611.25


Over head 10% 77,873.75
a. Bahan 592,550.00
1.2000 m3 Batu Belah 15/20 220,000.00 264,000.00
163.0000 Kg Portland Sement 1,250.00 203,750.00
0.5200 m3 Pasir pasang 240,000.00 124,800.00
b. Tenaga 186,187.50
1.500 Oh Pekerja 72,500.00 108,750.00
0.750 Oh Tukang kayu 85,000.00 63,750.00
0.075 Oh Kepala Tukang 90,000.00 6,750.00
0.075 Oh Mandor 92,500.00 6,937.50

9 1M3 Rabat beton 858,565.95


Over head 10% 78,051.45
a. Bahan 626,892.00
247.0000 Kg Portland Semen 1,250.00 308,750.00
869.0000 Kg Pasir Beton 156.00 135,564.00
999.0000 Kg Kerikil (maksimum 30 mm) 172.00 171,828.00
215.0000 ltr Air 50.00 10,750.00
b. Tenaga 153,622.50
1.650 Oh Pekerja 72,500.00 119,625.00
0.280 Oh Tukang kayu 85,000.00 23,800.00
0.028 Oh Kepala Tukang 90,000.00 2,520.00
0.083 Oh Mandor 92,500.00 7,677.50

10 1M3 Beton K250 1,024,135.75


Over head 10% 93,103.25
a. Bahan 777,410.00
384.0000 Kg Portland Semen 1,250.00 480,000.00
692.0000 Kg Pasir Beton 156.00 107,952.00
1,039.0000 Kg Kerikil (maksimum 30 mm) 172.00 178,708.00
215.0000 ltr Air 50.00 10,750.00
b. Tenaga 153,622.50
1.650 Oh Pekerja 72,500.00 119,625.00
0.280 Oh Tukang kayu 85,000.00 23,800.00
0.028 Oh Kepala Tukang 90,000.00 2,520.00
0.083 Oh Mandor 92,500.00 7,677.50

11 1M2 Bekisting sloof 201,569.50


ANALISA HARGA SATUAN PEKERJAAN
Over head 10% 18,324.50
a. Bahan 118,700.00
0.0450 m3 Kayu sengon 2,500,000.00 112,500.00
0.3000 Kg Paku Biasa 2" - 5" 20,000.00 6,000.00
0.1000 Ltr Minyak Bekisting 2,000.00 200.00
b. Tenaga 64,545.00
0.520 Oh Pekerja 72,500.00 37,700.00
0.260 Oh Tukang kayu 85,000.00 22,100.00
0.026 Oh Kepala Tukang 90,000.00 2,340.00
0.026 Oh Mandor 92,500.00 2,405.00

12 10 kg Pembesian 162,635.00
Over head 10% 14,785.00
a. Bahan 135,825.00
10.5000 m3 Besi beton 12,650.00 132,825.00
0.1500 Kg Kawat beton 20,000.00 3,000.00
b. Tenaga 12,025.00
0.070 Oh Pekerja 72,500.00 5,075.00
0.070 Oh Tukang kayu 85,000.00 5,950.00
0.007 Oh Kepala Tukang 90,000.00 630.00
0.004 Oh Mandor 92,500.00 370.00

13 1M3 Beton sloof bertulang besi 150kg 5,671,661.19

Bahan + upah + overhead 10% 5,671,661.19


1.0500 m3 Beton K250 1,024,135.75 1,075,342.54
150.0000 kg Besi beton 16,263.50 2,439,525.00
10.7000 m2 Bekisting 201,569.50 2,156,793.65

14 1M' Membuat kolom praktis 96,648.75


Over head 10% 8,786.25
a. Bahan 68,340.00
0.002 m3 Kayu sengon 2,500,000.00 5,000.00
0.010 kg Paku 5cm - 12cm 20,000.00 200.00
3.000 kg Besi beton 15,000.00 45,000.00
0.450 kg Kawat beton 20,000.00 9,000.00
4.000 kg PC 1,250.00 5,000.00
0.006 m3 Pasir beton 240,000.00 1,440.00
0.009 m3 Kerikil beton 300,000.00 2,700.00
b. Tenaga 19,522.50
0.180 Oh Pekerja 72,500.00 13,050.00
0.020 Oh Tukang batu 85,000.00 1,700.00
0.020 Oh Tukang kayu 85,000.00 1,700.00
0.020 Oh Tukang besi 85,000.00 1,700.00
0.006 Oh Kepala Tukang 90,000.00 540.00
0.009 Oh Mandor 92,500.00 832.50

15 1M' Membuat ring balok 119,537.00


Over head 10% 10,867.00
a. Bahan 76,435.00
0.003 m3 Kayu sengon 2,500,000.00 7,500.00
0.020 kg Paku 5cm - 12cm 20,000.00 400.00
3.600 kg Besi beton 15,000.00 54,000.00
0.050 kg Kawat beton 20,000.00 1,000.00
5.500 kg PC 1,250.00 6,875.00
0.009 m3 Pasir beton 240,000.00 2,160.00
0.015 m3 Kerikil beton 300,000.00 4,500.00
b. Tenaga 32,235.00
0.297 Oh Pekerja 72,500.00 21,532.50
0.033 Oh Tukang batu 85,000.00 2,805.00
ANALISA HARGA SATUAN PEKERJAAN
0.033 Oh Tukang Kayu 85,000.00 2,805.00
0.033 Oh Tukang Besi 85,000.00 2,805.00
0.010 Oh Kepala Tukang 90,000.00 900.00
0.015 Oh Mandor 92,500.00 1,387.50

16 1 m' Pasang Kusen pintu/jendela aluminium 149,380.00


Over head 10% 13,580.00
a. Bahan 118,687.50
1.100 m' Almunium powder coated 4" 75,000.00 82,500.00
1.100 m' Tatapan almunium powder coated 12,500.00 13,750.00
0.250 m' Spigot 9,000.00 2,250.00
2.000 bh Skrup Fixer 7 cm 4,500.00 9,000.00
0.025 duz Skrup 1 cm 67,500.00 1,687.50
1.100 m' karet tatapan pintu 5,000.00 5,500.00
0.100 tube Sealent 40,000.00 4,000.00
b. Tenaga 17,112.50
0.100 Oh Pekerja 72,500.00 7,250.00
0.100 Oh Tukang aluminium 85,000.00 8,500.00
0.010 Oh Kepala Tukang aluminium 90,000.00 900.00
0.005 Oh Mandor 92,500.00 462.50

17 1 Unit Daun Jendela Casement Almunium 0.6m x 1.2m 819,669.00


Over head 10% 66,404.00
a. Bahan 598,790.00
3.960 m' Casement 3 profil powder coated 112,500.00 445,500.00
0.200 m' Spigot 9,000.00 1,800.00
0.792 m2 Kaca bening 5mm 135,000.00 106,920.00
0.100 kg Skrup 1 cm 67,500.00 6,750.00
7.920 m' karet kaca 2,250.00 17,820.00
0.500 tube Sealent 40,000.00 20,000.00
b. Tenaga 154,475.00
0.900 Oh Pekerja 72,500.00 65,250.00
0.900 Oh Tukang aluminium 85,000.00 76,500.00
0.090 Oh Kepala Tukang aluminium 90,000.00 8,100.00
0.050 Oh Mandor 92,500.00 4,625.00

18 1Unit Pintu HPL 2,760,076.00


Over head 10% 250,916.00
a. Bahan 2,043,100.00
1.300 Lbr Multiplex 18mm 250,000.00 325,000.00
2.000 Lbr Multiplex 9mm 125,000.00 250,000.00
2.000 Lbr HPL Taco 250,000.00 500,000.00
1.000 Ls Aksesoris kunci & engsel 550,000.00 550,000.00
1.200 Kg Lem Kuning Prima D 75,000.00 90,000.00
0.500 Kg Lem Kayu 35,000.00 17,500.00
0.500 Dus Sekrup 3cm 135,000.00 67,500.00
0.500 Dus Sekrup 5cm 190,000.00 95,000.00
0.750 Dus Fisher S6 10,000.00 7,500.00
0.500 Dus Paku tembak 45,000.00 22,500.00
0.750 Kg Dempul sampolak 70,000.00 52,500.00
0.750 Lbr Ampelas 80 7,500.00 5,625.00
0.750 Lbr Ampelas 100 7,500.00 5,625.00
0.100 Bh Isolasi kertas 6,000.00 600.00
0.500 Tube Sealent 45,000.00 22,500.00
0.500 Ltr Thiner 35,000.00 17,500.00
0.500 Kg Kain Bal 27,500.00 13,750.00
b. Tenaga 466,060.00
1.750 Oh Pekerja 72,500.00 126,875.00
3.500 Oh Tukang kayu 85,000.00 297,500.00
0.420 Oh Kepala Tukang 90,000.00 37,800.00
ANALISA HARGA SATUAN PEKERJAAN
0.042 Oh Mandor 92,500.00 3,885.00

