MCset 4 - 24 kV
Withdrawable switchgear SF6
circuit-breaker
Installation instruction
November 2012
Content
General 3
Glossary 3
Symbols 3
Recommendations 4
Standard tightening torques 5
List of bags and accessories 5
Handling instructions 15
Packaging 15
Handling 16
Storing 17
Unpacking 19
07897542EN version 02
Content
Installation instructions 47
Preparation of the cubicle to the positioning 47
Adjusting cubicles on standard civil engineering works 48
Fastening to the floor on standard civil engineering works 48
Fastening to the floor on earthquake resistant civil engineering works 49
Verify correct positioning 49
Assembly tunnel 50
Cubicle coupling 54
Installation extension busbar 61
Connection of earthing busbar 63
End panels assembling 64
Fitting the main busbars 69
1250 A main busbars 70
2000 / 2500 A main busbars 71
Fitting joint covers 72
Positioning the joint covers 74
Tests on site 84
Voltage test on the main circuits 84
How to prepare the cubicles 84
Operations to be carried out on the cubicle to be connected
to the testing equipment 85
Withdraw the VT fuses 85
Close the earthing switch 86
Prevent the insertion of the circuit-breaker 87
Open the earthing switch 88
Restore the possibility of circuit-breaker insertion 89
After performing the test 89
Index 90
version 02 07897542EN
General
Mobile part
SF Withdrawable circuit-breaker with SF6 breaking which is
used in AD4 and CL4 cubicles
ERT Rack-in or rack-out and removal tool of the mobile parts on
the ground
Extraction table Extraction or insertion table without the removal tool of the
mobile parts on the ground
SMALT operation
07897542EN version 02
General
Operating position.
Racked-in position.
Racked-out position.
Insertion / extraction position.
Recommendations
Height (H) of ceiling for tunnel It is necessary to have a height of ceiling H u 2.80m to install a tunnel.
installation
Installation above the switchboard All type of equipment installation such as lamp or light are forbidden.
version 02 07897542EN
General
Package Content
(may be supplied)
Spare parts (bag located - fuses, cranks, etc.
inside of the 1st cubicle
of the switchboard)
Optional accessories - earthing truck (independant box)
- phase balance testing device
- mobile part tools: ERT or extraction table
(independant box)
* The VT’s fuses are already fitted inside their compartment in the cubicle.
** With internal arc version, the switchboard end sheets may be mounted
on the cubicles.
07897542EN version 02
Approximate dimensions
and weights
NAI version
Dimensions
AD4 CL4 + GL4 TT4 RD4 DI4
Width (mm) 900 900 + 900 900
Height (mm) 2325
Depth (mm) 1750 + 40 = 1790
version 02 07897542EN
Approximate dimensions
and weights
Dimensions
AD4 CL4 + GL4 TT4 RD4 DI4
Width (mm) 900 900 + 900 900
Height (mm) 2732
Depth (mm) 1750 + 91 = 1841
07897542EN version 02
Approximate dimensions
and weights
Dimensions
AD4 CL4 + GL4 TT4 RD4 DI4
Width (mm) 900 900 + 900 900
Height (mm) 2325
Depth (mm) 150 + 1750 + 40 = 1940
version 02 07897542EN
Approximate dimensions
and weights
Dimensions
AD4 CL4 + GL4 TT4 RD4 DI4
Width (mm) 900 900 + 900 900
Height (mm) 2732
Depth (mm) 150 + 1750 + 40 = 1940
07897542EN version 02
Approximate dimensions
and weights
Dimensions
AD4 CL4 + GL4 TT4 RD4 DI4
Width (mm) 900 900 + 900 900
Height (mm) 2732
Depth (mm) 150 + 1750 + 91 = 1991
10 version 02 07897542EN
Approximate dimensions
and weights
Dimensions
AD4 CL4 + GL4 TT4 RD4 DI4
Width (mm) 900 900 + 900 900
Height (mm) 2325
Depth (mm) 1900 + 40 = 1940
07897542EN version 02 11
Approximate dimensions
and weights
Dimensions
AD4 CL4 + GL4 TT4 RD4 DI4
Width (mm) 900 900 + 900 900
Height (mm) 2732
Depth (mm) 1900 + 40 = 1940
12 version 02 07897542EN
Approximate dimensions
and weights
Dimensions
AD4 CL4 + GL4 TT4 RD4 DI4
Width (mm) 900 900 + 900 900
Height (mm) 2732
Depth (mm) 1900 + 91 = 1991
07897542EN version 02 13
Approximate dimensions
and weights
AD4 cubicle
(for cubicle entry from above)
CL4-GL4 cubicles
(with upstream CT)
Dimensions
AD4 CL4-GL4
Width (mm) 900 900 + 900
Height (mm) 2325 2325
Depth (mm) 2250 + 40 = 2290 2250 + 40 = 2290
14 version 02 07897542EN
Handling instructions
Packaging
Standard packaging
Marine packaging
07897542EN version 02 15
Handling instructions
Handling
Cubicle AD4
(for cubicle entry from above)
16 version 02 07897542EN
Handling instructions
Handling on rollers
Storing
Prolonged storage After prolonged storage, thoroughly clean insulating parts before operation.
