Mcset 4 24 KV Schneider 4 24 KV Installation Instruction MV Voltage Class

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 94

Medium Voltage Distribution

MCset 4 - 24 kV
Withdrawable switchgear SF6
circuit-breaker

Installation instruction
November 2012
Content

General 3
Glossary 3
Symbols 3
Recommendations 4
Standard tightening torques 5
List of bags and accessories 5

Approximate dimensions and weights 6


NIA version 6
NIA version with IPX1 protection 7
Internal arc version with protection on 3 sides 8
Internal arc version with protection on 3 sides, with a ceiling
height between 2.8 and 4 m 9
Internal arc version with protection on 3 sides
with IPX1 protection 10
Internal arc version with protection on 4 sides,
height under ceiling lower than 4 m 11
Internal arc version with protection on 4 sides, in substations
with a ceiling height between 2.8 and 4 m 12
Internal arc version with protection on 4 sides in a substation
with a ceiling height of 2.8 to 4 m with IPX1 protection 13
AD4 cubicle (for cubicle entry from above) 14
CL4-GL4 cubicles (with upstream CT) 14

Handling instructions 15
Packaging 15
Handling 16
Storing 17

Installation and operation recommendations 18


The switchgear’s resistance to ageing in an MV substation 18
Operation and maintenance 18

Unpacking 19

Floor finishing and cubicle fastening 20


Surface condition 20
Floor quality 20
Description of the fixing rails and accessories 20
Placing and adjusting on standard civil engineering works 20
Placing and adjusting on earthquake resistant civil
engineering works 22

Procedure to draw-out/draw-in the mobile part 24


Safety rules for use 24
Extraction and lowering tool 24
Without lowering (extraction table) 24
Procedure to draw-out the mobile part 25
Procedure to draw-in the mobile part 28
Procedure to extract the VTs and opening the MV cable compartment 31
Procedure to insert the VT’s and closing the MV cable compartment 35

Access to the interior of the cubicles 40


AD4 - RD4 cubicle 40
CL4 cubicle (bus-section) 41
CL4 cubicle (bus-section) with upstream CT’s 42
GL4 cubicle (bus-riser) 43
TT4 cubicle 44
DI4 cubicle 45
AD4 RHC cubicle (for cubicle entry from above) 46

07897542EN version 02 
Content

Installation instructions 47
Preparation of the cubicle to the positioning 47
Adjusting cubicles on standard civil engineering works 48
Fastening to the floor on standard civil engineering works 48
Fastening to the floor on earthquake resistant civil engineering works 49
Verify correct positioning 49
Assembly tunnel 50
Cubicle coupling 54
Installation extension busbar 61
Connection of earthing busbar 63
End panels assembling 64
Fitting the main busbars 69
1250 A main busbars 70
2000 / 2500 A main busbars 71
Fitting joint covers 72
Positioning the joint covers 74

Connection of the LV cables 75


LV cables routing 75
LV cables connections 76
Closing the top entry LV cable steel sheet 76

Earthing circuit equipotential connection


and MV cable earthing 77
Starting conditions 77
Equipotential connection of the switchboard’s earth
to the substation earth 77
Connection of MV cables 78
One single core or three-core cable per phase 78
One to four single core cables per phase 79
Three-core cable per phase 79
Anchoring supports for MV cables 80
Earthing of MV cable shields 81
Earthing of MV cable shields (DI4) 81
Final operations 82

Fitting fuses in DI4 cubicle 83

Tests on site 84
Voltage test on the main circuits 84
How to prepare the cubicles 84
Operations to be carried out on the cubicle to be connected
to the testing equipment 85
Withdraw the VT fuses 85
Close the earthing switch 86
Prevent the insertion of the circuit-breaker 87
Open the earthing switch 88
Restore the possibility of circuit-breaker insertion 89
After performing the test 89

Index 90

 version 02 07897542EN
General

Glossary UF Functionnal Unit (cubicle + mobile part + Sepam)


NIA Basic version, without internal arc withstand
AD4 Incomming / outgoing cubicle
RD4 Incomming / outgoing cubicle (without circuit-breaker)
CL4 - GL4 Withdrawable line coupling cubicle
TT4 Mesurement and busbar earthing cubicle
AD4 RHB - RHC Cubicle with busbar connection from the top
DI4 Fuse switch outgoing cubicle
TT Voltage transformer
TC Current transformer or current sensor
VPIS Voltage Presence Indicating System
LV Low voltage
MV Voltage class 24 kV
SMALT Earthing switch
BB Busbar

Mobile part
SF Withdrawable circuit-breaker with SF6 breaking which is
used in AD4 and CL4 cubicles
ERT Rack-in or rack-out and removal tool of the mobile parts on
the ground
Extraction table Extraction or insertion table without the removal tool of the
mobile parts on the ground

Symbols Operation position.

SMALT operation

Open earthing switch mechanical


indicator.

Close earthing switch mechanical.

07897542EN version 02 
General

Mobile part operation

Operating position.

Racked-in position.

Racked-out position.

Insertion / extraction position.

Recommendations

Height (H) of ceiling for tunnel It is necessary to have a height of ceiling H u 2.80m to install a tunnel.
installation

Installation above the switchboard All type of equipment installation such as lamp or light are forbidden.

Marking It is compulsory forbidden to walk on


the parts bearing this marking.

It is compulsory forbidden to remove


the parts bearing this marking when
the equipment is energised.

 version 02 07897542EN
General

Standard tightening torques

(non greased screws and bolts) Screw Torque in Nm


Application methods:

Ø 6 13 The elastic washers placed on the


external sides of the pads and busbars
Ø 8 28 ensure better distribution of stress
Ø 10 50 regarding bolts tightened to the
recommended torques.
Ø 12 75
Ø 14 120

List of bags and accessories Package Content


Switchboard end and - switchboard end sheets **
fixing parts - tunnels
- cubicle fixing rails (lengh: 2m)
- bag of screws and expansion pins
Cubicle component* - busbar
(bag located inside of - bag of screws
each cubicle)
Standards accessories - operating crank
(bag located inside of - identification front plates
the 1st cubicle of the - civil engineering guide
switchboard) - installation instruction
- using instruction
Mobile part tools - ERT or extraction table

Package Content
(may be supplied)
Spare parts (bag located - fuses, cranks, etc.
inside of the 1st cubicle
of the switchboard)
Optional accessories - earthing truck (independant box)
- phase balance testing device
- mobile part tools: ERT or extraction table
(independant box)

* The VT’s fuses are already fitted inside their compartment in the cubicle.
** With internal arc version, the switchboard end sheets may be mounted
on the cubicles.

07897542EN version 02 
Approximate dimensions
and weights

NAI version

Dimensions
AD4 CL4 + GL4 TT4 RD4 DI4
Width (mm) 900 900 + 900 900
Height (mm) 2325
Depth (mm) 1750 + 40 = 1790

Approximate weights (without LV cables or accessories)


AD4* CL4 + GL4 TT4 RD4 DI4
Weight (kg) 1300 900 + 500 650 750 550

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

 version 02 07897542EN
Approximate dimensions
and weights

NIA version with IPX1


protection

Dimensions
AD4 CL4 + GL4 TT4 RD4 DI4
Width (mm) 900 900 + 900 900
Height (mm) 2732
Depth (mm) 1750 + 91 = 1841

Approximate weights (without LV cables or accessories)


AD4* CL4 + GL4 TT4 RD4 DI4
Weight (kg) 1350 950 + 550 700 800 600

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

07897542EN version 02 
Approximate dimensions
and weights

Internal arc version with


protection on 3 sides
(wall installation)

Dimensions
AD4 CL4 + GL4 TT4 RD4 DI4
Width (mm) 900 900 + 900 900
Height (mm) 2325
Depth (mm) 150 + 1750 + 40 = 1940

Approximate weights (without LV cables or accessories)


AD4* CL4 + GL4 TT4 RD4 DI4
Weight (kg) 1300 900 + 500 650 750 550

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

 version 02 07897542EN
Approximate dimensions
and weights

Internal arc version with protection


on 3 sides, with a ceiling height
between 2.8 and 4 m

Dimensions
AD4 CL4 + GL4 TT4 RD4 DI4
Width (mm) 900 900 + 900 900
Height (mm) 2732
Depth (mm) 150 + 1750 + 40 = 1940