19 1M2 Pasang Wallpaper (Inter choice/setara) 94,029.38


Over head 10% 8,548.13
a. Bahan 65,000.00
1.200 M2 Wallpaper 50,000.00 60,000.00
0.200 Kg Lem wallpaper 25,000.00 5,000.00
b. Tenaga 20,481.25
0.020 Oh Pekerja 72,500.00 1,450.00
0.200 Oh Tukang 85,000.00 17,000.00
0.020 Oh Kepala Tukang 90,000.00 1,800.00
0.003 Oh Mandor 92,500.00 231.25

20 1M2 Pek. Plafond gypsum board t.9mm rangka hollow galvalum 144,251.25
Over head 10% 13,113.75
a. Bahan 93,900.00
0.380 lbr Gypsum board 9 mm 80,000.00 30,400.00
0.050 roll Cotton Plaster 10,000.00 500.00
0.020 zak Compound 75,000.00 1,500.00
0.020 kg Skrup gypsum 75,000.00 1,500.00
1.000 btg Rangka hollow galvalum 2/4 25,000.00 25,000.00
1.000 btg Rangka hollow galvalum 4/4 35,000.00 35,000.00
b. Tenaga 37,237.50
0.300 Oh Pekerja 72,500.00 21,750.00
0.150 Oh Tukang cat 85,000.00 12,750.00
0.015 Oh Kepala Tukang 90,000.00 1,350.00
0.015 Oh Mandor 92,500.00 1,387.50

21 1M2 Partisi gypsum t.9mm 255,646.88


Over head 10% 23,240.63
a. Bahan 176,550.00
0.760 Lbr Gypsum 9mm 80,000.00 60,800.00
0.100 roll Cotton Plaster 10,000.00 1,000.00
0.040 Zak Compound 75,000.00 3,000.00
0.040 Kg Sekrup gypsum 75,000.00 3,000.00
6.000 Bh Dinabolt 2,500.00 15,000.00
2.500 Btg Rangka Metalfuring 37,500.00 93,750.00
b. Tenaga 55,856.25
0.450 Oh Pekerja 72,500.00 32,625.00
0.225 Oh Tukang cat 85,000.00 19,125.00
0.023 Oh Kepala Tukang 90,000.00 2,025.00
0.023 Oh Mandor 92,500.00 2,081.25

22 1 m2 Pasang lantai keramik 30x30 ex roman 285,381.25


Over head 10% 25,943.75
a. Bahan 172,550.00
1.050 m2 Keramik 30x30 ex roman 135,000.00 141,750.00
10.000 Kg PC 1,250.00 12,500.00
0.045 m3 Pasir pasang 240,000.00 10,800.00
0.500 Kg Semen putih 15,000.00 7,500.00
b. Tenaga 86,887.50
0.700 Oh Pekerja 72,500.00 50,750.00
0.350 Oh Tukang batu 85,000.00 29,750.00
0.035 Oh Kepala Tukang 90,000.00 3,150.00
0.035 Oh Mandor 92,500.00 3,237.50

23 1 m2 Pasang dinding granit 60x60 331,740.75


Over head 10% 30,158.25
a. Bahan 214,695.00
1.050 m2 Granit 60x60 175,000.00 183,750.00
9.300 Kg PC 1,250.00 11,625.00
0.018 m3 Pasir pasang 240,000.00 4,320.00
1.000 Kg Semen putih 15,000.00 15,000.00
b. Tenaga 86,887.50
ANALISA HARGA SATUAN PEKERJAAN
0.700 Oh Pekerja 72,500.00 50,750.00
0.350 Oh Tukang batu 85,000.00 29,750.00
0.035 Oh Kepala Tukang 90,000.00 3,150.00
0.035 Oh Mandor 92,500.00 3,237.50

24 1 M' Pasang Plint keramik 10x30 42,138.25


Over head 10% 3,830.75
a. Bahan 20,520.00
3.600 bh Keramik polos 10x30 5,000.00 18,000.00
1.140 Kg PC 1,250.00 1,425.00
0.003 m3 Pasir pasang 240,000.00 720.00
0.025 Kg Semen putih 15,000.00 375.00
b. Tenaga 17,787.50
0.090 Oh Pekerja 72,500.00 6,525.00
0.090 Oh Tukang batu 85,000.00 7,650.00
0.035 Oh Kepala Tukang 90,000.00 3,150.00
0.005 Oh Mandor 92,500.00 462.50

25 1 M2 Pasang kembali lantai ubin abu uk. 20x20 89,875.50


Over head 10% 8,170.50
a. Bahan 48,100.00
26.500 bh Ubin 3,600.00
10.400 Kg PC 1,250.00 13,000.00
0.045 m3 Pasir pasang 240,000.00 10,800.00
1.620 Kg Semen warna 15,000.00 24,300.00
b. Tenaga 33,605.00
0.270 Oh Pekerja 72,500.00 19,575.00
0.135 Oh Tukang batu 85,000.00 11,475.00
0.014 Oh Kepala Tukang 90,000.00 1,260.00
0.014 Oh Mandor 92,500.00 1,295.00

26 1 M2 Pasang Paving block K200 t.6cm 161,375.50


Over head 10% 14,670.50
a. Bahan 120,675.00
1.050 m2 paving t.6cm 87,500.00 91,875.00
0.120 m3 Pasir pasang 240,000.00 28,800.00
b. Tenaga 26,030.00
0.240 Oh Pekerja 72,500.00 17,400.00
0.080 Oh Tukang batu 85,000.00 6,800.00
0.008 Oh Kepala Tukang 90,000.00 720.00
0.012 Oh Mandor 92,500.00 1,110.00

27 1 M2 Pasang Paving block K300 t.6cm 170,038.00


Over head 10% 15,458.00
a. Bahan 128,550.00
1.050 m2 paving 95,000.00 99,750.00
0.120 m3 Pasir pasang 240,000.00 28,800.00
b. Tenaga 26,030.00
0.240 Oh Pekerja 72,500.00 17,400.00
0.080 Oh Tukang batu 85,000.00 6,800.00
0.008 Oh Kepala Tukang 90,000.00 720.00
0.012 Oh Mandor 92,500.00 1,110.00

28 1 M2 Pasang Paving block K300 t.8cm 198,913.00


Over head 10% 18,083.00
a. Bahan 154,800.00
1.050 m2 paving 120,000.00 126,000.00
0.120 m3 Pasir pasang 240,000.00 28,800.00
b. Tenaga 26,030.00
0.240 Oh Pekerja 72,500.00 17,400.00
0.080 Oh Tukang batu 85,000.00 6,800.00
0.008 Oh Kepala Tukang 90,000.00 720.00
0.012 Oh Mandor 92,500.00 1,110.00

29 1 M' Pasang Kanstin K5 154,022.00


Over head 10% 14,002.00
a. Bahan 109,420.00
ANALISA HARGA SATUAN PEKERJAAN
2.000 bh kanstin K5 50,000.00 100,000.00
6.000 kg Semen portland 1,250.00 7,500.00
0.008 m3 Pasir pasang 240,000.00 1,920.00
b. Tenaga 30,600.00
0.150 Oh Pekerja 72,500.00 10,875.00
0.200 Oh Tukang batu 85,000.00 17,000.00
0.020 Oh Kepala Tukang 90,000.00 1,800.00
0.010 Oh Mandor 92,500.00 925.00

30 1 M' Pasang Kanstin pasangan bata 108,809.00


Over head 10%
a. Bahan 108,809.00
0.330 m2 Pas. Bata 132,255.75 43,644.40
0.330 m2 Pas. Plester 69,242.25 22,849.94
0.330 m2 Pas. Aci 31,776.25 10,486.16
2.000 m' Skonengan 15,914.25 31,828.50
b. Tenaga -
Oh Pekerja 72,500.00 -
Oh Tukang batu 85,000.00 -
Oh Kepala Tukang 90,000.00 -
Oh Mandor 92,500.00 -

31 1M2 Pasangan bata ad. 1Pc : 4 Ps 132,255.75


Over head 10% 12,023.25
a. Bahan 87,695.00
70.000 bh Bata merah 900.00 63,000.00
11.500 kg Semen portland 1,250.00 14,375.00
0.043 m3 Pasir pasang 240,000.00 10,320.00
b. Tenaga 32,537.50
0.300 Oh Pekerja 72,500.00 21,750.00
0.100 Oh Tukang 85,000.00 8,500.00
0.010 Oh Kepala Tukang 90,000.00 900.00
0.015 Oh Mandor 92,500.00 1,387.50