07897542EN version 02 17
Installation and operation
recommendations
Ventilation control:
Grid size must be suited to the power dissipated in the substation.
These grids must be placed exclusively in the vicinity of the transformer, in order
to avoid air circulation on the MV switchboard.
Operation and maintenance After 6 to 12 month operations, we recommend you to check the busbars and MV
cable connection tightening.
It should be done with a calibrated torque spanner, adjust to lower torque compare
to values indicated in page 6.
If no problems are detected and if the busbars and cable connections haven’t been
modified, it will not necessary to do again this check. In case of dismantling,
the elastic washers must be change and replace by new ones supplied by
Schneider Electric.
18 version 02 07897542EN
Unpacking
Tools
- Fork or ring spanner n.18 (A1 ou A2).
Remove the plastic wrapping and lifting the cubicle AD4, RHC – RHB cubicles, CL4 cubicle with upstream CT’s
by the four anchoring devices.
07897542EN version 02 19
Floor finishing
and cubicle fastening
Surface condition The floor surface must be level (no bumps) and such that a 2 meters rule placed
on all surfaces and in every direction shows a clearance of no more than 5 mm.
Floor quality For the rolling of mobile part extraction tools without degrading the floor, it must
have a compression withstand u 33 Mpa.
Tools
Place and fix the rails to the floor using the supplied
expansion pins, screws and washers.
Cut the last rail to the required length.
20 version 02 07897542EN
Floor finishing
and cubicle fastening
Longitudinal adjustment
Using a water level and using shims before tightening
the screws.
07897542EN version 02 21
Floor finishing
and cubicle fastening
Tools
Drill.
Tools
22 version 02 07897542EN
Floor finishing
and cubicle fastening
Longitudinal adjustment
Using a water level and using shims before tightening
the screws.
Transversal adjustment.
Using a spirit level and using shims before tightening
the screws.
07897542EN version 02 23
Procedure to draw-out/draw-in
the mobile part
Safety rules for use These tools allow to extract the mobile parts (circuit-breaker, contactor, sectionning
truck).
The ERT allow to leave the mobile part on the floor.
These tools are intended to be used only as an accessory of MCset switchboards.
They shall be used when the cubicles have been laid on the floor.
They shall not be modified.
Weight
86 kg
A: crank
B: connecting device to the cubicles
C: circuit-breaker supporting rail
D: locating pins for matching to the cubicles
E: wheel brake
Weight
60 kg
24 version 02 07897542EN
Procedure to draw-out/draw-in
the mobile part
Procedure to draw-out
the mobile part
Starting condition Open the access door to the Unplug the connector of LV circuits.
circuit-breaker compartment.
Cubicle with circuit-breaker in disconnected / test
position. At the 1st extraction:
- Remove the strap part (1).
- Remove the block which hold the rod
in upper position (2).
Move the extraction tool into position Lock the trolley in position by pushing
in front of the cubicle (take care that and turning the two latching handles in
the locating pins engage with the holes the indicated way.
provided on the cubicle).
After the operation, make sure that
the trolley is locked.
breaker.
07897542EN version 02 25
Procedure to draw-out/draw-in
the mobile part
26 version 02 07897542EN
Procedure to draw-out/draw-in
the mobile part
07897542EN version 02 27
Procedure to draw-out/draw-in
the mobile part
Procedure to draw-in
the mobile part
Starting conditions
Set selector 2 to position . By turning the crank (1), lift the circuit-
breaker up to the insertion level.
Approach the trolley with the circuit- Move the trolley into position in front
breaker in front of the cubicle. of the cubicle; take care that
the locating pins engage with the holes
provided on the cubicle.
