Present Economy Studies
* This involves the analysis of problems
for manufacturing a product or
rendering a service upon the basis of
present or immediate costs.
Present economy studies usually
occur when the effects of time such
as interest and depreciation are
negligible.
Present economy analysis is employed
when the alternatives to be compared
will provide the same result and the
period of time involved in the study is
relatively short.Present economy studies occur in the
following situations:
1.Selection in present economy
2.Selection of method to be used
3.Selection of design
4.Selection of location or site for a project
5.Comparison of proficiency among workers
6.Economy of tool and equipment maintenance
7.Economy of number of laborers.Rules for Selecting Preferred Alternative
Rule 1 - When revenues and other economic
benefits are present and vary among alternatives,
choose alternative that maximizes overall
[profitability based on the number of defect-free
units of output.
Rule 2 - When revenues and economic benefits
are not present or are constant among
alternatives, consider only costs and select
alternative that fninimizes total cost|per defect-
free output.Sample Problem:
1. A building contractor has a contract which will expire in
30 days. He has 80 men on the job and can finish the work
in 50 days. The wage per day of 40 men is P20 and that of
the other 40 men is P18 each for 8 hours work per day. The
fine or liquidated damages for delay in the work is P400 per
day. How many more men should the contractor add in
order to enable him to complete the work on time?
Assuming that the additional men will have a wage of P20
each per day, will the contractor save money by employing
enough men to enable him to complete the work on time or
not adding men and paying the liquidated damages? How
much is the saving if any? No overtime.Solution:
Let x = # of men to be added in order to finish on time.
Using man-days equation:
(80men)(50 days) = (x + 80) men (30 days)
x = 53.33 men 54 men
80 men on the job:
Wage: 40 men x P20.00/day x 50 days = 40,000
40 men x 18/day x 50 days = 36,000
Liquidated domain 400/day x 20 days =_ 8,000
Total =P 84,000Solution:
134 men:
Wages :
40x 20x30 =24,000
40x18x30 =21,600
54x 20x30 = 32,400
Total = 78, 000
Thus, the contractor saves P 6,000.00 and finish completely only
when he employed 54 more men.Sample Problem:
2.In manufacturing a certain machine part, it is necessary
to make four holes in each part. Each hole will require one
minute if drilled with the aid of a jig. The drill jig would cost
P 100 to construct and the drill press operator is paid P
2.00 per hour.
The four holes can be made in 20 seconds on a punch
press, but a die costing P 350 will be required. It requires 4
hour setting up the die on the press and the same period of
time to tear it down when the job is completed. Overhead
charges for the punch press are P 3.50 per hour. The press
operator receives P3.00 per hour and the set-up man is
paid P 5.00 per hour.
a.)Determine the comparative cost for making 1,000 parts.
b.)Determine the number of parts to be made for equal cost.Solution:
a.Determine the comparative cost for making 1,000 parts.
O Drill jig
Time to drill 1000 parts = 1min x 4holes/1part x 1hr/60min 1000 parts
= 66.67 hr
Wage of drill jig operator = 66.67 hr x P 2.00/hr = 133.34
Cost of drill jig = 100
Total = P 233.34
O Punch Press
Time to punch 1000 parts = 20s/1part x 1000parts x 1hr/3600s
= 5.56hrs
Wage of punch press operator = 5.56hrs x P3.00/hr = 16.67
Wage of set-up man = (1/2+1/2)hr x 5.00/hr = 5.00
Cost of machine = 350
Overhead Cost = 5.56hrs x P350/hr =19.46
Total=P 391.13Solution:
b.Determine the number of parts to be made for equal cost.
Let x = number of parts
Unit cost drill jig = P 233.34/1000 parts = 0.2334/part
0.2334 (x) = 391.13
x= 1675.79
x = 1676 parts
The drill jig must procedure 1676 parts in order to equal the cost
punched press. Drill press is economical.Sample Problem:
3.Two types of filter are being considered for use in a diesel
engine. Filter A requires a premium quality lubricating oil
costing P 11.50 per liter. The filter and the oil will have to be
changed after 1,000 hours of operation and 4 liters of new
oil added after each 100 hours. This filter cost P 150. Forty
liters of oil fill the engine crankcase.
For filter B a lower grade of oil costing P 5.85 per liter
maybe used. This filter cost P 175. In this case the filter
would be change each 1000 hours, the oil completely
changed after each 500 hours and 4 liters of oil added after
250 hours of use. Which combination should be used?Solution:
Type A, filter (consider 1000 hrs. of operation)
Cost of filter = 150
Initial cost = (11.50/L) 40L = 460
Cost of additional oil = 9(4L) x (11.50/L) =414
Total = P 1024
Type B, filter (consider 1000 hrs. of operation)
Cost of filter =175
Initial cost of oil = 5.85 x (40 L/S500hrs)1000hrs = 468
Cost of additional = 5.85 x (4L/250hrs)500hrs = 46.8
Total = P 689.80
Filter B is cheaper 334.2 by filter A. So it is economical to use for.
every 1000 hrs. operation. ~References:
LT Blank, A Tarquin. Engineering Economy. McGraw Hill,
International Edition, 5th edition, 2002.
William G. Sullivan et al. Engineering Economy. 16th Edition. New
Jersey: Prentice — Hall,Inc, 2015
GJ Thuesen, WJ Fabrycky, GJ Thuesen. Engineering Economy.
Prentice Hall, Upper Saddle River, NY, 2001.
Chan S. Park. Contemporary Engineering Economics.2nd
Edition.USA:Addison-Wesley Publishing Company,|nc. 1997
Matias A. Arreola. Engineering Economy. 3rd Edition. Philippines:
Ken Inc., 1993.
G.J. Thuesen and W.J. Fabrycky. Engineering Economy.8th Edition.
New Jersey: Prentice — Hall, Inc., 1993
Max Kurtz. Engineering Economics for Professional Engineers’
Examination.2nd Edition. New York: McGraw-Hill, 1975