32 1M2 Plesteran ad. 1Pc : 4 Ps 69,242.25


Over head 10% 6,294.75
a. Bahan 13,560.00
6.240 kg PC 1,250.00 7,800.00
0.024 m3 Pasir pasang 240,000.00 5,760.00
b. Tenaga 49,387.50
0.300 Oh Pekerja 72,500.00 21,750.00
0.150 Oh Tukang batu 85,000.00 12,750.00
0.150 Oh Kepala Tukang 90,000.00 13,500.00
0.015 Oh Mandor 92,500.00 1,387.50

33 1M2 Skonengan 15,914.25


Over head 10% 1,446.75
a. Bahan 3,025.00
0.500 kg PC 1,250.00 625.00
0.010 m3 Pasir pasang 240,000.00 2,400.00
b. Tenaga 11,442.50
0.060 Oh Pekerja 72,500.00 4,350.00
0.040 Oh Tukang batu 85,000.00 3,400.00
0.040 Oh Kepala Tukang 90,000.00 3,600.00
0.001 Oh Mandor 92,500.00 92.50

34 1M2 Acian 31,776.25


Over head 10% 2,888.75
a. Bahan 4,062.50
3.250 kg PC 1,250.00 4,062.50
b. Tenaga 24,825.00
0.200 Oh Pekerja 72,500.00 14,500.00
0.100 Oh Tukang batu 85,000.00 8,500.00
0.010 Oh Kepala Tukang 90,000.00 900.00
0.010 Oh Mandor 92,500.00 925.00

35 1M' Pasang besi CNP 100 t.1.8mm 131,848.75


ANALISA HARGA SATUAN PEKERJAAN
Over head 10% 11,986.25
a. Bahan 77,175.00
1.100 m' Besi CNP 100 t.1.8mm 45,000.00 49,500.00
0.200 kg Meni 50,000.00 10,000.00
0.200 kg Cat 70,000.00 14,000.00
0.050 % Perlengkapan 73,500.00 3,675.00
b. Tenaga 42,687.50
0.175 Oh Pekerja 72,500.00 12,687.50
0.350 Oh Tukang 85,000.00 29,750.00
0.002 Oh Kepala Tukang 90,000.00 157.50
0.001 Oh Mandor 92,500.00 92.50

36 1M' Pasang besi CNP 100 t.1.8mm 248,994.63


Over head 10% 22,635.88
a. Bahan 161,700.00
1.100 m' Besi CNP 100 t.1.8mm 90,000.00 99,000.00
0.400 kg Meni 50,000.00 20,000.00
0.400 kg Cat 70,000.00 28,000.00
0.100 % Perlengkapan 147,000.00 14,700.00
b. Tenaga 64,658.75
0.300 Oh Pekerja 72,500.00 21,750.00
0.500 Oh Tukang 85,000.00 42,500.00
0.003 Oh Kepala Tukang 90,000.00 270.00
0.002 Oh Mandor 92,500.00 138.75

37 1M2 Rangka baja ringan 222,247.00


Over head 10% 20,204.27
a. Bahan 169,793.98
0.450 m' Truss 95X33 Z10 28,100.25 12,645.11
1.600 m' Truss 95X33 Z08 21,204.40 33,927.05
0.520 m' Web 65X26 C08 15,219.07 7,913.92
7.500 m' Reng 45X27 B50 10,583.46 79,375.92
0.300 m' Top Plate 75x40 W08 19,060.60 5,718.18
43.000 pcs Screw 278.51 11,976.02
1.000 pcs Dynabolt 2,080.00 2,080.00
1.000 pcs Multi Grip 3,503.50 3,503.50
0.950 m' Bracing 10,583.46 10,054.28
1.000 ls Peralatan 2,600.00 2,600.00
b. Tenaga 32,248.75
0.150 Oh Pekerja 72,500.00 10,875.00
0.220 Oh Tukang batu 85,000.00 18,700.00
0.022 Oh Kepala Tukang 90,000.00 1,980.00
0.008 Oh Mandor 92,500.00 693.75

38 1M2 Aluminium foil 30,215.63


Over head 10% 2,746.88
a. Bahan 11,200.00
1.600 m' Aluminium foil 7,000.00 11,200.00
b. Tenaga 16,268.75
0.150 Oh Pekerja 72,500.00 10,875.00
0.050 Oh Tukang batu 85,000.00 4,250.00
0.005 Oh Kepala Tukang 90,000.00 450.00
0.008 Oh Mandor 92,500.00 693.75

39 1M2 Pasang Dinding rooster/dinding terawang 335,156.25


Over head 10% 30,468.75
a. Bahan 272,150.00
25.000 Buah Terawang / Roster 10,000.00 250,000.00
11.000 kg Portland Semen 1,250.00 13,750.00
0.035 m3 Pasir Pasang 240,000.00 8,400.00
b. Tenaga 32,537.50
0.300 Oh Pekerja 72,500.00 21,750.00
0.100 Oh Tukang batu 85,000.00 8,500.00
0.010 Oh Kepala Tukang 90,000.00 900.00
0.015 Oh Mandor 92,500.00 1,387.50

40 1M2 Pasang Genteng kodok 20,581.00


ANALISA HARGA SATUAN PEKERJAAN
Over head 10% 1,871.00
a. Bahan -
25.000 bh Genteng kodok -
b. Tenaga 18,710.00
0.150 Oh Pekerja 72,500.00 10,875.00
0.075 Oh Tukang batu 85,000.00 6,375.00
0.008 Oh Kepala Tukang 90,000.00 720.00
0.008 Oh Mandor 92,500.00 740.00

41 1M2 Pasang Atap Polycarbonat 163,838.13


Over head 10% 14,894.38
a. Bahan 105,500.00
1.100 m2 Polycarbonat 90,000.00 99,000.00
4.000 bh Baut roofing 500.00 2,000.00
0.100 tube sealent 45,000.00 4,500.00
b. Tenaga 43,443.75
0.350 Oh Pekerja 72,500.00 25,375.00
0.175 Oh Tukang batu 85,000.00 14,875.00
0.018 Oh Kepala Tukang 90,000.00 1,575.00
0.018 Oh Mandor 92,500.00 1,618.75

42 1M' Pasang Bubungan Genteng kodok 113,481.50


Over head 10% 10,316.50
a. Bahan 55,180.00
5.000 Buah Genteng Bubung Kodok / Glasur 7,500.00 37,500.00
8.000 Kg Portland Semen 1,250.00 10,000.00
0.032 m3 Pasir Pasang 240,000.00 7,680.00
b. Tenaga 47,985.00
0.400 Oh Pekerja 72,500.00 29,000.00
0.200 Oh Tukang batu 85,000.00 17,000.00
0.020 Oh Kepala Tukang 90,000.00 1,800.00
0.002 Oh Mandor 92,500.00 185.00

43 1M2 Pasang rangka atap reng 100% usuk 30% 121,893.75


Over head 10% 11,081.25
a. Bahan 93,700.00
0.005 m3 Kaso-kaso 5 x 7 8,000,000.00 39,200.00
1.100 btg Reng baja ringan 45,000.00 49,500.00
0.250 Kg Paku 5 dan 10 cm 20,000.00 5,000.00
b. Tenaga 17,112.50
0.100 Oh Pekerja 72,500.00 7,250.00
0.100 Oh Tukang batu 85,000.00 8,500.00
0.010 Oh Kepala Tukang 90,000.00 900.00
0.005 Oh Mandor 92,500.00 462.50

44 1M' Wood plank 147,963.75


Over head 10% 13,451.25
a. Bahan 108,000.00
1.200 m' Wood plank 85,000.00 102,000.00
0.3000 Kg Paku Biasa 2" - 5" 20,000.00 6,000.00
b. Tenaga 26,512.50
0.100 Oh Pekerja 72,500.00 7,250.00
0.200 Oh Tukang batu 85,000.00 17,000.00
0.020 Oh Kepala Tukang 90,000.00 1,800.00
0.005 Oh Mandor 92,500.00 462.50

45 1m2 Pengecatan dinding dalam ( 1 lps plamur, 1 lps cat dasar, 2 lps cat penutup ) 28,362.65
Over head 10% 2,578.42
a. Bahan 15,900.00
0.100 kg Plamir tembok 30,000.00 3,000.00
0.100 kg Cat dasar 25,000.00 2,500.00
0.260 kg Cat penutup 2 x 40,000.00 10,400.00
b. Tenaga 9,884.23
0.026 Oh Pekerja 72,500.00 1,885.00
0.082 Oh Tukang 85,000.00 6,961.50
0.008 Oh Kepala Tukang 90,000.00 737.10
0.003 Oh Mandor 92,500.00 300.63
ANALISA HARGA SATUAN PEKERJAAN
46 1m2 Pengecatan dinding luar weathershield 33,598.25
Over head 10% 2,495.00
a. Bahan 23,500.00
0.150 kg Cat alkali resisting primer 40,000.00 6,000.00
0.250 kg Cat Eksterior Weathershield 70,000.00 17,500.00
b. Tenaga 7,603.25
0.020 Oh Pekerja 72,500.00 1,450.00
0.063 Oh Tukang 85,000.00 5,355.00
0.006 Oh Kepala Tukang 90,000.00 567.00
0.003 Oh Mandor 92,500.00 231.25