28 version 02 07897542EN
Procedure to draw-out/draw-in
the mobile part
Lock the trolley in position by pushing Lock the wheels by pressing the brakes.
and turning the two latching handles
(after the operation, make sure that
the trolley is locked).
Set the selector 2 to position . Push the circuit-breaker into the circuit-
breaker compartment until it stops.
07897542EN version 02 29
Procedure to draw-out/draw-in
the mobile part
Push and hold the locking device Lift the black shutter located on the back
(A - B). of the door before closing the door.
Plugging-in the connector of LV circuits.
(C).
If the connector is not properly inserted,
the locking device will prevent the door
from being closed.
30 version 02 07897542EN
Procedure to draw-out/draw-in
the mobile part
Tools Tools
- flat wrench 10 (A). Crank supplied.
- flat wrench 13 (B).
- ratchet wrench 10 (C1).
Close the earthing switch (see chapter Draw-out the VT fuses as per
“Close the earthing switch”). procedures (see chapter
“Withdraw the VT fuses”).
We recommend that you lock it
in this position.
07897542EN version 02 31
Procedure to draw-out/draw-in
the mobile part
32 version 02 07897542EN
Procedure to draw-out/draw-in
the mobile part
Tools Tools
- flat wrench 10 (A). Crank supplied.
- flat wrench 13 (B).
- ratchet wrench 10 (D).
Close the earthing switch (see chapter Open the disconnector protecting
“Close the earthing switch”). the VT secondaries placed in the LV
compartment.
We recommend that you lock it
in this position.
07897542EN version 02 33
Procedure to draw-out/draw-in
the mobile part
34 version 02 07897542EN
Procedure to draw-out/draw-in
the mobile part
Tools Tools
- flat wrench 10 (A). Crank supplied.
- flat wrench 13 (B).
- ratchet wrench 10 (D).
Put in place the barriers between Remount the bottom plate of the circuit-
phases following the sequence breaker compartment and fasten it by
indicated in the figure. means of the 4 bolts provided.
Close the door and secure it by means Open the earthing switch (see chapter
of the 2 bolts, to be tightened with the “Open earthing switch”).
operating crank.
07897542EN version 02 35
Procedure to draw-out/draw-in
the mobile part
Tools Tools
- flat wrench 10 (A). Crank supplied.
- flat wrench 13 (B).
- ratchet wrench 10 (D).
Put in place the barriers between Remount the bottom plate of the circuit-
phases following the sequence breaker compartment and fasten it by
indicated in the figure. means of the 4 bolts provided.
36 version 02 07897542EN
Procedure to draw-out/draw-in
the mobile part
Close the door and secure it by means Put the VT fuses in the inserted position
of the 2 bolts, to be tightened with the by following the proper operating
operating crank. sequence (see chapter “Procedure to
insert the VT’s and closing the MV
cable compartment”).
Close the MCCB of the VT secondaries. Open the earthing switch (see chapter
“Opening the earthing switch”).
07897542EN version 02 37
Procedure to draw-out/draw-in
the mobile part
Tools Tools
- flat wrench 10 (A). Crank supplied.
- flat wrench 13 (B).
- ratchet wrench 10 (D).
Remount the bottom plate of the circuit- Remount the crosspiece across.
breaker compartment and fasten it by
means of the 4 bolts provided.
38 version 02 07897542EN
Procedure to draw-out/draw-in
the mobile part
Close the door and secure it by means Close the MCCB of the VT secondaries.
of the 2 bolts, to be tightened with
the operating crank.
07897542EN version 02 39
Access to the interior
of the cubicles
Access to the rear adjustment bolts through the cable basement or trench.
Access to MV cables, VTs, earthing switch, CT secondaries or toroidal CT, access to the rear adjustment bolts.
Access to LV compartment.
40 version 02 07897542EN
Access to the interior
of the cubicles
Access to VTs, access to lower main busbar, access to the rear adjustment bolts.
07897542EN version 02 41
Access to the interior
of the cubicles
Access to VT’s and lower main busbar. Access to the rear adjustment bolts.
42 version 02 07897542EN
Access to the interior
of the cubicles
Access to the CT secondaries, access to the lower main busbar, access to the rear adjustment bolts.
07897542EN version 02 43
Access to the interior
of the cubicles
TT4 cubicle
Access to the VTs, earthing switch, access to the lower connections, access to the rear adjustment bolts.