Approximate weights (without LV cables or accessories)


AD4* CL4 + GL4 TT4 RD4 DI4
Weight (kg) 1350 1025 + 625 800 950 700

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

07897542EN version 02 
Approximate dimensions
and weights

Internal arc version with protection


on 3 sides with IPX1 protection

Dimensions
AD4 CL4 + GL4 TT4 RD4 DI4
Width (mm) 900 900 + 900 900
Height (mm) 2732
Depth (mm) 150 + 1750 + 91 = 1991

Approximate weights (without LV cables or accessories)


AD4* CL4 + GL4 TT4 RD4 DI4
Weight (kg) 1350 1025 + 625 800 950 700

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

10 version 02 07897542EN
Approximate dimensions
and weights

Internal arc version with protection


on 4 sides, height under ceiling
lower than 4 meters

Dimensions
AD4 CL4 + GL4 TT4 RD4 DI4
Width (mm) 900 900 + 900 900
Height (mm) 2325
Depth (mm) 1900 + 40 = 1940

Approximate weights (without LV cables or accessories)


AD4* CL4 + GL4 TT4 RD4 DI4
Weight (kg) 1350 1025 + 625 800 950 700

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

07897542EN version 02 11
Approximate dimensions
and weights

Internal arc version with protection


on 4 sides, in substations with a
ceiling height between 2.8 and 4 m

Dimensions
AD4 CL4 + GL4 TT4 RD4 DI4
Width (mm) 900 900 + 900 900
Height (mm) 2732
Depth (mm) 1900 + 40 = 1940

Approximate weights (without LV cables or accessories)


AD4* CL4 + GL4 TT4 RD4 DI4
Weight (kg) 1350 1025 + 625 800 950 700

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

12 version 02 07897542EN
Approximate dimensions
and weights

Internal arc version with protection


on 4 sides in a substation with
a ceiling height of 2.8 to 4 m
with IPX1 protection

Dimensions
AD4 CL4 + GL4 TT4 RD4 DI4
Width (mm) 900 900 + 900 900
Height (mm) 2732
Depth (mm) 1900 + 91 = 1991

Approximate weights (without LV cables or accessories)


AD4* CL4 + GL4 TT4 RD4 DI4
Weight (kg) 1350 1025 + 625 800 950 700

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

07897542EN version 02 13
Approximate dimensions
and weights

AD4 cubicle
(for cubicle entry from above)

Access from the rear is imperative


for this version.
Recommended distance: 800 mm
between the rear of the cubicle
and the wall.
Access to MV cables.

CL4-GL4 cubicles
(with upstream CT)

Access from the rear is imperative


for this version.
Recommended distance: 800 mm
between the rear of the cubicle
and the wall.

Dimensions
AD4 CL4-GL4
Width (mm) 900 900 + 900
Height (mm) 2325 2325
Depth (mm) 2250 + 40 = 2290 2250 + 40 = 2290

Approximate weights (without LV cables or accessories)


AD4* CL4-GL4
Weight (kg) 1400 1100 + 500

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

14 version 02 07897542EN
Handling instructions

Packaging

Standard packaging

The cubicles are shipped simply placed on a pallet


and wrapped in a polyethylene bag.

The cubicles may include or not their


circuit-breaker.

Marine packaging

The cubicles are shipped on a pallet, in a closed crate.

The cubicles may include or not the circuit-breaker.

Do not walk on the top of packaged


cubicles

07897542EN version 02 15
Handling instructions

Handling

Handling using a sling

Use a 900 mm minimum width crosspiece between


rings.

Attach the four slings to the relevant lifting devices.

As soon as the cubicle is lifted, the pallet can be


removed.

Cubicle AD4
(for cubicle entry from above)

Cubicle CL4 with upstream CTs

16 version 02 07897542EN
Handling instructions

Handling on rollers

Before putting the cubicle on


the rollers, remove the pallet.

Storing

Store the devices in their original packaging, placed


on dry ground or on a material insulating it from
moisture.

Prolonged storage After prolonged storage, thoroughly clean insulating parts before operation.

07897542EN version 02 17
Installation and operation
recommendations

The switchgear’s resistance The necessity of correct implementation of connections


New cold retractable or slip-on technology offers ease of installation that favours
to ageing in an MV substation resistance over time.
Their design allows them to used in polluted environments with harsh climatic
depends on 3 main factors conditions.

Impact of the relative humidity factor


Installing a heating device is essential in climates with high relative humidity levels
and major temperature differences.
Ensure that draughts and / or thermal shocks are avoided in all cubicle
compartments in order to avoid the creation of dew points (sources of partial
discharges).
The equipment must be installed in conformity with the relevant IEC standard.
Outside of these normal usage conditions, we recommend contacting Schneider
Electric to determine the operations to be carried out as well as their frequency
according to the actual service conditions.

Ventilation control:
Grid size must be suited to the power dissipated in the substation.
These grids must be placed exclusively in the vicinity of the transformer, in order
to avoid air circulation on the MV switchboard.

Operation and maintenance After 6 to 12 month operations, we recommend you to check the busbars and MV
cable connection tightening.
It should be done with a calibrated torque spanner, adjust to lower torque compare
to values indicated in page 6.
If no problems are detected and if the busbars and cable connections haven’t been
modified, it will not necessary to do again this check. In case of dismantling,
the elastic washers must be change and replace by new ones supplied by
Schneider Electric.

It is strongly advised to periodically carry out (minimum every 2 years


approximately) a few operation cycles on operating devices.
Outside normal conditions of use (between -5°C and 40°C , absence of dust,
corrosive gas, etc.), it is recommended to examine with our Schneider Electric
services centre the steps to be taken, in order to ensure correct functioning of the
installation.

Our service centre is at your disposal at any time:


- to undergo an installation diagnostic,
- to offer you, if need be, suitable maintenance operations,
- to offer you maintenance contracts,
- to offer you adaptations.

18 version 02 07897542EN
Unpacking

Unpacking Standard cubicle

Tools
- Fork or ring spanner n.18 (A1 ou A2).

Cubicles shall be unpacked in close proximity


to the erection site.

Remove the plastic wrapping and lifting the cubicle AD4, RHC – RHB cubicles, CL4 cubicle with upstream CT’s
by the four anchoring devices.

Remove the pallet and lay the cubicle on the floor


(see chapter “Handling instructions”).

Then remove the four anchoring devices

Remove the screws and the relevant cage nuts


except in the case of cubicles provided with end
panels where to put the spacer and the screw without
removing the nut cage side of the end panel.

Remove packings placed inside the cell.

The circuit breakers are delivered in cubicles


in a withdrawn position.

Don’t dismantle any


parts from the cubicle.

07897542EN version 02 19
Floor finishing
and cubicle fastening

Surface condition The floor surface must be level (no bumps) and such that a 2 meters rule placed
on all surfaces and in every direction shows a clearance of no more than 5 mm.

Floor quality For the rolling of mobile part extraction tools without degrading the floor, it must
have a compression withstand u 33 Mpa.

Description of the fixing rails


and accessories
Cubicle fixing

Take the equipment from the civil


engineering package of the
switchboard packaging.

Standard civil engineering: Earthquake resistant civil


- 1 fixing rail A (length 2 m), engineering:
- 4 expansion pins B, - 2 fixing rails A (length 2 m),
- 2 fastening shims C. - 8 expansion pins B,
- 4 fastening shims C.

Placing and adjusting on


standard civil engineering works
Preparation

Drill holes in the floor and the fixing rails.

Tools

Drill. Socket spanner n.13.

Placing the fixing rails

Place and fix the rails to the floor using the supplied
expansion pins, screws and washers.
Cut the last rail to the required length.

20 version 02 07897542EN
Floor finishing
and cubicle fastening

Tightening the fixing rails

Longitudinal adjustment
Using a water level and using shims before tightening
the screws.

For the correct installation of cubicles,


it is advised to comply with a tolerance
of ± 0.1 cm / m and a max gap of ± 0.3 cm
on the length of the switchboard.

07897542EN version 02 21
Floor finishing
and cubicle fastening

Placing and adjusting on


earthquake resistant civil
engineering works
Preparation

Drill holes in the floor and the fixing rails.

Tools

Drill.

Placing the fixing rails


Place and fix the rails to the floor using the supplied
expansion pins, screws and washers.
Cut the last rail the required length.