47 1m2 Pengerokan cat lama 13,615.00


Over head 10% 1,212.50
a. Bahan 1,250.00
0.050 kg Soda api 25,000.00 1,250.00
b. Tenaga 11,152.50
0.150 Oh Pekerja 72,500.00 10,875.00
0.003 Oh Mandor 92,500.00 277.50

48 1M' Rolag bata 154,517.00


Over head 10% 14,047.00
a. Bahan 97,400.00
84.000 bh Bata merah 750.00 63,000.00
16.000 kg Semen portland 1,250.00 20,000.00
0.060 m3 Pasir pasang 240,000.00 14,400.00
b. Tenaga 43,070.00
0.400 Oh Pekerja 72,500.00 29,000.00
0.130 Oh Tukang 85,000.00 11,050.00
0.013 Oh Kepala Tukang 90,000.00 1,170.00
0.020 Oh Mandor 92,500.00 1,850.00
HARGA PERKIRAAN SENDIRI (HPS)
PEKERJAAN LANDSCAPE FAKULTAS KEDOKTERAN
SURAKARTA

Volume Sat. Harga Satuan Sub Jumlah Total


No. URAIAN PEKERJAAN
(Rp.) (Rp.) (Rp.)

A Pekerjaan.Persiapan
1 Pek. Mobilisasi material 1.00 ls 750,000.00 750,000.00
2 Pek.Pengukuran dan Bouwplank 1.00 m' 1,000,000.00 1,000,000.00
3 Pek. Pembersihan akhir 1.00 ls 750,000.00 750,000.00
SUB JUMLAH 2,500,000.00
B Pekerjaan. Tanah
1 Pek. Perataan tanah 126.00 m2 35,000.00 4,410,000.00
2 Pek. Galian tanah pondasi 10.50 m3 50,000.00 525,000.00
3 Pek. Buang tanah sisa galian 63.00 m3 20,000.00 1,260,000.00
SUB JUMLAH 6,195,000.00

C Pekerjaan Talud
1 Pek. Pondasi talud batukali 39.38 m3 150,000.00 5,906,250.00
2 Pek. Pasangan batu muka 84.00 m² 50,000.00 4,200,000.00
3 Pek. Plesteran 14.00 m² 30,000.00 420,000.00
4 Pek. Acian 14.00 m² 15,000.00 210,000.00
5 Pek. Skonengan 70.00 m' 12,000.00 840,000.00
6 Pekerjaan. Perapihan area exisitng plester + aci 1.00 ls 750,000.00 750,000.00
SUB JUMLAH 12,326,250.00
JUMLAH Rp. 21,021,250.00

Surakarta, …. Februari 2023

Dibuat oleh;
harga
kolom decoratif pipa 3'' 6 1 500000 500000
pipa 2'' 12 2 250000 500000
pipa 1.5 20 3.333333 220000 733333.33333333
1,733,333.33
ANALISA PEKERJAAN
STRUKTUR DAN ARSITEKTUR
PROYEK : PERENCANAAN SARANA DAN PRASARANA BANGUNAN
PEMERINTAH
PEKERJAAN : DETAILED ENGINEERING DESIGN ( D E D ) TAMAN EKSPASAR LAMA KAYU AGUNG

LOKASI : KAYU AGUNG- OGAN KOMERING ILIR

NO : URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)


: 2004
PEKERJAAN PERSIAPAN

1 1 M' Pasangan Bouwplank Rp 18,044.50


Papan Kayu Meranti M3 0.0125 Rp 1,210,000.00 Rp 15,125.00 Rp 18,044.50
Paku Kg 0.0200 Rp 7,500.00 Rp 150.00
Pekerja Orang 0.0280 Rp 18,000.00 Rp 504.00
Tukang Kayu Orang 0.0800 Rp 25,000.00 Rp 2,000.00
Kepala Tukang Kayu Orang 0.0080 Rp 27,500.00 Rp 220.00
Mandor Orang 0.0014 Rp 32,500.00 Rp 45.50

2 1 M2 Los Kerja/Direksi Keet Rp 135,744.45


Asbes Gelombang Lembar 0.9900 Rp 38,975.00 Rp 38,585.25 Rp 135,744.45
Kayu Meranti M3 0.0346 Rp 1,200,000.00 Rp 41,460.00
Paku Kg 0.2500 Rp 7,500.00 Rp 1,875.00
Multiplek 6 mm Lembar 0.1736 Rp 72,000.00 Rp 12,499.20
Pasir Pasang M3 0.1500 Rp 50,500.00 Rp 7,575.00
Semen (PC) 50 kg Sak 0.1000 Rp 37,500.00 Rp 3,750.00
Peralatan Unit 1.0000 Rp 12,500.00 Rp 12,500.00
Upah Kerja M2 1.0000 Rp 17,500.00 Rp 17,500.00

3 1 M2 Pekerjaan pembersihan lapangan Rp 7,890.00


Pekerja org 0.013 Rp 30,000.00 Rp 390.00 Rp 7,890.00
Mandor org 0.125 Rp 60,000.00 Rp 7,500.00

4 1 UNIT Pekerjaan Papan Nama Proyek Rp 453,760.00


Kayu (Bengkirai) M3 0.0500 Rp 2,200,000.00 Rp 110,000.00 Rp 453,760.00
Seng plat M3 1.6200 Rp 17,000.00 Rp 27,540.00
Paku kg 0.6000 Rp 7,500.00 Rp 4,500.00
Cat kayu kg 1.5000 Rp 37,000.00 Rp 55,500.00
Beton Cor M3 0.1000 Rp 362,200.00 Rp 36,220.00
Tukang Kayu org 1.0000 Rp 50,000.00 Rp 50,000.00
Tukang Cat org 1.0000 Rp 50,000.00 Rp 50,000.00
Pekerja org 2.0000 Rp 30,000.00 Rp 60,000.00
Mandor org 1.0000 Rp 60,000.00 Rp 60,000.00
ANALISA PEKERJAAN
STRUKTUR DAN ARSITEKTUR
PROYEK : PERENCANAAN SARANA DAN PRASARANA BANGUNAN
PEMERINTAH
PEKERJAAN : DETAILED ENGINEERING DESIGN ( D E D ) TAMAN EKSPASAR LAMA KAYU AGUNG

LOKASI : KAYU AGUNG- OGAN KOMERING ILIR

NO : URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)


PEKERJAAN TANAH DAN PASIR
: 2004

5 1 M3 Galian Tanah biasa Rp 48,100.00


Pekerja Orang 0.7500 Rp 30,000.00 Rp 22,500.00 Rp 48,100.00
Mandor Orang 0.2500 Rp 60,000.00 Rp 15,000.00
Alat Set 1.0000 Rp 10,600.00 Rp 10,600.00

6 1 M3 Mengurug Pasir Urug Rp 48,975.00


Pasir Urug M3 1.0500 Rp 37,500.00 Rp 39,375.00 Rp 48,975.00
Pekerja Orang 0.3000 Rp 30,000.00 Rp 9,000.00
Mandor Orang 0.0100 Rp 60,000.00 Rp 600.00

1 M3 Urugan Tanah biasa Rp 45,200.00


Pekerja Orang 0.3000 Rp 30,000.00 Rp 9,000.00 Rp 45,200.00
Mandor Orang 0.0100 Rp 60,000.00 Rp 600.00
tanah urug m3 1.0000 Rp 25,000.00 Rp 25,000.00
Alat Set 1.0000 Rp 10,600.00 Rp 10,600.00

7 1 M3 Mengurug tanah biasa Rp 20,200.00


Pekerja Orang 0.3000 Rp 30,000.00 Rp 9,000.00 Rp 20,200.00
Mandor Orang 0.0100 Rp 60,000.00 Rp 600.00
Alat Set 1.0000 Rp 10,600.00 Rp 10,600.00

8 1 M3 Buangan Tanah Rp 21,100.00


Pekerja Orang 0.2500 Rp 30,000.00 Rp 7,500.00 Rp 21,100.00
Mandor Orang 0.0500 Rp 60,000.00 Rp 3,000.00
Alat Set 1.0000 Rp 10,600.00 Rp 10,600.00