44 version 02 07897542EN
Access to the interior
of the cubicles
DI4 cubicle
Access to the rear adjustment bolts through the cable basement or trench.
Access to the main busbar (if a single DI4 cubicle is placed side by side to other cubicles, it is easier to get access
from the busbar compartments of the adjacent cubicles).
07897542EN version 02 45
Access to the interior
of the cubicles
Access to the rear adjustment bolts through the cable basement or trench.
Access to VT’s, earthing switch and CT’s secondaries. Access to the rear adjustment bolts.
Access to MV cables.
46 version 02 07897542EN
Installation instructions
07897542EN version 02 47
Installation instructions
Tool
2 open end spanners n. 18.
Position the support plate E at the Place the 2 quick cage nuts B at the
rear of the cubicle by gaining access rear of the cubicle, by gaining access
through the maintenance space. underneath the cubicle.
Screw the lock nut A on each actuator Lift the rear of the cubicle by screwing
D, place washer C, then screw the the 2 actuators to level the cubicle.
actuators in the quick cage nuts.
To be retrieved from the bag of screws Place the fastening screws at the front
and bolts. of the cubicle and tighten them.
48 version 02 07897542EN
Installation instructions
Note:
Remove the front panel (if the cubicle is fitted with VT,
it is first necessary to remove them, see the chapter
“Access to the interior of the cubicles”).
To be retrieved from the bag of screws Place the fastening screws at the rear
and bolts. of the cubicle and tighten them.
To be retrieved from the bag of screws Place the fastening screws at the front
and bolts. of the cubicle and tighten them.
Tools
Remount the sheet steel bottom plate Check that the cubicle is level
of the circuit-breaker compartment. by means of a spirit level.
Fasten the 4 fixing bolts. Check that the doors could open
and close correctly.
07897542EN version 02 49
Installation instructions
Assembly tunnel
Cubicle configuration: Internal arc version on 4 sides, incoming from the top.
- internal arc version on 4 sides
Tools
- Ratchet spanner n.10 (A).
- Fork or ring spanner n.10 (B).
Take out from the wood crate the panels and the roof.
Fix the panels at the rear, then at the front of the cubicle.
Fix the roof.
Respect the assembly as shown on the diagram.
Tighten the tunnels only at the end of the complete assembly of tunnels.
50 version 02 07897542EN
Installation instructions
Cubicle configuration:
- internal arc version on 4 sides,
- IPX1 protection degree.
07897542EN version 02 51
Installation instructions
Cubicle configuration:
- internal arc version on a wall
52 version 02 07897542EN
Installation instructions
Cubicle configuration:
- NIA,
- IPX1 protection degree.
Tools
- Ratchet spanner n.10 (A).
- Fork or ring spanner n.10 (B).
07897542EN version 02 53
Installation instructions
Cubicle coupling
Cubicle configuration:
- NIA,
- AD4, CL4-GL4, TT4, DI4, RD4.
For more details, see drawing
ref. 03833104N0.
Tools
- 2 ratchet spanners n.13 (A) with the
relevant extension.
In order to put in place the 2nd cubicle, operate as for the 1st cubicle.
Fasten the two cubicles together (9 fixing points).
For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.
54 version 02 07897542EN
Installation instructions
Cubicle configuration:
- NIA,
- incoming from the top,
- AD4.
Tools
- 2 ratchet spanners n.13 (A) with the relevant
extension.
- 2 ratchet spanners n.10 (B).
In order to put in place the 2nd cubicle, operate as for the 1st cubicle.
Fasten the two cubicles together (12 fixing points).
For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.
07897542EN version 02 55
Installation instructions
Cubicle configuration:
- NIA,
- IPX1,
- AD4, CL4-GL4, TT4, DI4, RD4.
Tools
- 2 ratchet spanners n.13 (A) with the relevant
extension.
- 2 ratchet spanners n.10 (B).
In order to put in place the 2nd cubicle, operate as for the 1st cubicle.
Fasten the two cubicles together (12 fixing points).
For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.
Tighten the tunnels only at the end of the complete assembly of tunnels.
56 version 02 07897542EN
Installation instructions
Cubicle configuration:
- internal arc protection on 3 sides,
- AD4, CL4-GL4, TT4, DI4, RD4.
Tools
- 2 ratchet spanners n.13 (A) with the relevant
extension.