Tools

Socket spanners n.13.

22 version 02 07897542EN
Floor finishing
and cubicle fastening

Longitudinal adjustment
Using a water level and using shims before tightening
the screws.

The rails must be very smooth,


because adjustment-using actuators
is not possible.

Transversal adjustment.
Using a spirit level and using shims before tightening
the screws.

For the correct installation of cubicles,


it is advised to comply with a tolerance
of ± 0.1 cm / m and a max gap of ± 0.3 cm
on the length of the switchboard.

07897542EN version 02 23
Procedure to draw-out/draw-in
the mobile part

Safety rules for use These tools allow to extract the mobile parts (circuit-breaker, contactor, sectionning
truck).
The ERT allow to leave the mobile part on the floor.
These tools are intended to be used only as an accessory of MCset switchboards.
They shall be used when the cubicles have been laid on the floor.
They shall not be modified.

Extraction and lowering tool

Overall dimensions and weights

Weight
86 kg

A: crank
B: connecting device to the cubicles
C: circuit-breaker supporting rail
D: locating pins for matching to the cubicles
E: wheel brake

The support C rails might be adjusted independently


by an action the lever A one side only.

Without lowering (extraction table)

Overall dimensions and weights

Weight
60 kg

A: connecting device to the cubicles


B: circuit-breaker supporting rail
C: locating pins for matching to the cubicles
D: wheel brake
E: crank for width adjustment
F: screw for height fixing
G: screws for compensation of floor unevenness

For more details:


refer to the device attached manual.

24 version 02 07897542EN
Procedure to draw-out/draw-in
the mobile part

Procedure to draw-out
the mobile part

The mobile part shall be move with


the extraction tools only.
Do note apply effort on the
connection arms.
The extraction of the mobile part shall
be done when the cubicles have been
laid on the floor.

Starting condition Open the access door to the Unplug the connector of LV circuits.
circuit-breaker compartment.
Cubicle with circuit-breaker in disconnected / test
position. At the 1st extraction:
- Remove the strap part (1).
- Remove the block which hold the rod
in upper position (2).

Extraction of the mobile part (procedure


is the same with an ERT or an extraction
table)

Move the extraction tool into position Lock the trolley in position by pushing
in front of the cubicle (take care that and turning the two latching handles in
the locating pins engage with the holes the indicated way.
provided on the cubicle).
After the operation, make sure that
the trolley is locked.

Turn the selector 2 to the position

marked with .Then remove the circuit-

breaker.

Pull it out until it comes against the


stops of trolley.
Lock the wheels by pressing the brake.

During this operation


the circuit-breaker
springs can be tripped
automatically.

07897542EN version 02 25
Procedure to draw-out/draw-in
the mobile part

Return selector to the position . Release the brakes on the trolley


wheels.
Unlock the trolley from the cubicle by
turning the two handles in the indicated Take away the trolley (1).
way.

Closing the MV door

Lower the shutter. To close the door without the circuit-


breaker inside:
- push the hook A to the top,
- push the locking part B in the
indicated position, then let A free.

The locking system will reset


automatically when the circuit-breaker
is inserted.

26 version 02 07897542EN
Procedure to draw-out/draw-in
the mobile part

Leaving the mobile part on the floor


(only with ERT)

Put the circuit-breaker on the ground


by turning the crank (2). Set the selector 2 to position .

Take away the trolley.

07897542EN version 02 27
Procedure to draw-out/draw-in
the mobile part

Procedure to draw-in
the mobile part
Starting conditions

Cubicle: the circuit-breaker compartment door is open.

ERT: the rails of trolley are in the lowered position.

Circuit-breaker: it is on the floor with the selector 2

in the position marked .


ERT
Move the trolley under the circuit-
breaker until it comes against the stop.

Set selector 2 to position . By turning the crank (1), lift the circuit-
breaker up to the insertion level.

Insertion with the ERT or with extraction


table

Approach the trolley with the circuit- Move the trolley into position in front
breaker in front of the cubicle. of the cubicle; take care that
the locating pins engage with the holes
provided on the cubicle.

28 version 02 07897542EN
Procedure to draw-out/draw-in
the mobile part

Lock the trolley in position by pushing Lock the wheels by pressing the brakes.
and turning the two latching handles
(after the operation, make sure that
the trolley is locked).

Set the selector 2 to position . Push the circuit-breaker into the circuit-
breaker compartment until it stops.

Set selector 2 to position . Unlock the trolley from the cubicle by


turning the two handles and then pulling
them out.

Release the brakes on the trolley


wheels.

Remove the trolley.

07897542EN version 02 29
Procedure to draw-out/draw-in
the mobile part

Push and hold the locking device Lift the black shutter located on the back
(A - B). of the door before closing the door.

Plugging-in the connector of LV circuits.
(C).

If the connector is not properly inserted,
the locking device will prevent the door
from being closed.

30 version 02 07897542EN
Procedure to draw-out/draw-in
the mobile part

Procedure to extract the VTs


and opening the MV cable
compartment

For cubicles equipped with


withdrawable VTs
Remove the circuit-breaker, see chapter “Procedure
to draw-out the mobile part”.

Tools Tools
- flat wrench 10 (A). Crank supplied.
- flat wrench 13 (B).
- ratchet wrench 10 (C1).

Close the earthing switch (see chapter Draw-out the VT fuses as per
“Close the earthing switch”). procedures (see chapter
“Withdraw the VT fuses”).
We recommend that you lock it
in this position.

Open the disconnector protecting Loosen the 2 screws using


the VT secondaries placed in the LV the operating crank handle.
compartment.
Open the door leading to the MV cable
connection compartment.

07897542EN version 02 31
Procedure to draw-out/draw-in
the mobile part

Disconnect the VT secondaries LV Unbolt the 5 nuts.


connection connector.

Remove the 2 screws.

Withdraw the closing cross-bar. Extract the VT compartment.

32 version 02 07897542EN
Procedure to draw-out/draw-in
the mobile part

Cubicles equipped with fixed VTs

Tools Tools
- flat wrench 10 (A). Crank supplied.
- flat wrench 13 (B).
- ratchet wrench 10 (D).

Close the earthing switch (see chapter Open the disconnector protecting
“Close the earthing switch”). the VT secondaries placed in the LV
compartment.
We recommend that you lock it
in this position.

Close the earthing switch (see chapter Disconnect the VT secondaries LV


“Close the earthing switch”). connection connector.

Loosen the 2 screws using


the operating crank.

Open the door leading to the MV cable


connection compartment.

07897542EN version 02 33
Procedure to draw-out/draw-in
the mobile part

Disconnect the connection bar of each Remove the 5 nuts.


VT by unscrewing the nut.

Remove the crosspiece. Remove the VT assembly, by running it


on its wheels.

To have an easier access inside


the cubicle, remove the bottom sheet
of the circuit-breaker compartment
and the barriers between phases.

Open the circuit-breaker compartment Remove the barriers between phases


door. following the sequence indicated in
the figure.
Remove the bottom plate of the circuit-
breaker compartment by unscrewing Close again the circuit-breaker’s
the 4 fixing bolts. and VTs’ compartment doors.

34 version 02 07897542EN
Procedure to draw-out/draw-in
the mobile part

Procedure to insert the VT’s


and closing the MV cable
compartment

Cubicle without VTs

Tools Tools
- flat wrench 10 (A). Crank supplied.
- flat wrench 13 (B).
- ratchet wrench 10 (D).

Put in place the barriers between Remount the bottom plate of the circuit-
phases following the sequence breaker compartment and fasten it by
indicated in the figure. means of the 4 bolts provided.

Put the circuit-breaker back into its


compartment (see chapter “Procedure
to draw-in the mobile part”).

Close the door and secure it by means Open the earthing switch (see chapter
of the 2 bolts, to be tightened with the “Open earthing switch”).
operating crank.

07897542EN version 02 35
Procedure to draw-out/draw-in
the mobile part

Cubicle equipped with withdrawable VTs

Tools Tools
- flat wrench 10 (A). Crank supplied.
- flat wrench 13 (B).
- ratchet wrench 10 (D).

Put in place the barriers between Remount the bottom plate of the circuit-
phases following the sequence breaker compartment and fasten it by
indicated in the figure. means of the 4 bolts provided.