PEKERJAAN BETON

9 1 M3 Lantai Kerja (1PC : 3PS : 5KR) Rp 411,575.00


Semen Zak 4.2400 Rp 37,500.00 Rp 159,000.00 Rp 411,575.00
Split 2/3 M3 0.5500 Rp 75,000.00 Rp 41,250.00
Pasir Beton M3 0.4500 Rp 50,500.00 Rp 22,725.00
Peralatan ls 1.0000 Rp 55,000.00 Rp 55,000.00
Pekerja Orang 3.5000 Rp 30,000.00 Rp 105,000.00
Tukang Batu Orang 0.3500 Rp 50,000.00 Rp 17,500.00
Kepala Tukang Orang 0.0350 Rp 60,000.00 Rp 2,100.00
Mandor Orang 0.1500 Rp 60,000.00 Rp 9,000.00

10 1 M3 Cor Beton f'c 18 Mpa Ready Mix Rp 362,200.00


Ready Mix M3 1.1000 Rp 250,000.00 Rp 275,000.00 Rp 362,200.00
Pekerja Orang 2.0000 Rp 30,000.00 Rp 60,000.00
Tukang Batu Orang 0.2000 Rp 50,000.00 Rp 10,000.00
Kepala Tukang Orang 0.1000 Rp 60,000.00 Rp 6,000.00
Mandor Orang 0.0100 Rp 60,000.00 Rp 600.00
Alat bantu lot 1.0000 Rp 10,600.00 Rp 10,600.00

11 1 M3 Cor Beton f'c 25 Ready Mix Rp 389,700.00


Ready Mix M3 1.1000 Rp 275,000.00 Rp 302,500.00 Rp 389,700.00
Pekerja Orang 2.0000 Rp 30,000.00 Rp 60,000.00
Tukang Batu Orang 0.2000 Rp 50,000.00 Rp 10,000.00
Kepala Tukang Orang 0.1000 Rp 60,000.00 Rp 6,000.00
Mandor Orang 0.0100 Rp 60,000.00 Rp 600.00
Alat bantu lot 1.0000 Rp 10,600.00 Rp 10,600.00
ANALISA PEKERJAAN
STRUKTUR DAN ARSITEKTUR
PROYEK : PERENCANAAN SARANA DAN PRASARANA BANGUNAN
PEMERINTAH
PEKERJAAN : DETAILED ENGINEERING DESIGN ( D E D ) TAMAN EKSPASAR LAMA KAYU AGUNG

LOKASI : KAYU AGUNG- OGAN KOMERING ILIR

NO : URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)


12 1 M2 Pasang Bekisting
: 2004 Multiplek 9 mm Rp 55,662.50
Rangka Kayu Meranti 5/7 M3 0.0400 Rp 1,200,000.00 Rp 48,000.00 Rp 55,662.50
Multiplek 9mm M2 0.3500 Rp 95,000.00 Rp 33,250.00
Paku Kg 0.4000 Rp 7,500.00 Rp 3,000.00
Pekerja Orang 0.2000 Rp 30,000.00 Rp 6,000.00
Tukang Kayu Orang 0.5000 Rp 50,000.00 Rp 25,000.00
Kepala Tukang Orang 0.0500 Rp 60,000.00 Rp 3,000.00
Mandor Orang 0.0100 Rp 60,000.00 Rp 600.00
Dianggap Empat Kali Pakai Rp 118,850.00

13 1 KG Besi Beton Terpasang fy 343 Mpa Rp 13,110.00


Besi Beton rata-rata Kg 1.1000 Rp 8,000.00 Rp 8,800.00 Rp 13,110.00
Kawat Beton Kg 0.0200 Rp 9,000.00 Rp 180.00
Peralatan ls 1.0000 Rp 350.00 Rp 350.00
Pekerja Orang 0.0135 Rp 30,000.00 Rp 405.00
Tukang Besi Orang 0.0135 Rp 50,000.00 Rp 675.00
Kepala Tukang Orang 0.0450 Rp 60,000.00 Rp 2,700.00

14 1 KG Besi Beton Terpasang fy 240 Mpa Rp 13,110.00


Besi Beton rata-rata Kg 1.1000 Rp 8,000.00 Rp 8,800.00 Rp 13,110.00
Kawat Beton Kg 0.0200 Rp 9,000.00 Rp 180.00
Peralatan ls 1.0000 Rp 350.00 Rp 350.00
Pekerja Orang 0.0135 Rp 30,000.00 Rp 405.00
Tukang Besi Orang 0.0135 Rp 50,000.00 Rp 675.00
Kepala Tukang Orang 0.0450 Rp 60,000.00 Rp 2,700.00

PEKERJAAN PASANGAN PLESTERAN & ACIAN

15 1 M2 Pasangan Batu pecah Rp 59,132.50


Batu pecah 3-5 cm M2 1.2000 Rp 10,000.00 Rp 12,000.00 Rp 59,132.50
Pasir pasang M3 0.0250 Rp 50,500.00 Rp 1,262.50
Semen PC 50 kg Zak 0.2000 Rp 37,500.00 Rp 7,500.00
Bahan bantu Ls 1.0000 Rp 1,000.00 Rp 1,000.00
Pekerja Hari 0.1050 Rp 30,000.00 Rp 3,150.00
Tukang Hari 0.2100 Rp 50,000.00 Rp 10,500.00
Kepala tukang Hari 0.0210 Rp 60,000.00 Rp 1,260.00
Mandor Hari 0.0210 Rp 60,000.00 Rp 1,260.00
Alat bantu Ls 2.0000 Rp 10,600.00 Rp 21,200.00

16 1 M3 Pas. Bata merah 1pc : 3 Ps Rp 392,386.50


Batu bata Bh 495.0000 Rp 200.00 Rp 99,000.00 Rp 392,386.50
Pasir pasang M3 0.4780 Rp 50,500.00 Rp 24,139.00
Semen PC 50 Kg kg 158.6000 Rp 537.50 Rp 85,247.50
Pekerja org 4.5300 Rp 30,000.00 Rp 135,900.00
Tukang org 0.5000 Rp 50,000.00 Rp 25,000.00
Kepala tukang org 0.1500 Rp 60,000.00 Rp 9,000.00
Mandor org 0.2350 Rp 60,000.00 Rp 14,100.00
ANALISA PEKERJAAN
STRUKTUR DAN ARSITEKTUR
PROYEK : PERENCANAAN SARANA DAN PRASARANA BANGUNAN
PEMERINTAH
PEKERJAAN : DETAILED ENGINEERING DESIGN ( D E D ) TAMAN EKSPASAR LAMA KAYU AGUNG

LOKASI : KAYU AGUNG- OGAN KOMERING ILIR

NO : URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)


17 1 M3 Pasang Pondasi
: 2004 batu kali 1Pc : 4Ps Rp 550,360.00
Batu hitam M3 1.2000 Rp 180,000.00 Rp 216,000.00 Rp 550,360.00
Semen PC 50 Kg Zak 3.2560 Rp 37,500.00 Rp 122,100.00
Pasir Pasang M3 0.5200 Rp 50,500.00 Rp 26,260.00
Mandor Org 0.1800 Rp 60,000.00 Rp 10,800.00
Kepala Tukang Batu Org 0.1200 Rp 60,000.00 Rp 7,200.00
Tukang Batu Org 1.2000 Rp 50,000.00 Rp 60,000.00
Pekerja Org 3.6000 Rp 30,000.00 Rp 108,000.00

18 1 M3 Rabat Beton 1Pc : 3Ps : 5Sp Rp 516,755.00


Split M3 0.9000 Rp 75,000.00 Rp 67,500.00 Rp 516,755.00
Pasir Pasang M3 0.5100 Rp 50,500.00 Rp 25,755.00
Semen PC 50 Kg Zak 4.2800 Rp 37,500.00 Rp 160,500.00
Mandor Org 0.3000 Rp 60,000.00 Rp 18,000.00
Kepala Tukang Batu Org 0.1000 Rp 60,000.00 Rp 6,000.00
Tukang Batu Org 1.0000 Rp 50,000.00 Rp 50,000.00
Pekerja Org 6.3000 Rp 30,000.00 Rp 189,000.00

19 1M3 Pasang Bata Merah 1Pc : 4ps Rp 579,903.00


Bata Merah Bj 500.0000 Rp 475.00 Rp 237,500.00 Rp 579,903.00
Semen PC 50 Kg Zak 2.3840 Rp 37,500.00 Rp 89,400.00
Pasir Pasang M3 0.4060 Rp 50,500.00 Rp 20,503.00
Mandor Org 0.2250 Rp 60,000.00 Rp 13,500.00
Kepala Tukang Batu Org 0.1500 Rp 60,000.00 Rp 9,000.00
Tukang Batu Org 1.5000 Rp 50,000.00 Rp 75,000.00
Pekerja Org 4.5000 Rp 30,000.00 Rp 135,000.00