In order to put in place the 2nd cubicle, operate as for the 1st cubicle.
Fasten the two cubicles together (9 fixing points).
For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.
07897542EN version 02 57
Installation instructions
Cubicle configuration:
- internal arc protection on 4 sides,
- AD4, CL4-GL4, TT4, DI4, RD4,
- tunnel.
Tools
- 2 ratchet spanners n.13 (A) with the relevant
extension.
- 2 ratchet spanners n.10 (B).
In order to put in place the 2nd cubicle, operate as for the 1st cubicle.
Fasten the two cubicles together (27 fixing points).
For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.
Tighten the tunnels only at the end of the complete assembly of tunnels.
58 version 02 07897542EN
Installation instructions
Cubicle configuration:
- internal arc protection on 4 sides,
- incoming from the top,
- AD4.
Tools
- 2 ratchet spanners n.13 (A) with the relevant
extension.
- 2 ratchet spanners n.10 (B). In order to put in place the 2nd cubicle, operate as for the 1st cubicle.
Fasten the two cubicles together (12 fixing points).
For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.
07897542EN version 02 59
Installation instructions
Cubicle configuration:
- internal arc protection on 4 sides,
- IPX1 protection degree,
- AD4, CL4-GL4, TT4, DI4, RD4.
Tunnel coupling:
Tools
- 2 ratchet spanners n.13 (A) with the relevant
extension.
- 2 ratchet spanners n.10 (B).
In order to put in place the 2nd cubicle, operate as for the 1st cubicle.
Fasten the two cubicles together (30 fixing points).
For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.
Tighten the tunnels only at the end of the complete assembly of tunnels.
60 version 02 07897542EN
Installation instructions
Cubicle configuration:
- 1250 A AD4 and RD4,
- Entry busbar from the top.
Tools:
- Allen wrench.
Operating instructions:
- Assemble the extension bars,
- Add the protection covers.
Torque:
- Screws M12x35 21528282 (D): 7.5 daNm.
07897542EN version 02 61
Installation instructions
Cubicle configuration:
- 2500 A AD4 and RD4,
- Entry busbar from the top.
Tools:
- Allen wrench.
Operating instructions:
- Assemble the extension bars,
- Add the protection covers.
Torque:
- Screws M12x70 V1181270 (D): 7.5 daNm.
62 version 02 07897542EN
Installation instructions
07897542EN version 02 63
Installation instructions
Cubicle configuration:
- NIA.
:G+I+L
:H+I+L
:F+I+L
:G+L
:H+L
:H+I+M+N
Operating instructions:
- Position the profile C and fix them as show.
- Position the panel D and fix them in the upper locations.
- Position the panel E and fix them in the upper locations.
Tools - Finish the fixing of the 2 panels as show.
- 2 ratchet spanners n.10 (A) with the relevant - Apply the adhesive plate B on panel D.
extension.
- Repeat the operation for the right side.
For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.
64 version 02 07897542EN
Installation instructions
Cubicle configuration:
- NIA,
- incoming from the top,
- AD4.
:G+I+L
:H+I+L
:F+I+L
:G+L
:H+L
:H+I+M+N
Tools
- 2 ratchet spanners n.10 (A) with the relevant
extension.
Operating instructions:
- Position the profile C and fix them as show.
- Position the panel D and fix them in the upper locations.
- Position the panel E and fix them in the upper locations.
- Finish the fixing of the 2 panels as show.
- Position the panel O and fix them as show.
- Apply the adhesive plate B on panel D.
For access to the fixing points, see the chapter “Access to the interior
of the cubicles”.
07897542EN version 02 65
Installation instructions
Cubicle configuration:
- Internal arc protection on 3 sides.
For more details, see drawings:
- S1B5688102 : left end plates assembly
- S1B5688202 : right end plates assembly
A: screw HM6x16
B: screw HM6x16
C: screw HM6x16
D: nut HM6
E: washer Ø 6
F: washer Ø 12
G: rivet TR 6.5x14.1
H: rivet TR 6.5x20.3
I: cage nut M8
J: cage nut M6x9.5
Tools
- 2 ratchet spanners n.10 (B) with the relevant
extension.
Operating instructions:
- Position the 3 profiles L/M/N and fix them,
- Position the cover plate of the busbar O and fix,
- Position the end plate P and fix,
- Position the end plate Q and fix,
- Position the vents holes R and S and fix them.