Put the circuit-breaker back into its


compartment (see chapter “Procedure
to draw-in the mobile part”).

Replace the VT truck into position. Remount the crosspiece across.

36 version 02 07897542EN
Procedure to draw-out/draw-in
the mobile part

Fit the 5 nuts. Fit the 2 screws.

Racked-in the connector of the VT


secondaries.

Close the door and secure it by means Put the VT fuses in the inserted position
of the 2 bolts, to be tightened with the by following the proper operating
operating crank. sequence (see chapter “Procedure to
insert the VT’s and closing the MV
cable compartment”).

Close the MCCB of the VT secondaries. Open the earthing switch (see chapter
“Opening the earthing switch”).

07897542EN version 02 37
Procedure to draw-out/draw-in
the mobile part

Cubicle equipped with fixed VTs

Tools Tools
- flat wrench 10 (A). Crank supplied.
- flat wrench 13 (B).
- ratchet wrench 10 (D).

Put in place the barriers between Replace the VTs.


phases following the sequence
indicated in the figure. Connect the connection bar of each TV
by screwing the nut.

Remount the bottom plate of the circuit- Remount the crosspiece across.
breaker compartment and fasten it by
means of the 4 bolts provided.

Put the circuit-breaker back into its


compartment (see chapter “Procedure
to draw-in the mobile part”).

38 version 02 07897542EN
Procedure to draw-out/draw-in
the mobile part

Fit the 5 nuts. Fit the 2 screws.

Racked-in the connector of the VT


secondaries.

Close the door and secure it by means Close the MCCB of the VT secondaries.
of the 2 bolts, to be tightened with
the operating crank.

Open the earthing switch (see chapter


“Opening the earthing switch”).

07897542EN version 02 39
Access to the interior
of the cubicles

AD4 - RD4 cubicle

No access from the rear

Access to the rear adjustment bolts through the cable basement or trench.

Additional cable access from the front.

Access to the main busbar.

Access to MV cables, VTs, earthing switch, CT secondaries or toroidal CT, access to the rear adjustment bolts.

Access to the circuit-breaker (AD4).

Access to LV compartment.

Access to the LV terminal boards.

40 version 02 07897542EN
Access to the interior
of the cubicles

CL4 cubicle (bus-section)

No access from the rear

Additional access to lower main busbar from the front.

Access to the main busbar.

Access to VTs, access to lower main busbar, access to the rear adjustment bolts.

Access to the circuit-breaker.

Access to the LV compartment.

Access to the LV terminal boards.

07897542EN version 02 41
Access to the interior
of the cubicles

CL4 cubicle (bus-section)


with upstream CT’s

Access from the rear is


imperative for this version

Additional access to the lower main busbar from the front.

Access to the main bubars.

Access to VT’s and lower main busbar. Access to the rear adjustment bolts.

Access to the circuit-breaker.

Access to the LV compartment.

Access to the LV terminal boards.

Access to the CT’s and to the voltage cable measurment.

42 version 02 07897542EN
Access to the interior
of the cubicles

GL4 cubicle (bus-riser)

No access from the rear

Additional access to lower main busbar from the front.

Access to the main busbar.

Access to the CT secondaries, access to the lower main busbar, access to the rear adjustment bolts.

Access to the LV compartment.

Access to the LV terminal boards.

07897542EN version 02 43
Access to the interior
of the cubicles

TT4 cubicle

No access from the rear

Additional access to the lower main busbar from the front.

Access to the main busbar.

Access to the VTs, earthing switch, access to the lower connections, access to the rear adjustment bolts.

Access to the LV compartment.

Access to the LV terminal boards.

44 version 02 07897542EN
Access to the interior
of the cubicles

DI4 cubicle

No access from the rear

Access to the rear adjustment bolts through the cable basement or trench.

Access to the main busbar (if a single DI4 cubicle is placed side by side to other cubicles, it is easier to get access
from the busbar compartments of the adjacent cubicles).

Access to MV cables, earthing switch, access to the rear adjustment bolts.

Access to the LV compartment.

Access to the LV terminal boards.

07897542EN version 02 45
Access to the interior
of the cubicles

AD4 RHC cubicle


(for cubicle entry from above)

Access from the rear is


imperative for this version.
Access to MV cables.

Access to the rear adjustment bolts through the cable basement or trench.

Additional cables access from the front.

Access to the main busbars.

Access to VT’s, earthing switch and CT’s secondaries. Access to the rear adjustment bolts.

Access to the circuit-breaker.

Access to the LV compartment.

Access to the LV terminal boards.

Access to MV cables.

46 version 02 07897542EN
Installation instructions

Preparation of the cubicle


to the positioning
Cubicle shall be prepared in the erection site.
Operations Cubicle Page
Racking-out of the mobile part AD4, CL4-GL4 23
Racking-out of the VT’s AD4, CL4-GL4, RD4, TT4 29
Removal of the bottom plate of the MV AD4, CL4-GL4, RD4, TT4 30
compartment
Removal of the barriers between phases AD4, CL4-GL4, RD4, TT4 30

Positioning on the cable basement

Note: the positioning can be done by rolling or lifting.

Insert the roller (A) under the cubicle by using a lever.

For cubicles equipped with a tunnel,


it must be installed before placing
the cubicle in position (see chapter
“Assembly tunnel”).

Place the crossing tools across the cable basement.

If the cable basement consists of one uninterrupted


opening on the floor, the use of special crossing tools
is required.

Place the crossing tools across the cable basement,


in the location where the cubicle is to be placed.

Move the cubicle by means of rollers and position


it in front of the crossing tools.

Then push the cubicle in position.


A: rollers
B: crossing tools.

07897542EN version 02 47
Installation instructions

Adjusting cubicles on standard


civil engineering works
The operations described here
after must only be carried out once
the cubicle is positioned on civil
engineering works.

Tool
2 open end spanners n. 18.

Position the support plate E at the Place the 2 quick cage nuts B at the
rear of the cubicle by gaining access rear of the cubicle, by gaining access
through the maintenance space. underneath the cubicle.

Screw the lock nut A on each actuator Lift the rear of the cubicle by screwing
D, place washer C, then screw the the 2 actuators to level the cubicle.
actuators in the quick cage nuts.

Fastening to the floor on


standard civil engineering works
Note:
Remove the front panel (if the cubicle is fitted with VT,
it is first necessary to remove them, see the chapter
“Access to the interior of the cubicles”).

To be retrieved from the bag of screws Place the fastening screws at the front
and bolts. of the cubicle and tighten them.

48 version 02 07897542EN
Installation instructions

Fastening to the floor on


earthquake resistant civil
engineering works

Note:
Remove the front panel (if the cubicle is fitted with VT,
it is first necessary to remove them, see the chapter
“Access to the interior of the cubicles”).

To be retrieved from the bag of screws Place the fastening screws at the rear
and bolts. of the cubicle and tighten them.

To be retrieved from the bag of screws Place the fastening screws at the front
and bolts. of the cubicle and tighten them.

Verify correct positioning


Starting situation

Circuit breaker and VT truck removed from


the cubicle.
Bottom plate of the circuit-breaker compartment
removed from the cubicle.

Tools

- Fork or ring spanner n.10 (A).


- Ratchet spanner n.10 (B1).
- Spirit level.

Remount the sheet steel bottom plate Check that the cubicle is level
of the circuit-breaker compartment. by means of a spirit level.

Fasten the 4 fixing bolts. Check that the doors could open
and close correctly.

Insert the circuit breaker (see


chapter “Procedure to draw-in
the mobile part”).

07897542EN version 02 49
Installation instructions

Assembly tunnel

Cubicle configuration: Internal arc version on 4 sides, incoming from the top.
- internal arc version on 4 sides

See drawing ref. S1A6488002 for this version:


- internal arc version on 4 sides,
incoming from the top,

See drawing ref. S1A6487002 for this version:


- internal arc version on 4 sides,
incoming from the bottom.

See guide “Installation drawing files -


AAA13028EN”.

Internal arc version on 4 sides, incoming from the bottom.

Take out from bolts and screws bag:


- nuts F,
- bolts G,
- washers E.

Tools
- Ratchet spanner n.10 (A).
- Fork or ring spanner n.10 (B).

Take out from the wood crate the panels and the roof.
Fix the panels at the rear, then at the front of the cubicle.
Fix the roof.
Respect the assembly as shown on the diagram.
Tighten the tunnels only at the end of the complete assembly of tunnels.

50 version 02 07897542EN
Installation instructions

Cubicle configuration:
- internal arc version on 4 sides,
- IPX1 protection degree.

The assembly is identical to the page 50 with


the addition a sheet IPX1, see drawing
ref. S1A6488102.

See guide “Installation drawing files -


AAA13028EN”.

Take out from bolts and screws bag:


- nuts F,
- bolts G, Take out from the wood crate the panels and the roof.
- washers E. Fix the panels at the rear, then at the front of the cubicle.
Fix the roof.
Respect the assembly as shown on the diagram.
Tighten the tunnels only at the end of the complete assembly of tunnels.
Tools
- Ratchet spanner n.10 (A).
- Fork or ring spanner n.10 (B).

07897542EN version 02 51
Installation instructions

Cubicle configuration:
- internal arc version on a wall

See drawing ref. S1A6488202 for this version:


- internal arc version on 3 sides.

See guide “Installation drawing files -


AAA13028EN”.

Take out from bolts and screws bag:


- nuts F,
- bolts G,
- washers E. Take out from the wood crate the panels and the roof.
Fix the panel at the front and the plate at the rear of the cubicle.
Fix the roof on the front panel and on the wall.
Respect the assembly as shown on the diagram.
Tools Tighten the tunnels only at the end of the complete assembly of tunnels.
- Ratchet spanner n.10 (A).
- Fork or ring spanner n.10 (B).

52 version 02 07897542EN
Installation instructions

Cubicle configuration:
- NIA,
- IPX1 protection degree.

See drawing ref. S1A6581502 for this version:

- NIA, IPX1, incoming from the top.

See guide “Installation drawing files -


AAA13028EN”.

Take out from bolts and screws bag:


- bolts G, Take out from the wood crate the panels and the roof.
- washers E. Fix the panels at the rear, then at the front of the cubicle.
Fix the roof.
Respect the assembly as shown on the diagram.
Tighten the tunnels only at the end of the complete assembly of tunnels.

Tools
- Ratchet spanner n.10 (A).
- Fork or ring spanner n.10 (B).

07897542EN version 02 53
Installation instructions

Cubicle coupling

Cubicle configuration:
- NIA,
- AD4, CL4-GL4, TT4, DI4, RD4.
For more details, see drawing
ref. 03833104N0.

Take out from bolts and screws bag:


- nuts F and I,
- bolts G and H,
- washers L.

Tools
- 2 ratchet spanners n.13 (A) with the
relevant extension.

In order to put in place the 2nd cubicle, operate as for the 1st cubicle.
Fasten the two cubicles together (9 fixing points).
For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.

54 version 02 07897542EN
Installation instructions

Cubicle configuration:
- NIA,
- incoming from the top,
- AD4.

For more details, see drawing ref. 03833104N0.

Take out from bolts and screws bag:


- nuts F and I,
- bolts G and H,

Tools
- 2 ratchet spanners n.13 (A) with the relevant
extension.
- 2 ratchet spanners n.10 (B).

In order to put in place the 2nd cubicle, operate as for the 1st cubicle.
Fasten the two cubicles together (12 fixing points).
For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.

07897542EN version 02 55
Installation instructions

Cubicle configuration:
- NIA,
- IPX1,
- AD4, CL4-GL4, TT4, DI4, RD4.

For more details, see drawing ref. 03833104N0.

For the tunnels assembly, see page 53.

See guide “Installation drawing files -


AAA13028EN”.

Take out from bolts and screws bag:


- nuts F and I,
- bolts G and H,
- washers L.

Tools
- 2 ratchet spanners n.13 (A) with the relevant
extension.
- 2 ratchet spanners n.10 (B).

In order to put in place the 2nd cubicle, operate as for the 1st cubicle.
Fasten the two cubicles together (12 fixing points).
For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.
Tighten the tunnels only at the end of the complete assembly of tunnels.

56 version 02 07897542EN
Installation instructions

Cubicle configuration:
- internal arc protection on 3 sides,
- AD4, CL4-GL4, TT4, DI4, RD4.

For more details, see drawing ref. 03833105N0.

Take out from bolts and screws bag:


- nuts F ,
- bolts G .

Tools
- 2 ratchet spanners n.13 (A) with the relevant
extension.

In order to put in place the 2nd cubicle, operate as for the 1st cubicle.
Fasten the two cubicles together (9 fixing points).
For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.

07897542EN version 02 57
Installation instructions

Cubicle configuration:
- internal arc protection on 4 sides,
- AD4, CL4-GL4, TT4, DI4, RD4,
- tunnel.

For more details, see drawing ref. 03833105N0.

For the tunnels assembly, see page 50.

See guide “Installation drawing files -


AAA13028EN”.

Internal arc version on 4 sides, incoming from the top.

Take out from bolts and screws bag:


- nuts F and I,
- bolts G and H,
- washers L.

Tools
- 2 ratchet spanners n.13 (A) with the relevant
extension.
- 2 ratchet spanners n.10 (B).

Internal arc version on 4 sides, incoming from the bottom.

In order to put in place the 2nd cubicle, operate as for the 1st cubicle.
Fasten the two cubicles together (27 fixing points).
For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.
Tighten the tunnels only at the end of the complete assembly of tunnels.

58 version 02 07897542EN
Installation instructions

Cubicle configuration:
- internal arc protection on 4 sides,
- incoming from the top,
- AD4.

For more details, see drawing ref. 03833105N0.

Take out from bolts and screws bag:


- nuts F and I,
- bolts G and H.

Tools
- 2 ratchet spanners n.13 (A) with the relevant
extension.
- 2 ratchet spanners n.10 (B). In order to put in place the 2nd cubicle, operate as for the 1st cubicle.
Fasten the two cubicles together (12 fixing points).
For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.

07897542EN version 02 59
Installation instructions

Cubicle configuration:
- internal arc protection on 4 sides,
- IPX1 protection degree,
- AD4, CL4-GL4, TT4, DI4, RD4.

For more details and for the following version,


see drawing ref. 03833105N0:
- internal arc protection 3 sides, tunnel,
- internal arc protection 4 sides,
- internal arc protection 4 sides, tunnel, incoming
from the top.

Tunnel coupling:

Take out from bolts and screws bag:


- nuts F and I,
- bolts G and H,
- washers L.

Tools
- 2 ratchet spanners n.13 (A) with the relevant
extension.
- 2 ratchet spanners n.10 (B).

In order to put in place the 2nd cubicle, operate as for the 1st cubicle.
Fasten the two cubicles together (30 fixing points).
For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.
Tighten the tunnels only at the end of the complete assembly of tunnels.

60 version 02 07897542EN
Installation instructions

Installation extension busbar

Cubicle configuration:
- 1250 A AD4 and RD4,
- Entry busbar from the top.

Take out from bolts and screws bag:


- 3 washers Ø12 HUA12584 (C),
- 3 screws M12x35 21528282 (D),
- 36 plastic rivets 03829823N0.

Tools:
- Allen wrench.

Operating instructions:
- Assemble the extension bars,
- Add the protection covers.

A: 3 insulator supports 03829853N0


B: 3 sheated connection bars HRB82349
C: 3 washers Ø12 HUA12584
D: 3 screws M12x35 21528282
E: 3 sheated bars HRB82345
F: 36 plastic rivets 03829823N0
G: 3 covers junction 03833387N0.

Torque:
- Screws M12x35 21528282 (D): 7.5 daNm.

07897542EN version 02 61
Installation instructions

Cubicle configuration:
- 2500 A AD4 and RD4,
- Entry busbar from the top.

Take out from bolts and screws bag:


- 3 washers Ø12 HUA12584 (C),
- 3 screws M12x70 V1181270 (D),
- 24 plastic rivets 03829823N0.

Tools:
- Allen wrench.

Operating instructions:
- Assemble the extension bars,
- Add the protection covers.

A: 3 insulator supports 03829853N0


B: 6 sheated connection bars HRB82349
C: 3 washers Ø12 HUA12584
D: 3 screws M12x70 V1181270
E: 3 sheated bars HRB82345
F: 3 sheated bars HRB82347
G: 24 plastic rivets 03829823N0
H: 3 covers junction 03833387N0.

Torque:
- Screws M12x70 V1181270 (D): 7.5 daNm.

62 version 02 07897542EN
Installation instructions

Connection of earthing busbar

Take out from bolts and screws bag:


- nuts I,
- bolts H,
- washers E.

Tools For access to the fixing points,


- 2 ratchet spanners n.16 (A) with the relevant see the chapter “Access to the interior
extension. of the cubicles”.
- Ring spanner n.16 (B).
- Torque spanner (C).

Tightening torques 30 Nm.

07897542EN version 02 63
Installation instructions

End panels assembling

Cubicle configuration:
- NIA.

For more details, see drawing ref. 03835598N0.

Take out from bolts and screws bag:


- bolts F-G-H,
- nuts I,
- washers L-M-N.

:G+I+L
:H+I+L

:F+I+L

:G+L
:H+L
:H+I+M+N

Operating instructions:
- Position the profile C and fix them as show.
- Position the panel D and fix them in the upper locations.
- Position the panel E and fix them in the upper locations.
Tools - Finish the fixing of the 2 panels as show.
- 2 ratchet spanners n.10 (A) with the relevant - Apply the adhesive plate B on panel D.
extension.
- Repeat the operation for the right side.

For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.

64 version 02 07897542EN
Installation instructions

Cubicle configuration:
- NIA,
- incoming from the top,
- AD4.

For more details, see drawing ref. 03837100N0.

Take out from bolts and screws bag:


- bolts F-G-H,
- nuts I,
- washers L-M-N.

:G+I+L
:H+I+L

:F+I+L

:G+L
:H+L
:H+I+M+N

Tools
- 2 ratchet spanners n.10 (A) with the relevant
extension.

Operating instructions:
- Position the profile C and fix them as show.
- Position the panel D and fix them in the upper locations.
- Position the panel E and fix them in the upper locations.
- Finish the fixing of the 2 panels as show.
- Position the panel O and fix them as show.
- Apply the adhesive plate B on panel D.

- Repeat the operation for the right side.

For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.

07897542EN version 02 65
Installation instructions

Cubicle configuration:
- Internal arc protection on 3 sides.
For more details, see drawings:
- S1B5688102 : left end plates assembly
- S1B5688202 : right end plates assembly

See guide “Installation drawing files -


AAA13028EN”.

Take out from bolts and screws bag:

A: screw HM6x16
B: screw HM6x16
C: screw HM6x16

D: nut HM6

E: washer Ø 6
F: washer Ø 12

G: rivet TR 6.5x14.1
H: rivet TR 6.5x20.3

I: cage nut M8
J: cage nut M6x9.5

Tools
- 2 ratchet spanners n.10 (B) with the relevant
extension.

Operating instructions:
- Position the 3 profiles L/M/N and fix them,
- Position the cover plate of the busbar O and fix,
- Position the end plate P and fix,
- Position the end plate Q and fix,
- Position the vents holes R and S and fix them.

- Repeat the operation for the right side.

For access to the fixing points, see the chapter


“Access to the interior of the cubicles”.

66 version 02 07897542EN
Installation instructions

Cubicle configuration:
- Internal arc protection on 4 sides.
For more details, see drawings:
- S1B5688102 : left end plates assembly
- S1B5688202 : right end plates assembly
- S1A6487502 : left end panels assembly
- S1A6487702 : right end panels assembly

See guide “Installation drawing files -


AAA13028EN”.

Take out from bolts and screws bag:

A: screw HM6x16
B: screw HM6x16
C: screw HM6x16

D: nut HM6

E: washer Ø 6
F: washer Ø 12

G: rivet TR 6.5x14.1
H: rivet TR 6.5x20.3

I: cage nut M8
J: cage nut M6x9.5

Tools
- 2 ratchet spanners n.10 (B) with the relevant
extension.

Operating instructions:
- Position the 3 profiles L/M/N and fix them,
- Position the cover plate of the busbar O and fix,
- Position the end plate P and fix,
- Position the end plate Q and fix,
- Position the vents holes R and S and fix them.
- Position the cover plate of the tunnel T and fix.

- Repeat the operation for the right side.

For access to the fixing points, see the chapter


“Access to the interior of the cubicles”.

07897542EN version 02 67
Installation instructions

Cubicle configuration:
- internal arc protection on 4 sides
- incoming from the top.
For more details, see drawings:
- S1B5688102 : left end plates assembly
- S1B5688202 : right end plates assembly
- S1A6487802 : assembly of the finition rear panels
incoming from the top.

See guide “Installation drawing files -


AAA13028EN”.

Take out from bolts and screws bag:

A: screw HM6x16
B: screw HM6x16
C: screw HM6x16
K: screw HM6x20

D: nut HM6

E: washer Ø 6
F: washer Ø 12

G: rivet TR 6.5x14.1
H: rivet TR 6.5x20.3

I: cage nut M8
J: cage nut M6x9.5

Tools
- 2 ratchet spanners n.10 (B) with the relevant
extension for one.

Operating instructions:
- Position the 3 profiles L/M/N and fix them,
- Position the cover plate of the busbar O and fix,
- Position the end plate P and fix,
- Position the end plate Q and fix,
- Position the vents holes R and S and fix them.
- Position the cover plate of the tunnel U and fix.

- Repeat the operation for the right side.

For access to the fixing points, see the chapter


“Access to the interior of the cubicles”.

68 version 02 07897542EN
Installation instructions

Fitting the main busbars

For more details, see drawing ref. 03835661N0.

For access to busbars, see the chapter


“Access to the interior of the cubicles”.

Tools
- Fork or ring spanner n. 18 (A).
- 2 ring spanners n.18 (B1) or ratchet spanners n.18
(B2).
- torque spanner (C).

Cubicle type Cubicle type CL4 and GL4


AD4-CL4-GL4-TT4-RD4 and DI4.

Fit the main busbars between This procedure shall be repeated


the 2 cubicles. for any cubicle added to the
switchboard.
Insert the bolts and tighten them
(to be recommended tightening value).

1 : self-locking nut
2 : nut
3 : washer
4 : screw

07897542EN version 02 69
Installation instructions

1250 A main busbars Main busbars – top view

630 and 1250 A tee-connections

Lower main busbars – top view (CL4-GL4)

70 version 02 07897542EN
Installation instructions

2000 / 2500 A main busbars

630 / 1250 A tee-connections Main busbars – top view

2000 / 2500 A tee-connections Lower main busbars – top view

2000 / 2500 A tee-connections Lower main busbars – top view (CL4-GL4)

07897542EN version 02 71
Installation instructions

Fitting joint covers

For more details, see drawing Tool


ref. 03835661N0. - Stanley knife.

Choosing proper joint covers


Choose the proper joint cover type according to the
needs of each cubicle of the switchboard as shown in
the following drawing.
Tools
in any middle position

in any middle position

in any middle position

in any middle position


outgoing y 630A

outgoing y 630A

outgoing y 630A

outgoing y 630A

outgoing y 630A

outgoing y 630A
right side end

right side end

right side end

right side end

left end panel

left side end

left side end

left side end


cubicle AD4

cubicle AD4

cubicle AD4

cubicle AD4

cubicle AD4
cubicle CL4
cubicle TT4

cubicle TT4

cubicle TT4
cubicle DI4

cubicle DI4

cubicle DI4
y 630A

y 630A

y 630A
or

or

or

or

or

or
right side end panel left side end panel

Cutting joint covers

Cut the joint covers as shown in the drawings in this


page and in the following one.

03833376N0 1st cut 2nd cut 3rd cut


4 cut
th
1 cut
st

3rd cut 2nd cut

right end right end left end

4th cut 1st + 4th cut 2nd + 3rd cut

right end intermediate intermediate

72 version 02 07897542EN
Installation instructions

1st cut 2nd cut 3rd cut


4th cut 1st cut

3rd cut 2nd cut

right end right end left end


5th cut

4th cut 1st + 4th cut 2nd + 3rd cut

right end intermediate intermediate

2nd + 5th cut 2nd + 3rd + 5th cut

right end left end intermediate

1st cut 2nd cut 1st + 2nd cut

1st cut 2nd cut

right end right end intermediate

without cut 1st + 3rd cut 2nd + 4th cut


1st cut 2nd cut

3rd cut 4th cut

07897542EN version 02 73
Installation instructions

Positioning the joint covers

Clip

Open the joint cover and put it into position on the busbar joint (for the joint covers
of the 2500 A busbars, to put screws + washers + nuts nylon to close them).

Close it and fix by using the proper pins.

Closing the MV cable compartment.

Replace the VT truck into position (see the chapter “Procedure to insert the VT’s
and closing the MV cable compartment”).

74 version 02 07897542EN
Connection of the LV cables

LV cables routing

Entry from the bottom.


Entry from the bottom in every single cubicle.

LV cables shall be run to the LV compartment inside


the vertical duct on the right end side provided for
every single cubicle.

To install the LV cables in the vertical duct, you should


extract the circuit breaker and the VT’s
(see the chapters “Procedure to draw-out Maximum entry section available for LV
the mobile part” and “Procedure to extract the VTs cables.
and opening the MV cable compartment”).

Entry from the top.

Tools

- Socket spanners n.10.

- Drill.

Remove the 2 fixing bolts (1) of the LV


entry steel sheet.

Make a hole in the sheet according


to the number and type of cables.

Install the grommets (not supply)


on the sheet and insert the cables.

Remount the metal sheet for LV cables.

07897542EN version 02 75
Connection of the LV cables

LV cables connections

Tools
- Socket spanners n.10.

To reach the terminal blocks of the LV cables, take off the top front sheet metal
(remove the 6 fixing bolts).

Connect the cables to the terminal blocks according to the schematic diagrams.

Closing the top entry LV cable


steel sheet

To keep the panel protection degree between 2 cubicles, the top entry LV cable
sheet must be install:
- on the right for all cubicles,
- on the left on the cubicle positioned at the right side end of the switchboard.

To make an easier installation, the fixing holes are oblong.

76 version 02 07897542EN
Earthing circuit equipotential
connection and MV cable earthing

Starting conditions If the MV cables have not been connected at the erection of the switchboard,
in order to get access to the connecting terminals, it is necessary to carry out
the following operations:
- Remove circuit-breakers and VTs (both fixed and withdrawable versions)
(see the chapter “Procedure to draw-out the mobile part”).
- Remove barriers between phases and the bottom plates of the circuit-breaker
compartment (see the chapter “Procedure to extract the VTs and opening
the MV cable compartment”).

Equipotential connection
of the switchboard’s earth
to the substation earth

After connecting the earth links between cubicles,


the earth circuit shall be bonded to the substation
earth.
To that purpose, the earth conductor is provided
with holes suitable for M10 bolted connections.
The link to the substation earth can be ran through
an unused cable grommet.

Tools
- Ratchet spanner n.16 (A1).
- Fork or ring spanner n.16 (B).

07897542EN version 02 77
Earthing circuit equipotential
connection and MV cable earthing

Connection of MV cables

General

Remove the bottom metal plates Cut the cable grommets according
in the cable compartment. to the number and diameter of cables.

In order to terminate the MV cables, see the relevant


manufacturer’s instructions.

Fit them to the cables.

One single core or


three-core cable per phase
The instructions refer to one phase;
repeat the procedure for the other two.

Tools
- 2 fork or ring spanners n.18 (A).
- Torque spanner (B).

Bolt the cable lugs to the proper


connecting terminal, using
the grommets the closest to
the rear (tightening torque 50 Nm).

78 version 02 07897542EN
Earthing circuit equipotential
connection and MV cable earthing

One to four single core cables


per phase
The instructions refer to one phase;
repeat the procedure for the others.

Tools
- Fork or ring spanner n.13 (A).
- 2 fork or ring spanners n.18 (B).
- Torque spanner (C).

Bolt the cable lug to the proper Example of terminals (suggested by


connecting terminal. Schneider Electric) compatible for cable
630 mm²:
Insert the cable one by one starting -Raychem - type TMPP,
from the one closest to the rear. -Pirelli - type STI-GT,
-F&G - type Typ AV 20 E.
Tighten to 50 Nm.
Cable-terminals:
-Cembre - series A-M.

Three-core cable per phase

In order to terminate the cables, see the relevant


manufacturer’s instructions.

Cut the cable grommets according Run the three-core cable through
to the number and diameter of cables. the toroidal CT (if requested).

07897542EN version 02 79
Earthing circuit equipotential
connection and MV cable earthing

Anchoring supports for MV cables

The operation is the same for all types of cables.

Take off from the cubicle components package:


the metal bottom plates, the cable anchoring supports,
the crosspiece to fix the anchoring supports,
the screws bag.

Tools
- Fork or ring spanner n.13.

For access to the cable compartment (see the chapter


“Access to the interior of the cubicles”).

Take care to not hurt the cable isolating Fit the crosspiece on the bottom plate
when you clamp the anchoring support. (1 bolt – nuts assembling).

Fit the metal bottom plates. Fit the anchoring supports on the cable
according the picture above for 3 single
Unused holes shall be closed with cable core cables.
grommets (not cut).

1: fixing point for the crosspiece.

Fit the anchoring supports on the cable


according the picture above for 1 three-
core cables.

80 version 02 07897542EN
Earthing circuit equipotential
connection and MV cable earthing

Earthing of MV cable shields Rear Rear

The earth braids or wires shall be connected


to the principal earth conductor to the back provided
in each cable compartment.

In the presence of toroidal CTs, take care to run


the earthing connection through the CT before fixing it.
Example: one cable per phase, 3 braids or wires to
connect.

Front Front

Example: one cable per phase, 3 braids Two cables per phase, 6 braids or wires
or wires to connect. to connect.

Earthing of MV cable shields (DI4)

The earth braid shall be connected to the earth bar on


the rear of the switchboard.

07897542EN version 02 81
Earthing circuit equipotential
connection and MV cable earthing

Final operations

VT truck replacing For a description of VT truck replacing, see the chapter “Procedure to insert
the VT’s and to close the MV cable compartment”.

Insertion of circuit-breaker For a description of insertion of circuit-breaker, see the chapter


“Procedure to draw-in the mobile part”.

82 version 02 07897542EN
Fitting fuses in DI4 cubicle

Install FUSARC type fuses with medium


type strikes according to IEC 32 - 3IEC
282-1 and DIN 43-625.

To select fuses, consult the catalog reserved for them.

For different types of fuse, please contact


Schneider Electric.

The striker end of the fuse is marked. The fuse characteristics and direction
of mounting are printed on the fuse.

Turn the fuse so that the label is in front


(striker at the top end).

Start status

Open the MV compartment.

Insert in first the fuse of the farthest phase.

Checking the condition of the fuses


before assembling them.

Insert the bottom of the fuse all the way Fit the upper part of the fuse do not
into the lower annular contact. forget to draw by hand the upper field
repartitor (A).

When changing a fuse,


change all 3 fuses.

Do not re-used fuses that have already


been used.

Verify the correct mounting of the upper Turn the fuse so that the label appears
field repartitor (A). (B) in front.

07897542EN version 02 83
Tests on site

Voltage test on the main circuits After erection, the equipment shall be CTs secondaries shall be short-circuited
tested in order to check the correct at the LV terminal boards
installation. (if the auxiliary circuits are open).
The power-frequency test voltage The leads from the testing equipment
shall be 80% of the rated test value shall be connected to the MV cable lugs
(40kV rms), because the cubicles of a cubicle.
have already been tested in Schneider This requires the opening of a lower
Electric factory at 100% of the voltage door during the test for passing
rated value) and shall be applied to the above-mentioned leads.
each phase conductor of the main During the voltage tests, all the cubicle
circuit for 1 minute earthing the other shall be fitted with the relevant
two phase conductors. circuit-breakers.
The circuit-breakers shall be plugged
in service position and closed.
The test configuration
requires some locks to Since hand closing is not permitted
defraud. These operations with closed doors, a special procedure
should be performed only is required (see below) when auxiliary
by specialists. power supply is not available.
It is imperative to follow Obviously, the MV cables shall be
the procedures described disconnected and the earthing switch
below. shall be opened.
Voltage transformers
should be disconnected.
In the presence of
lightning, the latter must
be disconnected during
the test voltage frequency,
to avoid serious damage.

NB: In cubicles equipped with VTs


withdrawable fuse version, disconnect
the fuses. In cubicles equipped with
fixed VTs, disconnect the VTs power
supply primary circuit.

How to prepare the cubicles

Operations to be carried out on cubicles For a complete description of the


following operations, please consult
not directly connected to the testing the SF circuit-breaker instruction for use
equipment handbook.
- Circuit-breaker in disconnected
position and the compartment door
open.
- Lift the locking rod A located on the
top of the circuit-breaker mechanism.
- Insert spacer U to keep the rod in
raised position.
- Push the circuit-breaker to the service
position and remove spacer U.
- Charge the closing spring of the
circuit-breaker and close it by pressing
pushbutton “ I ”.

84 version 02 07897542EN
Tests on site

Operations to be carried out


on the cubicle to be connected
to the testing equipment

Starting conditions
The circuit-breaker is in disconnected position,
or in test / disconnected position or removed
from the cubicle.

Remove the possible keys or padlocks preventing


the operation of the earthing switch.

Verify that the voltage indicating lamps are off.

Withdraw the VT fuses

Starting conditions Set selector 6 to .


Selector 6 in position This operation requires first to pull
outward the selector and then to turn it.

This operation turns off the CT’s


secondaries.

Insert the crank into hole 7 and turn Set selector 6 to withdrawn
counter clockwise until further rotation position .
becomes impossible.

The symbols marked on the blue front


cover of the circuit-breaker summarise
the above-mentioned procedure.

07897542EN version 02 85
Tests on site

Close the earthing switch

Push the pushbutton of the earthing Set selector 4 to .


switch electromechanical lock. If the
cubicle is not equipped with this option,
go directly to the following sequence. This operation requires first to pull
outward the selector and then to turn it.

Insert the crank into hole 5 and turn Turn selector 4 clockwise to position I.
it clockwise until the earthing switch
position indicator reads “on”.

The earthing switch is in closed The symbols marked on the yellow front
position. The MV cables are short- cover summarise the above-mentioned
circuited and earthed. procedure.
The selector in this position prevents For more protection, it is possible
the insertion of the circuit-breaker. to prevent the insertion of the circuit-
breaker by setting the selector P
as shown in the following drawing.

86 version 02 07897542EN
Tests on site

Prevent the insertion


of the circuit-breaker
Open the VT compartment door

Push the pushbutton of the earthing


switch electromechanical lock. If the Set selector P to .
cubicle is not equipped with this option,
go directly to the following sequence.

Remove the 2 screws indicated in


the figure and open the lower door. The operation described
is allowed only for
Make ineffective the interlock testing configuration.
preventing the opening of the earthing This operation,
switch with open door by entering the performed when the
slot indicated with a screwdriver and switchboard is in
pushing it downwards. service, is extremely
This allows to introduce the operating dangerous because
handle into the hole 5 and the earthing it makes the operator
switch open. reach the live parts.

07897542EN version 02 87
Tests on site

Open the earthing switch

Push the pushbutton of the earthing Set selector 4 to .


switch electromechanical lock. If the
cubicle is not equipped with this option, This operation requires first to pull
go directly to the following sequence.
outward the selector and then to turn it.

Insert the crank into hole 5 and turn Set selector 4 to position “O”.
its counter clockwise until the earthing
switch position indicator reads “off”.

The earthing switch is in open position. The symbols marked on the yellow front
cover summarise the above-mentioned
procedure.

88 version 02 07897542EN
Tests on site

Restore the possibility


of circuit-breaker insertion

Push the pushbutton of the earthing Set selector P in horizontal position


switch electromechanical lock. If the
cubicle is not equipped with this option,
go directly to the following sequence.

With the circuit-breaker in disconnected Connect the leads from the testing
position and the compartment door equipment to the MV cable lugs.
open, lift the locking rod A located
on the top of the circuit-breaker
mechanism.Insert spacer U to keep
the rod in raised position.

Push the circuit-breaker to the service


position and remove spacer U.

Charge the closing spring of the


circuit-breaker and close it by pressing
pushbutton “ I ”.

After performing the test Move the circuit-breaker to the disconnected position.
Close the earthing switch.
Disconnect the test equipment.

In the presence of a VT truck, reinstall him:

- Remount the panel and fixing it by tightening the two screws.


- Open the earthing switch.
- Plug-in the VT fuses.

07897542EN version 02 89
Index

A
AD4 cubicle (for cubicle entry from above) 14
AD4 - RD4 cubicle 40
AD4 RHC cubicle (for cubicle entry from above) 46
Adjusting cubicles on standard civil engineering works 48
After performing the test 89
Anchoring supports for MV cables 80
Assembly tunnel 50

B
1250 A main busbars 70
2000 / 2500 A main busbars 71

C
CL4 cubicle (bus-section) 41
CL4 cubicle (bus-section) with upstream CT’s 42
CL4-GL4 cubicles (with upstream CT) 14
Close the earthing switch 86
Closing the top entry LV cable steel sheet 76
Connection of earthing busbar 63
Connection of MV cables 78
Cubicle coupling 54

D
Description of the fixing rails and accessories 20
DI4 cubicle 45

E
Earthing of MV cable shields 81
Earthing of MV cable shields (DI4) 91
End panels assembling 64
Equipotential connection of the switchboard’s earth
to the substation earth 77
Extraction and lowering tool 24

F
Fastening to the floor on standard civil engineering works 48
Fastening to the floor on earthquake resistant civil engineering works 49
Final operations 82
Fitting joint covers 72
Fitting the main busbars 69
Floor quality 20

G
Glossary 3
GL4 cubicle (bus-riser) 43
CL4-GL4 cubicles (with upstream CT) 14

H
Handling 16
How to prepare the cubicles 84

I
Installation extension busbar 61
Internal arc version with protection on 3 sides 8
Internal arc version with protection on 3 sides, with a ceiling
height between 2.8 and 4 m 9
Internal arc version with protection on 3 sides
with IPX1 protection cubicle 10
Internal arc version with protection on 4 sides,
height under ceiling lower than 4 m 11

90 version 02 07897542EN
Index

I
Internal arc version with protection on 4 sides, in substations
with a ceiling height between 2.8 and 4 m 12
Internal arc version with protection on 4 sides in a substation
with a ceiling height of 2.8 to 4 m with IPX1 protection cubicle 13

L
List of bags and accessories 5
LV cables connections 76
LV cables routing 75

N
NIA version 6
NIA version with IPX1 protection cubicle 7

O
One single core or three-core cable per phase 78
One to four single core cables per phase 79
Open the earthing switch 88
Operation and maintenance 18
Operations to be carried out on the cubicle to be connected
to the testing equipment 85

P
Packaging 15
Placing and adjusting on standard civil engineering works 20
Placing and adjusting on earthquake resistant civil
engineering works 22
Positioning the joint covers 74
Preparation of the cubicle to the positioning 47
Prevent the insertion of the circuit-breaker 87
Procedure to draw-out the mobile part 25
Procedure to draw-in the mobile part 28
Procedure to extract the VTs and opening the MV cable compartment 31
Procedure to insert the VT’s and closing the MV cable compartment 35

R
Recommendations 4
Restore the possibility of circuit-breaker insertion 89

S
Safety rules for use 24
Standard tightening torques 5
Starting conditions 77
Storing 17
Surface condition 20
Symbols 3

T
The switchgear’s resistance to ageing in an MV substation 18
Three-core cable per phase 79
TT4 cubicle 44

V
Verify correct positioning 49
Voltage test on the main circuits 84

W
Withdraw the VT fuses 85
Without lowering (extraction table) 24

07897542EN version 02 91
Schneider Electric group service centers are there to provide:
- engineering and technical assistance,
- commissioning,
- training,
- preventive and corrective maintenance,
- adaptation work,
- spare parts.

Call your sales representative who will put you in touch with your nearest
Schneider Electric group service center or directly call the following telephone
number: +33 (0)4 76 57 60 60 Grenoble France.

07897542EN - REV. 02 a Schneider Electric Industries SAS – All rights reserved.

Schneider Electric Industries S.A.S As standards, specifications and designs change from time to time, please ask for confirmation
Head Office of the information given in this publication.
35 rue Joseph Monier
CS 30323 This document has been printed
92506 Rueil-Malmaison on ecological paper.
www.schneider-electric.com
Publishing: Schneider Electric Industries SAS.
Design: Profil.
Printing:

07897542EN - REV. 02 11/2012