20 1 M2 Pek. Pasang Paving Conblok warna Rp 67,150.00


Paving block bh 40.0000 Rp 1,000.00 Rp 40,000.00 Rp 67,150.00
Pasir urug M3 0.1200 Rp 37,500.00 Rp 4,500.00
Bahan bantu Ls 1.0000 Rp 2,500.00 Rp 2,500.00
Pekerja Org 0.0650 Rp 30,000.00 Rp 1,950.00
Tukang Org 0.1250 Rp 50,000.00 Rp 6,250.00
Kepala tukang Org 0.0125 Rp 60,000.00 Rp 750.00
Mandor Org 0.0100 Rp 60,000.00 Rp 600.00
Alat bantu Ls 1.0000 Rp 10,600.00 Rp 10,600.00

21 1 M2 Pek. Pasang Paving Conblok Rp 59,610.00


Paving block M2 40.0000 Rp 800.00 Rp 32,000.00 Rp 59,610.00
Pasir urug M3 0.1200 Rp 37,500.00 Rp 4,500.00
Bahan bantu Ls 1.0000 Rp 2,500.00 Rp 2,500.00
Pekerja Org 0.0650 Rp 30,000.00 Rp 1,950.00
Tukang Org 0.1300 Rp 50,000.00 Rp 6,500.00
Kepala tukang Org 0.0130 Rp 60,000.00 Rp 780.00
Mandor Org 0.0130 Rp 60,000.00 Rp 780.00
Alat bantu Ls 1.0000 Rp 10,600.00 Rp 10,600.00
ANALISA PEKERJAAN
STRUKTUR DAN ARSITEKTUR
PROYEK : PERENCANAAN SARANA DAN PRASARANA BANGUNAN
PEMERINTAH
PEKERJAAN : DETAILED ENGINEERING DESIGN ( D E D ) TAMAN EKSPASAR LAMA KAYU AGUNG

LOKASI : KAYU AGUNG- OGAN KOMERING ILIR

NO : URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)


22 1 M' Pek. Pasang Kansteen
: 2004 Rp 61,411.60
Kansteen M' 1.2000 Rp 34,000.00 Rp 40,800.00 Rp 61,411.60
Pasir pasang M3 0.0082 Rp 50,500.00 Rp 414.10
Semen PC 50 Kg Zak 0.0506 Rp 37,500.00 Rp 1,897.50
Pekerja Org 0.0500 Rp 30,000.00 Rp 1,500.00
Tukang Org 0.1000 Rp 50,000.00 Rp 5,000.00
Kepala tukang Org 0.0100 Rp 60,000.00 Rp 600.00
Mandor Org 0.0100 Rp 60,000.00 Rp 600.00
Alat bantu Ls 1.0000 Rp 10,600.00 Rp 10,600.00

23 1 M2 Plesteran Trassram 1pc:3ps Rp 27,057.00


Pasir pasang M3 0.0140 Rp 50,500.00 Rp 707.00 Rp 27,057.00
Semen PC 50 Kg kg 4.4000 Rp 750.00 Rp 3,300.00
Pekerja org 0.4400 Rp 30,000.00 Rp 13,200.00
Tukang org 0.1550 Rp 50,000.00 Rp 7,750.00
Kepala tukang org 0.0150 Rp 60,000.00 Rp 900.00
Mandor org 0.0200 Rp 60,000.00 Rp 1,200.00

24 1 M2 Plesteran 1pc:4ps Rp 23,050.00


Pasir pasang M3 0.0250 Rp 50,500.00 Rp 1,262.50 Rp 23,050.00
Semen PC 50 Kg kg 0.2500 Rp 750.00 Rp 187.50
Pekerja org 0.4000 Rp 30,000.00 Rp 12,000.00
Tukang org 0.1500 Rp 50,000.00 Rp 7,500.00
Kepala tukang org 0.0150 Rp 60,000.00 Rp 900.00
Mandor org 0.0200 Rp 60,000.00 Rp 1,200.00

25 1 M' Sponengan Rp 3,000.00

26 1 M2 Waterproofing Rp 33,000.00

27 1 M2 Plesteran Beton 1pc:4ps Rp 23,050.00


Pasir pasang M3 0.0250 Rp 50,500.00 Rp 1,262.50 Rp 23,050.00
Semen PC 50 Kg kg 0.2500 Rp 750.00 Rp 187.50
Pekerja org 0.4000 Rp 30,000.00 Rp 12,000.00
Tukang org 0.1500 Rp 50,000.00 Rp 7,500.00
Kepala tukang org 0.0150 Rp 60,000.00 Rp 900.00
Mandor org 0.0200 Rp 60,000.00 Rp 1,200.00
ANALISA PEKERJAAN
STRUKTUR DAN ARSITEKTUR
PROYEK : PERENCANAAN SARANA DAN PRASARANA BANGUNAN
PEMERINTAH
PEKERJAAN : DETAILED ENGINEERING DESIGN ( D E D ) TAMAN EKSPASAR LAMA KAYU AGUNG

LOKASI : KAYU AGUNG- OGAN KOMERING ILIR

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)


Pekerja : Org 0.7400 Rp 18,000.00 Rp 13,320.00
PEKERJAAN LANTAI
: 2004

28 1 M2 Pek. Keramik KM/WC 20x20 Roman Rp 80,307.50


Keramik M2 1.0500 Rp 30,500.00 Rp 32,025.00 Rp 80,307.50
Pasir pasang M3 0.0250 Rp 50,500.00 Rp 1,262.50
Semen PC 50 Kg Zak 0.2000 Rp 37,500.00 Rp 7,500.00
Bahan bantu Ls 1.0000 Rp 12,750.00 Rp 12,750.00
Pekerja Org 0.1050 Rp 30,000.00 Rp 3,150.00
Tukang Org 0.2100 Rp 50,000.00 Rp 10,500.00
Kepala tukang Org 0.0210 Rp 60,000.00 Rp 1,260.00
Mandor Org 0.0210 Rp 60,000.00 Rp 1,260.00
Alat bantu Ls 1.0000 Rp 10,600.00 Rp 10,600.00

29 1 M2 Pek. Keramik Dinding KM/WC Roman 20 x 20 Rp 92,782.50


Keramik roman M2 1.0500 Rp 38,000.00 Rp 39,900.00 Rp 92,782.50
Pasir pasang M3 0.0250 Rp 50,500.00 Rp 1,262.50
Semen PC 50 Kg Zak 0.2800 Rp 37,500.00 Rp 10,500.00
Bahan bantu Ls 1.0000 Rp 13,000.00 Rp 13,000.00
Pekerja Org 0.1500 Rp 30,000.00 Rp 4,500.00
Tukang Org 0.2100 Rp 50,000.00 Rp 10,500.00
Kepala tukang Org 0.0210 Rp 60,000.00 Rp 1,260.00
Mandor Org 0.0210 Rp 60,000.00 Rp 1,260.00
Alat bantu Ls 1.0000 Rp 10,600.00 Rp 10,600.00

PEKERJAAN FINISHING

PEKERJAAN PLAFOND

30 1 M2 Pek. Plafon Gypsum 9 mm Rp 62,498.61


Kayu Kruing M3 0.0210 Rp 1,650,000.00 Rp 34,650.00 Rp 62,498.61
Gypsum 9 mm Lbr 0.3472 Rp 36,500.00 Rp 12,673.61
Paku Kg 0.2500 Rp 7,500.00 Rp 1,875.00
Bahan bantu Ls 1.0000 Rp 2,500.00 Rp 2,500.00
Pekerja Org 0.0500 Rp 30,000.00 Rp 1,500.00
Tukang Org 0.1500 Rp 50,000.00 Rp 7,500.00
Kepala tukang Org 0.0150 Rp 60,000.00 Rp 900.00
Mandor Org 0.0150 Rp 60,000.00 Rp 900.00

31 1 'M' Pek. List Profil Gypsum Rp 19,990.00


List profil gypsum M' 1.0000 Rp 5,075.00 Rp 5,075.00 Rp 19,990.00
Paku Kg 0.0500 Rp 7,500.00 Rp 375.00
Bahan bantu Ls 1.0000 Rp 2,500.00 Rp 2,500.00
Pekerja Org 0.0067 Rp 30,000.00 Rp 200.00
Tukang Org 0.0200 Rp 50,000.00 Rp 1,000.00
Kepala tukang Org 0.0020 Rp 60,000.00 Rp 120.00
Mandor Org 0.0020 Rp 60,000.00 Rp 120.00
Alat bantu Ls 1.0000 Rp 10,600.00 Rp 10,600.00
ANALISA PEKERJAAN
STRUKTUR DAN ARSITEKTUR
PROYEK : PERENCANAAN SARANA DAN PRASARANA BANGUNAN
PEMERINTAH
PEKERJAAN : DETAILED ENGINEERING DESIGN ( D E D ) TAMAN EKSPASAR LAMA KAYU AGUNG

LOKASI : KAYU AGUNG- OGAN KOMERING ILIR

NO : URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)


PEKERJAAN PENUTUP
: 2004ATAP DAN PYAN

32 1 M2 Listplang tebal 2 cm kayu Bengkirai Rp 212,500.00


Kayu Bengkirai M3 0.0260 Rp 2,600,000.00 Rp 67,600.00 Rp 212,500.00
Paku Kg 0.2000 Rp 7,500.00 Rp 1,500.00
Mandor Org 0.0300 Rp 60,000.00 Rp 1,800.00
Kepala tukang kayu Org 0.1800 Rp 50,000.00 Rp 9,000.00
Tukang kayu Org 1.8800 Rp 60,000.00 Rp 112,800.00
Pekerja Org 0.6600 Rp 30,000.00 Rp 19,800.00

33 1 M' Talang dengan seng BJLS 30 Rp 80,975.00


10 M' Talang dengan seng BJLS 30 Rp 809,750.00
Seng BJLS 30 lbr 3.5000 Rp 35,500.00 Rp 124,250.00 Rp 809,750.00
Paku8 Sumbat bj 450.0000 Rp 400.00 Rp 180,000.00
Tukang Org 6.0000 Rp 60,000.00 Rp 360,000.00
Kepala Talang Org 0.6000 Rp 50,000.00 Rp 30,000.00
Pekerja Org 3.5000 Rp 30,000.00 Rp 105,000.00
Mandor Org 0.1750 Rp 60,000.00 Rp 10,500.00
ANALISA PEKERJAAN STRUKTUR

PROYEK : PERENCANAAN SARANA DAN PRASARANA BANGUNAN


PEMERINTAH
PEKERJAAN : DETAILED ENGINEERING DESIGN ( D E D ) TAMAN EKSPASAR LAMA KAYU AGUNG

LOKASI : KAYU AGUNG- OGAN KOMERING ILIR


TAHUN : 2005 ( Lengkap )

:
NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH (RP) TOTAL (RP)
:
PEKERJAAN BETON : 2004
1 1 M3 PLAT LANTAI KOLAM Rp 2,165,430.33
Beton f'c 25 Mpa m3 1.00 Rp 389,700.00 Rp 389,700.00 Rp 2,165,430.33
Besi BJTD - 35 fy 343 Mpa kg 103.24 Rp 13,110.00 Rp 1,353,476.40
Besi BJTP - 24 fy 240 Mpa kg 0.00 Rp 13,110.00 Rp -
Bekisting m2 6.00 Rp 55,662.50 Rp 333,975.00
Stoodwerk ls 0.85 Rp 103,857.57 Rp 88,278.93
2 1 M3 PLAT DINDING KOLAM Rp 2,232,937.76
Beton f'c 25 Mpa m3 1.00 Rp 389,700.00 Rp 389,700.00 Rp 2,232,937.76
Besi BJTD - 35 fy 343 Mpa kg 103.24 Rp 13,110.00 Rp 1,353,476.40
Besi BJTP - 24 fy 240 Mpa kg 0.00 Rp 13,110.00 Rp -
Bekisting m2 6.00 Rp 55,662.50 Rp 333,975.00
Stoodwerk ls 1.50 Rp 103,857.57 Rp 155,786.36
3 1 M3 KOLOM UTAMA KOLAM Rp 2,120,295.36
Beton f'c 25 Mpa m3 1.00 Rp 389,700.00 Rp 389,700.00 Rp 2,120,295.36
Besi BJTD - 35 fy 343 Mpa kg 65.45 Rp 13,110.00 Rp 858,049.50
Besi BJTP - 24 fy 240 Mpa kg 37.63 Rp 13,110.00 Rp 493,329.30
Bekisting m2 4.16 Rp 55,662.50 Rp 231,288.98
Stoodwerk ls 1.50 Rp 98,618.39 Rp 147,927.58
4 1 M3 KEPALA KOLOM UTAMA KOLAM Rp 2,349,955.97
Beton f'c 25 Mpa m3 1.00 Rp 389,700.00 Rp 389,700.00 Rp 2,349,955.97
Besi BJTD - 35 fy 343 Mpa kg 0.00 Rp 13,110.00 Rp -
Besi BJTP - 24 fy 240 Mpa kg 98.53 Rp 13,110.00 Rp 1,291,728.30
Bekisting m2 10.00 Rp 55,662.50 Rp 556,625.00
Stoodwerk ls 1.00 Rp 111,902.67 Rp 111,902.67
5 1 M3 BALOK KEPALA KOLAM 200 x 200 Rp 2,360,447.64
Beton f'c 25 Mpa m3 1.00 Rp 389,700.00 Rp 389,700.00 Rp 2,360,447.64
Besi BJTD - 35 fy 343 Mpa kg 95.06 Rp 13,110.00 Rp 1,246,289.04
Besi BJTP - 24 fy 240 Mpa kg 45.26 Rp 13,110.00 Rp 593,358.60
Bekisting m2 10.00 Rp 13,110.00 Rp 131,100.00
Stoodwerk m2 0.00 Rp 122,743.28 Rp -
6 1 M3 SLOOF PRAKTIS (150 X 150) Rp 2,301,821.35
Beton f'c 25 Mpa m3 1.00 Rp 389,700.00 Rp 389,700.00 Rp 2,301,821.35
Besi BJTD - 35 fy 343 Mpa kg 0.00 Rp 13,110.00 Rp -
Besi BJTP - 24 fy 240 Mpa kg 102.46 Rp 13,110.00 Rp 1,343,250.60
Bekisting m2 10.22 Rp 55,662.50 Rp 568,870.75
Stoodwerk ls 0.00 Rp 115,091.07 Rp -
7 1 M3 KOLOM PRAKTIS (150 X 150) Rp 2,309,614.10
Beton f'c 25 Mpa m3 1.00 Rp 389,700.00 Rp 389,700.00 Rp 2,309,614.10
Besi BJTD - 35 fy 343 Mpa kg 0.00 Rp 13,110.00 Rp -
Besi BJTP - 24 fy 240 Mpa kg 102.46 Rp 13,110.00 Rp 1,343,250.60
Bekisting m2 10.36 Rp 55,662.50 Rp 576,663.50
Stoodwerk ls 0.00 Rp 205,555.65 Rp -
8 1 M3 RING BALOK (150x150) Rp 2,309,483.00
Beton f'c 25 Mpa m3 1.00 Rp 389,700.00 Rp 389,700.00 Rp 2,309,483.00
Besi BJTD - 35 fy 343 Mpa kg 0.00 Rp 13,110.00 Rp -
Besi BJTP - 24 fy 240 Mpa kg 102.45 Rp 13,110.00 Rp 1,343,119.50
Bekisting m2 10.36 Rp 55,662.50 Rp 576,663.50
Stoodwerk m2 0.00 Rp 127,714.41 Rp -
9 1 M3 FOOT PLAT Rp 1,726,771.95
Beton f'c 25 Mpa m3 1.00 Rp 389,700.00 Rp 389,700.00 Rp 1,726,771.95
Besi BJTD - 35 fy 343 Mpa kg 95.62 Rp 13,110.00 Rp 1,253,578.20
Besi BJTP - 24 fy 240 Mpa kg 0.00 Rp 13,110.00 Rp -
Bekisting m2 1.50 Rp 55,662.50 Rp 83,493.75
Stoodwerk ls 0.00 Rp 94,972.46 Rp -
DAFTAR SATUAN HARGA BAHAN

PROYEK : PENINGKATAN SARANA DAN PRASARANA FISIK


BANK PEMBANGUNAN DAERAH PROPINSI DIY
PEKERJAAN : PERENCANAAN PEMBANGUNAN BANGUNAN TAMBAHAN GEDUNG KANTOR
PUSAT / CABANG UTAMA BANK PEMBANGUNAN DAERAH PROPINSI DIY
LOKASI : JL. TENTARA PELAJAR NO 7 YOGYAKARTA
TAHUN : 2004

NO Uraian Bahan Harga Satuan


1 BATU
Batu kali Rp. 180,000.00 per M3
Batu putih Rp. 50,000.00 per M3
Batu kali belah Rp. 50,000.00 per M3
Split 2/3 pecah mesin Rp. 75,000.00 per M3
Batako Rp. 1,500.00 per Biji
Batu merah Rp. 475.00 per Biji

2 TANAH DAN PASIR


Tanah urug Rp. 25,000.00 per M3
Pasir urug Rp. 37,500.00 per M3
Pasir beton/ pasang Rp. 50,500.00 per M3

3 PC DAN KAPUR
PC 50 kg ex. Batu raja Rp. 37,500.00 per Zak
Semen putih Rp. 65,000.00 per Zak
Semen warna Rp. 2,750.00 per kg
Kapur Rp. 85,000.00 per M3
PC 50 kg ex. Nusantara / Gresik / Tiga Roda Rp. 750.00 per Kg
Ready Mix f'c 18 Mpa Rp. 250,000.00 per m3
Ready Mix f'c 25 Mpa Rp. 275,000.00 per m3

4 KAYU
Kayu jati Rp. 10,000,000.00 per M3
Kayu jati BCB Rp. 9,000,000.00 per M3
Kayu jati untuk daun panil Rp. 12,000,000.00 per M3
Kayu jati untuk daun panil Rp. 31,500.00 per M'
Reng Jati Rp. 2,600.00 per M'
Kayu bengkirai Rp. 2,200,000.00 per M3
Kayu bengkirai utk listplank Rp. 2,600,000.00 per M3
Kayu kamper Rp. 2,100,000.00 per M3
Kayu Kruing Rp. 1,650,000.00 per M3
Kayu kruing untuk listplank Rp. 1,850,000.00 per M3
Kayu glugu Rp. 1,250,000.00 per M3
Balok kayu Meranti
balok Rp. 1,200,000.00 per M3
papan Rp. 1,210,000.00 per M3
Papan bekisting Rp. 935,000.00 per M3
Kayu dolok Rp. 935,000.00 per M3
Teakwood Rp. 63,250.00 per M3
Multiplex 6 mm 4 X 8 Rp. 72,000.00 per Lbr
Multiplex 9 mm 4 X 8 Rp. 95,000.00 per Lbr
Multiplex 12 mm 4 X 8 Rp. 120,000.00 per Lbr
Papan tahun Rp. 935,000.00 per Lbr

BPD DIY HAL- 61 ENGINEER ESTIMATE (EE)


DAFTAR SATUAN HARGA BAHAN

PROYEK : PENINGKATAN SARANA DAN PRASARANA FISIK


BANK PEMBANGUNAN DAERAH PROPINSI DIY
PEKERJAAN : PERENCANAAN PEMBANGUNAN BANGUNAN TAMBAHAN GEDUNG KANTOR
PUSAT / CABANG UTAMA BANK PEMBANGUNAN DAERAH PROPINSI DIY
LOKASI : JL. TENTARA PELAJAR NO 7 YOGYAKARTA
TAHUN : 2004

NO Uraian Bahan Harga Satuan


5 BESI
Bendrat / Kawat Beton Rp. 9,000.00 per Kg
Besi BJTD-35 fy 343 Mpa Rp. 8,000.00 per Kg
Besi BJTP-24 fy 240 Mpa Rp. 8,000.00 per Kg
Kawat ayam Rp. 9,500.00 per m2

6 PAKU
Paku 2 s/d 4" Rp. 7,500.00 per Kg
Paku Usuk Rp. 7,500.00 per kg
Paku Reng Rp. 7,500.00 per kg
Paku sumbat Rp. 400.00 per bh
Paku asbes Rp. 400.00 per Biji
Paku anti karat Rp. 400.00 per Biji

7 KERAMIK, TEGEL DAN ETERNIT


Eternit asbes Rp. 18,575.00 per lbr
List Profil Gypsum Rp. 5,075.00 per M'
Gypsum tebal 9 mm Rp. 36,500.00 per M2
Batu pecah 3-5cm Rp. 10,000.00 per M2
Tegel abu-abu Rp. 17,500.00 per M2
Keramik 10X20 MULIA Rp. 29,500.00 per M2
Keramik 20X20 MULIA Rp. 37,950.00 per M2
Keramik 20X20 roman umum Rp. 33,000.00 per M2
Keramik 20X20 terakota Rp. 70,000.00 per M2
Keramik 20X20 Masterina Rp. 37,950.00 per M2
Keramik 30x30 KIA Rp. 29,000.00 per M2
Keramik 40x40 COTO Type Granity Blue Lilac Rp. 31,000.00 per M2
Granit 40x40 Cleopatra Polish Rp. 118,000.00 per M2
Conblok tebal 8 cm Rp. 42,500.00 per M2
Conblok tebal 6 cm Rp. 35,000.00 per M2
Glass block terpasang Rp. 20,250.00 per M2
Kansteen Rp. 34,000.00 per M'
Keramik 20X20 roman molina ocean Rp. 30,500.00 per M2
Keramik dinding roman 20X20 type luxor ocean Rp. 38,000.00 per M2

8 KACA
Kaca buram 5 mm Rp. 84,000.00 per M2
Temper glass mm Rp. 359,500.00 per M2
Kaca es Rp. 61,000.00 per M3

9 PENGUNCI
Slot Rp. 65,000.00 per Bh
Engsel Pintu Rp. 9,525.00 per Bh

10 GENTENG
Wuwungan genteng KIA standart Rp. 13,650.00 per Biji
Genteng Keramik KIA standart Rp. 3,650.00 per Biji
Bubungan genteng pres Kebumen Rp. 2,500.00 per Biji
Genteng Pres Kebumen Rp. 650.00 per Biji
Asbes gelombang besar Rp. 52,560.00 per Lbr
Asbes gelombang kecil Rp. 38,975.00 per Lbr

BPD DIY HAL- 62 ENGINEER ESTIMATE (EE)


DAFTAR SATUAN HARGA BAHAN

PROYEK : PENINGKATAN SARANA DAN PRASARANA FISIK


BANK PEMBANGUNAN DAERAH PROPINSI DIY
PEKERJAAN : PERENCANAAN PEMBANGUNAN BANGUNAN TAMBAHAN GEDUNG KANTOR
PUSAT / CABANG UTAMA BANK PEMBANGUNAN DAERAH PROPINSI DIY
LOKASI : JL. TENTARA PELAJAR NO 7 YOGYAKARTA
TAHUN : 2004

NO Uraian Bahan Harga Satuan


11 CAT
Plamur Rp. 8,500.00 per kg
Plamur tembok Rp. 6,000.00 per kg
Amplas Rp. 3,000.00 per Lbr
Cat Tembok Decolith / catylac Rp. 7,500.00 per kg
Cat kayu emco Rp. 37,000.00 per kg
Meni Rp. 8,500.00 per kg
Minyak cat Rp. 4,000.00 per liter
Plamur Rp. 42,500.00 per gl
Plamur tembok Rp. 30,000.00 per gl
Cat Tembok Decolith / catylac Rp. 37,500.00 per gl
Cat kayu Emco Lux Rp. 185,000.00 per gl
Perekat Rp. 7,000.00 per kg
Cat Tembok Dulux ICI Pentalite Rp. 35,780.00 per kg
Cat Tembok Dulux ICI Pentalite Rp. 178,900.00 per gl
Cat Tembok Dulux ICI Weathershield Rp. 61,800.00 per kg
Cat Tembok Dulux ICI Weathershield Rp. 309,000.00 per gl
sikromat Rp. 18,500.00 per kg

12 DLL
Waterproofing terpasang membrane 3 mm Rp. 33,000.00 per M2
Waterstop terpasang PVC L 20 cm Rp. 65,000.00 per M1
Seng Plat Rp. 17,000.00 per M3
Kusen Aluminium terpasang Rp. 84,700.00 per M'
Teakwood Uk. 90x240 Rp. 63,250.00 per lbr
Teakwood Uk. 90x240 Rp. 31,625.00 per M'
PVC decodoor Rp. 65,000.00 per M2
Seng BJLS 30 Rp. 35,500.00 per lbr

13 SANITAIR
Closed Monoblok KIA American Standart Type Granada 3000 Rp. 855,500.00 per Bh
Wastafel KIA American Standart Type Studio 50 Whisper Blue Rp. 264,500.00 per Bh
Kran Tembok Exel 7515 H3 Baling Rp. 50,000.00 per Bh
Tempat sabun TOTO TX 7A Rp. 33,000.00 per Bh
Tempat tissue TOTO TX 72 A Rp. 65,500.00 per Bh
Floor Drain SAN EI Rp. 85,500.00 per Bh
Kitchen zink BCP Royal 5 BI Rp. 310,000.00 per Bh
Kran zink BCP BCP Tasin HFC 676 NC Rp. 85,500.00 per Bh
Urinoir INA TypeU 15 warna biru tua Rp. 415,000.00 per Bh

BPD DIY HAL- 63 ENGINEER ESTIMATE (EE)