66 version 02 07897542EN
Installation instructions
Cubicle configuration:
- Internal arc protection on 4 sides.
For more details, see drawings:
- S1B5688102 : left end plates assembly
- S1B5688202 : right end plates assembly
- S1A6487502 : left end panels assembly
- S1A6487702 : right end panels assembly
A: screw HM6x16
B: screw HM6x16
C: screw HM6x16
D: nut HM6
E: washer Ø 6
F: washer Ø 12
G: rivet TR 6.5x14.1
H: rivet TR 6.5x20.3
I: cage nut M8
J: cage nut M6x9.5
Tools
- 2 ratchet spanners n.10 (B) with the relevant
extension.
Operating instructions:
- Position the 3 profiles L/M/N and fix them,
- Position the cover plate of the busbar O and fix,
- Position the end plate P and fix,
- Position the end plate Q and fix,
- Position the vents holes R and S and fix them.
- Position the cover plate of the tunnel T and fix.
07897542EN version 02 67
Installation instructions
Cubicle configuration:
- internal arc protection on 4 sides
- incoming from the top.
For more details, see drawings:
- S1B5688102 : left end plates assembly
- S1B5688202 : right end plates assembly
- S1A6487802 : assembly of the finition rear panels
incoming from the top.
A: screw HM6x16
B: screw HM6x16
C: screw HM6x16
K: screw HM6x20
D: nut HM6
E: washer Ø 6
F: washer Ø 12
G: rivet TR 6.5x14.1
H: rivet TR 6.5x20.3
I: cage nut M8
J: cage nut M6x9.5
Tools
- 2 ratchet spanners n.10 (B) with the relevant
extension for one.
Operating instructions:
- Position the 3 profiles L/M/N and fix them,
- Position the cover plate of the busbar O and fix,
- Position the end plate P and fix,
- Position the end plate Q and fix,
- Position the vents holes R and S and fix them.
- Position the cover plate of the tunnel U and fix.
68 version 02 07897542EN
Installation instructions
Tools
- Fork or ring spanner n. 18 (A).
- 2 ring spanners n.18 (B1) or ratchet spanners n.18
(B2).
- torque spanner (C).
1 : self-locking nut
2 : nut
3 : washer
4 : screw
07897542EN version 02 69
Installation instructions
70 version 02 07897542EN
Installation instructions
07897542EN version 02 71
Installation instructions
outgoing y 630A
outgoing y 630A
outgoing y 630A
outgoing y 630A
outgoing y 630A
right side end
cubicle AD4
cubicle AD4
cubicle AD4
cubicle AD4
cubicle CL4
cubicle TT4
cubicle TT4
cubicle TT4
cubicle DI4
cubicle DI4
cubicle DI4
y 630A
y 630A
y 630A
or
or
or
or
or
or
right side end panel left side end panel
72 version 02 07897542EN
Installation instructions
07897542EN version 02 73
Installation instructions
Clip
Open the joint cover and put it into position on the busbar joint (for the joint covers
of the 2500 A busbars, to put screws + washers + nuts nylon to close them).
Replace the VT truck into position (see the chapter “Procedure to insert the VT’s
and closing the MV cable compartment”).
74 version 02 07897542EN
Connection of the LV cables
LV cables routing
Tools
- Drill.
07897542EN version 02 75
Connection of the LV cables
LV cables connections
Tools
- Socket spanners n.10.
To reach the terminal blocks of the LV cables, take off the top front sheet metal
(remove the 6 fixing bolts).
Connect the cables to the terminal blocks according to the schematic diagrams.
To keep the panel protection degree between 2 cubicles, the top entry LV cable
sheet must be install:
- on the right for all cubicles,
- on the left on the cubicle positioned at the right side end of the switchboard.
76 version 02 07897542EN
Earthing circuit equipotential
connection and MV cable earthing
Starting conditions If the MV cables have not been connected at the erection of the switchboard,
in order to get access to the connecting terminals, it is necessary to carry out
the following operations:
- Remove circuit-breakers and VTs (both fixed and withdrawable versions)
(see the chapter “Procedure to draw-out the mobile part”).
- Remove barriers between phases and the bottom plates of the circuit-breaker
compartment (see the chapter “Procedure to extract the VTs and opening
the MV cable compartment”).
Equipotential connection
of the switchboard’s earth
to the substation earth
Tools
- Ratchet spanner n.16 (A1).
- Fork or ring spanner n.16 (B).
