Work Description Daily Rate Unit

Bituminous Membrane Waterproofing No. of Crew Remarks


2
Primer 500 M Technician + Assistant For Roofs = 300M2
MBM*1 Layer Horizontal Raft 220(Loose-Laid) M2 Technician + Assistant Fully bonded = 140M2
MBM*1 Layer Vertical Retaining Wall 70 M2 Technician + Assistant
MBM*2 Layers Horizontal Raft 90 M2 Technician + Assistant Two layers per day
MBM*2 Layer Vertical Retaining Wall 40 M2 Technician + Assistant Two layers per day
Waterproofing

MBM*1 Layer Roof 80 M2 Technician + Assistant


MBM*1 Layer Wet Area 30 M2 Technician + Assistant
MBM*1 Layer Isolated Footing 60 M2 Technician + Assistant
Protection Board Vertical 120 M2 Technician + Assistant Protection Board Horizontal = 220M2
Cartonal Vertical 160 M2 Technician + Assistant
XPS Spreading 250 M2 Technician + Assistant
Geotextile 300 M2 Technician + Assistant
Metal Flashing Fixing 200 L.m Technician + Assistant Without Selant
Cementitious Waterproofing*2 Coats Only No. of Crew Remarks
2
Wet Area 35 M Technician + Assistant For 2 Coats
Tanks & Roofs floors 225 M2 Technician + Assistant For Close Tanks = 125 M2
Tanks Walls 90 M2 Technician + Assistant For Close Tanks = 75 M2
Ceiling 45 M2 Technician + Assistant
Cold Apply* 3 Coats Only No. of Crew Remarks
2
Foundation 100 M Technician + Assistant
2
Elevations 30 M Technician + Assistant
Surface preparation

Surface Preparation No. of Crew Remarks


Intersection opening& Angle Fillet 60 L.m Technician
Tie Rods Filling 20 M2 Technician + Assistant
Floor Grinding By Angle grinding(‫)ﺻﺎﺭﻭﺥ‬ 200 M2 Technician + Assistant For Close Tanks = 120 M2
Floor Grinding By Mechanical grinding(‫)ﺟﻼﻳﺔ‬ 450 M2 Technician + Assistant For Close Tanks = 300 M2
Walls Grinding By Angle grinding 160 M2 Technician + Assistant For Close Tanks = 80 M2
Sand Blasting M2
2
Concrete Demolition M
Concrete Repair using Mortar M2
Epoxy For Tanks No. of Crew Remarks
Grinding 80 M2 Technician + Assistant
2
Primer 150 M Technician + Assistant
First Putty 100 M2 Technician + Assistant
Second Putty 100 M2 Technician + Assistant
2
Grinding Second putty 80 M Technician + Assistant
First Coat 150 M2 Technician + Assistant
Epoxy

Grinding Second Coat 80 M2 Technician + Assistant


Second Coat 150 M2 Technician + Assistant
Epoxy For Flooring No. of Crew Remarks
2
Grinding 200 M Technician + Assistant
Primer 200 M2 Technician + Assistant
This rate for closed areas
First Putty 200 M2 Technician + Assistant like as rooms
Second Putty 200 M2 Technician + Assistant if open areas
Grinding Second putty 200 M2 Technician + Assistant like as hungers ,
First Coat 200 M2 Technician + Assistant this rate will increse
M2 to 700m2
Grinding Second Coat 200 Technician + Assistant
2
Second Coat 200 M Technician + Assistant