07897542EN version 02 77
Earthing circuit equipotential
connection and MV cable earthing
Connection of MV cables
General
Remove the bottom metal plates Cut the cable grommets according
in the cable compartment. to the number and diameter of cables.
Tools
- 2 fork or ring spanners n.18 (A).
- Torque spanner (B).
78 version 02 07897542EN
Earthing circuit equipotential
connection and MV cable earthing
Tools
- Fork or ring spanner n.13 (A).
- 2 fork or ring spanners n.18 (B).
- Torque spanner (C).
Cut the cable grommets according Run the three-core cable through
to the number and diameter of cables. the toroidal CT (if requested).
07897542EN version 02 79
Earthing circuit equipotential
connection and MV cable earthing
Tools
- Fork or ring spanner n.13.
Take care to not hurt the cable isolating Fit the crosspiece on the bottom plate
when you clamp the anchoring support. (1 bolt – nuts assembling).
Fit the metal bottom plates. Fit the anchoring supports on the cable
according the picture above for 3 single
Unused holes shall be closed with cable core cables.
grommets (not cut).
80 version 02 07897542EN
Earthing circuit equipotential
connection and MV cable earthing
Front Front
Example: one cable per phase, 3 braids Two cables per phase, 6 braids or wires
or wires to connect. to connect.
07897542EN version 02 81
Earthing circuit equipotential
connection and MV cable earthing
Final operations
VT truck replacing For a description of VT truck replacing, see the chapter “Procedure to insert
the VT’s and to close the MV cable compartment”.
82 version 02 07897542EN
Fitting fuses in DI4 cubicle
The striker end of the fuse is marked. The fuse characteristics and direction
of mounting are printed on the fuse.
Start status
Insert the bottom of the fuse all the way Fit the upper part of the fuse do not
into the lower annular contact. forget to draw by hand the upper field
repartitor (A).
Verify the correct mounting of the upper Turn the fuse so that the label appears
field repartitor (A). (B) in front.
07897542EN version 02 83
Tests on site
Voltage test on the main circuits After erection, the equipment shall be CTs secondaries shall be short-circuited
tested in order to check the correct at the LV terminal boards
installation. (if the auxiliary circuits are open).
The power-frequency test voltage The leads from the testing equipment
shall be 80% of the rated test value shall be connected to the MV cable lugs
(40kV rms), because the cubicles of a cubicle.
have already been tested in Schneider This requires the opening of a lower
Electric factory at 100% of the voltage door during the test for passing
rated value) and shall be applied to the above-mentioned leads.
each phase conductor of the main During the voltage tests, all the cubicle
circuit for 1 minute earthing the other shall be fitted with the relevant
two phase conductors. circuit-breakers.
The circuit-breakers shall be plugged
in service position and closed.
The test configuration
requires some locks to Since hand closing is not permitted
defraud. These operations with closed doors, a special procedure
should be performed only is required (see below) when auxiliary
by specialists. power supply is not available.
It is imperative to follow Obviously, the MV cables shall be
the procedures described disconnected and the earthing switch
below. shall be opened.
Voltage transformers
should be disconnected.
In the presence of
lightning, the latter must
be disconnected during
the test voltage frequency,
to avoid serious damage.
84 version 02 07897542EN
Tests on site
Starting conditions
The circuit-breaker is in disconnected position,
or in test / disconnected position or removed
from the cubicle.
Insert the crank into hole 7 and turn Set selector 6 to withdrawn
counter clockwise until further rotation position .
becomes impossible.
07897542EN version 02 85
Tests on site
Insert the crank into hole 5 and turn Turn selector 4 clockwise to position I.
it clockwise until the earthing switch
position indicator reads “on”.
The earthing switch is in closed The symbols marked on the yellow front
position. The MV cables are short- cover summarise the above-mentioned
circuited and earthed. procedure.
The selector in this position prevents For more protection, it is possible
the insertion of the circuit-breaker. to prevent the insertion of the circuit-
breaker by setting the selector P
as shown in the following drawing.
86 version 02 07897542EN
Tests on site
07897542EN version 02 87
Tests on site
Insert the crank into hole 5 and turn Set selector 4 to position “O”.
its counter clockwise until the earthing
switch position indicator reads “off”.
The earthing switch is in open position. The symbols marked on the yellow front
cover summarise the above-mentioned
procedure.
88 version 02 07897542EN
Tests on site
With the circuit-breaker in disconnected Connect the leads from the testing
position and the compartment door equipment to the MV cable lugs.
open, lift the locking rod A located
on the top of the circuit-breaker
mechanism.Insert spacer U to keep
the rod in raised position.
After performing the test Move the circuit-breaker to the disconnected position.
Close the earthing switch.
Disconnect the test equipment.
07897542EN version 02 89
Index
A
AD4 cubicle (for cubicle entry from above) 14
AD4 - RD4 cubicle 40
AD4 RHC cubicle (for cubicle entry from above) 46
Adjusting cubicles on standard civil engineering works 48
After performing the test 89
Anchoring supports for MV cables 80
Assembly tunnel 50
B
1250 A main busbars 70
2000 / 2500 A main busbars 71
C
CL4 cubicle (bus-section) 41
CL4 cubicle (bus-section) with upstream CT’s 42
CL4-GL4 cubicles (with upstream CT) 14
Close the earthing switch 86
Closing the top entry LV cable steel sheet 76
Connection of earthing busbar 63
Connection of MV cables 78
Cubicle coupling 54
D
Description of the fixing rails and accessories 20
DI4 cubicle 45
E
Earthing of MV cable shields 81
Earthing of MV cable shields (DI4) 91
End panels assembling 64
Equipotential connection of the switchboard’s earth
to the substation earth 77
Extraction and lowering tool 24
F
Fastening to the floor on standard civil engineering works 48
Fastening to the floor on earthquake resistant civil engineering works 49
Final operations 82
Fitting joint covers 72
Fitting the main busbars 69
Floor quality 20
G
Glossary 3
GL4 cubicle (bus-riser) 43
CL4-GL4 cubicles (with upstream CT) 14
H
Handling 16
How to prepare the cubicles 84
I
Installation extension busbar 61
Internal arc version with protection on 3 sides 8
Internal arc version with protection on 3 sides, with a ceiling
height between 2.8 and 4 m 9
Internal arc version with protection on 3 sides
with IPX1 protection cubicle 10
Internal arc version with protection on 4 sides,
height under ceiling lower than 4 m 11
90 version 02 07897542EN
Index
I
Internal arc version with protection on 4 sides, in substations
with a ceiling height between 2.8 and 4 m 12
Internal arc version with protection on 4 sides in a substation
with a ceiling height of 2.8 to 4 m with IPX1 protection cubicle 13
L
List of bags and accessories 5
LV cables connections 76
LV cables routing 75
N
NIA version 6
NIA version with IPX1 protection cubicle 7
O
One single core or three-core cable per phase 78
One to four single core cables per phase 79
Open the earthing switch 88
Operation and maintenance 18
Operations to be carried out on the cubicle to be connected
to the testing equipment 85
P
Packaging 15
Placing and adjusting on standard civil engineering works 20
Placing and adjusting on earthquake resistant civil
engineering works 22
Positioning the joint covers 74
Preparation of the cubicle to the positioning 47
Prevent the insertion of the circuit-breaker 87
Procedure to draw-out the mobile part 25
Procedure to draw-in the mobile part 28
Procedure to extract the VTs and opening the MV cable compartment 31
Procedure to insert the VT’s and closing the MV cable compartment 35
R
Recommendations 4
Restore the possibility of circuit-breaker insertion 89
S
Safety rules for use 24
Standard tightening torques 5
Starting conditions 77
Storing 17
Surface condition 20
Symbols 3
T
The switchgear’s resistance to ageing in an MV substation 18
Three-core cable per phase 79
TT4 cubicle 44
V
Verify correct positioning 49
Voltage test on the main circuits 84
W
Withdraw the VT fuses 85
Without lowering (extraction table) 24
07897542EN version 02 91
Schneider Electric group service centers are there to provide:
- engineering and technical assistance,
- commissioning,
- training,
- preventive and corrective maintenance,
- adaptation work,
- spare parts.
Call your sales representative who will put you in touch with your nearest
Schneider Electric group service center or directly call the following telephone
number: +33 (0)4 76 57 60 60 Grenoble France.
Schneider Electric Industries S.A.S As standards, specifications and designs change from time to time, please ask for confirmation
Head Office of the information given in this publication.
35 rue Joseph Monier
CS 30323 This document has been printed
92506 Rueil-Malmaison on ecological paper.
www.schneider-electric.com
Publishing: Schneider Electric Industries SAS.
Design: Profil.
Printing: