Road Rate Analysis 077-78 Final

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 162

Item no 21 Road work RATE ANALYSIS OF CONSTRUCTION WORK ITEMS

Norms
and Serial No:15
2-5.4.3

Scarifying existing granular/bituminous road surface for carrying out the required operations necessary to complete the work. This
includes handling, salvaging, stacking and disposing of scarified material up to a lead of 100 m along the lead route.( For 10to 20 cm
depth)
unit 1 m3
Rate in Amount in
S.No. Description Unit Quantity Remarks
NRs NRs
1.00 Labour
Unskilled md 0.20 750.00 150.00
Skilled md 0.00 0.00
Sub Total Labor 150.00
2.00 Tools / Equipment
Axes, Khukuri, Saws, Crowbars, Wheel Barrows or
Bullock Carts 4.50
Sub Total Tool/Equipment 4.50
Sub Total (Labor+Tool/Equipment) -I 154.50
Contractor Over head 15% of I 23.18
Total rate per m3 177.68
Per sq m 35.54 20cm depth
Excavation in Roadway , drain and foundation of structure including removal and satisfactory disposal of all
materials up to a lead of 50m along the lead route using excavator or breaker and finishing manually wherever and to
what extent necessary
Unit : 1 cum
Manual Equipment
Equipment
Manual Excavation Excavation Excavation Average Rate
S.No Description Excavation
(5%) (95%)
NRs NRs NRs NRs NRs
1 Ordinary soil 444.19 93.15 22.21 88.49 110.70
2 Hard soil 533.03 93.15 26.65 88.49 115.14
3 Ordinary rock 1776.75 93.15 88.84 88.49 177.33
4 Medium rock 3553.50 557.75 177.68 529.86 707.54
5 Hard rock 13426.01 839.50 671.30 797.53 1468.83
Note: Contracter Over head of 15% is included in Equipment Excavation Cost
Item no 21 Road work RATE ANALYSIS OF CONSTRUCTION WORK ITEMS

Norms Serial No: 10.05 (DOR)


Clause No.: 8
Preparation of sub-grade for rehabilitation or other similar works (filling or cutting depth of 10 to 20 cm) in:
Unit : m3

SNo Description of works Unit Quantity Rate Amount Remarks

1.00 Labour
Unskilled md 0.10 750.00 75.00
Skilled md 0.01 1030.00 10.30
Sub Total Labor 85.30
2.00 Material
Diesel Lit 0.12 88.50 10.80
Sub Total Material 10.80
3.00 Tools and equipment
Grader Hr 0.01 1,649.34 16.49
Roller Hr 0.02 1,102.50 18.74
Sub Total Tool/Equipment 35.24
Sub Total (Labor+Material+Tool/Equipment) -I 131.33
Contractor Over head 15% of I 19.70
Total rate per m3 151.03
Total rate per sqm 30.21

Norms Serial No: 12.01 (DOR)


Clause No.: 1201
Providing, laying, spreading, watering, leveling and compaction of natural sand gravel sub base grading as per table 12.1 of standard
specification
Unit : m3

SNo Description of works Unit Quantity Rate Amount Remarks

1.00 Labour
Unskilled md 0.04 750.00 30.00
Skilled md 0.0050 1,030.00 5.15
Sub Total Labor 35.15
2.00 Material
Diesel Lit 0.79 88.50 70.09
Sub base aggregate m3 1.28 2,540.16 3251.40
Item no 21 Road work RATE ANALYSIS OF CONSTRUCTION WORK ITEMS
Sub Total Material 3321.49
3.00 Tools and equipment
Grader Hr 0.0220 1,649.34 36.29
Vibrating roller Hr 0.0220 1,670.00 36.74
Water browser Hr 0.0380 1,405.00 53.39
Loader Hr 0.0110 2,500.00 27.50

Sub Total Tool/Equipment 153.92


Sub Total (Labor+Material+Tool/Equipment) -I 3510.56
Contractor Over head 15% of I 526.58
Total rate per m3 4037.14

Norms Serial No: 12.06(DOR)


Clause No.: 1202

Providing, laying, spreading, watering, leveling and compaction of crusher run materials for base course lead up to 10m.

SNo Description of works Unit Quantity Rate Amount Remarks

1.00 Labour
Unskilled md 0.0200 750.00 15.00
Skilled md 0.0050 1,030.00 5.15
Sub Total Labor 20.15
2.00 Material
Diesel Lit 0.99 88.50 87.61
Base aggregate m3 1.20 2,998.80 3598.56
Sub Total Material 3686.17
3.00 Tools and equipment
Grader Hr 0.03 1,649.34 54.43
Vibrating roller Hr 0.03 1,670.00 55.11
Water browser Hr 0.03 1,405.00 46.37
Loader Hr 0.0110 2,500.00 27.50

Sub Total Tool/Equipment 183.40


Sub Total (Labor+Material+Tool/Equipment) -I 3889.72
Contractor Over head 15% of I 583.46
Total rate per m3 4473.18
Item no 21 Road work RATE ANALYSIS OF CONSTRUCTION WORK ITEMS

Norms Serial No: 13.01 (DOR)


Clause No.: 1301/ 1302

Providing and spraying bituminous tack coat MC30/MC70 including cleaning the road surface using wire, brushes, broom etc before
applying prime coat. (@0.60lit/sqm)
Unit : lit

SNo Description of works Unit Quantity Rate Amount Remarks

1.00 Labour
Unskilled md 0.0460 750.00 34.50
Skilled md 0.0030 1,030.00 3.09
Sub Total Labor 37.59
2.00 Material
Bitumen Lit 1.05 78.10 82.01
Kerosene Lit 0.10 88.50 8.85
Diesel Lit 0.275 88.50 24.34
Sub Total Material 115.19
3.00 Tools and equipment
Boiler Hr 0.0025 880.00 2.20
Sprayer Hr 0.0025 1,800.00 4.50
Air compressor Hr 0.0030 589.00 1.77
Sub Total Tool/Equipment 8.47
Sub Total (Labor+Material+Tool/Equipment) -I 161.25
Contractor Over head 15% of I 24.19
Total rate per litre 185.44
Item no 21 Road work RATE ANALYSIS OF CONSTRUCTION WORK ITEMS
Norms Serial No: 13.03 (DOR)
Clause No.: 1301/ 1302
Providing and spraying bituminous prime coat MC30/MC70 including cleaning the road surface using wire, brushes, broom etc before applying prime
coat.
Unit : lit
SNo Description of works Unit Quantity Rate Amount Remarks
1.00 Labour
Unskilled md 0.0460 750.00 34.50
Skilled md 0.0030 1,030.00 3.09
Sub Total Labor 37.59
2.00 Material
Bitumen Lit 1.05 78.10 82.01
Kerosene Lit 0.10 88.50 8.85
Diesel Lit 0.275 88.50 24.34
Sub Total Material 115.19
3.00 Tools and equipment
Boiler Hr 0.0025 880.00 2.20
Sprayer Hr 0.0025 1,800.00 4.50
Air compressor Hr 0.0030 589.00 1.77
Sub Total Tool/Equipment 8.47
Sub Total (Labor+Material+Tool/Equipment) -I 161.25
Contractor Over head 15% of I 24.19
Total rate per litre 185.44
Norms Serial No: 13.09 (DOR)
Clause No.: 1307 / 1308
Providing, mixing, laying and compaction of premixed carpet
SNo Description of works Unit Quantity Rate Amount Remarks
1.00 Labour
Unskilled md 4.50 750.00 3375.00
Skilled md 0.45 1,030.00 463.50
Sub Total Labor 3838.50
2.00 Material
Bitumen Lit 77.00 78.10 6013.70
Kerosene Lit 7.70 88.50 681.42
Aggregates cum 1.20 3,213.21 3855.85
Sub Total Material 10550.97
3.00 Tools and equipment
Sprayer Hr 0.50 1,800.00 900.00
Roller Hr 0.50 1,102.50 551.25
Sub Total Tool/Equipment 1451.25
Sub Total (Labor+Material+Tool/Equipment) -I 15840.72
Contractor Over head 15% of I 2376.11
Total rate per m3 18216.83
Item no 21 Road work RATE ANALYSIS OF CONSTRUCTION WORK ITEMS

Norms Serial No: 13.07 (DOR)

Clause No.: 1301 / 1305


Providing and laying sand seal (for 10sqm)
Unit : m3

SNo Description of works Unit Quantity Rate Amount Remarks

1.00 Labour
Unskilled md 0.14 750.00 105.00
Skilled md 0.10 1,030.00 103.00
Sub Total Labor 208.00
2.00 Material
Bitumen Lit 6.60 78.10 515.46
Kerosene Lit 0.10 88.50 8.85
Diesel Lit 0.81 88.50 71.68
Fine Aggregates cum 0.12 3,213.21 385.59
Sub Total Material 981.58
3.00 Tools and equipment
Boiler Hr 0.04 880.00 35.20
Roller Hr 0.04 1,670.00 66.80
Sprayer Hr 0.01 1,800.00 18.00

Sub Total Tool/Equipment 120.00


Sub Total (Labor+Material+Tool/Equipment) -I 1309.58
Contractor Over head 15% of I 196.44
Total rate per sqm 1506.01 150.60
Item no 21 Road work RATE ANALYSIS OF CONSTRUCTION WORK ITEMS

Norms Serial No: 13.10 (DOR)

Clause No.: 1307 / 1308

Providing, mixing, laying asphalt concrete with compaction


Unit : m3

SNo Description of works Unit Quantity Rate Amount Remarks

1.00 Labour
Unskilled md 0.13 750.00 97.50
Skilled md 0.03 1,030.00 30.90
foreman md 0.01 750.00 7.50
Sub Total Labor 135.90
2.00 Material
Bitumen Lit 117.00 78.10 9137.70
cement t 0.022 16,500.00 363.00
Diesel Lit 10.45 88.50 924.78
Aggregates cum 1.20 2,928.24 3513.89
Sub Total Material 13939.37
3.00 Tools and equipment
Asphalt mixing plant Hr 0.044 2,625.00 115.50
Wheel Loader Hr 0.66 2,500.00 1650.00
asphalt paver Hr 0.22 2,150.00 473.00
Tipper Trucks Hr 0.32 1,050.00 336.00
Steel tyred Roller Hr 0.55 1,270.00 698.50
Pneumatic Rollers Hr 0.55 1670.00 918.50
Sub Total Tool/Equipment 4191.50
Sub Total (Labor+Material+Tool/Equipment) -I 18266.77
Contractor Over head 15% of I 2740.02
Total rate per m3 21006.78
Item no 21 Road work RATE ANALYSIS OF CONSTRUCTION WORK ITEMS

Norms Serial No: 12.12 (DOR)


Clause No.: 1205

Providing, laying, spreading, watering, leveling and compaction of natural sand gravel sub base grading as per table 12.1 of
standard specification (Gravelling)
Unit : m3
SNo Description of works Unit Quantity Rate Amount Remarks

1.00 Labour
Unskilled md 0.02 750.00 15.00
Skilled md 0.01 1030.00 5.15
Sub Total Labor 20.15
2.00 Material
Diesel Lit 1.98 88.50 175.22
Sub base aggregate m3 1.22 2540.16 3099.00
Sub Total Material 3274.22
3.00 Tools and equipment
Grader Hr 0.04 1649.34 59.38
Vibrating roller Hr 0.04 1670.00 60.12
Water browser Hr 0.05 1405.00 70.25
Loader Hr 0.01 2500.00 27.50
Sub Total Tool/Equipment 217.25
Sub Total (Labor+Material+Tool/Equipment) -I 3511.61
Contractor Over head 15% of I 526.74
Total rate per m3 4038.35
>ldssf] Hofnf b/
Hofnf b/ k|ltlbg ?=
cf=j= cf=j=
l;= g+= sfdbf/x?sf] lja/0f PsfO{ @)&४÷) @)&५÷)&६
&५
1 lgdf{0fsfdsf] nflu >lds -HofdL_ k|lt lbg 670.00 700.00
2 kmf]x/ 9n ;kmf ug]{ sfdbf/ k|lt lbg 750.00 1000.00
3 bIf -8sdL,{ l;sdL{, gsdL{, lrqsf/, jh|sdL{_, KnDa/, k|lt lbg 910.00 960.00
9'Ëf / sf7 a'§f sf6\g] ;fwf/0f d"lt{sf/ ,lrqsf/, cfl6{:6,
4 cw{bIf -8sdL{, l;sdL{, gsdL{_ ,lrqsf/, KnDa/,
k|lt lbg 750.00 790.00
On]S6«f]l;og, cf/fjfnf, h'lgo/ ;'k/efO{h/, gbL lg/LIfs,
5 cfbL . सपु रभाइजर
इन्जिनीयर, k|lt lbg 1080.00 1080.00
6 ;a OlGhlgo/, -8«fk\m6 d]g, cldg,
k|lt lbg 910.00 910.00
On]S6«Ll;og, ;e{]o/_, आदी .
7 l;lgo/ 6fO{lki6÷sDKo'6/ cप/]6/, cjfn, cflb . k|lt lbg 880.00 880.00
8 Nofj 6]lSgl;og, h'lgo/ 6fO{lki6÷सहायक sDKo'6/
k|lt lbg 800.00 800.00
cK/]6/, l;lgo/ ;'k/efO{h/, 9n ;kmf ug]{ sfdbf/, cflb .
9 cl;i6]06 ;a OlGhlgo/, 8«fˆ6d]g, सहायक cldg, h'lgo/
k|lt lbg 750.00 750.00
;'k/efO{h/ cflb .
10 x]eL OSo'Kd]G6M P:sfe]6/, /f]n/
ck|]6/,d]sflgS; ,x]eL e]lxsn 8«fOe/, 6«s k|lt lbg 980.00 980.00
8«fOe/, ;fwf/0f d]l;g cपरेटर, Nofj cl;:6]G6, cflb .
11 मेकानिक्स हेभी भेहिकल ड्राइभर ट्र क ड्राइभर साधारण मेसिन अपरेटर ल्याब असिस्टेन्ट आदि
k|lt lbg 700.00 700.00

5 ;fOSnf] :6fOn 6]«l;Ë, Pdf]lgof lk|G6LË


k|lt lbg 670.00 700.00
kmf]/d]g, ;fdflhs kl/rfns, v+b]n -vfgL ;DaGwL sfd
6 ug{] sfdbf/_,
lgdf{0f sfo{sf]cfbL . js{/, ;'k/efOh/, Jnf:6/,
SofDk
d]sflgS;, sflnu9, l8«n/, kmf]6f]u|flkmS;,
kmf]/d]g, ;]So'/]6L uf8{{, gfO6 jfrd]g, /f]8 n]Gy
js{/, x]Nk/ d]sflgS;, nfO6 e]lxsn 8«fOe/, clkm; k|lt lbg 610.00 640.00
cl;:6]G6, ;e{] x]Nk/, j]N8/ ;xfos, /g/, u0fs r]g Dofg,
6]k Dofg, :6fkm Dofg, l8«n x]Nk/, 6«s x]Nk/, ;o;
Enumerator -Go'gtd P;=Pn=;L jf ;f] ;/x_, cfदी .
7 dfnL, ;xfos kl/rfns, :jLk/, d]xQ/, wf]jL, jg x]/fn',
rf}lsbf/, आदी . ,, 560.00 590.00

8 ;fdfg nf]8 cgnf]8 ug]{ Hofnf !)) lsnf] 20.00 20.00


;8ssf] sfdsf] nflu
1 lkr :k|]o/, lkr Jjfon/ k|lt lbg 680.00 715.00
2 Kofr js{/ -lbp;f] sf] ;dodf sfd ug]{_ . k|lt lbg 670.00 700.00

Kofr js{/ ;'k/efOh/ -lbp;f] sf] ;dodf sfd ug]{_


3 k|lt lbg 700.00 735.00
;'k/efOh/ ;/x .
4 Kofr js{/ -/fqL ;dodf sfd ug]{_ . k|lt lbg 950.00 1000.00
5 Kofr js{/ ;'k/efOh/ -/fqL ;dodf sfd ug]{_ k|lt lbg 980.00 1030.00
6 el/of -$) s]=hL= tf}n ;Dd k|lt lbg 700.00 735.00
7 jf]n]/f] $ JxLn 8jn Sofj lksck ef8f O{Gwg / rfns ;d]t k|lt lbg 5000.00 5000.00

8 :s/lkof] $ JxLn 8jn Sofj lksck ef8f O{Gwg / rfns ;d]t k|lt lbg 6000.00 6000.00

dfly pNn]v gePsf cGo ;j} kb÷>]l0fsf Hofnfbf/L sd{rf/L÷sfdbf/x?sf] xsdf ;+jlGwt kb÷>]l0fsf] nf
jf ;DalGwt ;+:yfgsf] k|rlnt tnj dfgnfO{ #) n] efu ubf{ x'g cfpg] /sdnfO{ b}lgs Hofnfb/ dfGg'kg]{ 5 .
3/ / hUuf ef8f tyf Ifltk"lt{÷d'cfJhf lgwf{/0f
3/ / hUuf ef8f tyf Ifltk"lt{÷d'cfJhf lgwf{/0f k|of]hgsf] nflu ljleGg k|sf/sf] 3/sf] agfj6 x]/L tklzn j
cf=j= cf=j=
@)&#÷) @)&$÷)&
l;= g+= 3/sf] agfj6 ljj/0f OsfO &$ sf] b/ % sf] b/ -?
(रु) _
1 ejgsf] lgdf{0f leq sfFrf], jflx/ kfsf] O{6fdf df6f]sf] a=km'= 1092.00 1267.00
२ hf]8fO{ eO{ 5fgf
ejgsf] lgdf{0f leq, h:tf,
jflx/ lem+u6L, 6fon,
kfsf] O{6fdf P;j];6;\ l;6 .
df6f]sf]
hf]8fO{ eO{ 5fgf h:tf, lem+u6L, 6fon, P;j];6;\ l;6 . a=km'= 1403.00 1629.00

3 ejgsf] lgdf{0f leq, jflx/ kfsf] O{6fdf df6f]sf]


hf]8fO{ eO{ leq jflx/ l;d]06 Knfi6/ eO{ 5fgf h:tf, a=km'= 1561.00 1811.00
lem+u6L, 6fon, P;j];6;\ l;6 .
४ ejgsf] lgdf{0f leq, jflx/ kfsf] O{6fdf df6f]sf]
hf]8fO{ eO{ leq jflx/ l;d]06 Knfi6/ eO{ 5fgf a=km'= 1641.00 1906.00

5 cf/=lj=;L=÷
ejgsf] lgdf{0fcf/=l;=l;=
leq, jflx/.kfsf] O{6fdf jh|sf]
a=km'= 1602.00 1859.00
hf]8fO{ eO{ 5fgf h:tf, lem+u6L, 6fon, P;j];6;\ l;6 .
६ ejgsf] lgdf{0f leq, jflx/ kfsf] O{6fdf jh|sf] hf]8fO{ /
leq jflx/ l;d]06 Knfi6/ eO{ 5fgf h:tf, lem+u6L, 6fon, a=km'= 1742.00 2022.00
P;j];6;\ l;6 .
7 ejgsf] lgdf{0f leq, jflx/ kfsf] O{6fdf jh|sf] hf]8fO{ /
a=km'= 1813.00 2105.00
leq jflx/ l;d]06 Knfi6/ eO{ 5fgf
8 cf/=lj=;L=÷cf/=l;=l;=
ejgsf] lgdf{0f leq, jflx/. kfsf] O{6fdf l;d]06
hf]8fO{ eO{ 5fgf h:tf, lem+u6L, 6fon, P;j];6;\ l;6 . a=km'= 1756.00 2038.00

9 ejgsf] lgdf{0f leq, jflx/ kfsf] O{6fdf l;d]06


hf]8fO{ eO{ 5fgf cf/=lj=;L=÷cf/=l;=l;= . a=km'= 1818.00 2110.00

10 cf/=l;=l;=k|m]d :6Sr/ ejg . a=km'= 1920.00 2229.00


11 sf7}sf7sf] ejg eO{ 5fgf h:tf, lem+u6L, 6fon, P;j];6;\
l;6 . a=km'= 1680.00 1950.00

ejgsf] jgfj6 / lkmlgl;Ë tyf ;fdfg÷pks/0f h8fgsf] cfwf/df juL{s/0f


s_ ejgsf] leq Wall Putty u/L OdN;g k]lG6Ë u/]sf] .
v_ ejgsf] aflx/ Weather Coat painting/wall cladding/Almunium composite pannel ePsf] .
u_ lnkm\6 tyf PS;fn]6/ h8fg ePsf] .
3_ ljB'tLs/0fsf] nflu pRr:t/Lo ;fdu|Lsf] k|of]u ePsf] .
ª_ Kof;]h, e/\ofËdf dfj{n÷kfs]{l6Ë ePsf] .
r_ zf}rfnodf 6fon, lkmS;/ / l;=lk= lkml6Ë pRr:t/Lo k|of]u ePsf] .
5_ cUgL lgoGq0f k|ljlw -Fire Hose Reel / Extinguisher_ h8fg ePsf] .
h_ j];d]06df (Basement) kfls{Ë ;'ljwf ePsf] .
em_ Raft/Pile foundation ePsf] .
pNn]]lvt dflysf ;a} ;'ljwf ePsf] eP 's' ju{, / pNn]lvt dWo] sDtLdf & uf]6f ;'ljwf ePsf]
ju{ c_
dflgg] 5 . o; ejgsf]
'u' ju{sf] cg';f/ juL{s[t ul/Psf] tflnsf
xsdf pk/f]Qm ejgsf]cg';f/sf]
xsdf lgDgfg';f/sf]
b/ dflgg] 5b/. sfod x'g] 5 M
cf_ 'v' ju{sf] ejgsf] xsdf pk/f]Qm tflnsf cg';f/sf] b/df @) k|ltzt yk ul/g] 5 .
O_ 's' ju{sf] ejgsf] xsdf pk/f]Qm tflnsf cg';f/sf] b/df $) k|ltzt yk ul/g] 5 .
3/ef8f d"Nof+sg k|of]hgsf] nflu lgDg d'Vo ;8ssf] bfofF / jfofF lgdf{0f ePsf 3/x?sf] xsdf
Return (IRR)M!) k|ltzt / hUufsf] xsdf IRR % k|ltzt sfod ug]{ / d'Vo ;8s;+u hf]l8Psf ;xfos ;8s /
d'Vo ;8sx?
!_ dgf]x/f k'n -h8Lj'6L_ b]lv sf]6]Zj/–;'ljwfgu/–jfg]Zj/–dfO{tL3/–lqk'/]Zj/–sn+sL–yfgsf]6 r]skf
gfu9'+uf;Ddsf]
@_ ;8s .
dfO{tL3/–l;+xb/jf/–k'tnL;8s–sdnkf]v/L–ho g]kfn xn–gfukf]v/L–gS;fn–ef6e6]gL–k|x/L tfln
s]Gb|;Ddsf]
#_ ;8s .
lqk'/]Zj/–;'Gwf/f–Go"/f]8u]6–ljzfnjhf/ -Ogb|rf]s_–Go"/f]8 u]6–jL/ c:ktfn–hdn–n}grf}/– nflh
c:ktfn–dxf/fhu+h rf]s–a"9fgLns07;Ddsf] ;8s .
$_ rqmky k'/} .
%_ z+vd'n k'n –gofFjfg]Zj/–k'/fgf] jfg]Zj/–uf}zfnf rf]s;Ddsf] ;8s .
^_ l;gfd+un k'/fgf] jfg]Zj/ rf]s–d}tLb]jL–l8NnLjhf/–jfujhf/ x'Fb} /Tgkfs{;Ddsf] ;8s .
&_ uf}zfnf rf]s – 1fg]Zj/ – sdnkf]v/L–Ps]8]dL ejg–tLgwf/f kf7zfnf–dx]Gb| zflns;Ddsf] ;8s .
*_ rfjlxn rf]s –jf}4 – hf]/kf6L ;fFv' j;kfs{ ;Ddsf] ;8s .
(_ n}grf}/ – gofFjhf/– jfnfh' rf]s – jfnfh' jfO{kf;– sf7df8f}+ / g'jfsf]6sf] l;dfgf;Ddsf] ;8s .
!)_ sflndf6L rf]s–s'n]Zj/–jNv'rf]s–kmlk{Ë blIf0fsfnLsf] kfls{Ë:yn;Ddsf] ;8s .

kmnfd hGo lgdf{0f ;fdfu|L


d'=c=s/ afx]ssf] b//]6
cf=j=
l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j=
@)&$÷&
२)&#÷&$
%
1 ljleGg ;fOhsf TMT Bar
a) 8 mm dia s]=hL 74.75 76.00
b) 10,12,16,20, mm dia s]=hL 72.00 74.00
c) 25 mm dia s]=hL 74.75 77.00
c) 28,32 mm dia s]=hL 77.00
2 ljleGg ;fOhsf] TOR Steel
a) 8mm dia TOR steel s]=hL 77.35 78.85
b) 10-25mm TOR steel s]=hL 76.35 77.85
c) 28-32mm TOR steel s]=hL 78.85 80.35
3 TOR kari-4.75, 7 mm dia s]=hL 86.72 78.65
4 808L afFWg]tf/ s]=hL 89.00 88.22
5 Pd=P;=;f]ln8 :jfo/ /8 s]=hL 81.01 70.00
6 ljleGg ;fOhsf] Pd=P;= PËn s]=hL 87.24 71.00
7 ljleGg ;fOhsf] Jofs kfO{k s]=hL 81.01 74.42
8 ljleGg ;fOhsf] Pd=P;= Rofgn s]=hL 88.37 71.00
9 ljleGg ;fOhsf] cfO=ljd s]=hL 89.51 72.00
10 ljleGg ;fOhsf] Pd=P;= Kn]6 s]=hL 86.11 139.10
11 ljleGg df]6fOsf] Pd=P;= sfnf] l;6 s]=hL 81.58 139.10
11 G.I. Wire
i) Heavy Zinc coated
8mm dia s]=hL 95.79 94.30
10mm dia s]=hL 95.79 94.30
12mm dia s]=hL 95.79 95.30
ii) Medium zinc Coated
8mm dia s]=hL 90.64 93.60
10mm dia s]=hL 90.64 89.30
12mm dia s]=hL 90.64 90.30
iii) Light Zinc Coated/Commercial
8mm dia s]=hL 85.49 86.30
10mm dia s]=hL 85.49 86.30
12mm dia s]=hL 85 87.30
12 d]lzgaf6 a'lgPsf, Mechanically selvedged double Twist wire
mesh sf] x]lj lhÍ sf]6]8 tof/L u]ljog jfs; mesh size-
100x120mm , mesh wire-3.0 mm , selvedge wire-3.9mm and
j=ld= 207.00
lacing wire-2.4mm
13 d]lzgaf6 a'lgPsf, Mechanically selvedged double Twist wire
mesh sf] x]lj lhÍ sf]6]8 tof/L u]ljog jfs; mesh size-
60x80mm , mesh wire-2.2 mm , selvedge wire-2.7mm and
j=ld= 242.00
lacing wire-2.2mm
14 d]lzgaf6 a'lgPsf, Mechanically selvedged double Twist wire
mesh sf] x]lj lhÍ / lk=le=l;=sf]6]8 tof/L u]ljog jfs;
mesh size-60x80mm , mesh wire-2.2 mm , selvedge wire- j=ld= 395.00
2.7mm and lacing wire-2.2mm

15 d]lzgaf6 a'lgPsf, Mechanically selvedged double Twist wire


mesh sf] x]lj lhÍ / lk=le=l;=sf]6]8 tof/L hDjf] u]ljog
jfs; mesh size-100x120mm , mesh wire-3.0 mm , selvedge j=ld= 261.00

wire-3.9mm and lacing wire-2.4mm


16 d]lzgaf6 a'lgPsf, Mechanically selvedged double Twist wire
mesh sf] x]lj lhÍ / lk=le=l;=sf]6]8 tof/L hDjf] u]ljog
jfs; mesh size-100x120mm , mesh wire-2.70mm , selvedge j=ld= 235.00
wire-3.40 mm and lacing wire-2.20mm

17 Barbed Wire -sfF9]tf/_


12 guage commercial, Medium duty s]=hL 98.34 85.00
U-hook for barbed wire fencing uf]6f 0.76 0.74
18 Fabrication of chain link mesh of size
1"x1" 12 guage au{ dL= 697.00 697.00
1.5"x1.5" 12 guage au{ dL= 652.00 652.00
2"x2" 10 guage au{ dL= 517.00 517.00
3"x3" 10 guage au{ dL= 423.00 423.00
4"x4" 10 guage au{ dL= 337.00 337.00
19 ljleGg k|sf/sf] hfnLx?
dl;gf] vfnsf] Mosquito proof hfnL j=ld= 118.97 116.00

jfn'jf rfNg] hfnL j=ld= 124.37 121.00

s'v'/] hfnL (Chicken wire mesh) j=ld= 75.71 74.00

a|f; qml;Ë hfnL j=ld= 194.67 189.00

:6Ln hfnL -crossing ) j=ld= 156.82 152.00


dl;gf] vfnsf] Steel Mosquito proof hfnL j=ld= 270.38 263.00
kmnfdaf6 lgld{t ;fdfgx?
20
ljleGg ;fO{hsf]] Pd=P;=kmnfd] kl§sf] u|Ln 144.20 130.00
agfO{ h8fg ug]{ sfd s]=hL
21
;f]ln8 :jfo/ /8sf] u|Ln agfO{ h8fg ug]{ sfd Pssf]6 k| 120.00
fO{d/ ;d]t s]=hL
22  sf]NofK;Lan u]6 agfO{ h8fg ug]{ j=lkm= 515.00 500.00
23 !^–!* u]hsf] kmnfd] /f]lnË ;6/ agfO{ h8fg ug]{ j=lkm= 360.00 350.00
kmnfd] /f]lnË ;6/ !^–!* u]h h8fg ;lxt :6«Lk ;6/ Kjfn
24 j=lkm= 453.20 280.00
ePsf]
25
kmnfd] /f]lnË ;6/ 808L k|of]u u/L agfOsf] ;fy} h8fg 515.00 500.00
ug]{ ;d]t j=lkm=
26
!^ u]h kftfaf6 sDkfp08 jfnsf] u]6 agfO{ h8fg ug]{ - j=lkm= 669.50 650.00
%) x %)x % mm) sf] k|m]d ;d]t
#æ–$æ Jof;sf] Iron Black Pipe df PËn / kl§ /fvL
v'8lsnf ;lxtsf] 3'Dg] e¥ofË (Spiral Staircase) tof/ u/L
27 h8fg ;d]t -e¥ofªsf] gfkL ubf{ floor to floor height /=lkm= 3141.50 2961.17

lng]_
28 kmnfdsf] xf]N8kmf:6 -& j6fsf] ! S]=lh=_ s]=hL= 125.00 125.00
29 ljleGg ;fOhsf] lsnf sf6L s]=hL= 112.00 112.00
30 ljleGg ;fOhsf] g6 jf]N6 s]=hL= 165.00 165.00
31 kmnfd] ;fdfu|Lsf] km]la|a]zg tyf h8fg sfo{ s]=hL= 46.00 45.00
32 Readymade Black Pipe Tubular Truss fitting & fixing work s]=hL= 196.00 140.00
Mild Steel Props for Concreting 2" dia 3.5 mm wall thickness
33
and 3.5 m- 4.0 m height uf]6f 1998.00 1940.00

34 :6]gn]; :6Ln kfOk


#÷$Æ Jof; ePsf] !^ u]h df]6fO{ dL6/ 194.00 194.00
!Æ Jof; ePsf] !^ u]h df]6fO{ dL6/ 243.00 243.00
! !÷$Æ Jof; ePsf] !^ u]h df]6fO{ dL6/ 310.00 310.00
! !÷@Æ Jof; ePsf] !^ u]h df]6fO{ dL6/ 376.00 376.00
@Æ Jof; ePsf] !^ u]h df]6fO{ dL6/ 508.00 508.00

;8s / k'n ;DjlGw lgdf{0f ;fdfu|L

d'=c=s= afx]ssf] b//]


lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j= cf=j=
l;=g+++ २)&#÷& @)&$÷&
+= $ %
1 *)÷!)) u|]8sf] lj6'dLg s]=hL 67.50 68.40
2 CRMB-DIGO 55 Bitumen s]=hL 77.40 73.70
3 l56f] hDg] (RS 60%) s]=hL 64.30 63.80
4 l56f] hDg] (RS 65%) s]=hL 68.10 67.60
5 l56f] hDg] (RS 70%) s]=hL 71.90 71.30
6 dWod hDg] (MS 60%) s]=hL 65.10 64.60
7 dWod hDg] (MS 65%) s]=hL 69.80 69.30
8 9Lnf] hDg] (SS60%) s]=hL 66.20 65.70
9 Slurry Seal with 60% bitumen s]=hL 72.90 72.40
10 Hi - seal Redymix s]=hL - 94.00
11 Polymer Bitumen s]=hL - 105.00
12 ;8s sfnf]kq] ubf{ lj6'dLg gpKsLgsf] nfuL k|of]u ug]
{ ;fdfg Anti stripping s]=hL 323.50 323.50

13 sfn]kq] ;8s Pot hole 6fNgsf] nfuL k|of]u ul/g] Pre-


coated Aggregate ;fdfu|L
s]=hL 30.00 30.00

14 sfnf]kq] ;8sdf /]vf+sg ug{ k|of]u ul/g] Therom Plastic


Road marking ;fdfu|L
a) B.S. Grade s]=lh 170.00 165.00
b) Most Grade s]=hL 18.00 182.00
c) Glass beads s]=hL 154.00 150.00
15 Elastomeric Bearing Pad
Free Type uf]6f 19575.00 21247.00
Fix end Dowel Type uf]6f 46180.00 47077.00
16 Expansion Joint Works
Single strip seal /= ld= 8884.00 9316.00
Slab seal (320*50) /= ld= 18360.00 18716.00
17 df]6/ 6«; k'nsf] nflu :6Ln kf6{ km]lj|s]zg km]lj|
s]zg / x6 l8k UofNegfO{h];g ;d]t ug]{ sfd 6g 165000.00

18 df]6/ k'nsf] nflu :6Ln Kn]6 u8{/sf] km]lj|s]zg / x6


l8k UofNegfO{h];g ;d]t ug]{ sfd 6g 169000.00

19 High density polyethene geo-membrane


1.00 mm thickness j=ld= 634.00
2.00 mm thickness j=ld= 1265.00
20 Needle punched non woven geo-textile
weight-120gm/sqm j=ld= 72.00
weight-150gm/sqm j=ld= 80.00
weight-200gm/sqm j=ld= 117.00
21 Tendon sheath dL= 360.00
22 Tendon wire 6g 140400.00
23 Ancorage block with cap uf]6f 9950.00
24 Road divider ( polythene ) uf]6f 1650.00 1650.00
25 Dust bin ( polythene ) 165 ltr uf]6f 3135.00 3135.00
26
! dL6/ Jof; ;Ddsf] af]/xf]n cf/=l;=l;= kfOksf] PDA
Test ug]{ sfd kfOn x]8 tof/ ug]{ / k|ltj]bg ;d]t tof/ uf]6f 190000.00
ug]{ sfd
27 ! dL6/ Jof; ;Ddsf] af]/xf]n cf/=l;=l;= kfOnsf]
Entrigrety Test u/L k|ltj]bg ;d]t tof/ ug]{ sfd
uf]6f 6000.00

28 ! dL6/ Jof; ;Ddsf] af]/xf]n cf/=l;=l;= kfOnsf] Cross


hole ultrasonic monitor (CHUM) Test u/L k|ltj]bg ;d]t uf]6f 10500.00
tof/ ug]{ sfd
emf]n'ª] k'n ;DjlGw
1 Φ 13 mm thimble uf]6f 72.00 72.00
2 Φ 26 mm thimble uf]6f 361.00 361.00
3 Φ 32 mm thimble uf]6f 618.00 618.00
4 Φ 36 mm thimble uf]6f 1236.00 1236.00
5 Φ 40 mm thimble uf]6f 1545.00 1545.00
6 Wire mesh netting -10 SWG 50x50 mesh size a= ld= 412.00 412.00
7 Sign Board with Fittings (Size - 60cm X 90cm) uf]6f 6695.00 6695.00
8 Hot deep galvanized Bolts, Nuts & Washers s]=hL= 258.00 265.00
9 Bolts, Nuts & Washers (Hotdip friction Grip) s]=hL= 361.00 370.00
10 High tensile friction grip nut bolts s]=hL= 335.00 350.00
11 Hot deep galvinazation s]=hL= 45.00 45.00

:yfgLo lgdf{0f ;fdfu|Lx?


d'=c=s= afx]ssf] b/ d'=c=s= afx]ssf]
l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j=
cf=j=
@)&$÷&
२)&#÷&$
%
1 d]lzgaf6 pTkflbt O+{6f -!–g+=_
tf/s]Zj/ g=kf= k|lt xhf/ 15760.00 14880.00

2 lrDgL e§fsf] O{+6f


tf/s]Zj/ g=kf= k|lt xhf/ 14420.00 12470.00
3 t/fO{ sf] ! g+=O{6f
tf/s]Zj/ g=kf= k|lt xhf/ 18025.00 15220.00
4 6'qmf O{6f 3=ld= 2500.00
5 l;d]G6sf] O{6f
BK108N k|lt xhf/ 15450 15450.00
BK118As k|lt xhf/ 16274 16274.00
Concrete block size (40*15*20 ) cm uf]6f 37 37.00
Concrete block size ( 40*10*20 ) cm uf]6f 32 32.00
Concrete block size ( 39*14*19 ) cm uf]6f 50 50.00
Cellular light weight concrete(CLC) block -24"*8"*4" uf]6f 148 162.00
Cellular light weight concrete(CLC) block-24"*8"*6" uf]6f 215 299.00
Cellular light weight concrete(CLC) block- 24"x8"x4" uf]6f 114.00
Cellular light weight concrete(CLC) block 24"x8"x6" uf]6f 171.00
Cellular light weight concrete(CLC) block24"x8"x8" uf]6f 228.00
Autoclaved Aerated Concrete Blocks(Sand based)
Size 2'*8"*4" uf]6f
Size 2'*8"*6" uf]6f
Size 2'*8"*8" uf]6f
6 vfgLsf] 9'+uf
tf/s]Zj/ g=kf= 3=lkm 79 69.00

7 ljleGg k|sf/sf] vfgLsf] afn'jf


tf/s]Zj/ g=kf= j=lkm 79 80.00

8 qm;/af6 pTkflbt ^–!) dL= dL= ;fOhsf] lul§


tf/s]Zj/ g=kf= 3=lkm= 83.00 84.00

9 qm;/af6 pTkflbt !)–@) dL= dL= ;fOhsf] lul§


tf/s]Zj/ g=kf= 3=lkm= 90.00 91.00

10 qm;/af6 pTkflbt @)–$) dL= dL= ;fOhsf] lul§


tf/s]Zj/ g=kf= 3=lkm= 87.00 88.00

11 qm;/af6 pTkflbt ^ dL=dL= eGbf sdsf] lul§


tf/s]Zj/ g=kf= 3=lkm= 75.00 77.00
12 Crusher run sub-base material (63mm down

tf/s]Zj/ g=kf= 3=lkm= 66.00 67.00


13 40 mm down crushed Base material (Wet)
tf/s]Zj/ g=kf= 3=lkm= 77.00 79.00

14 5fgfdf 5fpg] Sn] 6fonx?


d]lzgaf6 pTkflbt 6fon uf]6f 18.00

lrDgL e§fsf] 6fon uf]6f 16.00


d]lzgaf6 pTkflbt w'/L uf]6f 32.00

lrDgL e§fsf] w'/L uf]6f 26.00


15 e'O{df÷ sf};Ldf 5fKg] Sn] 6fonx?
d]lzgaf6 pTkflbt Sn] 6fon uf]6f 10 10.00

lrDgL e§fsf] Sn] 6fon uf]6f 9 9.00

16 5fKg] 9'Ëf -Flag stone_


!Æ ;Dd afSnf] ;km{]; 8]«; u/]sf] 5fKg] 9'Ëf j=lkm 75 74.00

!!÷@Æ ;Dd afSnf] ,, ,, j=lkm 88 86.00

2 ;Dd afSnf] 9'Ëf ,, ,, j=lkm 104 101.00

2.5 ;Dd afSnf] 9'Ëf ,, ,, j=lkm 112 109.00

2.5Æ – #Æ ;Dd afSnf] 9'Ëf ,, j=lkm 139 136.00


17 vf]nfsf] jf]N8/ sf]jn !)) ld=ld= ;Dd 3=lkm= 101.00 103.00

:yfgLo :t/df kfpg] u|fe]n -d]nDrL, l6sfe}/j, es'08] j]l;


18 3=lkm= 53.00 53.00
vfgL jfx]ssf]_
19 kxf8L efudf :yfgLo 9'Ëf -cf};t b'/L *)) ld6/ ;Dd_ 3=lkm= 65.00 65.00

ejgsf] e"FO{+ sf]7fdf k'g{, ;f]lnËsf] Void filling


20 ,, 42.00
ug{ k|of]u ul/g] afn'jf
21 9'uf+sf] w'nf] (Stone dust) 3=lkm= 36.00 38.00

22 lnpg /fVg] Dff6f] (ट्रक ढु वानी बाहेक) 3=ld= 268.00 295.00

23 ;au]|8df /fVg] df6f] -Capping layer Granular soil_ 3=ld= 464.00 510.00
24 e'; s]=lh= 5.15 5.50
25 uf]j/ s]=lh= 4.95 5.00

26 lgdf{0f sfo{sf] nfuL kfgL


# ls=dL= ;Dd sf] b'/Ldf ln6/ 0.26 0.26

# ls=dL= b]lv dfyLsf] b'/Ldf ln6/ 0.31 0.31

27 %)) u]h Knfli6s l;6 j=dL= 31.00 31.00

28 Plastic felt -@)dL= × !dL=_ /f]n 2318.00 2355.00

29 !*–@) lkm6 nfdf] afF; uf]6f 204.00 210.00

lk|sfi6 cf/=l;=l;=kfO{kx? tyf l/ªx?


d'=c=s/ afx]ssf] b//]6
l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j=२)& cf=j= )&$÷
#÷&$ &%
1 NP-2 Class Pipes(Plain)
150 mm dia. /=ld 503.00 503.00
200 mm dia. /=ld 653.00 653.00
250 mm dia. /=ld 818.00 818.00
300 mm dia. /=ld 1109.00 1109.00
350 mm dia. /=ld 1225.00 1225.00
375 mm dia. /=ld 1342.00 1342.00
400 mm dia. /=ld 1543.00 1543.00
450 mm dia. /=ld 1633.00 1633.00
500 mm dia. /=ld 1832.00 1832.00
600 mm dia. /=ld 2417.00 2417.00
700 mm dia. /=ld 3154.00 3154.00
750 mm dia. /=ld 3411.00 3411.00
800 mm dia. /=ld 3807.00 3807.00
900 mm dia. /=ld 5144.00 5144.00
1000 mm dia. /=ld 6002.00 6002.00
1200 mm dia. /=ld 7320.00 7320.00
1500 mm dia. /=ld 15389.00 15389.00
2 NP-3 Class Pipes(Plain)
150 mm dia. /=ld 1156.00
200 mm dia. /=ld 1540.00
250 mm dia. /=ld 1925.00
300 mm dia. /=ld 2767.00
350 mm dia. /=ld 3104.00
375 mm dia. /=ld 3318.00
400 mm dia. /=ld 3536.00
450 mm dia. /=ld 3969.00
500 mm dia. /=ld 4425.00
600 mm dia. /=ld 5468.00
700 mm dia. /=ld 6602.00
750 mm dia. /=ld 7583.00
800 mm dia. /=ld 8276.00
900 mm dia. /=ld 10734.00
1000 mm dia. /=ld 11927.00
1200 mm dia. /=ld 14196.00
1500 mm dia. /=ld 22307.00
3 NP-2 RCC Collar
150 mm dia uf]6f 129.00
200 mm dia uf]6f 170.00
250 mm dia uf]6f 211.00
300 mm dia uf]6f 286.00
350 mm dia uf]6f 315.00
375 mm dia uf]6f 346.00
400 mm dia uf]6f 398.00
450 mm dia uf]6f 420.00
500 mm dia uf]6f 472.00
600 mm dia uf]6f 623.00
700 mm dia uf]6f 812.00
750 mm dia uf]6f 878.00
800 mm dia uf]6f 980.00
900 mm dia uf]6f 1324.00
1000 mm dia uf]6f 1545.00
1200 mm dia uf]6f 1885.00
1500 mm dia uf]6f 3962.00

4 NP-3 Class Collars


150 mm dia. uf]6f 281.00 289.00
200 mm dia. uf]6f 374.00 385.00
250 mm dia. uf]6f 467.00 481.00
300 mm dia. uf]6f 671.00 691.00
350 mm dia. uf]6f 753.00 776.00
375 mm dia. uf]6f 805.00 829.00
400 mm dia. uf]6f 857.00 883.00
450 mm dia. uf]6f 964.00 993.00
500 mm dia. uf]6f 1075.00 1107.00
600 mm dia. uf]6f 1328.00 1368.00
700 mm dia. uf]6f 1602.00 1650.00
750 mm dia. uf]6f 1840.00 1895.00
800 mm dia. uf]6f 2008.00 2068.00
900 mm dia. uf]6f 2605.00 2683.00
1000 mm dia. uf]6f 2895.00 2982.00
1200 mm dia. uf]6f 3446.00 3549.00
1500 mm dia. uf]6f 5415.00 5577.00
5 NP-3 Pipes Socket and Spigot
150 mm dia. /=ld 1306.00 1306.00
200 mm dia. /=ld 1772.00 1772.00
250 mm dia. /=ld 2213.00 2213.00
300 mm dia. /=ld 3181.00 3181.00
400 mm dia. /=ld 4067.00 4067.00
450 mm dia. /=ld 4566.00 4566.00
500 mm dia. /=ld 5089.00 5089.00
600 mm dia. /=ld 6288.00 6288.00
700 mm dia. /=ld 7593.00 7593.00
800 mm dia. /=ld 9517.00 9517.00
900 mm dia. /=ld 12346.00 12346.00
1000 mm dia. /=ld 13717.00 13717.00
1200 mm dia /=ld

ejg lgdf{0fdf k|of]u x'g] lgdf{0f ;fdfu|L


d'=c=s= afx]ssf] b//]6
l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j=
२)&#÷& cf=j=
$ @)&$÷&%
1 नेपालबाट उत्पादित बिभिन्न ओ.पि.सि सिमेन्ट Aofu 797.00 795.00
2 नेपालबाट उत्पादित बिभिन्न पि.पि.सि सिमेन्ट Aofu 765.00 715.00
3 ;]tf] l;d]G6 -40kg/bag) Aofu 1055.00 1230.00
4 l;d]G6 nf]8 ‌/ cgnf]8 Aofu 10.00 10.00
5 Ready Mix Concrete (चक्रपथवाट ३ कि.मि. वाहिर सम्म) 0.00
M 10 Grade 3= ld
M 15 Grade 3= ld 13205.00 14000.00
M 20 Grade 3= ld 13725.00 14500.00
M 25 Grade 3= ld 14375.00 15500.00
M 30 Grade 3= ld 15240.00 16300.00
M 35 Grade 3= ld 0.00 17600
M 40 Grade 3= ld 0.00 18100
6 :6]gn]; :6Ln /]]nLËsf] sfo{– @ OGr kfO{ksf] 7f8f]
kf]i6, @ OGrsf] x]08/]n tyf ! OGr Jof;sf] ltg tx /=kmL= 1168.00 1200.00
t];f{ kfO{k /fvL tof/ ul/ h8fg ug]{ sfd -
7 prfO{
:6]gn];():6Ln
;]=ld=_
/]]nLËsf] sfo{–@ OGr kfO{ksf] 7f8f]
kf]i6, x]08/]n @ OGr tyf ! OGr Jof;sf] b'O{ tx t];f{ /=kmL= 0.00 1050.00
kfO{k /fvL tof/ ul/ h8fg ug]{ sfd
8 :6]gn]; :6Ln /]]nLËsf] sfo{– !=% OGr kfO{ksf]
7f8f] kf]i6, x]08/]n @ OGr tyf ! OGr Jof;sf] ltg tx /=kmL= 0.00 950.00
t];f{ kfO{k /fvL tof/ ul/ h8fg ug]{ sfd
9 ;fbf ;]tf] l;;f 0.00
# dL=dL= j=lkm= 52.00 49.00
#.५ dL=dL= j=lkm= 58.00 56.00
$ dL=dL= j=lkm= 66.00 65.00
% dL=dL= j=lkm= 89.00 75.00
^ dL=dL= j=lkm= 103.00 100.00
८ dL=dL= j=lkm= 173.00 150.00
!) dL=dL= j=lkm= 0.00 190.00
!@ dL=dL= j=lkm= 0.00 220.00

10 a'§]bf/ l;;f 0.00

#.dL=dL= j=lkm= 47.00 48.41


$ dL=dL= j=lkm= 55.00 56.65

11 kf]ln kmfO{j/ Unf; 0.00


^ dL=dL= j=lkm= 150.00 154.50

12 sfnf] /Ësf] l;;f 0.00

#.dL=dL= j=lkm= 89.00 96.00


$ dL=dL= j=lkm= 96.00 103.00
% dL=dL= j=lkm= 109.00 120.00
^ dL=dL= j=lkm= 150.00 180.00
८ dL=dL= j=lkm= 219.00 250.00
!) dL=dL= j=lkm= 211.00 350.00
!@ dL=dL= j=lkm= 355.00 400.00
13 Tinted Float glass aflx/ af6 gb]lvg] leqaf6 b]lvg] 0
% ld=ld afSnf] j=lkm= 107.00 116.00
14
5fgfdf k|of]u ul/g] a'§]bf/ P]gf Itching Glass with j=ld= 5753.00 6200.00
simple shade Reflector
ljleGg /+usf] and texture –$ -lzzf_
Glass dL=dL= –%afSnf]
dL=dL+
15 df]6f] j=lkm= 171.00

Readymade Plaster of Parish cornice and molding 0.00


16
POP Molding 1" to 1½" /=ld 238.00 238.00
Up to 5" wide /=ld 285.00 285.00
Up to 8" wide /=ld 393.00 393.00
Above 8" wide /=ld 161.00 161.00
17 Plaster of paris ls=u|f= 23.00 23.00
18 Wall putty-Normal ls=u|f= 0.00 35.00
19 Wall putty-water proof ls=u|f= 69.00 60.00

20 /fh:yfgL dfj{n 0.00


!# dL=dL afSnf] /fh:yfgL a=lkm= 158.00 160.00
!^ dL=dL afSnf] /fh:yfgL a=lkm= 164.00 175.00
21 u]|gfO6 0
!@ dL=dL afSnf] u]|gfO6 a=lkm= 262.50 289.00
!^ dL=dL afSnf] u]|gfO6 a=lkm= 267.75 295.00
!* dL=dL afSnf] u]|gfO6 a=lkm= 304.50 336.00

22 sf]6f :6f]g 0.00


1" thick a=lkm= 142.00 142.00
3/4" thick a=lkm= 130.00 130.00
23 Porcelain Glazed Tiles 0.00
Thai Tiles a=lkm= 126.00 126.00
Kajaria, Vermura,Somany, Orient Tile or equivalent floor tile a=lkm= 85.00 85.00
Ordinary Floor and Wall tiles a=lkm= 54.00 54.00
Border Tile - 2"x8" /=lkm= 43.00 43.00
Indian Ceramic Wall Tile (31*45cm) j=lkm= 180.00 180.00
Indian Ceramic Floor Tile (31*45cm) j=lkm= 150.00 150.00
24" x 24" GVT j=lkm= 165.00 165.00
24" x 24" GRES Virtified ( Digital Floor) j=lkm= 144.00 144.00
12" x 12" GRES homogenous Vertified parking Tile j=lkm= 106.00 106.00
24" x 24" Virtified j=lkm= 111.00 111.00
Floor tiles-Kajaria, Vermura,Somany, Orient or equivalent 0.00
16"X16" j=lkm= 98.00 98.00
12"x12" j=lkm= 88.00 88.00
12'X12" (White / Ivory) j=lkm= 77.00 77.00
24"x24" (Digital) j=lkm= 129.00 129.00
12"x24" (Walls) j=lkm= 134.00 134.00
12"x18"(wall) j=lkm= 103.00 103.00

24 5fgfdf 6fOnsf] j'§f sf6\g] / kfgL k§L sfo{ 0.00


!=$ efusf] ld>0fsf] l;d]G6 d;nf tof/ ul/ v6 /flv !Æ
jfSnf] Knfi6/df ?lkmª 6fOnsf] j'§f sf6\g] ;fdfg ;lxt j=ld= 623.00 623.00

!Æ ;fOhsf] !M# efusf] ld>0fsf] d;nf tof/ ul/ v6 /flv


/=dL 75.00 75.00
jiff{bsf] kfgL k§L agfpg] sfd
25 Heritage Wall Surface Texture (Interior and Exterior)
including the cost of supplying and fitting
Heritage granular j=lkm 88.00 87.00
Heritage flakes j=lkm 108.00 107.00
Heritage granite finish j=lkm 88.00 87.00
Heritage Top coat (plastic lamination) j=lkm 23.00 22.00

df6f] tyf 9'+Ëfjf6 lgld{t k/Dk/fut lgdf{0f ;fdfu|Lx?


d'=c=s/ afx]ssf] b//]6
l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j= cf=j=
२)&#÷&$ २)&$÷&%
d7dlGb/df k|of]u x'g] 9'Ësf ljleGg ;fdu|Lx?
1 sfnf] 9'+ufsf] a'6f ;lxtsf] yfd ^ÆÍ (ÆÍ ^)Æ k|lt uf]6f 70000
2 sfnf] 9'+ufsf] a'6f ;lxtsf] yfd ^ÆÍ (ÆÍ ^=^Æ k|lt uf]6f 105000
3 sfnf] 9'+ufsf] a'6f ;lxtsf] yfd !@ÆÍ !@ÆÍ &=^Æ k|lt uf]6f 240000
4 $Æ afSnf] k]6L 9'+uf -!)ÆÍ $Æ_ lkm6 800
5 $Æ afSnf] gfuf]n 9'+uf -!)ÆÍ $Æ_ lkm6 900
6 $Æ afSnf] a'6]bf/L sl;df], sfg]{; / ˆof] -!)ÆÍ $Æ_ lkm6 3700
7 sfnf] ;fO8n 9'+uf -ONxf]+_ -#)Æ Í#)ÆÍ !*Æ_ k|lt uf]6f 40000
8 Peti kuna Dhunga(19.9"*9"*18") k|lt uf]6f 2266.00 2720.00
9 Peti kuna Dhunga(10"*10"*14") k|lt uf]6f 1586.00 1900.00
10 Bichako naykha nhu k|lt uf]6f 793.00 950.00
11 Dhungey dhara k|lt uf]6f 1133.00 1360.00
12 Peti Dhunga 4" k|lt uf]6f 2039.00 2450.00
13 Peti Dhunga 5" ld6/ 2493.00 2990.00
14 Shree Ganesh/Kumar Dhunga ko Murti k|lt uf]6f 1133.00 1360.00
15 9'Ë]wf/f uf]6f 1133.00 1155.00

df6f] jf6 lgld{t k/Dk/fut lgdf{0f ;fdfu|Lx?


1 Daachi Appa uf]6f 21.00 25.00
2 Daachi kuna uf]6f 25.00 35.00
2 Twa Aapa uf]6f 18.00 27.00
3 Gol Aapa uf]6f 18.00 27.00
4 Ganesh/kumar/tara/Panch Buddha uf]6f 340.00 320.00
5 Kalash(4"x6") uf]6f 57.00 53.00
6 Kalash(9"x12") uf]6f 158.00
7 Nagol uf]6f 27.00
8 Nagol kuna uf]6f 40.00
9 Kashimo uf]6f 29.00 27.00
10 Kashimo Kuna uf]6f 40.00
11 Sakuli uf]6f 25.00 27.00
12 Sakuli Kuna uf]6f 40.00
13 Paan butta uf]6f 25.00 27.00
14 Paan butta Kuna uf]6f 40.00
15 Sano Fa butta uf]6f 29.00 27.00
16 Sano Fa butta Kuna uf]6f 40.00
17 Thulo Fa butta uf]6f 29.00 27.00
18 Thulo Fa butta kuna uf]6f 40.00
19 Naya fa butta uf]6f 29.00 27.00
20 Naya fa butta Kuna uf]6f 40.00
21 Sano ga butta uf]6f 25.00 27.00
22 Sano ga butta Kuna uf]6f 40.00
23 Thulo Ga butta uf]6f 29.00 27.00
24 Thulo Ga butta Kuna uf]6f 40.00
25 Pumha buta uf]6f 29.00 27.00
26 Pumha buta Kuna uf]6f 40.00
27 Tinkune swa uf]6f 29.00 27.00
28 Tinkune swa Kuna uf]6f 40.00
29 Tinkune Pali uf]6f 29.00 27.00
30 Tinkune Pali kuna uf]6f 40.00
31 Sano swa butta uf]6f 25.00 27.00
32 Sano swa butta Kuna uf]6f 40.00
33 Thulo swa Butta uf]6f 29.00 27.00
34 Thulo swa Butta Kuna uf]6f 40.00
35 Nag tauko R/L uf]6f 142.00 132.00
36 Nag Ghati R/L uf]6f 74.00 70.00
37 Nag Jiu uf]6f 25.00 27.00
38 Kuna uf]6f 40.00
39 Thulo Nag tauko R/L uf]6f 132.00
40 Nag Ghati uf]6f 70.00
41 Thulo Nag Jiu uf]6f 27.00
42 Thulo Nag Jiu Kuna uf]6f 40.00
43 Nag Male/Female uf]6f 566.00 530.00
44 Khal Nagol uf]6f 20.00 27.00
45 Khal Nagol Kuna uf]6f 40.00
46 Khal Fyo uf]6f 20.00 27.00
47 Khal Fyo Kuna uf]6f 40.00
48 Lahara butta uf]6f 25.00 27.00
49 Lahara butta Kuna uf]6f 40.00
50 Nagbeli uf]6f 25.00 27.00
51 Nagbeli kuna uf]6f 40.00
52 Mikhafushi mathi R/L uf]6f 34.00 32.00
53 Mikhafushi mathi R/L Kuna uf]6f 25.00 32.00
54 Mikhafushi mathi Bitch uf]6f 32.00
55 Mikhafushi Tal R/L Kuna uf]6f 32.00
56 Mikhafushi Tal R/L uf]6f 32.00
57 Mikhafushi Tal Bitch uf]6f 32.00
58 Palifo R/L uf]6f 29.00 27.00
59 Palifo R/L Kuna uf]6f 40.00
60 Palifo Bitch uf]6f 40.00
61 Naya Palifo uf]6f 29.00 27.00
62 Naya Palifo Kuna uf]6f 40.00
63 Shida Palifo uf]6f 29.00 27.00
64 Shida Palifo kuna uf]6f 40.00
65 Thulo Palifo R/L uf]6f 27.00
66 Thulo Palifo R/L Kuna uf]6f 40.00
67 Thulo Palifo Bitch uf]6f 27.00
68 2" Singh uf]6f 34.00 32.00
69 2" Garud uf]6f 34.00 32.00
70 Dhalimo uf]6f 34.00 32.00
71 3" Singh uf]6f 42.00
72 3" Garud uf]6f 42.00
73 3" singh full Jodiyako uf]6f 53.00
74 3" Astmangal uf]6f 42.00
75 3" Garud full uf]6f 53.00
76 4" Singh uf]6f 53.00
77 4" Garud uf]6f 53.00
78 Twa fyo uf]6f 27.00
79 Twa fyo Kuna uf]6f 40.00
80 4" Astmangal uf]6f 53.00
81 6" Singh uf]6f 105.00
82 6" Garud uf]6f 105.00
83 Chaal butta uf]6f 27.00
84 Chaal butta Kuna uf]6f 40.00
85 2" fyo uf]6f 27.00
86 2" fyo Kuna uf]6f 40.00
87 4" fyo uf]6f 27.00
88 4" fyo Kuna uf]6f 40.00
89 Tara Butta Puralo uf]6f 25.00 27.00
90 Tara Butta Puralo Kuna uf]6f 40.00
91 Naya tara butta uf]6f 29.00 27.00
92 Naya tara butta Kuna uf]6f 40.00
93 Swafo tara uf]6f 29.00 27.00
94 Swafo tara Kuna uf]6f 40.00
95 Sikri butta uf]6f 29.00 27.00
96 Sikri butta Kuna uf]6f 40.00
97 Na Sikri uf]6f 27.00
98 Na Sikri Kuna uf]6f 40.00
99 Nhaya butta sano uf]6f 29.00 27.00
100 Na Sikri Kuna uf]6f 40.00
101 Nhaya butta Thulo uf]6f 29.00 27.00
102 Nhaya butta Thulo Kuna uf]6f 40.00
103 Gol Nagol uf]6f 20.00 27.00
104 Gol Nagol kuna uf]6f 40.00
105 Ga swa butta uf]6f 27.00
106 Ga swa butta Kuna uf]6f 40.00
107 Chandrama butta uf]6f 27.00
108 Chandrama butta kuna uf]6f 40.00
109 Ga tha butta uf]6f 27.00
110 Ga tha butta Kuna uf]6f 40.00
111 Bajra lahara uf]6f 27.00
112 Bajra lahara Kuna uf]6f 40.00
113 Simakacha uf]6f 27.00
114 Simakacha Kuna uf]6f 40.00
115 Methpau uf]6f 27.00
116 Chir butta uf]6f 27.00
117 Chir butta Kuna uf]6f 40.00
118 Thi butta uf]6f 29.00 27.00
119 Thi butta Kuna uf]6f 40.00
120 32 No. swa uf]6f 27.00
121 32 No. swa Kuna uf]6f 40.00
122 Sano Ribbon uf]6f 27.00
123 Sano Ribbon Kuna uf]6f 40.00
124 Thulo Ribbon uf]6f 27.00
125 Thulo Ribbon Kuna uf]6f 40.00
126 Bajra tara butta uf]6f 27.00
127 Bajra tara butta Kuna uf]6f 40.00
128 fa paliha swa uf]6f 60.00
129 2" Tham uf]6f 53.00
130 3" Tham uf]6f 69.00
131 4" Tam uf]6f 105.00
132 Ga tara butta uf]6f 27.00
133 Ga tara butta Kuna uf]6f 40.00
134 Full tara butta uf]6f 27.00
135 Full tara butta Kuna uf]6f 40.00
136 Meth uf]6f 500.00
137 12" Tham Set uf]6f 1896.00
138 6"x6" teliya/ 6*6 tinkune uf]6f 14.00 22.00
139 8*8 teliya uf]6f 35.00
140 Teliya nagol uf]6f 25.00
141 Teliya nagol kuna uf]6f 37.00
142 Khoshi Kerafo uf]6f 27.00
143 Khoshi Kerafo Kuna uf]6f 40.00
144 teliya skating uf]6f 37.00
145 Naya lahara butta uf]6f 27.00
146 Naya lahara butta Kuna uf]6f 40.00
147 kamal lahara uf]6f 27.00
148 kamal lahara Kuna uf]6f 40.00
149 Sano kera Fo uf]6f 27.00
150 Sano kera Fo Kuna uf]6f 40.00
151 Thulo kera fo uf]6f 27.00
152 Thulo kera fo Kuna uf]6f 40.00
153 Dhalimo uf]6f 32.00
154 Dhalimo Kuna uf]6f 40.00
155 Illa butta uf]6f 27.00
156 Illa butta Kuna uf]6f 40.00
157 Parda Butta Sano R/L uf]6f 27.00
158 Parda Butta Sano R/L Kuna uf]6f 40.00
159 Parda Butta Sano Bitch uf]6f 40.00
160 Parda butta Thulo R/L uf]6f 27.00
161 Parda butta Thulo R/L Kuna uf]6f 40.00
162 Parda butta Thulo bitch uf]6f 40.00
163 Pu pali butta uf]6f 63.00
164 Thulo Singal Palifo uf]6f 63.00
165 Kalash jhalar uf]6f 63.00
166 ganesh Gajur Pali uf]6f 63.00
167 ganesh Gajur Pali Kuna uf]6f 105.00
168 60 No. khwabutta uf]6f 27.00
169 60 No. khwabutta Kuna uf]6f 40.00
170 Tiki jhaya uf]6f 27.00
171 bhyafyo apa uf]6f 69.00
172 Naya Jhalar uf]6f 27.00
173 Naya Jhalar Kuna uf]6f 40.00
174 nyakucha uf]6f 27.00
175 Jingati uf]6f 10.00
176 Lock Dhuri uf]6f 75.00
177 Dhuku uf]6f 75.00
178 df cfkf uf]6f 19.00
179 Tjf cfkf uf]6f 25.00
180 ˆof ckf uf]6f 27.00
181 brL s'nf uf]6f 35.00
182 uf]+urf ;fgf] uf]6f 150.00
183 uf]+urf dme}nf uf]6f 250.00
184 uf]+urf 7"nf] uf]6f 300.00
185 Gofs'rf uf]6f 22.00
186 >L u0f]z uf]6f 1133.00 1155.00
187 s'df/ uf]6f 1133.00 1155.00
188 $ÆÍ $Æ e}/j uf]6f 2000.00
189 %ÆÍ %Æ e}/j uf]6f 3000.00
190 7'nf] snz uf]6f 170.00 173.00
191 d;Lgf] ;"ls{ s]=hL= 13.00 14.00
192 v;|f] ;'ls{ s]=hL= 8.00 8.00
193 गट्टा r'g s]=lh= 23.00 23.00
194 tfdf kftf= s]=hL= 1076.00 1350.00
195 lkQn kftf s]=hL= 850.00 1025.00
196 kf/f] tf]nf 170.00 300.00
197 ;"ls{ O6f s'l6 w'nf] agfPsf] 6g 1360.00 1386.00
198 xjf 306L $Æ uf]6f 467.00 476.00

sf7 tyf KnfOp8 ;+jlGw lgdf{0f ;fdfu|L


d'=c=s/ afx]ssf] b//]6
cf=j= cf=j=
l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{
२)&#÷& @)&$÷&
$ %
1 ^Ú ;Ddsf] ;fnsf7 3= lkm 5800.00
2 ^… b]lv *Ú ;Ddsf] ;fnsf7 3= lkm 5975.00 5975.00
3 *… b]lv !@Ú ;Ddsf] ;fnsf7 3= lkm 6260.00 6250.00
4 !@ lkm6 b]lv dflysf] ;fn sf7 3= lkm 6550.00 6600.00
5 ;fh sf7 3= lkm 3500.00 3350.00
6 hfd'g sf7 3= lkm 2135.00 2150.00
7 ;Nnfsf] sf7 3= lkm 1130.00 1550.00
8 l;;f}+ sf7 3= lkm 2300.00 3500.00
9 h+unL l;;f}+ sf7 ,, 3= lkm 5270.00 5270.00
10 ptL; sf] sf7 3= lkm 595.00 625.00
11 sf7 bfp/f s]=hL 18.00 18.00
12 #* ld=ld= df]6fO{sf] s]ldsNnL l6«6]]8 d]l;gd]8 jf6/k|'km, af]// lkm| ;f]nL8sf]/ km\n;8f]/ ;6/

;fwf/0f
Plain j=lkm 233.00 235.00

Ordinary-one side teak water proof j=lkm 280.00

Both side teak water Proof j=lkm 325.00

jf6/ k|'km ul/Psf]


Plain j=lkm 245.00

One side teak j=lkm 262.00 288.00

Both side teak j=lkm 317.00 333.00

13 s'lbPsf] sf7sf] sfd tof/L


e¥ofËsf] /]lnË tyf afb{nL cflbdf
uf]6f 746.00 1080.00
s'FlbPsf] :yfgLo ;L;f} sf7sf] x'Ssf (2'-6"x3"x3")
e¥ofËsf] /]lnË tyf afb{nL cflbdf s'FlbPsf]
h+unL :k]zn ;L;f} sf7sf] x'Ssf (2'-6"x3"x3") uf]6f 814.00 1260.00

e¥ofËsf] /]lnË tyf afb{nL cflbdf s'FlbPsf] ;L;f} /=lkm= 678.00 680.00
sf7sf] x]08 /]n (3"x4")
e¥ofËsf] /]lnËsf] 3'Dg] 7fpFdf s'FlbPsf] ;L;f} uf]6f 2984.00 2250.00
sf7sf] uf]nf] x]08 /]n (3"x4")
b]jL b]jtfsf] d'lt{ s'FlbPsf] $… b]lv %… nfdf] - uf]6f 9493.00 13500.00
#Æx *Æ_ ;fn sf7df 6'F8fn agfpg] sfd
b]jL b]jtfsf] d'lt{ s'FlbPsf] ^… b]lv &… nfdf] -
#Æx *Æ_ ;fn sf7df 6'F8fn agfpg] sfd uf]6f 10850.00 22500.00

ljleGg a'§f tyf b]jL b]jtfsf] d'lt{ s'FlbPsf] ;fn sf7sf]


em\ofn 9f]sf agfpg] sfd -vfkfsf] df6fO{ $) ld=ld= j=lkm= 2034.00 3150.00
b]lv %) ld=ld= ;Dd _
3f]8fsf] cfs[lt ul/ s'FlbPsf] $Æx %Æ ;fOhsf] #…
b]lv $… nfdf] ;fn sf7sf] tof/L 6'F8fn agfpg] sfd . uf]6f 4747.00 7280.00

;fdfGo k|sf/sf] s'FlbPsf] ;fnsf] sf7sf] cfFvL em\ofn j=lkm= 678.00 1350.00
tof/L
dWod k|sf/sf] s'FlbPsf] ;fnsf] sf7sf] cfFvL em\ofn j=lkm= 949.00 1620.00
tof/L
ljz]if k|sf/sf] s'FlbPsf] ;fnsf] sf7sf] cfFvL em\ofn
j=lkm= 2034.00 2250.00
tof/L ns ;xLt
ljz]if k|sf/sf] s'FlbPsf] ;fnsf] sf7sf] cfFvL em\ofn
j=lkm= 1288.00 1980.00
tof/L ns gePsf]
#Æx !=%Æ ;fOhsf] ;fnsf] sf7sf] s'FlbPsf] knL
tof/L ug]{ sfd /=lkm= 475.00 360.00

sF'lbPsf] ljleGg a'§f /fvL agfPsf] ;fn sf7sf] $Æx


%Æsf] sfg]{; lad cflb tof/L ug]{ sfo{ /=lkm= 814.00 1620.00

$Æx %Æsf] ;fn sf7sf] gfu a'§f sF'lb tof/L u/L h8fg
ug]{ sfo{ /=lkm= 678.00 1710.00

14 Wooden Parquet Flooring


Shisam wooden parqueting150mm*30mm*8mm j=lkm= 167.00 220.00

Wall panelling ( with wood frame) sisam wood.


(75mm*16mm) j=lkm= 556.00 560.00

15 ljleGg df]6fO{sf] KnfOp8x?


;fwf/0f KnfOp8
# dL=dL j=lkm 36.00 36.00

#=% dL=dL= j=lkm 26.00 26.00

$ dL=dL j=lkm 26.00 26.00

^ dL=dL j=lkm 53.00 53.00

* dL=dL j=lkm 57.00 57.00

!@ dL=dL j=lkm 80.00 80.00

!( dL=dL B/B j=lkm 107.00 107.00

!* dL=dL PLY j=lkm 110.00 110.00

16 jf6/ k|'km KnfOp8 0.00

$ dL=dL j=lkm 39.00 52.00


^ dL=dL j=lkm 52.00 67.00

* dL=dL= j=lkm 57.00 63.00

( dL=dL= j=lkm 62.00 89.00

!@ dL=dL j=lkm 72.00 99.00

!% dL=dL PLY j=lkm 118.00 113.00

!* dL=dL B/B j=lkm 100.00 139.00

17 Natural Teak Plywood 0.00 0.00

# dL =dL j=lkm 55.00 48.00

$ dL= dL] (Group Match of in 5 pcs) j=lkm 72.00 69.00

$ dL= dL] -Regular_ j=lkm 62.00 60.00

$ dL= dL] -Crown_ j=lkm 42.00 43.00

$ dL= dL] -Beri_ j=lkm 48.00 49.00

$ dL= dL] -Whitest line_ j=lkm 38.00 39.00

$ dL= dL] -Beach_ j=lkm 45.00 46.00

$ dL= dL] -Recon 18 No._ j=lkm 36.00 37.00

18 ;gdfO{sf tyf km/dfO{sf


;gdfO{sf (4' x 8') j=lkm kftf 486 17.00

kmf]/dfO{sf j=lkm 75.00 75.00

xf8{jf]8{ (Hard board) 12 mm thick j=lkm 44.00 44.00


19 DECORATIVE (THICKER)
6 OST j=lkm 84.00 126.00
6 BST j=lkm 107.00 160.00
9 OST j=lkm 95.00 140.00
9 BST j=lkm 119.00 173.00
12 OST j=lkm 107.00 153.00
12 BST j=lkm 132.00 187.00
19 B/B OST j=lkm 119.00 165.00
19 B/B BST j=lkm 144.00 200.00
18 OST j=lkm 132.00 187.00
18 BST j=lkm 157.00 221.00
20 Ready made Teak wood Doors (Seasoned and
Poisoned treated )
( excluding the cost of fitting, transportation, Painting)

Readymade door shutter Recon, ordinary (1 side teak) j=lkm 174.00 174.00

Readymade door shutter Recon, Special (1 side teak) j=lkm 237.00 237.00

Oneside water proof ply fitting

Readymade door shutter Recon, ordinary (1 side teak) j=lkm 199.00 199.00

Readymade door shutter Recon, Special (1 side teak) j=lkm 268.00 268.00

21 sf7sf] lnli6
1/2" wide /=lkm= 14.00 14.00

3/4" wide /=lkm= 16.00 16.00

1.5" wide /=lkm= 27.00 27.00

Decorative /=lkm= 38.00 38.00


22 Infill Material
Frame C - Studs( 0.55mm*0.75mm*3m) uf]6f 391.40 380.00

Frame U - Studs( 0.55mm*0.75mm*3m) uf]6f 391.40 380.00

Board 9 mm uf]6f 2294.00 2227.00

Fiber mess tape (for 90mm/roll) uf]6f 309.00 300.00

PU sasuage rod uf]6f 1854.00 1800.00

Aluminum Doors and Windows

d'=c=s/ afx]ssf] b//]6


l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j=
cf=j= @)&$÷&
२)&#÷&$ %
102 SERIES WINDOWS
1 Providing and fixing Single Panel Casement (Hinged) Door of
aluminum section in natural or color anodized/powder coated color
Section size (102×45×1.5 mm) fitted with 5 mm clear glass or 9 Sq.ft. 611.00 657.00
mm both side laminated board (excluding the cost of handle and
door closer ).

2 Providing and fixing Double Panel Casement (Hinged) Door of


aluminum section in natural or color anodized/powder coated color
Section size (102×45×1.5 mm) fitted with 5 mm clear glass or 9 Sq.ft. 611.00 723.00
mm both side laminated board (excluding the cost of handle and
door closer ).

3 Providing and fixing Single Panel Swing Door of aluminum section


in naturally anodized or black anodized/powder coated color
Section size (102×45×1.50 mm) fitted with 5 mm clear glass or 9 Sq.ft. 611.00 836.00
mm both side laminated board (excluding the cost of handle).

4 Providing and fixing Double Panel Swing Door of aluminum section


in naturally anodized or black anodized/powder coated color
Section size (102×45×1.50 mm) fitted with 5 mm clear glass or 9 Sq.ft. - 920.00
mm both side laminated board (excluding the cost of handle).

90 SERIES WINDOWS
1 Providing and fixing 2 or 3 Panel Sliding Window of aluminum
section in naturally anodized or Black anodized/powder coaded
color, Section size (87x56×1.20 mm) fitted with 5 mm clear glass Sq.ft. 542.00 529.00
without fly mesh shutter. (window size 6' x 5' or average area 30
sq. feet per window).

2 Providing and fixing 2 or 3 panel sliding window of aluminum


section in naturally anodized or black anodized/powder coated
color, Section size (87x56x1.50 mm) fitted with 5 mm clear glass Sq.ft. 536.00 604.00
with out fly mesh shutter. (window size 6'x5' or average area 30 sq.
feet per window).

3 Providing and fixing 2 or 3 panel sliding window with top fix glass
of aluminum section in naturally anodized or black
anodized/powder coated color, Section size (87×65×1.20 mm) Sq.ft. 499.00 571.00
fitted with 5 mm clear glass with out fly mesh shutter. (window
size 6'x5' or average area 30 sq. feet per window).

4 Providing and fixing 2 or 3 panel sliding window with top fix glass
of aluminum section in naturally anodized or black
anodized/powder coated color, Section size (87x56×1.50 mm) Sq.ft. 645.00 658.00
fitted with 5 mm clear glass with out fly mesh shutter. (window
size 6'x5' or average area 30 sq. feet per window).
5 Providing and fixing Fixed Window of aluminum section in
naturally anodized or black anodized/powder coated color, Section
size (87x25+12×1.20 mm) fitted with 5 mm clear glass with out fly Sq.ft. 403.00 428.00
mesh shutter. (Average area 5 sq. feet per panel).
6 Providing and fixing Fixed Window of aluminum section in
naturally anodized or black anodized/powder coated color, Section
size (87x25+12×1.5 mm) fitted with 5 mm clear glass with out fly Sq.ft. 492.00 492.00
mesh shutter. (Average area 5 sq. feet per panel).
7 Providing and fixing Fly Mesh Shutter with stainless steel fly mesh
in 90 series for sliding window. (Section thickness 1 mm) Sq.ft. 140.00 188.00

102 SERIES PARTITION


1 Providing and fixing Full Height Partition of aluminum section in
naturally anodized or black anodized/powder coated color Section
size (102×45×1.5 mm) fitted with 5 mm clear glass or 9 mm both Sq.ft. 469.00 519.00
side laminated board.(average panel area 8.00 Sq.ft).

2 Providing and fixing Half Height Partition of aluminum section in


naturally anodized or black anodized/powder coated color Section
size (102×45×1.5 mm) fitted with 5 mm clear glass or 9 mm both Sq.ft. - 563.00
side laminated board.(average panel area 6.00 Sq.ft).

64 SERIES PARTITION
1 Providing and fixing Full Height Partition of aluminum section in
naturally anodized or black anodized color Section size
(64x38x1.10 mm) fitted with 5 mm clear glass or 9 mm both side Sq.ft. 377.00 390.00
laminated board.(average panel area 8.00 Sq.ft).
2 Providing and fixing low height partition of aluminum section in
naturally anodized or black anodized color Section size
(64x38x1.10 mm) fitted with 5 mm clear glass or 9 mm both side Sq.ft. 469.00 478.00
laminated board.(average panel area 6.00 Sq.ft).

STRUCTURAL GLAZING
1 Providing and fixing Structural Glazing of aluminum section in
natural or color anodized/powder coated color Section size
(60x50+13x1.3 mm) fitted with 5 mm color glass. Sq.ft. 525.00 548.00
(average panel area 6.00 Sq.ft.)
2 Providing and fixing Structural Glazing of aluminum section in
natural or color anodized/powder coated color Section size
(60x75+13x1.6 mm) fitted with 5 mm color glass . Sq.ft. 609.00 636.00
(average panel area 6.00 Sq.ft.)
3 Providing and fixing Structural Glazing of aluminum section in
natural or color anodized/powder coated color Section size
(60x100+13x2 mm) fitted with 5 mm color glass . (average panel Sq.ft. 740.00 773.00
area 6.00 Sq.ft.)

GLASS DOOR & PARTITION


1 Providing and fixing Fixid Glass Door of 12 mm Clear Toughened
Glass with Stainless Steel patches or Aluninium Frame (Ground Sq.ft. - 1259.00
Floor).
2 Providing and fixing Fixid Glass Partition of 12 mm Clear
Toughened Glass with Stainless Steel patches or Aluninium Frame Sq.ft. - 817.00
(Ground Floor).
3 Providing and fixing Fixid Glass Partition of 12 mm Clear
Toughened Glass with Spider Fitting. Sq.ft. - 1354.00

Aluminium Composite Panel (ACP). -


1 Providing and fixing ACP Cladding on wall (Exterior) 3 mm thick
ACP (0.25 mm Aluminium PVDF Core) on 25x38 mm Aluminium Sq.ft. - 333.00
Tube framing.
2 Providing and fixing ACP Cladding on wall (Exterior) 4 mm thick
ACP (0.25 mm Aluminium PVDF Core) on 25x38 mm Aluminium Sq.ft. - 447.00
Tube framing.

UPVC Profile for Door/Window


d'=c=s/ afx]ssf] b//]6
l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j=
cf=j= @)&$÷&
२)&#÷&$ %
Supplying and installation of UPVC Profile: Sliding window frame 50*80mm; sash 58*36mm, Sliding Door frame 52*88; sash 80*42, Casement
60*60mm:sash
A Single60*78mm,
glazing Casement Door frame 60*60; sash 60*104mm white colour with reinforcement, 5mm thick clear float glass, insect net, p
1 UPVC Sliding window with net (frame 50*80 mm, sash 58*36 mm,
white colour with 5mm glass)
j=ld 7,005.00 7215.00
2 UPVC Sliding window without net (frame 60*60 mm, sash 66*42
mm, white colour with 5mm glass) j=ld 6,470.00 6664.00

3 UPVC Top Hung window (frame 60*60 mm, sash 60*78 mm, white
colour with 5mm glass) j=ld 7275.00 7493.00

4 UPVC Casement window (frame 60*60 mm, sash 60*78 mm, white
colour with 5mm glass) j=ld 7275.00 7493.00

5 UPVC Single Door with half panel half glass (frame 60*60 mm,
sash 60*104 mm, white colour with 5mm glass) j=ld 7975.00 8214.00

6 UPVC Single Door with full panel (frame 60*60 mm, sash 60*104
mm, white colour) j=ld 8085.00 8328.00

7 UPVC Double Door (frame 60*60 mm, sash 60*104 mm, white
colour with 5mm glass) j=ld 8625.00 8884.00

8 UPVC Sliding Door with net (frame 52*88 mm, sash 88*42 mm,
white colour with 5mm glass) j=ld 8625.00 8884.00

9 UPVC Sliding Door without net (frame 60*60 mm, sash 88*42 mm,
white colour with 5mm glass) j=ld 8355.00 8606.00

10 UPVC Swing Door with half glass half uPVC panel (frame 60*60
mm) j=ld 9700.00 9991.00

11 UPVC 88x60mm Sliding white colour window with 5mm glass


pannele j=ld 8375.00 8626.00

11 UPVC 60x64mm white colour casement window with 5mm glass


pannele j=ld 9511.00 9796.00

12 UPVC110x64mm x9mmthick board and 5mm tjick glass pannel


white colour j=ld 10051.00 10353.00

12 UPVC60x60mm x9mmthick white colour partition board with


5mm glass j=ld 10405.00 10717.00

13 UPVC60x60mm white colour swing door with 5mm glass pannel


j=ld 6531.00 6727.00

B Double glazing
1 UPVC Sliding window with net (frame 50*80 mm, sash 58*36 mm,
white colour with 5mm double glass) j=ld 9160.00 9435.00

2 UPVC Sliding window without net (frame 60*60 mm, sash 66*42
mm, white colour with 5mm double glass) j=ld 8675.00 8935.00

3 UPVC Top Hung window (frame 60*60 mm, sash 60*78 mm, white
colour with 5mm double glass) j=ld 9435.00 9718.00

4 UPVC Casement window (frame 60*60 mm, sash 60*78 mm, white
colour with 5mm double glass) j=ld 9435.00 9718.00

5 UPVC Single Door with half panel half glass (frame 60*60 mm,
sash 60*104 mm, white colour with 5mm double glass) j=ld 10135.00 10439.00

6 UPVC Double Door (frame 60*60 mm, sash 60*104 mm, white
colour with 5mm double glass) j=ld 10240.00 10547.00

7 UPVC Sliding Door with net (frame 52*88 mm, sash 88*42 mm,
white colour with 5mm double glass) j=ld 10780.00 11103.00

8 UPVC Sliding Door without net (frame 60*60 mm, sash 88*42 mm,
white colour with 5mm double glass) j=ld 10510.00 10825.00

9 Supply & fixing of 80*50 mm white colour casement window j=ld 9331.00 9611.00

5fgf 5fpg] lgdf{0f ;fdfu|L


d'=c=s/ afx]ssf] b//]6
l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{
l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j= cf=j=
२)&#÷&$ २)&$÷&%

1 UofNegfO{h ;]tf] ;fbf h:tfkftf


0.20 mm (30 guage light) a08n 3782.74 4274
0.22 mm (30 guage Medium) a08n 4120.00 4655
0.24 mm (30 guage Heavy) a08n 4439.03 5035
0.26 mm (28 guage light) a08n 4639.56 5283
0.28 mm (28 guage Medium) a08n 4931.24 5611
0.31 mm (28 guage Heavy) a08n 5405.22 6177
0.35 mm (26 guage light) a08n 5988.58 6823
0.37 mm (26 guage Medium) a08n 6252.92 7142
0.41 mm (26 guage Heavy) a08n 6517.26 7823
0.45 mm (24 guage light) a08n 7428.76 8478
0.50 mm (24 guage Medium) a08n 8221.77 9372
0.52 mm (24 guage Heavy) a08n 8467.88 9690
0.75 mm a08n 12159.47 14770

2 sf]?u]6]8 /+lug h:tfkftf


0.20 mm (30 guage light) a08n 5077.08 5513
0.22 mm (30 guage Medium) a08n 5414.34 5854
0.24 mm (30 guage Heavy) a08n 5724.25 6226
0.26 mm (28 guage light) a08n 6034.16 6558
0.28 mm (28 guage Medium) a08n 6371.42 6929
0.31 mm (28 guage Heavy) a08n 6854.51 7504
0.35 mm (26 guage light) a08n 7574.60 8274
0.37 mm (26 guage Medium) a08n 7957.43 8686
0.41 mm (26 guage Heavy) a08n 8613.72 9420
0.45 mm (24 guage light) a08n 9233.54 10102
0.50 mm (24 guage Medium) a08n 929.73 11000
0.52 mm (24 guage Heavy) a08n 10382.04 11389
0.55 mm(24 guage Medium) a08n 11929
0.75 mm a08n 14565.84 15991

3 UofNefgfOH8 sf]?u]6]8 h:tfkftf


0.20 mm (30 guage light) a08n 3782.74 4274
0.22 mm (30 guage Medium) a08n 4074.42 4615
0.24 mm (30 guage Heavy) a08n 4393.45 4991
0.26 mm (28 guage light) a08n 4584.87 5230
0.28 mm (28 guage Medium) a08n 4885.66 5558
0.31 mm (28 guage Heavy) a08n 5350.53 6102
0.35 mm (26 guage light) a08n 5933.89 6765
0.37 mm (26 guage Medium) a08n 6198.23 7088
0.41 mm (26 guage Heavy) a08n 6808.94 7761
0.45 mm (24 guage light) a08n 7374.07 8420
0.50 mm (24 guage Medium) a08n 8167.08 9315
0.52 mm (24 guage Heavy) a08n 8413.19 9628
0.75 mm a08n 12159.47 13885

4 h:tf kftfsf] w'/L


0.20 mm base metal a08n 1294 1460
0.22 mm base metal a08n 1395 1580
0.24 mm base metal a08n 1504 1705
0.26 mm base metal a08n 1568 1785
0.28 mm base metal a08n 1668 1894
0.31 mm base metal a08n 1823 2075
0.35 mm base metal a08n 2014 2297
0.38 mm base metal a08n 2106 2404
0.41 mm base metal a08n 2306 2628

5 $ lkm6 x* lkm6 sf] lh=cfO{= Kn]g l;6


1.1 mm base metal lk; 2598 3119
0.90 mm base metal lk; 2151 2398
0.80 mm base metal lk; 1942 2170
0.75 mm base metal lk; 1823 2038
0.70 mm base metal lk; 1705 1902
0.62 mm base metal lk; 1522 1704
0.55 mm base metal lk; 1367 1528
0.50 mm base metal lk; 1249 1394
0.48 mm base metal lk; 1194 1336
0.45 mm base metal lk; 1130 1265
0.42 mm base metal lk;
0.40 mm base metal lk; 1021 1137
0.37 mm base metal lk; 948 1062
0.35 mm base metal lk; 912 1014
0.30 mm base metal lk; 793 883
0.28 mm base metal lk; 747 832

6 $ x * lkm6 sf] /lËg Kn]g l;6


0.90 mm base metal lk; 2434 2701
0.80 mm base metal lk; 2206 2457
0.75 mm base metal lk; 2096 2307
0.70 mm base metal lk; 201 2228
0.62 mm base metal lk; 1805 1994
0.55 mm base metal lk; 1622 1797
0.50 mm base metal lk; 1486 1640
0.48 mm base metal lk; 1422 1572
0.45 mm base metal lk; 1367 1486
0.42 mm base metal lk;
0.40 mm base metal lk; 1249 1391
0.37 mm base metal lk; 1158 1285
0.35 mm base metal lk; 1121 1233
0.30 mm base metal lk; 994 1091
0.28 mm base metal lk; 939 1040
7 GI Expanded metal Mesh
1.20 mm df]6fO{ / # lkm6 rf}8fO{ ePsf] hfnL /=ld= 118 135
1.20 mm df]6fO{ / $ lkm6 rf}8fO{ ePsf] hfnL /=ld= 164 128
1.00 mm df]6fO{ / # lkm6 rf}8fO{ ePsf] hfnL /=ld= 100 123
1.00 mm df]6fO{ / $ lkm6 rf}8fO{ ePsf] hfnL /=ld= 137 151
0.90 mm df]6fO{ / # lkm6 rf}8fO{ ePsf] hfnL /=ld= 91 103
0.90 mm df]6fO{ / $ lkm6 rf}8fO{ ePsf] hfnL /=ld= 128 137
8 UPVC Roofing Sheet (3mm thick )
PMMA coating & Mesh ( Regular ) j=ld= 1440 1506
Stone coated (18 inch* 4 feet) j=ld= 1200
Ridge cover Regular Profile 1.10 R.m. /=ld= 1288 1925
Ridge cover Tile Profile 1.05 R.m. /=ld= 1288 1925
UPVC Clip uf]6f 26 26
self tapping screw 3" uf]6f 26 30
self tapping screw 2.2" uf]6f 10 20
self tapping screw 2" uf]6f 10 11
self tapping screw 1.5" uf]6f 8 9
9 Eco-UPVC Roofing Sheet (Ultra Modern Technology)
Corrugated sheets(2mm) j=lkm=
Corrugated ridge (2mm) (3'*1.4') uf]6f
Corrugated ridge side(2mm)(3'*1.4') uf]6f
Spanish tile without fiber mesh(3mm) j=lkm=
Spanish tile with fiber mesh(3mm) j=lkm=
Spanish ridge(3mm)(3'*1.4') uf]6f
Spanish ridge side(3mm) uf]6f
Spanish tile tripod(3mm) uf]6f
Clip Set uf]6f
10 PNd'lgod Kn]g l;6
-s_ @^ u]h j=lkm= 29 29
-v_ #) u]h j=lkm= 27 27
11 Corrugated/Plain Fiber Glass Sheet
)=* dL= dL= df]6f] Kn]g j=lkm= 112.00 115.00
)=* dL= dL= df]6f] sf]/f]u]6]8 j=lkm= 125.00 127.00
!=@ dL=dL= df]6f Kn]g j=lkm= 125.00 127.00
!=@ dL=dL= df]6f] sf]/f]u]6]8 j=lkm= 143.00 146.00
2 dL=dL= df]6f] Kn]g j=lkm= 212.00 216.00
2 dL=dL= df]6f] sf]/f]u]6]8 j=lkm= 250.00 255.00
# dL= dL= df]6f] Kn]g j=lkm= 287.00 293.00
# dL= dL= df]6f] sf]/f]u]6]8 j=lkm= 375.00 382.00
12
ASP Corrugated roofingSheet (L-6,8,10,12,14,16,18 ft W-3ft

Corrugated steel Sheet-Thickness-1.mm , Weight-5.5Kg/sqm) 1076.00


j=ld6/
Ridge Cover corrugated /=ld6/ 1550.00
Self tapping screw 75mm with clip set uf]6f 20.00
13 Fiber Glass 5fgfsf] nflu Alumunium strip (25 x 1.5) mm /=ld= 69.01 67.00

14 Fiber Glass 5fgfsf] nflu Ribet nut uf]6f 7.21 7.00


15 ljleGg ;fO{hs]f h]–x's, o'–x's s]hL 137.09 137.00
16 @Æ ;fOh ?lkmË g]N; uf]6f 6.85 7.00
17 #Æ ;fOh ?lkmË g]N; uf]6f 9.60 10.00

Partition Board and Ceiling


d'=c=s/ afx]ssf] b//]6
l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{
l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j= cf=j=
२)&#÷&$ २)&$÷&%

1 Plain Particle Board (Exteriors Grade)


( dL =dL j=lkm 37.00 38.00
!@ dL =dL j=lkm 41.00 43.00
!* dL =dL j=lkm 53.00 55.00
25 dL =dL j=lkm 71.00 74.00
PPB One side lamination Melamined faced
2 0.00
(Exterior Grade)
( dL =dL j=lkm 74.00 77.00
!@ dL =dL j=lkm 83.00 86.00
!* dL =dL j=lkm 98.00 102.00
25 dL =dL j=lkm 127.00 132.00
PPB Both side lamination Melamined faced
3 (Exteriors Grade)
0.00 0.00

( dL =dL j=lkm 83.00 86.00


!@ dL =dL j=lkm 95.00 99.00
!* dL =dL j=lkm 110.00 114.00
25 dL =dL j=lkm 139.00 145.00

4 Plain Particle Board (Interiors Grade) 0.00 0.00

( dL =dL j=lkm 27.00 28.00


!@ dL =dL j=lkm 31.00 32.00
!* dL =dL j=lkm 46.00 48.00
25 dL =dL j=lkm 59.00 61.00
5
PPB One side lamination Melamined faced (InteriorGrade) 0.00 0.00

# dL =dL j=lkm 40.00 42.00


^ dL =dL j=lkm 57.00 59.00
( dL =dL j=lkm 65.00 68.00
!@ dL =dL j=lkm 74.00 77.00
!* dL =dL j=lkm 86.00 89.00
25 dL =dL j=lkm 107.00 111.00

6 PPB Both side lamination Melamined faced (Interiors Grade) 0.00 0.00

# dL =dL j=lkm 46.00 48.00


^ dL =dL j=lkm 62.00 64.00
( dL =dL j=lkm 74.00 77.00

7 PPB One side lamination Melamined faced (Interior Grade) 0.00 0.00

# dL =dL j=lkm 46.00 48.00


$ dL =dL j=lkm 53.00 55.00
^ dL =dL j=lkm 65.00 68.00
( dL =dL j=lkm 85.00 88.00
!@ dL =dL j=lkm 95.00 99.00
!* dL =dL j=lkm 122.00 127.00
25 dL =dL j=lkm 169.00 176.00
8 PPB Both side lamination Melamined faced -Alstone
Hybrid Board (WPC Board) , Rucca Eco-Wood, Femiuha, 0.00 0.00
Century & equivalent (Interiors Grade)

# dL =dL j=lkm 53.00 55.00


$ dL =dL j=lkm 59.00 61.00
^ dL =dL j=lkm 73.00 76.00
( dL =dL j=lkm 91.00 95.00
!@ dL =dL j=lkm 101.00 105.00
!* dL =dL j=lkm 128.00 133.00
25 dL =dL j=lkm 173.00 180.00
9 Alstone Hybrid Board (WPC Board) 0.00 0.00

^ dL =dL -!@@) x @$$)_ j=lkm 168.00 175.00

!@ dL =dL j=lkm 269.00 280.00


!* dL =dL j=lkm 407.00 423.00
10 Alstone Hybrid Board 0.00 0.00

४ मी.मी बाक्लो Hybrid Board (WPC Board) j=lkm - 84.00


६ मी.मी बाक्लो Hybrid Board (WPC Board) j=lkm 162.00 120.00
१२ मी.मी बाक्लो Hybrid Board (WPC Board) j=lkm 269.00 221.00
१८ मी.मी बाक्लो Hybrid Board (WPC Board) j=lkm 407.00 305.00
६ मी.मी बाक्लो Hybrid Board (WPC Art Jali) j=lkm - 370.00
१२ मी.मी बाक्लो Hybrid Board (WPC Art Jali) j=lkm - 553.00
१८ मी.मी बाक्लो Hybrid Board (WPC Art Jali) j=lkm - 713.00
WPC door framme 100*50 mm upto ht 7 ft j=lkm - 380.00
WPC door shutter 30 mm th. (7*3) size j=lkm - 540.00
18 mm th. WPC OLIGO (colour) j=lkm - 575.00
11 Alstone Hybrid Board (WPC Board) ,
Rucca Eco-Wood, Femiuha, Century & equivalent
^ dL =dL size ( 1220*2440) mm j=lkm 162.00 168.00
!@ dL =dL size ( 1221*2440) mm j=lkm 307.00 319.00
!* dL =dL size ( 1222*2440) mm j=lkm 427.00 444.00
12 Supplying and fixing of Thai gypsum board 0.00
0.00
Wall partition j=lkm 119.00 124.00
Wall paneling j=lkm 79.00 82.00
12.5mm thick Gypsum Board False ceiling j=lkm 80.00 83.00
13 Fiber cement board (infield wall 8+75+8) a=ld 0.00
3.2 MM (2'x2') j=lkm= 0.00 26.00
3.2 MM (4'x8') j=lkm= 0.00 28.00
3.5 MM (4'x8') j=lkm= 0.00 32.00
4MM (4'x8') j=lkm= 0.00 33.00
6MM (4'x8') j=lkm= 0.00 47.00
8MM (4'x8') j=lkm= 0.00 63.00
9MM (4'x8') j=lkm= 0.00 71.00
10MM (4'x8') j=lkm= 0.00 80.00

12MM (4'x8') j=lkm= 0.00 89.00

14 Fiber Cement Board 0.00 0.00


8MM (3"x9'-10") 9'-10"Rft j=lkm= 0.00 32.00
8MM (6"x9'-10") 9'-10"Rft j=lkm= 0.00 50.00
8MM (8"x9'-10") 9'-10"Rft j=lkm= 0.00 68.00
15 Fiber cement board (infield wall 10+75+10) a=ld 0.00 6370.00

16 Vinyl Laminated gypsum ceiling board (7 mm thick) j=lkm= 90.00


Prefab Panel for wall Partition
d'=c=s/ afx]ssf] b//]6
l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{
cf=j= cf=j=
२)&२÷&३ २)&#÷&$
Supply and erection of different mm th. cement base prefabricated
everst solid wall panel (RAPION) non asbestos including 1.1 mm thick
GI chennel (50*25*20) mm with necessary accessories and fittings
charge in partation wall all complete

a) 75 mm thick j=lkm 285.00 294.00


b)50 mm thick j=lkm 225.00 232.00
1 False Ceiling/Partition/External cladding of SCG/Shera or
equivalent Fiber Board 0.00
Supplying, making, fixing of false ceiling with everest fibre designer
board in E-grid j=lkm 88.00 91.00
Supplying, making, fixing of 70mm thick exterior with full height of
partirion with everest fibre cemnet board j=lkm 263.00 271.00
Supplying, making, fixing of 66mm thick exterior with full height of
partirion with everest fibre cemnet board j=lkm 230.00 237.00
Supplying, making, fixing of 91mm thick exterior with full height of
partirion with everest fibre cemnet board j=lkm 293.00 302.00
Supplying, making, fixing of external cladding with 9 mm HD/ 7.5mm
everest sliding board j=lkm 258.00 266.00
Supplying, making, fixing of 50mm thick full height of partirion with
everest RAPICON wall panels j=lkm 205.00 211.00
Supplying, making, fixing of 75mm thick full height of partirion with
everest RAPICON wall panels j=lkm 271.00 279.00
6 mm thick Flex-O- Board (Water proof cement board) 6mm thick for
false ceiling j=lkm 32.00
3 Cement board Aerocon C Board

6 mm thick j=lkm 32.00 33.00


8 mm thick j=lkm 40.00 41.00
10 mm thick j=lkm 50.00 52.00
12 mm thick j=lkm 60.00 62.00
4 Supplying and fixing 130 mm thick EVG 3D panel with mesh size
50 x 50 GI wire
Supplying and fixing 130 mm thick EVG 3D panel with mesh size 50
x 50 GI wire 2 mm both side 40 mm thick 1:4 cement sand plaster all
complete work.
j=lkm 370.00 381.00

Supplying and fixing 130 mm thick EVG 3D panel with mesh size 50
x 50 GI wire 3 mm both side 40 mm thick 1:4 cement sand plaster all
complete work.
j=lkm 400.00 412.00

Supplying and fixing 130 mm thick EVG 3D panel with mesh size 50
x 50 GI wire 4 mm both side 40 mm thick 1:4 cement sand plaster all
complete work.
j=lkm 494.00 509.00

Joint less false celling chanel 0.55mm thick flange of 20 mm and


another flange 30mm ( conform to IS 4862 : 2000 ) all complete work
Everest or equivalent
j=lkm 106.00 109.00

Rapicon solid wall panel 50/75 mm thick conform to IS 14862


( density more than 1200kg /m3) Everest or equivalent
50 mm thick
j=lkm 248.00 255.00
75 mm thick
j=lkm 327.00 337.00
External cladding with 9mm /7.5 mm siding board and GI steel frame
work j=lkm 266.00 274.00
Full Height Partition (With 9mm thick Fiber Cement Heavy Duty Wall
Board on exterior side and 10mm Standard FCB Interior side and
51mm G.I wall frame system) Exterior cum Interior Wall confirming to
IS 14862:2000 & Type A Category IV of ISO 8336:1993 j=lkm 270.00 278.10

Full Height Partition (With 8mm thick Fiber Cement Wall Board on
both side and 51mm G.I wall frame system) Interior Wall confirming
to IS 14862:2000 & Type A Category IV of ISO 8336:1993 j=lkm 236.00 243.08

Full Height Partition (With 9mm thick Fiber Cement Wall Board
exterior & 10mm Interior on interior side and 72mm G.I wall frame
system) Exterior cum Interior confirming to IS 14862:2000 & Type A j=lkm 301.00 310.03
Category IV of ISO 8336:1993

False Floor / Cavity Floor (With 15mm thick Heavy Duty Fiber
Cement / 20mm Standard FCB Floor Board and Specified M.S frame
system for design load) confirming to IS 14862 : 2000
j=lkm 338.00 348.14

5 EPS ( Expanded Polystyrene) and Cement Base Light Weight


Sandwitch Panel with 4.5mm thick Calcium Silicate Board (Non
Asbestos ) as face board on both sides (Size 2270*610mm)-
excluding installation

50mm thickness j=lkm


60mm thickness j=lkm
75mm thickness j=lkm
90mm thickness j=lkm
120mm thickness j=lkm
Installation charge j=lkm 50

em\ofn 9f]sfdf k|of]ux'g] lkmS;r/x?

d'=c=s/ afx]ssf] b//]6


l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j= cf=j=
२)&#÷&$ २)&$÷&%
1 kmnfdsf] sAhf
-s_ #Æ ;fOh uf]6f 15.14 15.00

-v_ $Æ ;fOh uf]6f 28.12 28.00

-u_ %Æ ;fOh uf]6f 43.26 43.00

-3_ ^Æ ;fOh uf]6f 56.24 56.00

2 Locking Set (L-drop)


300 mm uf]6f 259.56 260.00

225 mm uf]6f 227.12 227.00

150 mm uf]6f 194.67 195.00

3 Aluminum Towerbolt -5]:sLgL_


-s_ #Æ nfdf] uf]6f 20.39 20.00
-v_ $Æ nfdf] uf]6f 39.66 40.00
-u_ ^Æ nfdf] uf]6f 66.85 67.00
-3_ *Æ nfdf] uf]6f 80.44 80.00
-ª_ !)Æ nfdf] uf]6f 94.04 94.00
-r_ !@Æ nfdf] uf]6f 106.50 107.00
4 Aluminum Handle (xtsn)
Ordinary uf]6f 31.55 32.00
Special uf]6f 47.33 47.00
5 j|f;sf] sJhf
2"× 1/2 " uf]6f 63.10 63.00

21/2×3/4" uf]6f 70.99 71.00

3" × 3/4 " uf]6f 86.77 87.00

2" ×3/4" uf]6f 70.99 71.00

21/2"×3/4" uf]6f 78.88 79.00

3"×3/4" uf]6f 86.77 87.00


3"×1" uf]6f 189.31 189.00
4"×1" uf]6f 283.97 284.00
5"×1" uf]6f 378.62 379.00
6"×1" uf]6f 457.50 458.00
6 BrassTowerbolt -5]:sLgL_
-s_ #Æ nfdf] uf]6f 141.98 142.00
-v_ $Æ nfdf] uf]6f 189.31 189.00
-u_ ^Æ nfdf] uf]6f 283.97 284.00
-3_ *Æ nfdf] uf]6f 378.62 379.00
-ª_ !)Æ nfdf] uf]6f 473.28 473.00
-r_ !@Æ nfdf] uf]6f 567.93 568.00
7 Brass Handle (xtsn)
6" Brass handle uf]6f 149.87 150.00
8" Brass handle uf]6f 457.50 458.00
10" Brass handle uf]6f 946.55 947.00
8 Brass Locking Set (L-drop)
-s_ *Æ nfdf] uf]6f 946.55 947.00
-v_ !)Æ nfdf] uf]6f 1561.81 1562.00
-u_ !@Æ nfdf] uf]6f 1735.35 1735.00
Special Fittings
9 Pn 8«k
*Æ nfdf] uf]6f 1061.76 1062.00
!)Æ nfdf] uf]6f 1199.17 1199.00
!@Æ nfdf] uf]6f 1248.57 1249.00
10 x\of08n *Æ nfdf] uf]6f 1248.57 1249.00
11 6fj/ af]N6
^Æ nfdf] uf]6f 224.84 225.00
*Æ nfdf] uf]6f 299.79 300.00
!)Æ nfdf] uf]6f 374.74 375.00
12 8an sn/ -uf]N8 l;Ne/÷ANofs l;Ne/_
Pn 8«k
*Æ nfdf] uf]6f 891.67 892.00
!)Æ nfdf] uf]6f 1129.60 1130.00
!@Æ nfdf] uf]6f 1248.57 1249.00
x\of08n
^Æ nfdf] uf]6f 249.83 250.00
*Æ nfdf] uf]6f 374.74 375.00
df]l6{; ns
Ordinary uf]6f 624.57 625.00
Chinese uf]6f 415.81 416.00
Indian Godrej Company uf]6f 2557.18 2557.00
Brass 1129.60 1130.00
13 Door Spring (Door Closer)
Ordinary uf]6f 177.88 178.00
hydraulic uf]6f 1873.70 1874.00
Window I-hook uf]6f 18.13 18.00
14 Gate Hook
4" Gate hook uf]6f 30.59 31.00
5" Gate hook uf]6f 35.12 35.00
6" Gate hook uf]6f 41.92 42.00
Brass Gate hook uf]6f 74.95 75.00
15 Door stopper 0.00
Butterfly uf]6f 148.42 148.00
Bell catch 2" size uf]6f 196.01 196.00
C.P. handle uf]6f 424.88 425.00
Power coated handle uf]6f 405.61 406.00
Brass coated handle uf]6f 874.39 874.00
Door stopper, single brass stopper uf]6f 99.93 100.00
Door stopper double brass stopper uf]6f 177.88 178.00
16 Screw Brass
20mm uf]6f 1.92 1.92
25mm uf]6f 2.67 2.67
35mm uf]6f 4.11 4.11
50mm uf]6f 12.06 12.06
75mm uf]6f 15.08 15.08
17 Screw Steel
20mm uf]6f 1.17 1.17
25mm uf]6f 1.92 1.92
35mm uf]6f 2.33 2.33
50mm uf]6f 7.20 7.20
75mm uf]6f 7.54 7.54
18 Staircase sf] 3/4" x 3/4" square pipe df nufpg] Brass cap uf]6f 92.70 92.70
19 Staircase sf] 1" x 1" square pipe df nufpg] Brass cap uf]6f 97.85 97.85

/+u/f]ug tyf k'l6sf ;fdfgx?


d'=c=s/ afx]ssf] b//]6
l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j= cf=j=
२)&#÷&$ २)&$÷&%
1 l;d]G6 k]G6 s]=lh= 72.00 65.00
2 l;d]G6 k|fOd/ ;]tf] s]=lh= 259.88 271.00
3 p8 k|fOd/ ln6/ 365.20 365.00
4 ;]Gy]l6s Ogfd]n k]G6 ln6/ 509.41 509.00
5 g]kfn /]8sf] Dof6 lkmlgl;Ë ln6/ 490.88 491.00
6 sf]?u]6]8 ?km k]G6 ln6/ 462.00 462.00
7 tof/L cNd'lgod k]G6 ln6/ 530.20 530.00
8 tof/L jfg]{; ln6/ 427.35 427.00
9 tof/L jfg]{/ ;]Gy]l6s ln6/ 330.00 330.00
10 ef/lto lyg/ ln6/ 224.40 224.00
11 p8 P08 Unf; k'l6g s]=hL 127.60 128.00
12 d]6n k'l6g s]=hL 150.70 151.00
13 r'gf k]G6 ug{ /fVg] ud s]=hL 196.90 197.00
14 g]kfnL lyg/ ln6/ 211.20 211.00
15 tf/lkg t]n ln6/ 207.90 208.00
16 /]8 cs;fO8 k]G6 ln6/ 254.10 254.00
17 p8 lk|h/e]l6j k]G6 ln6/ 221.76 222.00
18 Jofs hfkfg ln6/ 277.20 466.00
19 /fd ltns s]=lh= 54.29 54.00
20 u]? /+u s]=lh= 132.83 133.00
21 rk|f s]=lh= 889.35 1280.00
22 :k|L^ ln^/ 87.00
23 tof/L jf;]jn l8:t]Dk/ ln6/ 216.70 217.00
24 tof/L Knfl:6S; OdN;g k]G6 (interior) ln6/ 510.62 511.00
25 tof/L j]b/sf]6 k]G6 (exterior) ln6/ 612.15 612.00
26 Knfl:^s O{dN;g k])^ ln6/ 650.00
27 PS;^]l/o/ j]b/ sf]^ ln6/ 683.00
28 /f]* dfsL{ª yd]fKnf:^Ls k])^ ln6/ 562.10 562.00
29 lngl;8 cfon ln6/ 190.58 191.00
30 :yfgLo :k|L6 ln6/ 114.35 114.00
31 df]ljsn÷km]ljsn s]=lh= 254.10 255.00
32 d}g kfln; s]=lh= 206.00 345.00
33 cShflns Pl;8 s]=lh= 118.00 118.00
34 1" rf}*f k]G^ a|; uf]^f 100.00 70.00
35 2" rf}*f k]G^ a|; uf]^f 200.00 140.00
36 3" rf}*f k]G^ a|; uf]^f 300.00 210.00
37 4" rf}*f k]G^ a|; uf]^f 400.00 280.00
38 /+u nufpg] /f]n/ uf]^f 400.00 400.00
39 Sand paper uf]6f 6.00 6.00
40 Wall putty plain s]=lh= 66.99 36.00
41 Wall putty- water Proof 60.00
42 Plaster of Parish (POP) s]=lh= 21.95 22.00
43 Redoxide zink cromate primer For Bridge ln6/ 449.90 450.00
44 Silk Breathless easy ln6/ 1237.50 1238.00
45 Epoxy Paint for Operation theater j=dL= 11706.20 11706.00
Decorative Painting Material
A Specialized paints
1 Acro Bio-guard (Anti bacterial Hospital Paint) ln6/ 1099.00 1099.00
2 Acro Ellastocrab (Anti carbonisation paint) ln6/ 761.80 762.00
B Texture paints 0.00
1 Mediterrano s]=lh= 176.40 176.00
2 Stucco Veneziano s]=lh= 1638.80 1639.00
3 Velvetino s]=lh= 4305.40 4305.00
4 Travertino s]=lh= 412.30 412.00
5 Gtone plaster s]=lh= 120.70 121.00
6 Colorato (Multi color) s]=lh= 921.15 921.00
7 Pearl skin texture s]=lh= 149.10 149.00
8 TS 52 Spray white s]=lh= 198.95 199.00
9 Rustic s]=lh= 198.96 199.00
10 Rockart ln6/ 198.96 199.00
11 Manhattan s]=lh= 237.90 238.00
12 Sabbia s]=lh= 237.90 238.00
13 Sandy Stone s]=lh= 174.40 174.00
14 Insulplast s]=lh= 236.80 237.00
15 Poly Under White s]=lh= 263.80 264.00
16 Antica(Top coat) s]=lh= 1266.80 1267.00
17 T.C 100(Top coat) s]=lh= 728.20 728.00
18 Dekorica White s]=lh= 2630.80 2631.00
19 Poly Plaster s]=lh= 107.45 107.00
20 Granite tone s]=lh= 165.30 165.00
21 Graffiato s]=lh= 158.96 159.00
22 Elligance stone s]=lh= 188.75 189.00
23 Marmorino Base s]=lh= 412.30 412.00
24 Acro fine ln6/ 180.80 181.00
25 Marmocastro base s]=lh= 138.50 139.00
26 Selva Granite s]=lh= 215.20 215.00
27 Romart s]=lh= 239.05 239.00
C Weather coat paints
1 Guard ln6/ 503.10 503.00
2 Guard -3x ln6/ 587.75 588.00
3 Shield ln6/ 321.90 322.00
4 Acrotex matt ln6/ 509.85 510.00
5 Ext wall Primer ln6/ 238.10 238.00
D Emulsion Paints/Distemper 0.00
1 silk Emulsion paints ln6/ 521.80 522.00
2 Aqualin Int.Emulsion ln6/ 279.50 280.00
3 pearl Emulsion paints ln6/ 772.00 772.00
4 int. wall Primer ln6/ 172.30 172.00
5 Acrylic Washable Distemper ln6/ 141.55 142.00
6 Acro gold Enamel ln6/ 512.10 512.00
7 Universal primer ( wood primer) ln6/ 312.67 313.00
8 Red oxide metal primer ln6/ 276.00 276.00
9 Construction Chemical / waterproof coating system 0.00
crack sill ln6/ 387.40 387.00
crack fill A+B ln6/ 169.95 170.00
10 Silicon Bases water repellent impregnation 0.00
Acropreg ln6/ 466.10 466.00
Acropreg W ln6/ 619.30 619.00
Wall putty s]=lh= 38.50 39.00
Acro Texture ISO certified 9001-2008 ( Silicone & Ceramic
technology / All weather resistance / Fire retardant / Heat
reflecting / Algae & Fungi resistant / Ultra violet resistant)
for painting works

A Acro Spanezia maestro finishes texture 0.00


1 Mediterrano texture j=lkm= 127.70 128.00
2 Traventino texture j=lkm= 195.40 195.00
3 Velvetino texture j=lkm= 167.05 167.00
4 Gtone plaster and Colorato texture(Multicolour texture) j=lkm= 133.40 133.00
5 Stucco veneziano texture j=lkm= 140.05 140.00
6 Pearl skin texture j=lkm= 119.65 120.00
7 Marmorino texture j=lkm= 155.65 156.00
B Acro texture
1 Acro spray flat/Acro spray dews texture j=lkm= 64.75 65.00
2 Featherglow/Royal touch/Superfine/Ceratex texture j=lkm= 73.55 74.00
3 Rustic texture j=lkm= 99.35 99.00
4 Rockart texture j=lkm= 93.05 93.00
5 Graffiato texture j=lkm= 103.00 103.00
6 Marmocastro texture j=lkm= 89.80 90.00
7 Marmoplast texture j=lkm= 89.90 90.00
8 Sabbia texture j=lkm= 111.95 112.00
9 Manhattan texture j=lkm= 111.95 112.00
10 Sandy stone texture j=lkm= 153.80 154.00
11 Selva Granite texture j=lkm= 115.75 116.00
12 Elligance stone texture j=lkm= 107.00 107.00
13 Granite tone texture j=lkm= 97.85 98.00
14 Romaart texture j=lkm= 124.10 124.00
15 Insulplast texture j=lkm= 134.50 135.00
16 Acro Bio-guard (Hospital Paint) j=lkm= 53.70 54.00
17 Acro Ellastocarb(anti carbonisation paint) j=lkm= 37.94 38.00
18 Acro fire guard (fire retardent paint) j=lkm= 34.35 34.00
C EXTERIOR SURFACE WEATHERCOAT PAINTS 0.00
ACROGUARD 3X j=lkm= 23.05 23.00
ACROGUARD j=lkm= 21.10 21.00
ACROSHIELD j=lkm= 17.15 17.00
ACROTEX MATT j=lkm= 30.75 31.00
D INTERIOR SURFACE EMULSION PAINTS
ACROPEARL EMULSION PAINTS j=lkm= 23.50 24.00
ACROSILK EMULSION PAINTS j=lkm= 19.80 20.00
AQUALIN EMULSION PAINTS j=lkm= 16.10 16.00
AQUALIN ACRYLIC WASHABLE DISTEMPER j=lkm= 10.50 11.00
ACRO GOLD ENAMEL PAINTS j=lkm= 18.10 18.00
E Wall Paper
Wall paper (10m.x 0.53m) /f]n 1236.00 1236.00

Fittings for wall paper j=lkm 7.00 7.00

White glue for wall paper ln= 108.00 108.00

F Pro_Plaster Material s]=hL

Water Proofing Chemicals & Treatment works


d'=c=s/ afx]ssf] b/
l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{
l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j= cf=j=
२)&#÷&$ २)&$÷&%
A CONCRETE ADMIXTURES (Chemical)
1 Form Oil ln6/ 100.00
2 Polymer for M35, M 40 or higher concrete ln6/ 350.00
3 Epoxy Bonding agent for old and new construction ln6/ 2000.00
4 *}Dk k|'km tyf xf*]{lgª sDkfp)* ;]km dfO{^ ln6/ 235.00
5 (Damp proof, Anti Termite , Anti Fungal,Anti Saltpetre and benefit of
High Compressive Strength)
Waterproof Coating With Latex s]=hL= 350.00
Waterproof Coating with Polymer s]=hL= 450.00
1 Water Reducing Admixture Concrete & Mortar [ Lignosulphonate
Based] ASTM C 494 -( Type A,B&D) IS 9103/2645 /1981 s]=hL= 165.00 150.00

2 High Range Water Reducing Super Plasticizer for Concrete & Mortar
[ Napthalene Formladehyde Based] ASTM C 494 -( Type A,C,E & F) IS s]=hL= 248.00 250.00
9103-79 /1999 Dose 0.2 to 3% by wt of cement .

3 Ultra High Range Water Reducing Super Plasticizer for Concrete &
Mortar [ Polycarboxylate Ether Based] ASTM C 494 -( Type A,F& G) IS s]=hL= 495.00 450.00
9103-1999 /1981

4 Integral Waterproofing Additive for Concrete & Plaster .ASTM C 494 IS


2645-75 ( Type G) , IS 9103-2007 / IS 2645 s]=hL= 303.00 300.00

5 Integral Crystalline Waterproofing Powder Admixture STD .


Conformane : ASTM C 494, IS 3085-1997, DIN 1048 -1991 Part 5 s]=hL= 935.00 1000.00

6 Integral Crystalline Waterproofing Liquid Admixture STD Conformance :


ASTM C 494 IS 3085 -1997 , DIN 1048-1991 Part s]=hL= 935.00 1000.00

7 Integral Crystalline Waterproofing Powder Admixture STD .


Conformane : ASTM C 494, IS 3085-1997, DIN 1048 -1991 Part 5 s]=hL= 1375.00 1250.00

8 Integral Waterproofing Powder Admixture for Mortars Std. Coformance


: ASTM C 494, IS 3085-1997, DIN 1048-1991 Part 5 s]=hL= 165.00 180.00

9 Accelerator & Spray Shotcrete / Concrete Plasticizer [ Silicate Based]


s]=hL= 275.00 250.00

10 Accelerator & Spray Shotcrete / Concrete Liquid Plasticizer [ Alkali


Free] s]=hL= 385.00 350.00

11 Accelerator & Spray Shotcrete / Concrete Powder Plasticizer [ Alkali


Free] ASTM C 1240, IS 15388-2003 s]=hL= 330.00 350.00

12 Retarding Superplasticiczer for Concrete [ Napthalene Based] ASTM C


494-1981 ( TYPE G/D), IS 9103-2007 s]=hL= 248.00 250.00

13 Retarding Superplasticiczer for Concrete [ Polycarboxylate Ether


Based] ASTM C 494-1981 ( Type G ) s]=hL= 495.00 450.00

B CONCRETE ADMIXTURES (Mineral) 0.00


1 Silica Cement Admixture (Volcanic Product Inorganic) s]=hL= 315.00 315.00
2 Micro Silica for High Performance Concrete ASTM C 1240 -2005 , IS
15388-2003. s]=hL=
3 Processed FA Based Mineral Additives s]=hL= 94.00 85.00
C FOR JOINT SEALANTS & SYSTEMS 0.00
1 Two Component Gun Grade Polysulphide Sealant for Vertical Surfaces
s]=hL= 1980.00 1800.00

2 Two Component Pour Grade Polysulfide Sealant for Horizontal


Surfaces s]=hL= 1980.00 1800.00

3 One Component Low Viscosity Primer For Polysulfide Sealant s]=hL= 3300.00 3000.00
4 Two Component Pour Grade Polyurethane Sealant for Joints s]=hL= 2200.00 2000.00
5 Low Viscosity Primer For Polyurethane Sealant s]=hL= 3300.00 3000.00
6 High Performance Hybrid Silyl Sealant (290 ml per set) ;]6 1320.00 1200.00
7 HOT APPLIED Bituminous Sealing Compound Sealent [TYPE A] s]=hL= 0.00 350.00
8 HOT APPLIED Bituminous Sealing Compound Sealent [TYPE B] s]=hL= 0.00 450.00
9 Butyl Tape for various Applications /= ld= 138.00 125.00
10 Waterproofing Joint Tape [ 120 mm] /= ld= 550.00 550.00
11 Waterproofing Joint Tape [ 200 mm] /= ld= 715.00 750.00
12 NBR based Waterproofing Joint Tape [ 200 mm] /= ld= 4400.00 4000.00
13 Joint Tape Epoxy Adhesive s]=hL= 3300.00 3000.00
14 Glass Fiber Joint Tape /= ld= 300.00 275.00
15 Waterproofing / Expansion Joint Tape [100 mm] /= ld= 1650.00 1500.00
16 Waterproofing / Expansion Joint Tape [200 mm] /= ld= 2970.00 2700.00
17 Construction Joint Tape [ 100 mm] /= ld= 880.00 800.00
18 Cross Linked Premoulded Compressive Joint Filler [25 mm] a= ld= 2695.00 2450.00
19 Cross Linked Premoulded Compressive Joint Filler [50 mm] a= ld= 5335.00 4850.00
20 Closed Cell Polymerbased Joint Filler [25 mm] a= ld= 880.00 800.00
21 Closed Cell Polymerbased Joint Filler [50 mm] a= ld= 1650.00 1500.00
22 Compressable Resilint Non- Extrudible Joint EXJO FILLER [12 mm {4'
X 4'}] a= ld= 0.00 2500.00

23 Compressable Resilint Non- Extrudible Joint EXJO FILLER [18 mm {4'


X 4'}] a= ld= 0.00 3500.00

24 Compressable Resilint Non- Extrudible Joint EXJO FILLER [25 mm {4'


X 4'}] a= ld= 0.00 4500.00

D INDUSTRIAL FLOORING SOLUTIONS 0.00


1 Hardwearing, abrasion resistant monolithic industrial flooring compound
[ Metallic] s]=hL= 121.00 120.00

2 Liquid Concrete Hardener & Dust Proofer s]=hL= 413.00 450.00


3 Anti Bacterial Floor & Wall Coating [ Epoxy] s]=hL= 2475.00 2500.00
4 Anti Bacterial Floor & Wall Coating [ Polyurethane] s]=hL= 2750.00 3000.00
5 Anti bacterial Floor & Wall Coating [ Acrylic] s]=hL= 2200.00 2000.00
6 Self Levelling Flooring System [ Epoxy] s]=hL= 1100.00 2200.00
7 Self Levelling Flooring System [ Polyurethane] s]=hL= 1650.00 3000.00
8 Self Levelling Cementitious Flooring System s]=hL= 330.00 500.00
E ENGINEERING GROUTS 0.00
1 General Purpose High Strength Free Flowing, Non Shrink Cementitious
Grout [ M40] s]=hL= 121.00 110.00

2
Ultra High Strength Free Flowing, Non Shrink Cementitious Grout [M60] s]=hL= 135.00 125.00

3 Hard wearing cementitious tile grout s]=hL= 176.00 160.00


4 Hard wearing epoxy based tile grout s]=hL= 1100.00 1000.00
5 Super Plasticizer, Shrinkage Compensating Grout Admixture s]=hL= 550.00 500.00
6 High Strength Precision Grade, Non Shrink Structural Epoxy Anchor
Grout s]=hL= 2750.00 2500.00

7 Epoxy Acrylate High Strength Precision Grade, Non Shrink Structural


Grout [ 400 Ml Cartridge] ldln ln6/ 4950.00 4500.00

8 Low Viscosity Injection Epoxy Grout s]=hL= 7150.00 7500.00


9 Low Viscosity Polyurethane Injection Grout s]=hL= 15400.00 12500.00
10 Low Viscosity Acrylate Gel Injection Grout s]=hL= 9350.00 8500.00
11 Low Viscosity Soil Stabilization Hydrophobic one component Injection
Grout s]=hL= 15400.00 14000.00

12 Low Viscosity Soil Stabilization Hydrophobic, water reactive, solvent


and phthalate free Injection Grout s]=hL= 15400.00 9500.00

13 Resin Capsule (32*300mm) lk; 0.00 130.00


14 Cement Capsule(32*300mm) lk; 0.00 60.00
15 Microfine Cement (MFC) s]=hL= 0.00 250.00
F BONDING ADHESIVES FOR CONCRETE & MORTAR (Polymer 0.00
& Epoxy Resin)
1 Acrylic Bonding Agent For Concrete & Mortar s]=hL= 715.00 750.00
2 Versatile SBR Latex for Bonding, Grouting & Repair Mortars s]=hL= 935.00 950.00
3 High Performanance Pure Acrylic Polymer for Concrete & Mortar
Modification' & Bonding Adhesive s]=hL= 1320.00 1200.00

4 Two Component Epoxy Resin Bonding Agent [ For bonding new to old
concrete] s]=hL= 1980.00 1800.00

G FIBERS (Steel & Polypropylene) 0.00


1 FIBERMESH MF [Monofilament PP Fibers] s]=hL= 1100.00 1200.00
2 FIBERMESH FB [Collated PP Fibers] s]=hL= 1430.00 1500.00
3 FIBERMESH MACRO [Structural PP Fibers] s]=hL= 2200.00 2000.00
4 Loose steel Fibers s]=hL= 275.00 250.00
5 Glued Steel Fibers s]=hL= 385.00 350.00
6 Crimped Steel Fibers s]=hL= 245.00 250.00
H SURFACE TREATMENT 0.00
1 Protective, Decorative Anti Carbonation Coating s]=hL= 1320.00 1200.00
2 Protective, Decorative Insulating Anti Carbonation Coating s]=hL= 1485.00 1350.00
3 Concrete Penetrating Corrosion Inhibitor s]=hL= 4950.00 4500.00
4 Protective Acrylic Sealer s]=hL= 1650.00 1500.00
5 Protective Polyurethane Sealer s]=hL= 1980.00 1800.00
6 Water Based Fire Retardant Coating s]=hL= 1320.00 1500.00
7 High Performance Water Repellent Paint ln6/ 9900.00 900.00
8 Concentrated & Emulsified Chemical Mould Release Agent ln6/ 550.00 500.00
9 Ready to use Chemical Mould Release Agent ln6/ 440.00 500.00
10 Concrete Curing Aid s]=hL= 440.00 450.00
I CONCRETE REPAIRS 0.00 0.00
1 Rust Remover & Passivator ln6/ 1100.00 1000.00
2 Corrosion Inhibitor s]=hL= 1100.00 1200.00
3 Micro Concrete [ M60] for Permanant Repairs s]=hL= 154.00 140.00
4 Single Component Polymer Modified Cementitious Repair Mortar s]=hL= 190.00 175.00
5 Two Component Polymer Modified Cementitious Repair Mortar s]=hL= 275.00 250.00
6 Cementitious, Waterproof Crack Repair Mortar s]=hL= 220.00 200.00
7 Acrylic Based Crack Filling Putty s]=hL= 1320.00 1200.00
J PREPACKED MORTARS 0.00
1 Tile, Mabrble, Granite etc. Adhesive s]=hL= 83.00 85.00
2 Marble & Granite etc. Adhesive s]=hL= 385.00 350.00
3 Coarse and water resistant Readymix plastring Mortar s]=hL= 90.00 85.00
4 High Performanance Polymer Based Wall Putty (Skim Coat) s]=hL= 70.00 85.00
5 High Performanance Polymer Based Insulting Wall Putty (Skim
Coat) s]=hL= 90.00 90.00

K WATERPROOFING SYSTEMS 0.00


INTEGRAL 0.00
1 Integral Waterproofing Additive for Concrete & Plaster s]=hL= 300.00 275.00
2 High Performance Sodium Silicate CWS 100 Based Deep
Penetrating Sealer Waterproofing System s]=hL= 315.00 7500.00

L LIQUID APPLIED 0.00


1 Single Pack Polymer Modified Flexible Waterproof Coating System
Dose : Cover area 30 sqft. -45 sqft /kg 2 coat . s]=hL= 770.00 700.00

2 Two Component Polymer Modified Flexible Elastomeric


Waterproof Coating System Dose : Cover area 5 sqft. - 7 sqft /kg 2 s]=hL= 550.00 500.00
coat .
3 Two Component Polymer Modified Flexible Elastomeric
Waterproof & Thermal Insulating Coating System Dose : s]=hL= 825.00 750.00
consumption : 1:kg/m2.
4 Heavy duty reinforced elastomeric acrylic water proof coating for
terrace Dose : cover area : 6 sqft/litre 3 coat. s]=hL= 750.00 850.00

5 Acrylic elastomeric exterior water proof coating for exterior wall


Dose : 35 sqft / litre 2 coat . s]=hL= 700.00 750.00

6 Crystalline Based Waterproofing System s]=hL= 330.00 350.00


7
Fast setting plugging compound for stopping running water system s]=hL= 385.00 400.00

8 Polyurethane based waterproof coating system s]=hL= 1650.00 1650.00


9
Polymer modified Bitumen Based Water Proofing Coating System s]=hL= 1320.00 1250.00

10 Efflorescence Resistance Penetrating primer Dose : Cover Area:


80sqft/ltr 1 coat s]=hL= 600.00 600.00

M PREFORMED 0.00
1 Fiber Reinforced Polymer Modified Bituminous Membranes [3mm
Plain] a= ld= 1980.00 1800.00

2 Fiber Reinforced Polymer Modified Bituminous Membranes [3mm


Mineral / Sand Finish] a= ld= 2200.00 2000.00

3 Polymer Modified Self Adhesive Bituminous Membranes [1mm] a= ld= 1100.00 1050.00
4 Polymer Modified Self Adhesive Bituminous Membranes [ 2mm] a= ld= 1650.00 1500.00
5 Polymer Modified Self Adhesive Bituminous Membranes with
Aluminium Cover a= ld= 1650.00 1500.00

6 1.2 mm High Polymer PVC Membranes a= ld= 2200.00 2000.00


7 PVC Adhesive s]=hL= 2750.00 2500.00
8 1.2 mm EPDM Membranes a= ld= 2200.00 2500.00
9 EPDM Adhesive s]=hL= 2750.00 2500.00
10 EPDM Primer s]=hL= 3300.00 3000.00
11 2mm TPO Membranes a= ld= 3850.00 3500.00
12
Polythene & Polypropylene Polymer Compound Waterproof Membrane a= ld= 880.00 800.00

13 100% Synthetic Rubber Roof Coating s]=hL= 4950.00 4500.00


N SPECIALTY 0.00
1 Antistripping Agent for Bitumen s]=hL= 440.00 550.00
2 Cold Applied Multi Purpose Modified Bituminous Compound in semi
Liquid Creamy for Bonding s]=hL= 0.00 225.00

3 Cold Applied Viscous Heavy Duty Modified Bituminous Protective water


Barrier Coating for Below Ground Structures (Raft / Pile / Footings etc) s]=hL= 0.00 525.00

4 Bituminous based Aluminized Heat Reflective Paint s]=hL= 0.00 650.00


5 Cold Applied Sealing & Calking Compound s]=hL= 0.00 1250.00
6 ROAD REPAIR PRE-MIX s]=hL= 0.00 1000.00
7 ANTI CORROSIVE PIPE WRAP 2 mm s]=hL= 0.00 750.00
8 ANTI CORROSIVE PIPE WRAP 4 mm s]=hL= 0.00 1000.00
9 Anti Termite [ Imidacloprid 30.5% ] s]=hL= 0.00 12000.00
10 Expanding Concrete Joint WATERSTOP /= ld= 0.00 2500.00
11 WB ADHESIVE Primer for Expanding Waterstop ln6/ 0.00 7500.00
12 Swellable WATERSTOP /= ld= 0.00 2500.00
13 SEALGUARD PVC WATERSTOP - PVC Waterstops /= ld= 0.00 2500.00
14 Nodular Drain with Geotextile Roof Garden a= ld= 0.00 2500.00
15 SEALGUARD GEOTEX [P] -Polyester Geotextile a= ld= 0.00 110.00
16 XPS - Extruded Polystyrene Boards [ 25 mm] a= ld= 0.00 2800.00
17 XPS - Extruded Polystyrene Boards [ 50 mm] a= ld= 0.00 3500.00
STRUCTURAL STRENGTHENING & SEISMIC RETROFITTING

d'=c=s/ afx]ssf] b/
cf=j=
l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j=
२)&#÷&
२)&$÷&%
$
A STRUCTURAL STRENGTHENING
1 Carbon Laminate [50 mm Wide 1.4 mm Thick] /= ld= 8500.00
2 Carbon Laminate [75 mm Wide 1.4 mm Thick] /= ld= 10000.00
3
Fiber Reinforced Polymer] CARBON FiberWRAP Sheet 230 GSM a= ld= 8000.00

4
Fiber Reinforced Polymer] CARBON FiberWRAP Sheet 450 GSM a= ld= 12000.00

5 Fiber Reinforced Polymer] CARBON FiberWRAP Sheet 640 a= ld= 16000.00


6 Fiber Reinforced Polyer] GLASS FiberWRAP Sheet 900 GSM a= ld= 12000.00
7 EPOXY PRIMER s]=hL= 3500.00
8 SATURANT s]=hL= 3500.00
9 LAMINATE ADHESIVE s]=hL= 2500.00
10 EPOXY TOPCOAT s]=hL= 3500.00
11 POLYURETHANE TOPCOAT s]=hL= 4500.00
12 Glass Fiber anchor system 5to 10 mm /= ld= 2500.00
13 Carbon Fiber anchor system 5to 10 mm /= ld= 3500.00
14 Carbon Laminate [50 mm Wide 2 mm Thick] /= ld= 10000.00
15 Carbon Laminate [75 mm Wide 2 mm Thick] /= ld= 12000.00

B Horizontal Expansion Joint for Slab


1 Expansion Joint for Horizontal Slab Area with 3 to 5mm Different
Aluminium Plates with Joint Gap upto 4" /= ld= 10490.00

2 Expansion Joint for Horizontal Slab Area with 3 to 5mm Different


Aluminium Plates with Joint Gap from 5" to 8" /= ld= 12460.00

3 Expansion Joint for Horizontal Slab Area with 3 to 5mm Different


Aluminium Plates with Joint Gap from 9" to 12" /= ld= 14760.00

4 Expansion Joint for Horizontal Slab Area with 3 to 5mm Different


Aluminium Plates with Joint Gap from 13" to 18" /= ld= 19680.00

C Expansion Joint for Basement


1 Expansion Joint for Basement Area with 3 to 5mm Different
Aluminium Plates and Covering with 20 gauge copper sheet with /= ld= 18040.00
Joint Gap upto 4" Gap
D Expansion Joint for Roof
1 Expansion Joint for Roof Slab Area with 3 to 5mm Different
Aluminium Plates with Joint Gap upto 4" /= ld= 12580.00

2 Expansion Joint for Roof Slab Area with 3 to 5mm Different


Aluminium Plates with Joint Gap from 5" to 8" /= ld= 14955.00

3 Expansion Joint for Roof Slab Area with 3 to 5mm Different


Aluminium Plates with Joint Gap from 9" to 12" /= ld= 17710.00

4 Expansion Joint for Roof Slab Area with 3 to 5mm Different


Aluminium Plates with Joint Gap from 13" to 18" /= ld= 23615.00

E Inside Vertical Expansion Joint


1 Expansion Joint for Inside Vertical Wall and Ceiling Area with 3mm
Different Aluminium Plates with Joint Gap upto 4" /= ld= 6560.00

2 Expansion Joint for Inside Vertical Wall and Ceiling Area with 3mm
Different Aluminium Plates with Joint Gap from 5" to 8" /= ld= 8200.00

3 Expansion Joint for Inside Vertical Wall and Ceiling Area with 3mm
Different Aluminium Plates with Joint Gap from 9" to 12" /= ld= 9840.00

4 Expansion Joint for Inside Vertical Wall and Ceiling Area with 3mm
Different Aluminium Plates with Joint Gap from 13" to 18" /= ld= 13120.00

F Outside Vertical Expansion Joint


1 Expansion Joint for Outside Vertical Wall Area with 3mm Different
Aluminium Plates with Joint Gap upto 4" /= ld= 7540.00

2 Expansion Joint for Outside Vertical Wall Area with 3mm Different
Aluminium Plates with Joint Gap from 5" to 8" /= ld= 9430.00

3 Expansion Joint for Outside Vertical Wall Area with 3mm Different
Aluminium Plates with Joint Gap from 9" to 12" /= ld= 11310.00

4 Expansion Joint for Outside Vertical Wall Area with 3mm Different
Aluminium Plates with Joint Gap from 13" to 18" /= ld= 15080.00

Cement Concrete Block

d'=c=s/ afx]ssf] b//]6


l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j= cf=j=
२)&#÷&$ २)&$÷&%
1 Interlocking Cement Concrete Block ( Not less
than M20 concrete
Curb stone-Not less than M20 concrete /=ld= 1020.00 1020.00
25 mm thick C.C. Tile (Grey color)-Burfi , Round , Boby
Checker j=lkm 39.00 39.00

25 mm thick C.C. Tile (Red color)-Burfi , Round , Boby


Checker j=lkm 41.00 41.00

50 mm thick CC Block (Grey color)-Cosmix , Hexagon ,


Threehex , Royal tone Interlock , I-Interlock j=lkm 47.00 47.00

50 mm thick CC Block (Red color)-Cosmix , Hexagon , Threehex


, Royal tone Interlock , I-Interlock j=lkm 48.00 48.00
60 mm thick CC Block (Grey color)-Cosmix , Hexagon ,
Threehex , Royal tone Interlock , I-Interlock , Plus Interlock j=lkm 49.00 49.00

60 mm thick CC Block (Red color)-Cosmix , Hexagon ,


Threehex , Royal tone Interlock , I-Interlock , Plus Interlock j=lkm 50.00 50.00

70 mm thick CC Block (Red color)-Cosmix , Hexagon ,


Threehex , Royal tone Interlock , I-Interlock j=lkm 57.00 57.00

2 60 mm thick CC Block ( Ocm or equivalent ) 0.00 0.00


Brick type (23*11*6cm)non colour uf]6f 9.00 9.00
Hexagon (22*22 cm) non colour uf]6f 21.00 21.00
Hexagon (22*22 cm) colour uf]6f 23.00 23.00
Squire paver (30*30*4.5cm)non colour uf]6f 29.00 29.00
Squire paver (30*30*4.5cm)colour uf]6f 32.00 32.00
inter block(24*13*6cm) uf]6f 14.00 14.00
Isave paver (20*16*6cm) uf]6f 15.00 15.00
3 Concrete Block different items
Hollow Block ( 16"*8"*6") uf]6f 73.00 73.00
Hollow Block ( 16"*8"*4") uf]6f 64.00 64.00
Corner Hollow Block ( 16"*8"*6") uf]6f 82.00 82.00
Lintel Block ( 16"*8"*6") uf]6f 82.00 82.00
Pavers Block ( fish or other shape ) 60mm thick uf]6f 18.00 18.00
concrete Brick ( 9"*4"*2.5") uf]6f 12.00 12.00
5 Concrete block
Concrete block size (40*15*20 ) cm uf]6f 37 37.00
Concrete block size ( 40*10*20 ) cm uf]6f 32 32.00
Concrete block size ( 39*14*19 ) cm uf]6f 50 50.00
6 Cellular light weight concrete(CLC) block
Cellular light weight concrete(CLC) block -24"*8"*4" uf]6f 148 162.00
Cellular light weight concrete(CLC) block-24"*8"*6" uf]6f 215 299.00
Cellular light weight concrete(CLC) block- 24"x8"x4" uf]6f 114.00
Cellular light weight concrete(CLC) block 24"x8"x6" uf]6f 171.00
Cellular light weight concrete(CLC) block24"x8"x8" uf]6f 228.00
7 Interlock Concrete Paving Blocks
Behaton Interlock I Paver (Grey Color) with Compressive Strength
M25 or Above 80MM Thickness. j=dL
Behatone Interlock I Paver (Single Color) with Compressive
Strength M25 or Above. 80MM Thickness j=dL
Behaton Interlock I Paver (Multi Color) with Compressive Strength
M25 or Above. 80MM Thickness j=dL
Hexagon Interlock Pavers (Grey Color) with Compressive
Strength M25 or Above. 60MM Thickness j=dL
Interlock Pavers (Single Color) with Compressive Strength M25 or
Above. 60MM Thickness j=dL
Hexagon Interlock Pavers (Multi Color) with Compressive Strength
M25 or Above. 60MM Thickness j=dL
Rectangular Interlock Paver (Grey Color) with Compressive
Strength M25 or Above. 60MM Thickness j=dL
Rectangular Interlock Paver (Single Color) with Compressive
Strength M25 or Above. 60MM Thickness j=dL
Rectangular Interlock Paver (Multi Color) with Compressive
Strength M25 or Above. 60MM Thickness j=dL
Half Battered Kerb Stone with Compressive Strength M25 or
Above /=dL
Bull Nose Kerb Stone with Compressive Strength M25 or Above /=dL
Matrix Slab (Grey Color) with Compressive Strength M25 or
Above. 40MM Thickness j=dL
Matrix Slab (Single Color) with Compressive Strength M25 or
Above. 40MM Thickness j=dL
Matrix Slab (Multi Color) with Compressive Strength M25 or
Above. 40MM Thickness j=dL

Security System
d'=c=s/ afx]ssf] b//]6
l;=g+= ;fdu|Lx?sf] ljj/0f PsfO{ cf=j= cf=j=
२)&#÷&$ २)&$÷&%
1 Steel Security Gate
Metal detector (black Scorpian Company) uf]6f 16995.00 16995.00
Access Controller (Taiwanese ) uf]6f 28840.00 28840.00
Access Controller (Chainese ) uf]6f 13905.00 13905.00
2 Steel Security Door 0.00
Single leaf :- 50 mm, 70 mm, 100mm a= ld= 8682.90 8683.00
Half leaf : - 50 mm, 70 mm, 100mm a= ld= 9930.23 9930.00
Double leaf : - 50 mm, 70 mm, 100mm a= ld= 10419.48 10419.00
3 Security System
i) Short range wireless intruder Alarm (including Host Unit-1,
PIR moton detector-1, Door Sensor-1, Remote Controller -2) uf]6f 34332.99 34333.00

iii) Access Controller with record using Card and Pin ( with
10 piece RFID Card.) uf]6f 20600.00 20600.00

iv) Access Controller without record using Card and Pin


( with 5 piece RFID Card.) uf]6f 12875.00 12875.00
v) Finger print access system with software uf]6f 36050.00 36050.00

vi) Securty from Panic Alarm uf]6f 36050.00 36050.00

4 CCTV System
Out door high speed Dome Integrated CAMERA Multi
Protocal ,480 TVL,128 preset points , automatic surveillance,360
degrees horizontal rotation , AC 240V power supply , integrated
heating system , highest angle speed 360 degree/ sec ,weather
resistance, water resistance, robust type.

Integrated camera chip, normal colour, 23 times optical Zoom,


10 times digital zoom ;]6 56650.00 56650.00

Integrated camera chip, day & night, 23 times optical Zoom, 10


times digital zoom ;]6 58916.00 58916.00

5 Indoor high speed Dome Integrated CAMERA


CANON Integrated camera chip, normal colour, 23 times
optical Zoom, 10 times digital zoom ;]6 54384.00 54384.00

CANON Integrated camera chip, day & night, 23 times optical


Zoom, 10 times digital zoom ;]6 56650.00 56650.00

VISTA Box camera with adoptor, IR view distance 25mm


Mirror shutter;with mirror image switchable,white balance;
auto,Horizontal resolution ; 480 TV line , system signal;
NTSC/PALBlacklight compression :ON/OFF(Switchable) ,
;]6 15450.00 15450.00
AGC; ON/OFF

7" Sphirical Shilded with bracket included chip excluded


8364.00 8364.00
Camera
8 Channel DVR MJPEG Compression Type 8 Channel
ionput 2 Channel output USB2.0Interface , Hard Disc >
200G, Multi-Record ,Motion Detector Function , Remote ;]6 33990.00 33990.00
Control

6 Channel Alarm input , 16 Channel Record 8 channel Alarm


output , Internate Explore, MPG-4 Record ;]6 50985.00 50985.00

17" LCD Monitor ;]6 10815.00 10815.00

NON DESTRUCTIVE TEST FOR FORENSIC ENGINEERING

d'=c=s/ afx]ssf] b//]6


l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j= cf=j=
२)&#÷&$ २)&$÷&%
1 Surface Hardness Element 1000
2 Cover Survey/ Rebar Orientation Element 4000
3 Homogeneity Element 5000
4 Crack Depth Measurement Element 5000
5 E-Modulus Calculation Test Element 5000
6 Resistivity Element 2500
7 Curing Efficency Test Element 2500
8 Corrosion Mapping Element 15000
9 Half Cell Potential Element 7000
10 Sonic Echo/ Void Detection Test Element 10000
11 Pulloff Test/ Bond Test Element 7000
12 Concrete Tensile Strength Test Element 7000
13 Moisture Content Element 4500
14 Core Extraction
32 mm Dia Element 7500
52 mm Dia Element 8000
75 mm Dia Element 8500
100 mm Dia Element 1000
150 mm Dia Element 12500
200 mm Dia Element 15000
250 mm Dia Element 17500
300 mm Dia Element 20000
350 mm Dia Element 25000
15 Rapid Chloride Penetration Test Element 15000
16 Anchor Pullout Test Element 20000
17 Infrared Thermography Element 3500
18 Low Strain Pile Integrity Test Element 11000
19 High Strain Dynamic Pile Load Test Element 500000
20 Fresh Concrete Resistivity (Smart Box) Element 4000
21 Fine/ Coarse Aggregate Moisture Content Element 3500
22 Fresh Concrete Moisture Content (W/C Ratio) Element 3500
23 Cross Hole Sonic Logging Element 12500
24 Impulse Echo Element 10000
25 Maturity Meter Test Element 35000
26 Chloride Profile Element 12500
27 Carbonation Depth Detection Test Element 2500
28 Boroscope Element 35000
29 Videoscope Element 85000
30 Ground Penetrating Radar Element 50000
31 CAPO Test Element 12500
32 Permeability Test Element
Air 30000
Water 40000
33 Concrete Cutting Services R. M. 30000
34 Wall Cutting Services R. M. 50000
35 Impact Echo Element 10000
36 Mortar Strength Test (Penetrometer) Element 5000
37 ASR Detection Test Element 10000
38 Moisture Content Test
Concrete Element 2000
Brick Element 2000
Masonry Element 2000
Wood Element 2500

jgh+un ;+u ;DjlGwt ljp tyf lj?jfx?

d'=c=s/ afx]ssf] b//]6


l;=g+= lgdf{0f ;fdu|Lx?sf] ljj/0f PsfO{ cf=j= cf=j=
२)&#÷&$ @)&$÷&5
1 x]h * OGr kf]nL uf]6f 30.00 55.00
2 sfk]{6 b'jf] j=lkm 30.00 33.00
3 sfk]{6 b'jf]sf] nflu 6fKg] sfo}{ Hofnf j=lkm 20.00 22.00
4 lgufnf] -h/f ;lxt_ uf]6f 12.00 12.00
5 :yfgLo :t/df pTkfl;bt lj?jf kmnkm"n afx]s uf]6f 5.00 11.00
6 uf]7] dn tof/L s]=hL= 3.00 4.00
7 8fn] 3fF;sf] lj?jf uf]6f 6.00 11.00
8 df]nf6f] lj?jf uf]6f 2.00 2.00
9 gl/jn 8f]/L s]=hL= 120.00 132.00
10 gfOng 8f]/L s]=hL= 250.00 275.00
11 nf}8 ;Nnf g]kfnL uf]6f 70.00 85.00
12 nf}7 ;Nnf cd]l/sg uf]6f 120.00 132.00
13 7"nf] ;fOhsf] afF;sf] lj?jf ljpaf6 pTkflbt uf]6f 220.00
jg sfof{noaf6 ;Dkfbg ul/g] sfo{x?
1 kf]lnyLg 6o'j $ Kjfn ePsf] @)) u]hsf] ljleGg ;fOh s]=hL= 350.00 385.00
2 7"nf lj?jf /f]kg $ lkm6 ;Dd k|lt la?jf 138.00
3 7"nf lj?jf /f]kg $ lkm6 ^ ;Dd k|lt la?jf 154.00
4 cUnf lj?jf /f]kg ^ lkm6 * ;Dd k|lt la?jf 140.00 231.00
So"=lkm
5 uf]lnof sf7 nf]8
=
So"=lkm
6 uf]lnof sf7 cgnf]g
bfp/f ;+sng , 9'jfgL r§f lgdf{0f -@) lkm=* % lkm=* =
7 r§f
% lkm_
8 bfp/f nf]8 r§f
9 bfp/f cgnf]8 r§f
10 ;s+ng s6fg , d'5fg r§f 340.00
12 cgnf]l8Ë r§f 140.00
13 r§f lgdf{0f r§f 140.00
14 7'6f pv]nL 3f6u2L :yn !)) dL= ;Dd n}hfg] sfo{ uf]6f 20.00
15 jg ;'kf/L k|lt la?jf 30.00
zx/L j[Iff/f]k0fsfo{
1 $ lkm6 ;Ddsf] lj?jf k|lt la?jf 800.00 880.00
2 % lkm6 ;Ddsf] lj?jf k|lt la?jf 1150.00 1250.00
3 ^ lkm6 ;Ddsf] lj?jf k|lt la?jf 1400.00 1540.00
4 * lkm6 ;Ddsf] lj?jf k|lt la?jf 1700.00 1870.00
$ lkm6 ;Ddsf] lj?jfsf] d'No
1 sk"/ k|lt la?jf 1200.00 770.00
2 ?b|fIf k|lt la?jf 950.00
3 sNsL af]6n a|; k|lt la?jf 660.00
4 Hofsf/08f uf]N8df]xf]/ k|lt la?jf 660.00
5 c;f/] k|lt la?jf 660.00
6 k}o" k|lt la?jf 440.00
7 nK;L k|lt la?jf 440.00
8 w"kL k|lt la?jf 1500.00 495.00
9 auda]nL k|lt la?jf 660.00
10 sfOof] k|lt la?jf 660.00
11 /Stsdn k|lt la?jf 1320.00
12 ;dL k|lt la?jf 1500.00 1100.00
13 a/ k|lt la?jf 1320.00
14 lkkn k|lt la?jf 1320.00
15 % lkm6 ;Ddsf] s/lj/ lj?jf k|lt la?jf 1200 1200.00
16 % lkm6 ;Ddsf] ltsf]df lj?jf k|lt la?jf 1200 1200.00
17 % lkm6 ;Ddsf] rfksf] lj?jf k|lt la?jf 1300 1300.00

jfof] O{lGhlgol/ª ;DjlGw sfd


3f;sf] ljp
1 hO{ ls=u|f 75.00 75.00
2 e]r ls=u|f 150.00 150.00
3 g]kLo/ ;]6 3.00 3.00
4 jl;{d ls=u|f 175.00 175.00
5 3fF;sf] lap / cf}iflw lhNnf leq 9'jfgL ubf{ ls=u|f 0.50 0.50
6 3fF;sf] lap lhNnf aflx/af6 9'jfgL ubf{ ls=u|f 1.00 1.00
7 df6f] eg]{ vfnL af]/f uf]6f 12.00 12.00
8 af; sf6]sf] l;+uf] 3fgf 3fgf 350.00 350.00

9
af+;sf] sl6+u :6Dk la?jf-!% dlxg] g;{/Ldf /fv]sf]_ != प्रति कटिंग
% lkm6 b]lv @ lkm6 nfdf] 55.00 55.00
Vegitation/Shrubs Cuttings/Slip/Plants/etc.
1 cld|;f]-/fOhf]d_ k|lt la?jf 7.00 7.00
2 cn}+rL ufgf] k|lt la?jf 11.00 11.00
3 cn}+rL la?jf k|lt la?jf 8.00 8.00
4 xf8{p8 sl6Ë;\ -a}+;_ k]lG;n ;fOh k|lt la?jf 5.00 5.00
5 g]lko/ sl6Ë;\ k|lt la?jf 2.00 2.00
6 NB 21 3fF; k|lt la?jf 2.00 2.00
7 lgufnf] /fO{hf]d k|lt la?jf 50.00 50.00
8 af;sf] a]gf{ -s6Lu /fO{hf]d+_ k|lt la?jf 400.00 400.00
9 aflaof] tfOjfgL b'af] k|lt la?jf 3.00 3.00
10 l;hgn km'n * OGr kf]nL uf]6f 25.00 25.00
11 u'nfkm km''n * OGr kf]nL uf]6f 150.00 150.00
12 x]h * OGr kf]nL uf]6f 30.00 30.00
13 sfk]{6 b'af] j=kmL= 30.00 30.00
14 sfk]{6 b'af] sf] nfuL 5fKg] sfo{sf] Hofnf j=kmL= 20.00 20.00
15 lgufnf] -h/f ;xLt_ uf]6f 12.00 12.00
16 :YffgLo :t/df pTkfbLt la?jf kmnkm'n afx]s uf]6f 5.00 5.00
17 uf]7] dn tof/L s]=hL= 3.00 3.00
18 8fn] 3f;sf] la?jf uf]6f 6.00 6.00
19 df]nf6f] la/jf uf]6f 2.00 2.00
20 nf}7 ;Nnf g]kfnL uf]6f 70.00 70.00
21 nf}7 ;Nnf cd]l/sg uf]6f 120.00 120.00
22 v/ uf]6f
23 cDjf k|lt la?jf
24 plt; ,wo]/f],c;'/f],jsfOgf],lgd cfbL uf]6f
25 e'h]qf] s]=hL=
26 v/,km's]{ l;6f] cflbsf]] ljp s]=hL=
27 h'6 g]6 j=dL=
b l6Dj/ skf]{/]zgaf6 ;Dkfbg ul/g] sfo{x?
1 lr/fg pTkfbg-afsn,e'if,kmfNg] qm; sl6+u ;d]t_ So"=lkm=
2 lr/fg nf]8 So"=lkm=
3 lr/fg kfOln+u So"=lkm=
4 lr/fg cgnf]8 So"=lkm=
5 ldn l;kd]G6sf] uf]lnof cgnf]8 So"=lkm=
6 ef8fsf] ;Mldnaf6 uf]lnof lr/fg Hofnf-uf]lnofdf_ So"=lkm=
7 bfp/f nf]8 SjLG6n
8 bfp/f cgnf]8 SjLG6n
9 kf]n nf]8 k|lt uf]6f
10 kf]n cgnf]8 k|lt uf]6f

29 Road equipment

Roller vib. 6.3 ton per hour.(with fuel ) 53.pp


Roller Pneumatic per hour.(with fuel ) 53.nn
Truck 7 cum
Dozer D50 53.z
Diesel 071.4.29
water browser (with fuel ) aaa
loader (with fuel ) gg
Grader (with fuel ) bb
Vibrator Roller (with fuel )
Bitumen heater/Boiler 53.ee 0
Sprayer bitumen 53.uu 0
Air compressor
Asphalt Plant
Asphalt Paver

17 Grader Hr 1600
18 Roller Hr 700
asphalt paver Hr 1400
19 Vibrating roller Hr 800
Pneumatic roller Hr 1200
20 Water browser Hr 550
21 Loader Hr 1500
22 Sprayer Hr 1300
23 Air compressor Hr 250
24 Boiler Hr 180
25 Kerosene Lit 74
26 Bitumen Kg 68.4
30 Diesel Lit 100
31 Truck/Tripper Hr 450
32 Enamel paint Lit 509
33 100mm Dia. HDPE Pipe Rm 426
34 Heavy Duty GI pipe(dia 40mm) Rm 493
35 Dozer D50 hr 1800
36 Asphalt plant hr 500
7 Bitumen 80/100 kg 68.4
Hofnf b/ k|ltlbg ?=
cf=j= cf=j=
@)&६÷)७७ २०७७÷०७८

750.00 750.00
1070.00 1070.00

1030.00 1030.00

845.00 845.00

@@@@@ @@@@@

750.00 750.00

690.00 690.00

630.00 630.00

765.00 765.00
750.00 750.00

785.00 785.00

1070.00 1070.00
1100.00 1100.00
785.00 785.00
5500.00 5500.00

6600.00 6600.00

df ;+jlGwt kb÷>]l0fsf] nflu g]kfn ;/sf/sf]


s Hofnfb/ dfGg'kg]{ 5 .
lgwf{/0f
3/sf] agfj6 x]/L tklzn jdf]lhd b/ sfod
cf=j= @)& cf=j=
%÷)^% sf] b/ @)&^÷)&&sf]
-?_ b/-?_
1330.00 1370.0

1710.00 1760.0

1902.00 1960.0

2001.00 2060.0

1952.00 2010.0

2123.00 2185.0

2210.00 2276.0

2140.00 2205.0

2216.00 2285.0

2340.00 2410.0

2048.00 2110.0

]6f ;'ljwf ePsf] 'v' ju{ cGoyf 'u'


'g] 5 M
f{0f ePsf 3/x?sf] xsdf Internal Rate of
8s;+u hf]l8Psf ;xfos ;8s / ;f] ;xfos ;8saf6
]Zj/–sn+sL–yfgsf]6 r]skf]i6–
S;fn–ef6e6]gL–k|x/L tflnd
c:ktfn–hdn–n}grf}/– nflhDkf6–6LlrË

fs{;Ddsf] ;8s .
x]Gb| zflns;Ddsf] ;8s .

] l;dfgf;Ddsf] ;8s .
sf] ;8s .

L
d'=c=s/ afx]ssf] b//]6
cf=j= @)& cf=j=
%÷&^ @)&^÷&&

94.00 86.00
91.50 84.00
92.50 85.00
92.50 85.00

88.94 82.00
85.84 79.00 79000
88.94 82.00
94.15 86.00
101.77 92.00
70.00 70.00
81.42 81.42
81.00 81.00
83.19 83.19
82.30 82.30
139.10 139.10
139.10

107.00 105.00
107.00 105.00
107.00 105.00

102.00 100.00
102.00 100.00
103.00 100.00
97.00 95.00
97.00 95.00
98.00 95.00

220.00 231.00

266.00 280.00

435.00 457.00

287.75 302.00

259.09 272.00

97.35 97.35
0.75 0.75

697.00 967.00
652.00 652.00
517.00 517.00
423.00 423.00
337.00 337.00

116.00 116.00

121.00 121.00

74.00 74.00

189.00 189.00

152.00 152.00

263.00 263.00

130.00 130.00

120.00 120.00

500.00 500.00
350.00 350.00
280.00 280.00

500.00 500.00

650.00 650.00

3050.00 2874.00

125.00 125.00
112.00 112.00
165.00 165.00
45.00 45.00
140.00 140.00

1940.00 1940.00

194.00 194.00
243.00 243.00
310.00 310.00
376.00 376.00
508.00 508.00

d'=c=s= afx]ssf] b//]6

cf=j= @)& cf=j=


%÷&^ @)&^÷&&
74.62 78.10
75.82 75.82
67.82 68.50
71.72 72.50
75.62 76.50
68.62 69.35
72.62 73.35
69.82 70.60
74.92 75.70
98.52 98.32
109.52 109.52

328.02 322.50

30.00 31.50
165.00 173.00
182.00 191.00
150.00 157.00

21247.00 23107.00
47077.00 49032.00

9316.00 9650.00
18716.00 19230.00

175000.00 175000.00

175000.00 175000.00

634.00 634.00
1265.00 1265.00

72.00 72.00
80.00 80.00
117.00 117.00
360.00 360.00
148820.00 148820.00
9950.00 9950.00
1650.00 1650.00
3135.00 3135.00

190000.00 190000.00

6000.00 6000.00

10500.00 10500.00

74.00 74.00
372.00 372.00
637.00 637.00
1273.00 1273.00
1591.00 1591.00
424.00 424.00
6695.00 6695.00
290.00 290.00
380.00 380.00
350.00 350.00
48.00 48.00
d'=c=s= afx]ssf] b//]6
cf=j= @)& cf=j=
%÷&^ @)&^÷&&

16880.00 16880.00

14470.00 14470.00 14.47

16720.00 16720.00
2500.00 2500.00

15450.00 15450.00
16274.00 16274.00
37.00 37.00
32.00 32.00
50.00 50.00
162.00 162.00
299.00 299.00
114.00 114.00
171.00 171.00
228.00 228.00

121.00 127.00
181.00 190.00
244.00 256.00

73.00 73.00 2577.8766

91.00 91.00 3213.21

91.00 91.00 3213.21

0.00 35.313378

95.00 95.00 3344.95

0.00

95.00 95.00 3344.95

83.00 83.00

72.00 72.00 2542.32


0.00
85.00 85.00

18.00 18.00
16.00 16.00
32.00 32.00
26.00 26.00

10.00 10.00
9.00 9.00

76.00 76.00

88.00 88.00

103.00 103.00
111.00 111.00
138.00 138.00
105.00 105.00

57.24 57.24 2021.1444

65.00 65.00

45.36 45.36

41.04 41.04
318.60 318.60
550.80 550.80
5.50 5.50
5.00 5.00

0.26 0.26
0.31 0.31
31.00 31.00
2355.00 2355.00
210.00 210.00

l/ªx?
d'=c=s/ afx]ssf] b//]6
cf=j=@)&
@)&^÷&&
%÷&^

543.00 570.00
705.00 740.00
883.00 925.00
1198.00 1260.00
1323.00 1325.00
1449.00 1520.00
1666.00 1750.00
1764.00 1852.00
1979.00 2080.00
2610.00 2740.00
3406.00 3575.00
3684.00 3870.00
4112.00 4320.00
5556.00 5835.00
6482.00 6805.00
7906.00 8301.00
16620.00 17450.00

1248.00 1310.00
1663.00 1745.00
2079.00 2185.00
2988.00 3140.00
3352.00 3520.00
3583.00 3760.00
3819.00 4010.00
4287.00 4500.00
4779.00 5020.00
5905.00 6200.00
7130.00 7485.00
8190.00 8600.00
8938.00 9385.00
11593.00 12172.00
12881.00 13525.00
15332.00 16100.00
24092.00 25300.00

139.00 145.00
184.00 193.00
228.00 239.00
309.00 324.00
340.00 357.00
374.00 392.00
430.00 451.00
454.00 476.00
510.00 535.00
673.00 706.00
877.00 920.00
948.00 995.00
1058.00 1110.00
1430.00 1500.00
1669.00 1752.00
2036.00 2137.00
4279.00 4492.00

312.00 327.00
416.00 436.00
519.00 544.00
746.00 783.00
838.00 879.00
895.00 940.00
954.00 1000.00
1072.00 1125.00
1196.00 1255.00
1477.00 1550.00
1782.00 1871.00
2047.00 2150.00
2233.00 2344.00
2898.00 3042.00
3221.00 3382.00
3833.00 4024.00
6023.00 6324.00

1410.00 1480.00
1914.00 2010.00
2390.00 2510.00
3435.00 3605.00
4392.00 4610.00
4931.00 5180.00
5496.00 5770.00
6791.00 7130.00
8200.00 8610.00
10278.00 10790.00
13334.00 14000.00
14814.00 14814.00
18600.00

;fdfu|L
d'=c=s= afx]ssf] b//]6

cf=j= @)& cf=j=


%÷&^ @)&^÷&&
841.00 825.00 16500
743.00 725.00
1230.00 1230.00
10.00 10.70

13000.00 13650.00
14000.00 14700.00
14500.00 15225.00
15500.00 16275.00
16300.00 17115.00
17600 18382.00
19000 19950.00
1200.00 1200.00

1050.00 1050.00

950.00 950.00

49.00 49.00
56.00 56.00
65.00 65.00
75.00 75.00
100.00 100.00
150.00 150.00
190.00 190.00
220.00 220.00

48.41 48.41
56.65 56.65

154.50 154.50

96.00 96.00
103.00 103.00
120.00 120.00
180.00 180.00
250.00 250.00
350.00 350.00
400.00 400.00

116.00 116.00

6200.00 6200.00

184.00 184.00

238.00 238.00
285.00 285.00
393.00 393.00
161.00 161.00
23.00 23.00
35.00 35.00
60.00 60.00

160.00 168.00
175.00 184.00
250.00 262.00
335.00 352.00
376.00 395.00

142.00 150.00
130.00 137.00

126.00 126.00
85.00 85.00
54.00 54.00
43.00 43.00
180.00 180.00
150.00 150.00
165.00 165.00
144.00 144.00
106.00 106.00
111.00 111.00

98.00 98.00
88.00 88.00
77.00 77.00
129.00 129.00
134.00 134.00
103.00 103.00

623.00 623.00

75.00 75.00

87.00 87.00
107.00 107.00
87.00 87.00
22.00 22.00

{0f ;fdfu|Lx?
d'=c=s/ afx]ssf] b//]6
cf=j= २)& cf=j=
%÷&6 २)&^÷&&

70000.00 70000.00
105000.00 105000.00
240000.00 240000.00
800.00 800.00
900.00 900.00
3700.00 3700.00
40000.00 40000.00
2720.00 2720.00
1900.00 1900.00
950.00 950.00
1360.00 1360.00
2450.00 2450.00
2990.00 2990.00
1360.00 1360.00
1155.00 1155.00

25.00 25.00
35.00 35.00
27.00 27.00
27.00 27.00
320.00 320.00
53.00 53.00
158.00 158.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
132.00 132.00
70.00 70.00
27.00 27.00
40.00 40.00
132.00 132.00
70.00 70.00
27.00 27.00
40.00 40.00
530.00 530.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
32.00 32.00
32.00 32.00
32.00 32.00
32.00 32.00
32.00 32.00
32.00 32.00
27.00 27.00
40.00 40.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
32.00 32.00
32.00 32.00
32.00 32.00
42.00 42.00
42.00 42.00
53.00 53.00
42.00 42.00
53.00 53.00
53.00 53.00
53.00 53.00
27.00 27.00
40.00 40.00
53.00 53.00
105.00 105.00
105.00 105.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
60.00 60.00
53.00 53.00
69.00 69.00
105.00 105.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
500.00 500.00
1896.00 1896.00
22.00 22.00
35.00 35.00
25.00 25.00
37.00 37.00
27.00 27.00
40.00 40.00
37.00 37.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
32.00 32.00
40.00 40.00
27.00 27.00
40.00 40.00
27.00 27.00
40.00 40.00
40.00 40.00
27.00 27.00
40.00 40.00
40.00 40.00
63.00 63.00
63.00 63.00
63.00 63.00
63.00 63.00
105.00 105.00
27.00 27.00
40.00 40.00
27.00 27.00
69.00 69.00
27.00 27.00
40.00 40.00
27.00 27.00
10.00 10.00
75.00 75.00
75.00 75.00
19.00 19.00
25.00 25.00
27.00 27.00
35.00 35.00
150.00 150.00
250.00 250.00
300.00 300.00
22.00 22.00
1155.00 1155.00
1155.00 1155.00

2000.00 2000.00

3000.00 3000.00
173.00 173.00
14.00 14.00
8.00 8.00
23.00 23.00
1350.00 1350.00
1025.00 1025.00
300.00 300.00
1386.00 1386.00
476.00 476.00

;fdfu|L
d'=c=s/ afx]ssf] b//]6
cf=j= @)& cf=j=
%÷&^ @)&^÷&&
5600.00 5600.00 197736
5800.00 5800.00 204798
6250.00 6250.00 220687.5
6600.00 6600.00 233046
3350.00 3350.00 118288.5
2150.00 2150.00 75916.5
1550.00 1550.00 54730.5
3500.00 3500.00 123585
5270.00 5270.00 186083.7
625.00 625.00 22068.75 50905.25
18.00 18.00 635.58

235.00 235.0
280.00 280.0

325.00 325.0

245.00 245.0

288.00 288.0

333.00 333.0
1080.00 1080.00

1260.00 1260.00

680.00 680.00

2250.00 2250.00

13500.00 13500.00

22500.00 22500.00

3150.00 3150.00

7280.00 7280.00

1350.00 1350.00

1620.00 1620.00

2250.00 2250.00

1980.00 1980.00

360.00 360.00

1620.00 1620.00

1710.00 1710.00

220.00 220.00

560.00 560.00

36.00 36.00

26.00 26.00

26.00 26.00

53.00 53.00

57.00 57.00

80.00 80.00

107.00 107.00 1151.32


110.00 110.00 1183.6
0
52.00 52.00 559.52
67.00 67.00 720.92
63.00 63.00 677.88
89.00 89.00 957.64
99.00 99.00 1065.24
113.00 113.00 1215.88
139.00 139.00 1495.64

48.00 48.00

69.00 69.00

60.00 60.00

43.00 43.00

49.00 49.00

39.00 39.00

46.00 46.00

37.00 37.00

17.00 17.00
75.00 75.00
44.00 44.00

126.00 126.00
160.00 160.00
140.00 140.00
173.00 173.00
153.00 153.00
187.00 187.00
165.00 165.00
200.00 200.00
187.00 187.00
221.00 221.00

174.00 174.00

237.00 237.00

199.00 199.00

268.00 268.00

14.00 14.00
16.00 16.00
27.00 27.00

38.00 38.00
380.00 380.00

380.00 380.00

2227.00 2227.00

300.00 300.00

1800.00 1800.00

ws

d'=c=s/ afx]ssf] b//]6

cf=j= @)& cf=j=


%÷&^ @)&^÷&&

657.00 657.00

723.00 723.00

836.00 836.00

920.00 920.00

529.00 529.00

604.00 604.00

571.00 571.00

658.00 658.00
428.00 428.00

492.00 492.00

188.00 188.00

519.00 519.00

563.00 563.00

390.00 390.00

478.00 478.00

548.00 548.00

636.00 636.00

773.00 773.00

1259.00 1259.00

817.00 817.00

1354.00 1354.00

333.00 333.00

447.00 447.00

w
d'=c=s/ afx]ssf] b//]6

cf=j= @)& cf=j=


%÷&^ @)&^÷&&
rame 52*88; sash 80*42, Casement window frame
m thick clear float glass, insect net, patented standard
7215.00 7215.00

6664.00 6664.00

7493.00 7493.00

7493.00 7493.00

8214.00 8214.00

8328.00 8328.00

8884.00 8884.00

8884.00 8884.00

8606.00 8606.00

9991.00 9991.00

8626.00 8626.00

9796.00 9796.00

10353.00 10353.00

10717.00 10717.00

6727.00 6727.00

9435.00 9435.00

8935.00 8935.00

9718.00 9718.00

9718.00 9718.00

10439.00 10439.00

10547.00 10547.00

11103.00 11103.00

10825.00 10825.00

9611.00 9611.00

d'=c=s/ afx]ssf] b//]6


cf=j= २)& cf=j=
%÷&^ २)&^÷&&

4690 4707.96
5133 5141.59
5522 5522.12
5841 5840.71
6159 6185.84
6779 6734.51
7522 7460.18
7885 8097.35
8708 8619.47
9460 9407.08
10469 10398.23
10841 11336.28
15513 15415.93

5796 5858.41
6195 6265.49
6584 6707.96
6973 7061.95
7336 7433.63
7956 7982.30
8823 8831.86
9265 9451.33
10133 10079.65
10912 10929.20
11920 11938.05
12354 12380.53
12947 12964.60
17389 17415.93

4690 4707.96
5088 5106.19
5487 5486.73
5796 5805.31
6115 6141.59
6726 6681.42
7478 7407.08
7841 8035.40
8655 8566.37
9416 9362.83
10416 10345.13
10788 10716.81
15513 15415.93

1602 1601.77
1735 1743.36
1867 1867.26
1973 1973.45
2080 2088.50
2283 2265.49
2531 2513.27
2655 2716.81
2920 2893.81
0
3274 3265.49
2708 2699.12
2442 2433.63
2292 2283.19
2142 2132.74
1912 1911.50
1717 1707.96
1566 1557.52
1496 1495.58
1416 1415.93
1336 1327.43
1274 1265.49
1186 1176.99
1133 1132.74
982 991.15
920 929.20
0
2973 2982.30
2699 2707.96
2531 2539.82
2434 2433.63
2177 2176.99
1956 1955.75
1788 1787.61
1708 1716.81
1619 1619.47
1513 1513.27
1487 1486.73
1389 1389.38
1327 1327.43
1168 1176.99
1106 1115.04

159 159.29
212 212.39
133 132.74
177 176.99
124 123.89
159 159.29
1506.00 1506.00
1200.00 1200.00
1925.00 1925.00
1925.00 1925.00
26.00 26.00
30.00 30.00
20.00 20.00
11.00 11.00
8.50 8.50

66.37 66.37
745.13 745.13
447.79 447.79
101.77 101.77
110.62 110.62
1343.36 1343.36
745.13 745.13
996.46 996.46
8.85 8.85

29 29.00
27 27.00

115.00 115.00
127.00 127.00
127.00 127.00
146.00 146.00
216.00 216.00
255.00 255.00
293.00 293.00
382.00 382.00

1076.00 1076.00

1550.00 1550.00
20.00 20.00
67.00 67.00
7.00 7.00
137.00 137.00
7.00 7.00
10.00 10.00

d'=c=s/ afx]ssf] b//]6


cf=j= २)&%÷&^ cf=j= २)&^÷&&

38.00 38.00
43.00 43.00
55.00 55.00
74.00 74.00

77.00 77.00
86.00 86.00
102.00 102.00
132.00 132.00

0.00 0.00

86.00 86.00
99.00 99.00
114.00 114.00
145.00 145.00
0.00 0.00
28.00 28.00
32.00 32.00
48.00 48.00
61.00 61.00

0.00 0.00

42.00 42.00
59.00 59.00
68.00 68.00
77.00 77.00
89.00 89.00
111.00 111.00

0.00 0.00

48.00 48.00
64.00 64.00
77.00 77.00

0.00 0.00

48.00 48.00
55.00 55.00
68.00 68.00
88.00 88.00
99.00 99.00
127.00 127.00
176.00 176.00

0.00 0.00

55.00 55.00
61.00 61.00
76.00 76.00
95.00 95.00
105.00 105.00
133.00 133.00
180.00 180.00
0.00 0.00

175.00 175.00
280.00 280.00
423.00 423.00
0.00 0.00
84.00 84.00
120.00 120.00
221.00 221.00
305.00 305.00
370.00 370.00
553.00 553.00
713.00 713.00
380.00 380.00
540.00 540.00
575.00 575.00

168.00 168.00
319.00 319.00
444.00 444.00

0.00 0.00
124.00 124.00
82.00 82.00
83.00 83.00

26.00 26.00
28.00 28.00
32.00 32.00
33.00 33.00
47.00 47.00
63.00 63.00
71.00 71.00
80.00 80.00
89.00 89.00
0.00 0.00
32.00 32.00
50.00 50.00
68.00 68.00
6370.00 6370.00
90.00 90.00
n
d'=c=s/ afx]ssf] b//]6

cf=j= २)&$÷& cf=j= २)&


% %÷&^

302.00 302.00
239.00 239.00

0.00 0.00

93.00 93.00

279.00 279.00

244.00 244.00

311.00 311.00

274.00 274.00

217.00 217.00

288.00 288.00
35.00 35.00

34.00 34.00
42.00 42.00
53.00 53.00
64.00 64.00

393.00 393.00

424.00 424.00

524.00 524.00

112.00 112.00

263.00 263.00
347.00 347.00

282.00 282.00
286.00 286.00

250.00 250.00

319.00 319.00

359.00 359.00

200.00 200.00
275.00 275.00
330.00 330.00
385.00 385.00
465.00 465.00
50 50.00

S;r/x?

d'=c=s/ afx]ssf] b//]6

cf=j= २)& cf=j=


%÷&^ २)&^÷&&

15.00 15.00

28.00 28.00

43.00 43.00

56.00 56.00

260.00 260.00

227.00 227.00

195.00 195.00

20.00 20.00
40.00 40.00
67.00 67.00
80.00 80.00
94.00 94.00
107.00 107.00
32.00 32.00
47.00 47.00

63.00 63.00

71.00 71.00

87.00 87.00

71.00 71.00

79.00 79.00

87.00 87.00
189.00 189.00
284.00 284.00
379.00 379.00
458.00 458.00

142.00 142.00
189.00 189.00
284.00 284.00
379.00 379.00
473.00 473.00
568.00 568.00

150.00 150.00
458.00 458.00
947.00 947.00

947.00 947.00
1562.00 1562.00
1735.00 1735.00

1062.00 1062.00
1199.00 1199.00
1249.00 1249.00
1249.00 1249.00

225.00 225.00
300.00 300.00
375.00 375.00

892.00 892.00
1130.00 1130.00
1249.00 1249.00

250.00 250.00
375.00 375.00
625.00 625.00
416.00 416.00
2557.00 2557.00
1130.00 1130.00

178.00 178.00
1874.00 1874.00
18.00 18.00

31.00 31.00
35.00 35.00
42.00 42.00
75.00 75.00
0.00 0.00
148.00 148.00
196.00 196.00
425.00 425.00
406.00 406.00
874.00 874.00
100.00 100.00
178.00 178.00

1.92 1.92
2.67 2.67
4.11 4.11
12.06 12.06
15.08 15.08

1.17 1.17
1.92 1.92
2.33 2.33
7.20 7.20
7.54 7.54
92.70 92.70
97.85 97.85

x?
d'=c=s/ afx]ssf] b//]6
cf=j= २)& cf=j=
%÷&^ २)&^÷&&
65.00 65.00
271.00 271.00
365.00 365.00
509.00 509.00
491.00 491.00
462.00 462.00
530.00 530.00
427.00 427.00
330.00 330.00
224.00 224.00
128.00 128.00
151.00 151.00
197.00 197.00
211.00 211.00
208.00 208.00
254.00 254.00
222.00 222.00
466.00 466.00
54.00 54.00
133.00 133.00
1280.00 1280.00
87.00 87.00
217.00 217.00
511.00 511.00
612.00 612.00
650.00 650.00
683.00 683.00
562.00 562.00
191.00 191.00
114.00 114.00
255.00 255.00
345.00 345.00
118.00 118.00
70.00 70.00
140.00 140.00
210.00 210.00
280.00 280.00
400.00 400.00
6.00 6.00
36.00 36.00
60.00 60.00
22.00 22.00
450.00 450.00
1238.00 1238.00
11706.00 11706.00

1099.00 1099.00
762.00 762.00
0.00 0.00
176.00 176.00
1639.00 1639.00
4305.00 4305.00
412.00 412.00
121.00 121.00
921.00 921.00
149.00 149.00
199.00 199.00
199.00 199.00
199.00 199.00
238.00 238.00
238.00 238.00
174.00 174.00
237.00 237.00
264.00 264.00
1267.00 1267.00
728.00 728.00
2631.00 2631.00
107.00 107.00
165.00 165.00
159.00 159.00
189.00 189.00
412.00 412.00
181.00 181.00
139.00 139.00
215.00 215.00
239.00 239.00

503.00 503.00
588.00 588.00
322.00 322.00
510.00 510.00
238.00 238.00
0.00
522.00 522.00
280.00 280.00
772.00 772.00
172.00 172.00
142.00 142.00
512.00 512.00
313.00 313.00
276.00 276.00
0.00 0.00
387.00 387.00
170.00 170.00
0.00
466.00 466.00
619.00 619.00
39.00 39.00

0.00
128.00 128.00
195.00 195.00
167.00 167.00
133.00 133.00
140.00 140.00
120.00 120.00
156.00 156.00

65.00 65.00
74.00 74.00
99.00 99.00
93.00 93.00
103.00 103.00
90.00 90.00
90.00 90.00
112.00 112.00
112.00 112.00
154.00 154.00
116.00 116.00
107.00 107.00
98.00 98.00
124.00 124.00
135.00 135.00
54.00 54.00
38.00 38.00
34.00 34.00
0.00
23.00 23.00
21.00 21.00
17.00 17.00
31.00 31.00

24.00 24.00
20.00 20.00
16.00 16.00
11.00 11.00
18.00 18.00

1236.00 1236.00

7.00 7.00

108.00 108.00

32.4333333333333 32.43

ent works
d'=c=s/ afx]ssf] b/
cf=j= २)& cf=j=
%÷&^ २)&^÷&&

100.00 100.00
350.00 350.00
2000.00 2000.00
235.00 235.00

350.00 350.00
450.00 450.00

150.00 150.00

250.00 250.00

450.00 450.00

300.00 300.00

1000.00 1000.00

1000.00 1000.00

1250.00 1250.00

180.00 180.00

250.00 250.00

350.00 350.00

350.00 350.00

250.00 250.00

450.00 450.00

330.00 330.00

110.00 110.00

85.00 85.00

1800.00 1800.00

1800.00 1800.00

3000.00 3000.00
2000.00 2000.00
3000.00 3000.00
1200.00 1200.00
350.00 350.00
450.00 450.00
125.00 125.00
550.00 550.00
750.00 750.00
4000.00 4000.00
3000.00 3000.00
275.00 275.00
1500.00 1500.00
2700.00 2700.00
800.00 800.00
2450.00 2450.00
4850.00 4850.00
800.00 800.00
1500.00 1500.00

2500.00 2500.00

3500.00 3500.00

4500.00 4500.00

120.00 120.00

450.00 450.00
2500.00 2500.00
3000.00 3000.00
2000.00 2000.00
2200.00 2200.00
3000.00 3000.00
500.00 500.00

110.00 110.00

125.00 125.00

160.00 160.00
1000.00 1000.00
500.00 500.00

2500.00 2500.00

4500.00 4500.00

7500.00 7500.00
12500.00 12500.00
8500.00 8500.00

14000.00 14000.00

9500.00 9500.00

130.00 130.00
60.00 60.00
250.00 250.00
750.00 750.00
950.00 950.00

1200.00 1200.00

1800.00 1800.00

1200.00 1200.00
1500.00 1500.00
2000.00 2000.00
250.00 250.00
350.00 350.00
250.00 250.00

1200.00 1200.00
1350.00 1350.00
4500.00 4500.00
1500.00 1500.00
1800.00 1800.00
1500.00 1500.00
900.00 900.00
500.00 500.00
500.00 500.00
450.00 450.00

1000.00 1000.00
1200.00 1200.00
140.00 140.00
175.00 175.00
250.00 250.00
200.00 200.00
1200.00 1200.00

85.00 85.00
350.00 350.00
85.00 85.00
85.00 85.00

90.00 90.00

275.00 275.00

7500.00 7500.00

700.00 700.00

500.00 500.00
750.00 750.00

850.00 850.00

750.00 750.00

350.00 350.00

400.00 400.00

1650.00 1650.00

1250.00 1250.00

600.00 600.00

1800.00 1800.00

2000.00 2000.00

1050.00 1050.00
1500.00 1500.00

1500.00 1500.00

2000.00 2000.00
2500.00 2500.00
2500.00 2500.00
2500.00 2500.00
3000.00 3000.00
3500.00 3500.00

800.00 800.00

4500.00 4500.00

550.00 550.00

225.00 225.00

525.00 525.00

650.00 650.00
1250.00 1250.00
1000.00 1000.00
750.00 750.00
1000.00 1000.00
12000.00 12000.00
2500.00 2500.00
7500.00 7500.00
2500.00 2500.00
2500.00 2500.00
2500.00 2500.00
110.00 110.00
2800.00 2800.00
3500.00 3500.00
TROFITTING

d'=c=s/ afx]ssf] b/
cf=j= २)& cf=j=
%÷&^ २)&^÷&&

8500.00 8500.00
10000.00 10000.00

8000.00 8000.00

12000.00 12000.00

16000.00 16000.00
12000.00 12000.00
3500.00 3500.00
3500.00 3500.00
2500.00 2500.00
3500.00 3500.00
4500.00 4500.00
2500.00 2500.00
3500.00 3500.00
10000.00 10000.00
12000.00 12000.00

10490.00 10490.00

12460.00 12460.00

14760.00 14760.00

19680.00 19680.00

18040.00 18040.00

12580.00 12580.00

14955.00 14955.00

17710.00 17710.00

23615.00 23615.00

6560.00 6560.00

8200.00 8200.00

9840.00 9840.00

13120.00 13120.00
7540.00 7540.00

9430.00 9430.00

11310.00 11310.00

15080.00 15080.00 samma clear

d'=c=s/ afx]ssf] b//]6


cf=j= २)& cf=j=
%÷&^ २)&^÷&&

1020.00 1051.00

39.00 40.00

41.00 42.00

47.00 48.00

48.00 49.00

49.00 50.00

50.00 52.00

57.00 59.00

0.00
9.00 10.00
21.00 22.00
23.00 24.00
29.00 30.00
32.00 33.00
14.00 15.00
15.00 16.00

73.00 75.00
64.00 66.00
82.00 84.00
82.00 84.00
18.00 19.00
12.00 12.00

37.00 38.00
32.00 33.00
50.00 52.00

162.00 167.00
299.00 308.00
114.00 117.00
171.00 176.00
228.00 235.00

2278

2827

3466

1684

2118

2573

1829

2323

2818

1589

1852

1082

1298

1684

d'=c=s/ afx]ssf] b//]6


cf=j= २)& cf=j=
%÷&^ २)&^÷&&

16995.00 16995.00
28840.00 28840.00
13905.00 13905.00
0.00 0.00
8683.00 8683.00
9930.00 9930.00
10419.00 10419.00

34333.00 34333.00

20600.00 20600.00

12875.00 12875.00
36050.00 36050.00

36050.00 36050.00

56650.00 56650.00

58916.00 58916.00

54384.00 54384.00

56650.00 56650.00

15450.00 15450.00

8364.00 8364.00

33990.00 33990.00

50985.00 50985.00

10815.00 10815.00

GINEERING

d'=c=s/ afx]ssf] b//]6


cf=j= २)& cf=j=
%÷&^ २)&^÷&&
1000.00 1000.00
4000.00 4000.00
5000.00 5000.00
5000.00 5000.00
5000.00 5000.00
2500.00 2500.00
2500.00 2500.00
15000.00 15000.00
7000.00 7000.00
10000.00 10000.00
7000.00 7000.00
7000.00 7000.00
4500.00 4500.00
7500.00 7500.00
8000.00 8000.00
8500.00 8500.00
1000.00 1000.00
12500.00 12500.00
15000.00 15000.00
17500.00 17500.00
20000.00 20000.00
25000.00 25000.00
15000.00 15000.00
20000.00 20000.00
3500.00 3500.00
11000.00 11000.00
500000.00 500000.00
4000.00 4000.00
3500.00 3500.00
3500.00 3500.00
12500.00 12500.00
10000.00 10000.00
35000.00 35000.00
12500.00 12500.00
2500.00 2500.00
35000.00 35000.00
85000.00 85000.00
50000.00 50000.00
12500.00 12500.00

30000.00 30000.00
40000.00 40000.00
30000.00 30000.00
50000.00 50000.00
10000.00 10000.00
5000.00 5000.00
10000.00 10000.00

2000.00 2000.00
2000.00 2000.00
2000.00 2000.00
2500.00 2500.00

?jfx?

d'=c=s/ afx]ssf] b//]6


cf=j= @)&
%÷&^ cf=j=
@)&^÷&&
55.00 55.00
33.00 33.00
22.00 22.00
12.00 12.00
11.00 11.00
4.00 4.00
11.00 11.00
2.00 2.00
132.00 132.00
275.00 275.00
85.00 85.00
132.00 132.00
220.00 220.00

385.00 385.00
140.00 140.00
155.00 155.00
240.00 240.00
30.00 30.00
20.00 20.00

4000.00 4000.00
2000.00 2000.00
4500.00 4500.00
140.00 140.00
2000.00 2000.00
28.00 28.00
30.00 30.00

880.00 880.00
1250.00 1250.00
1540.00 1540.00
1870.00 1870.00

770.00 770.00
950.00 950.00
660.00 660.00
660.00 660.00
660.00 660.00
440.00 440.00
440.00 440.00
495.00 495.00
660.00 660.00
660.00 660.00
1320.00 1320.00
1100.00 1100.00
1320.00 1320.00
1320.00 1320.00
1200.00 1200.00
1200.00 1200.00
1300.00 1300.00

75.00 75.00
150.00 150.00
3.00 3.00
175.00 175.00
0.50 0.50
1.00 1.00
12.00 12.00
350.00 350.00

55.00 55.00

7.00 7.00
11.00 11.00
8.00 8.00
5.00 5.00
2.00 2.00

2.00 2.00
50.00 50.00
400.00 400.00
3.00 3.00
25.00 25.00
150.00 150.00
30.00 30.00

30.00 30.00

20.00 20.00
12.00 12.00
5.00 5.00
3.00 3.00
6.00 6.00
2.00 2.00
70.00 70.00
120.00 120.00
4 4.00
450 450
410 410
1550 1550
1450 1450
485 485

65 65
17 17
8 8
9 9
11 11
90 90
50 50
17 17
60 60
30 30

Roller 1102.5
Grder 1649.34
kerosene 100
diesel 100
petrol 113
sparayer 1821.75
jute 76

Fuel
cosumtion Fuel
charge cosumtion
Hire Rate Amount charge ltr
1270.00 hr. 800.00 470.00 4.70 100.00
1670.00 hr. 1200.00 470.00 4.70 100.00
1050.00 hr. 450 600.00 6 100.00
2800.00 hr. 1800 1000.00 10 100.00
0.00 lt 100.00 0.00 100.00
1405.00 hr. 550 855.00 8.55 100.00
2500.00 hr. 1500 1000.00 10 100.00
2020.00 hr. 1600 420.00 4.2 100.00
900.00 800 100.00 1 100.00
880.00 hr. 180.00 700.00 7.00 100.00
1800.00 hr. 1300.00 500.00 5.00 100.00
589.00 hr. 250.00 339.00 3.00 113.00
1388.00 hr. 500.00 888.00 8.88 100.00
2150.00 hr. 1400.00 750.00 7.50 100.00
0.00 kg
Analysis of Rates for Road Works ( F.Y. 2076/077 )
Item No 1 SITE CLEARANCE
A ) Description : Site clearance- Clearing and grubbing including the cutting of trees ( only if necessary ) having girth of less than 30 cm when measured at 1 m above the ground.
Unit : 1 sq m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Norms Rate (Nrs) Amount Amount Rate Amount
Specifications n. Category Unit Qty. (Nrs) Type Unit Qty. Rate (Nrs) (Nrs) Type Unit Qty. (Nrs) (Nrs) Remarks
1-1.5(a) 1
1-1.5(b) Unskilled person-day 0.04 750.00 30.00
1-1.6

Total Labour Component ( A ) 30.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 30.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 4.50
Total Cost: Nrs. 34.50
Rate : Nrs. 34.50 Per Sq.m.

B) Description : Surface dressing work including filling pot hole and cutting topsoil with levelling work for service road etc
Unit : 1 sq m
Respective Dor Labour (A) Material(B) Equipment ( c )
Clause of Norms Rate (Nrs) Amount Amount Rate Amount
Specifications n. Category Unit Qty. (Nrs) Type Unit Qty. Rate (Nrs) (Nrs) Type Unit Qty. (Nrs) (Nrs) Remarks
1.7
Unskilled person-day 0.01 750.00 7.50

Total Labour Component ( A ) 7.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 7.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1.13
Total Cost: Nrs. 8.63 Rate : Nrs. 8.63 Per Sq.m.

C) Description : Stripping of top soil work for minimum depth of 150 mm including storing or reapplication within a lead up to 100 m along the lead route
Unit : 1 cu m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Norms Rate (Nrs) Amount Amount Rate Amount
Specifications n. Category Unit Qty. (Nrs) Type Unit Qty. Rate (Nrs) (Nrs) Type Unit Qty. (Nrs) (Nrs) Remarks
4
Unskilled person-day 0.80 750.00 600.00

Total Labour Component ( A ) 600.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 600.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 90.00
Total Cost: Nrs. 690.00 Rate : Nrs. 690.00 Per Cu M

1
Item No 2 EXCAVATION WORK
2.1 Excavation in road and drain
Description : Exacavation in roadways and drain including removal and satisfactory disposal of all materials of 50 m along the lead route. This includes
handling and stacking or hauling ( to sites of embankment construction) suitable cut materials and also the disposal of unsuitable cut materials in specified manner . This further
covers trimming and finishing of roadway .
A) Ordinary Soil
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount
of Specifications n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) (Nrs) Remarks
2-1.2.2 5.a
2-1.8 Unskilled person-day 0.50 750.00 375.00
2-1.9
T and P @ 3% of Labour Cost 11.25
Total Labour Component ( A ) 386.25 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 386.25
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 57.94
Total Cost: Nrs. 444.19 Rate : Nrs. 444.19 Per Cu M
(B) Hard Soil
Respective Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount
Specifications Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) (Nrs) Remarks
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Norms Rate (Nrs) Amount(Nr Rate (Nrs) Amount Rate Amount(Nrs
Specifications n. Category Unit Qty. s) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) ) Remarks
2-1.2.2 5.b
2-1.8 Unskilled person-day 0.60 750.00 450.00
2-1.9
T and P @ 3% of Labour Cost 13.50
Total Labour Component ( A ) 463.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 463.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 69.53
Total Cost: Nrs. 533.03 Rate : Nrs. 533.03 Per Cu M
Unit : 1 Cu m
C) Ordinary Rock
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount
Specifications n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
(Nrs) (Nrs) (Nrs) (Nrs)
2-1.2.2
2-1.8 5.c Unskilled person-day 2.00 750.00 1500.00
2-1.9
T and P @ 3% of Labour Cost 45.00
Total Labour Component ( A ) 1545.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 1545.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 231.75
Total Cost: Nrs. 1776.75 Rate : Nrs. 1776.75 Per Cu M

2
D) Marshy soil
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
2-1.2.2 5.f
2-1.8 Unskilled person-day 1.00 750.00 750.00
2-1.9
T and P @ 3% of Labour Cost 22.50
Total Labour Component ( A ) 772.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 772.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 115.88
Total Cost: Nrs. 888.38
Rate : Nrs. 888.38 Per Cu M

Description : Exacavation in roadways and drain including removal and satisfactory disposal of all materials of 50 m along the lead route. This includes
handling and stacking or hauling ( to sites of embankment construction) suitable cut materials and also the disposal of unsuitable cut materials in specified manner . This further
covers trimming and finishing of roadway .
Unit : 1 Cu m
E) Hard Rock ( chiselling,wedging,tempering )
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
2-1.2.2 5.f
2-1.8 Unskilled person-day 17.00 750.00 12750.00
2-1.9
T and P @ 3% of Labour Cost 382.50
Total Labour Component ( A ) 13132.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 13132.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1969.88
Total Cost: Nrs. 15102.38
Rate : Nrs. 15102.38 Per Cu M
Item No 2 (1)
Description : Exavation for other structure including cutting of slopes , shoring ,shuttering, planking, ordinary sealing and disposal of materials up to a lead of 50 m along the lead route
Unit : 1 Cu m
( A) Ordinary Soil
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
2.4 9.a
Unskilled person-day 1.00 750.00 750.00

T and P @ 3% of Labour Cost 22.50


Total Labour Component ( A ) 772.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 772.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 115.88
Total Cost: Nrs. 888.38
Rate : Nrs. 888.38 Per Cu M

3
Unit : 1 Cu m
-2.2 Hard Soil
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
2.4 9.b
Unskilled person-day 2.00 750.00 1500.00

T and P @ 3% of Labour Cost 45.00


Total Labour Component ( A ) 1545.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 1545.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 231.75
Total Cost: Nrs. 1776.75
Rate : Nrs. 1776.75 Per Cu M

( 2.3 Ordinary Rock


Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
2.4 9.c
Unskilled person-day 4.00 750.00 3000.00

T and P @ 3% of Labour Cost 90.00


Total Labour Component ( A ) 3090.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 3090.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 463.50
Total Cost: Nrs. 3553.50
Rate : Nrs. 3553.50 Per Cu M
Unit : 1 Cu m
-2.4 Hard Rock ( Blasting Prohibited )
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
2.4 9.e
Unskilled person-day 30.00 750.00 22500.00

T and P @ 3% of Labour Cost 675.00


Total Labour Component ( A ) 23175.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 23175.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 3476.25
Total Cost: Nrs. 26651.25
Rate : Nrs. 26651.25 Per Cu M

4
2.5) Special provision for preparation of rock foundation
Unit : 1 Cu m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
2.4 9.f
Unskilled person-day 0.50 750.00 375.00

T and P @ 3% of Labour Cost 11.25


Total Labour Component ( A ) 386.25 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 386.25
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 57.94
Total Cost: Nrs. 444.19
Rate : Nrs. 444.19 Per Cu. M
Item No 3 Filling Work
Description : 3.1 Construction of roadway in embankment and miscellaneous backfilling areas with approved materials obtained either from
excavation for road construction or borrowpits or other sources
excluding the excavation ( which shall be covered separately under S n No 5 ) and transporation ( which shall be covered under S N No 6 or 11 ) components
In this case, initial lead is 50 m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
10
Unskilled person-day 0.25 750.00 187.50
2.5
T and P @ 3% of Labour Cost 5.63
Total Labour Component ( A ) 193.13 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 193.13
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 28.97
Total Cost: Nrs. 222.09
Rate : Nrs. 222.09 Per Cu M

Description : 3.2 Construction of roadway in embankment and miscellaneous backfilling areas with approved materials ( Hard soil cutting for filling material )obtained either from
excavation for road construction
borrowpits or other sources
excluding the excavation ( which shall be covered separately under S n No 5 ) and transporation ( which shall be covered under S N No 6 or 11 ) components
In this case, initial lead is 50 m
Unit : 1 Cu m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
5&10
Unskilled person-day 0.25 750.00 187.50 filling
Unskilled person-day 0.60 750.00 450.00 cutting
T and P @ 3% of Labour Cost 19.13
Total Labour Component ( A ) 656.63 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 656.63
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 98.49
Total Cost: Nrs. 755.12
Rate : Nrs. 755.12 Per Cu M

5
3.3
Compaction of filling material by 8-10 tonne roller by layer to layer .( for 100 cu m )
Respective Clause of Dor Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs)
Specifications norms(old) Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
2.ka.35 Skilled person-day Roller(8-10 t) hrs 1.67 1270.00 2120.90
Unskilled person-day 0.00
Total Labour Component ( A ) 0.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 2120.90
Sub Total (A+B+C ) : Nrs. 2120.90
Rate per Cu m 21.21
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 3.18
Total Cost: Nrs. 24.39
Rate : Nrs. 24.39 per cu m
Item no 4 SUB GRADE WORK
Description: 4.1 Scarifying existing granular/bituminuous road surface for carrying out the required operation necessary to complete the work . This include handling, salvaging, stack
ing and disposing of scarified material upto a lead of 100 m along the lead route .
Unit : 1 cu m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
15
2-5.7.6 Unskilled person-day 0.20 750.00 150.00
2-5.4.3
T and P @ 3% of Labour Cost 4.50
Total Labour Component ( A ) 154.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 154.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 23.18
Total Cost: Nrs. 177.68
Rate : Nrs. 177.68 Per Cu M
4.2 SUB Grade
According to Norms of (DOR new norms no-10.04, clause-1004)
Description : 4.1 Subgrade construction with treated materials formation of as per specification.
Unit : 1 cu m
Respective Clause of Labour (A) Material(B) Equipment ( c )
Amount
Category Unit Qty. Rate (Nrs) Amount(Nrs) Type Unit Qty. Rate (Nrs) Amount (Nrs) Type Unit Qty. Rate (Nrs)
Specifications (Nrs) Remarks
Suitable materail
Skilled person-day 0.01 1030.00 10.30 soil m 3
1.100 318.60 350.46 Grader hrs 0.020 2020.00 40.40
1004 Unskilled person-day 0.10 750.00 75.00 Roller(8-10t) hrs 0.017 1270.00 21.59
Water lit 100.00 0.31 31.00
Total Labour Component ( A ) 85.30 Total Material Component ( B ) 381.46 Total Equipment Component ( C) ) 61.99
Sub Total (A+B+C ) : Nrs. 528.75
Contractor 's Miscellaneous Overhead Expenses ( 15 % ): Nrs. 79.31
Total Cost: Nrs. 608.06
Rate : Nrs. 608.06 Per Cu M

6
4.3
According to Norms of ((DOR new norms no-10.04, clause-1004)
Description : Subgrade construction without treated materials formation of as per specification.
Unit : 1 cu m
Respective Clause of Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount(Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specifications Category Unit Qty. Type Unit Qty. Type Unit Qty. s) Remarks
Skilled person-day 0.01 1030.00 10.30 Grader hrs 0.020 2020.00 40.40
1004 Unskilled person-day 0.10 750.00 75.00 Roller(8-10t) hrs 0.017 1270.00 21.59
Water lit 100.00 0.26 26.00
Total Labour Component ( A ) 85.30 Total Material Component ( B ) 26.00 Total Equipment Component ( C) ) 61.99
Sub Total (A+B+C ) : Nrs. 173.29
Contractor 's Miscellaneous Overhead Expenses ( 15 % ): Nrs. 25.99
Total Cost: Nrs. 199.28
Rate : Nrs. 199.28 Per Cu M
4.4
According to Norms of ((DOR new norms no-10.05, clause-1003)
Description : Preparation of Subgrade for rehabilitaion or other similar works ( filing or cutting depth 10cm to 20cm thick)
Unit : 1 sq m a) Common soil
Respective Clause of Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount(Nrs) Rate (Nrs) Amount(Nrs) Rate (Nrs) Amount(Nr
Specifications Category Unit Qty. Type Unit Qty. Type Unit Qty. s) Remarks
1004 Unskilled person-day 0.15 750.00 112.50 0.00
Tools & plants 3 3.38
Total Labour Component ( A ) 115.88 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 115.88
Contractor 's Miscellaneous Overhead Expenses ( 15 % ): Nrs. 17.38
Total Cost: Nrs. 133.26
Rate : Nrs. 133.26 Per Sq M
Description : Preparation of Subgrade for rehabilitaion or other similar works ( filing or cutting depth 10cm to 20cm thick)
Unit : 1 sq m b) gravel & boulder mixed soil
Respective Clause of Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount(Nrs) Rate (Nrs) Amount(Nrs) Rate (Nrs) Amount(Nr
Specifications Category Unit Qty. Type Unit Qty. Type Unit Qty. s) Remarks
1004 Unskilled person-day 0.30 750.00 225.00 0.00
Tools & plants 3 6.75
0.00
Total Labour Component ( A ) 231.75 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 231.75
Contractor 's Miscellaneous Overhead Expenses ( 15 % ): Nrs. 34.76
Total Cost: Nrs. 266.51
Rate : Nrs. 266.51 Per sq M

7
Item No 5
Description : Carrying out the construction operation of granular sub- base including full compensations for
making arrangements for traffic in accordance with clause G -12 of the Specification except for initial treatment to shoulders and construction of diversions
fumishing all materials to be incorporated in the work including all royalties, fees, rents wherever necessary and all leads along the lead route
all labour and incindentals to complete the work to the specification and
and carrying out the work in part widths of roadway where directed.
A. With naturally found deposits of sand/gravel aggregates conforming to the specification for
(a) Class II Grading ( When CBR = 25 % )
Procuring sieved river gravel aggregates having sizes of 63-80 mm, 4.75-63 mm, 75 micron- m4.75 mm
Preparation of sub- grade that was finished earlier
5.1)Local gravel For laying of aggregates including compaction and the incidentals
Unit : 1 cu m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
3,1 Skilled person-day 0.005 1030.00 5.15 local gravel Cu m 1.28 2021.14 2587.06 8-10 t roller hrs 0.09 1270.00 114.30
deisel ltr 0.79 86.00 68.11
26.A Unskilled person-day 0.04 750.00 30.00 Transportation DOR 12.02
Total Labour Component ( A ) 35.15 Total Material Component ( B ) 2655.18 Total Equipment Component ( C) ) 114.30
Sub Total (A+B+C ) : Nrs. 2804.63
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 420.69
Total Cost: Nrs. 3225.32
Rate : Nrs. 3225.32 Per Cu M

Unit : 1 cu m
5.2)Gravel from Tikabhairav, Bhakunde Equv.Quarry site

Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )


Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
Tikabhairav,
Bhakunde
Equv.Quarry site
gravel screening
3,1 Skilled person-day 0.01 1030.00 5.15 63mm down size Cu M 1.28 2542.32 3254.17 8-10 t roller hrs 0.09 1270.00 114.30
diesel ltr 0.79 86.00 68.11
26.A Unskilled person-day 0.04 750.00 30.00 Transportation
Total Labour Component ( A ) 35.15 Total Material Component ( B ) 3322.28 Total Equipment Component ( C) ) 114.30
Sub Total (A+B+C ) : Nrs. 3471.73
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 520.76
Total Cost: Nrs. 3992.49
Rate : Nrs. 3992.49 Per Cu M

8
(5.3) Class II Grading ( When CBR = 25 % ) without compaction .
Procuring sieved river gravel aggregates having sizes of 63-80 mm, 4.75-63 mm, 75 micron- m4.75 mm
Preparation of sub- grade that was finished earlier
a)Local gravel For laying of aggregates including compaction and the incidentals
Unit : 1 cu m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
3,1 Skilled person-day 0.005 1030.00 5.15 gravel Cu M 1.28 2021.14 2587.06
26.A Unskilled person-day 0.04 750.00 30.00 Transportation 0.00
Total Labour Component ( A ) 35.15 Total Material Component ( B ) 2587.06 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 2622.21
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 393.33
Total Cost: Nrs. 3015.55

Description : carrying out the construction operation of water bound macadam ( WBM ), sub- base/base course including full compensation for
making arrangements for traffic in accordance with clause G 12 of the specification except for initial treatment to shoulders and construction of diversions
fumishing all materials to be incorporated in the work including all royalties, fees, rents wherever necessary and all leads along the lead route
all labour and incindentals to complete the work to the specification and
and carrying out the work in part widths of roadway where directed Collection of rubble for aggregates
Grading No I ( Restricted to use for sub-base only ) Laying of sub-base For sub -base
Breaking stones for aggregates sizes -10-20, 20-40mm, 40-63mm,80-100mm Incidentals
Unit : 1 Cu m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
27 Skilled person-day 0.01 1030.00 5.15 Mix soling Cu M 1.27 2577.88 3273.90 8-10 t roller hrs 0.09 1270.00
dor 12.13
3,2 Unskilled person-day 0.04 750.00 30.00 Transportation 0.00
Total Labour Component ( A ) 35.15 Total Material Component ( B ) 3273.90 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 3309.05
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 496.36
Total Cost: Nrs. 3805.41
Rate : Nrs. 3805.41 Per Cu M

9
Grading No I I For base
Breaking stones for aggregates sizes -10-20, 20-40mm, 40-50mm,50-63mm,63-80mm
For screening - 150microm down,150 microm, 4.75 mm ,4.75mm-10mm, 10-12.5mm
Collection of rubble for aggregates
Laying of base
Incidentals
Unit : 1 Cu m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
27 Skilled person-day 0.25 1030.00 257.50 Mix soling Cu M 1.3 2577.88 3351.24 8-10 t roller hrs 0.09 1270.00 114.30

3,2 Unskilled person-day 2.00 750.00 1500.00 Transportation 0.00


Total Labour Component ( A ) 1757.50 Total Material Component ( B ) 3351.24 Total Equipment Component ( C) ) 114.30
Sub Total (A+B+C ) : Nrs. 5223.04
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 783.46
Total Cost: Nrs. 6006.50

Rate : Nrs. 6006.50 Per Cu M

Item No 8
Description : Preparation base for bituminuous macadam by carrying out the preparatory work of scarifying and relaying the aggregate base course including full compensation for
making arrangements for traffic in accordance with clause G 12 of the specification except for initial treatment to shoulders and construction of diversions
Preparation of base including filling of potholes except for levelling course
providing all materials to be incorporated in the work including all royalties fees, rents where necessary and all leads along the lead route
all labour and incindentals to complete the work to the specification and
This item is same as S No 8 but with due deduction for the procurement of quantity received from the scarifying of receiving surface
Item No 11
Description Cleaning top surface by brush and broom before pitching
of Item

Unit : 10 sq m
.a) On water Bound Macadam
Respective Clause of Labour (A) Material(B) Equipment ( c )
Dor norms
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nrs)
(old)
Specifications Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
15.16.1 Skilled person-day 1030.00 brush, kuchho L.S 55.00 55.00
Unskilled person-day 0.25 750.00 187.50
Total Labour Component ( A ) 187.50 Total Material Component ( B ) 55.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 242.50
Nrs. 24.25 Per sqm
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 3.64
Total Cost: Nrs. 27.89
Rate : Nrs. 27.89 Persqm

10
On Other Surface
Respective Clause Dor Labour (A) Material(B) Equipment ( c )
norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications (old) Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
15.16.2 Skilled person-day brush, kuchho L.s 55.00 55.00
Unskilled person-day 0.20 750.00 150.00
Total Labour Component ( A ) 150.00 Total Material Component ( B ) 55.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 205.00
Nrs. 20.50 Per sqm
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 3.08
Total Cost: Nrs. 23.58
Rate : Nrs. 23.58 Per10sqm

Description of Item
Semi-grouting works including compaction ( Ref norms of Dor Item no 15-21(a) in Open oven
( 5 cm thickness )
Unit 10 sq M
Respective Clause Dor Labour (A) Material(B) Equipment ( c )
norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications (old) Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
15.21 Skilled person-day Bitumen kg 35.00 78.10 2733.50
Roller
Unskilled person-day 1.20 750.00 900.00 kerosine lit 0.25 100.00 25.00 machine hrs 0.07 1270.00 88.90
Fire wood ( in
open oven) kg 48.00 18.00 864.00 Sprayer hrs 0.07 1800.00 126.00
Aggregate 38-
40mm Cu M 0.60 0.00
Aggregate 12mm
Cu M 0.15 0.00 0.00 dor
13.06/01
Total Labour Component ( A ) 900.00 Sub Total 3622.50 Total Equipment Component ( C) ) 214.90
Transportation 0.00
Total Material Component ( B ) 3622.50
Sub Total (A+B+C ) : Nrs. 4737.40
Nrs. 473.74 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 710.61
Total Cost: Nrs. 5448.01
Rate : Nrs. 544.80 per sq m

11
Description : Carrying out the required operation for the application of tack coat including full compensation for
making arrangements for traffic in accordance with clause G 12 of the specification except for initial treatment to shoulders and construction of diversions
providing all materials to be incorporated in the work including all royalties fees, rents where necessary and all leads along the lead route
all labour and incindentals to complete the work to the specification and
Carrying out the work in part widths of roadway where directed
Unit : 10 10 sq m
a) When the application is upon existing bituminuous treated surface
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
4,2 30.a Skilled person-day Bitumen kg 5.00 78.10 390.50
Unskilled person-day 0.15 750.00 112.50 Fire wood kg 8.00 18.00 144.00 Sprayer hrs 0.04 1800 72.00
kerosine lit 0.50 100.00 50.00
Sub Total 584.50
Transportation
Total Labour Component ( A ) 112.50 Total Material Component ( B ) 584.50 Total Equipment Component ( C) ) 72.00
Sub Total (A+B+C ) : Nrs. 769.00
Rate : Nrs. 76.90 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 11.54
Total Cost: Nrs. 88.44
Rate : Nrs. 88.44 per sq m

Tack Coat
b) When the application is upon existing WBM
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit. Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
4,2 30.b Skilled person-day Bitumen kg 10.00 78.10 781.00
Unskilled person-day 0.20 750.00 150.00 Fire wood kg 16.00 18.00 288.00 Sprayer hrs 0.04 1800.00 72.00
kerosine lit 0.50 100.00 50.00
Sub Total 1119.00
Transportation 0.00
Total Labour Component ( A ) 150.00 Total Material Component ( B ) 1119.00 Total Equipment Component ( C) ) 72.00
Sub Total (A+B+C ) : Nrs. 1341.00
Rate : Nrs. 134.10 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 20.12
Total Cost: Nrs. 154.22 per sq m

12
Description : Carrying out the required operation for the application of prime coat supplying of all necessary material.
Unit : 10 10 sq m
a) When the application is upon existing bituminuous treated surface
Respective Clause Dor Labour (A) Material(B) Equipment ( c )
norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications (old) Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
4,2 15.18.1 Skilled person-day Bitumen kg 4.90 78.10 382.69
Fire wood in
Unskilled person-day 0.20 750.00 150.00 open oven kg 8.00 18.00 0.00 Sprayer hrs 0.04 1800.00 72.00
Kerosine lit 0.50 100.00 50.00
Sub Total 432.69
Transportation 0.00
Total Labour Component ( A ) 150.00 Total Material Component ( B ) 432.69 Total Equipment Component ( C) ) 72.00
Sub Total (A+B+C ) : Nrs. 654.69
Rate : Nrs. 65.47 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 9.82
Total Cost: Nrs. 75.29
Rate : Nrs. 75.29 per sq m

Item No
According to Norms of DoR 18 (B)
Description :
Unit : 10
Description : Carrying out the required operation for the application of prime coat supplying of all necessary material.
b)When the application is upon base course.
Respective Clause Dor Labour (A) Material(B) Equipment ( c )
norms Rate (Nrs) Amount Rate (Nrs) Amount(Nrs Rate Amount(Nrs)
of Specifications (old) Category Unit Qty. (Nrs) Type Unit Qty. ) Type Unit Qty. (Nrs) Remarks
4,2 15.18.2 Skilled person-day Bitumen kg 9.75 78.10 761.48
Fire wood in Sprayer
Unskilled person-day 0.20 750.00 150.00 open oven kg 16.00 18.00 0.00 hrs 0.04 1800 72.00
Kerosine lit 0.50 100.00 50.00
Sub total 811.48
Transportation 0.00
Total Labour Component ( A ) 150.00 Total Material Component ( B ) 811.48 Total Equipment Component ( C) ) 72.00
Sub Total (A+B+C ) : Nrs. 1033.48
Rate : Nrs. 103.35 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 15.50
Total Cost: Nrs. 118.85
Rate : Nrs. 118.85 per sq m

13
Item No
Description : Premix carpeting work including compactions
making arrangements for traffic in accordance with clause G 12 of the specification except for initial treatment to shoulders and construction of diversions
providing all materials to be incorporated in the work including all royalties fees, rents where necessary and all leads along the lead route
Unit : 1 cu m In norms unit is in sq.m. Now calculate is in cu.m. there for (10m2 *.02m thick =.2 m3 then 1m3/.20 m3 =5 times)
Respective Clause
Labour (A) Material(B) Equipment ( c )
Dor
norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
(old)
of Specifications Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks

8-10 t
4,2 15.24.khaSkilled person-day 0.45 1030.00 463.50 Bitumen kg 77.00 78.10 6013.70 roller hrs 0.50 1270 635.00
Sprayer

Fire wood in open


Unskilled person-day 4.50 750.00 3375.00 oven kg 120.00 18.00 0.00 hrs 0.50 1800 900.00

Due to m3
unit
multiply
by above
Agg( 6 -12 mm ) cu m 1.20 3213.21 3855.85 5 times
kerosene.
lit 7.70 100.00 770.00

Sub Total 10639.55 Half of


Transportation 0.00 According
to
15.24.ka
Agg.qty
multiply
Total Labour Component ( A ) 3838.50 Total Material Component ( B ) 10639.55 Total Equipment Component ( C) 1535.0 by 5 times
Sub Total (A+B+C ) : Nrs. 16013.05
Rate : Nrs. 16013.05 per cu m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 2401.96
Total Cost: Nrs. 18415.01

Rate : Nrs. 18415.01 per cu m

14
Item No
Description : Sand seal including compaction .
Unit : 10 10 sq m
Respective Clause Dor Labour (A) Material(B) Equipment ( c )
norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications (old) Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
8-10 t
15.23 Skilled person-day Bitumen kg 9.60 78.10 749.76 roller hrs 0.04 1270.00 50.80
Unskilled person-day 0.45 750.00 337.50 Fire wood kg 16.00 18.00 0.00 Sprayer hrs 0.04 1800.00 72.00
( in open oven )
coarse sand cu m 0.07 3213.21 224.92
Sub Total 974.68
Transportation 0.00
Total Labour Component ( A ) 337.50 Total Material Component ( B ) 974.68 Total Equipment Component ( C) ) 122.80
Sub Total (A+B+C ) : Nrs. 1434.98
Rate : Nrs. 143.50 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 21.52
Total Cost: Nrs. 165.02
Rate : Nrs. 165.02 per sq m

Item No 6
Description : Brick masonry with all necessary operations including full compensations for all labour , materials , scaffolding, and other incidentals required to complete the work
as per the specifications and as shown on the drawings. It includes full compensation for using specially moulded bricks on the face of walls with better provision
of weep holes jointed with cement sand mortar.
Unit : 1cu m
6.1 in 1:4 mix ratio
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
Brick
7 37.A.b Skilled person-day 1.50 1030.00 1545.00 (224*108*57mm) No 530.00 14.47 7669.10
Unskilled person-day 4.99 750.00 3742.50 Cement OPC bag 2.00 825.00 1650.00
Sand cu m 0.35 3213.21 1124.62
Sub Total 10443.72
Transportation 0.00
Total Labour Component ( A ) 5287.50 Total Material Component ( B ) 10443.72 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 15731.22
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 2359.68
Total Cost: Nrs. 18090.91
Rate : Nrs. 18090.91 per cu m

15
6.2 in 1:6mix ratio
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
Brick
7 37.A.c Skilled person-day 1.50 1030.00 1545.00 (224*108*57mm) No 530.00 14.47 7669.10
Unskilled person-day 5.02 750.00 3765.00 Cement bag 1.40 825.00 1155.00
Sand cu m 0.38 3213.21 1221.02
Sub Total 10045.12
Transportation 0.00
Total Labour Component ( A ) 5310.00 Total Material Component ( B ) 10045.12 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 15355.12
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 2303.27
Total Cost: Nrs. 17658.39
Rate : Nrs. 17658.39 per cu m

Item no 7 7
Description 12.5 mm th. Plastering with cement sand mortar on brick walls or concrete surfaces with all necessary operations including full compensation for all labours, materials
scaffolding and other incidentals required to complete the work as per the specifications
Unit 100 sq m

7.1 in 1:4mix ratio


Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amoun Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. t(Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
7-9.4 37.B.c Skilled person-day 15.00 1030.00 15450.00 Cement Bag 7.26 825.00 5989.50
,7-12 Unskilled person-day 13.59 750.00 10192.50 Sand cu m 1.46 3213.21 4691.29
Bamboo nos 2.00 220.00 440.00
Rope ls 100.00 15 mutha
7-13.2 Sub Total 11220.79
Transportation 0.00
Total Labour Component ( A ) 25642.50 Total Material Component ( B ) 11220.79 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 36863.29
Rate : Nrs. 368.63 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 55.29
Total Cost: Nrs. 423.93
Rate : Nrs. 423.93 per sq m

16
Description 12.5 mm th. Plastering with cement sand mortar on brick walls or concrete surfaces with all necessary operations including full compensation for all labours, materials
scaffolding and other incidentals required to complete the work as per the specifications
Unit 100 sq m
7.2 in 1:6mix ratio
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
7-9.4 37.B.d Skilled person-day 15.00 1030.00 15450.00 Cement Bag 5.76 825.00 4752.00
,7-12 Unskilled person-day 13.70 750.00 10275.00 Sand cu m 1.58 3213.21 5076.87
Bamboo nos 2.00 220.00 440.00
Rope 100.00
7-13.2 Sub Total 10368.87
Transportation 0.00
Total Labour Component ( A ) 25725.00 Total Material Component ( B ) 10368.87 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 36093.87
Rate : Nrs. 360.94 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 54.14
Total Cost: Nrs. 415.08
Rate : Nrs. 415.08 per sq m

Item no 8
Description Pointing work with cement sand mortar on brick wall with all required operations including full compensation for all labours, materials and other incidentals necessary
to complete the work as per the specifications
Unit 100 sq m
22.a) in 1:3mix ratio
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. (Nrs) Type Unit Qty. Remarks
7-9.3 37.C.c Skilled person-day 8.00 1030.00 8240.00 Cement Bag 1.92 825.00 1584.00
7-12 Unskilled person-day 8.88 750.00 6660.00 Sand cu m 0.29 3213.21 931.83
Bamboo nos 2.00 220.00 440.00
Rope Ls 100.00
and 7-13.3 Sub Total 3055.83
Transportation 0.00
Total Labour Component ( A ) 14900.00 Total Material Component ( B ) 3055.83 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 17955.83
Rate : Nrs. 179.56 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 26.93
Total Cost: Nrs. 206.49

Rate : Nrs. 206.49 per sq m

17
Item no 9
Description Dry brick laying
Unit 10 sq m
9.1 Flat
Respective Clause Dor Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
11.15.ka Skilled person-day 0.50 1030.00 515.00 Brick Nos 420.00 14.47 6077.40
Unskilled person-day 1.00 750.00 750.00 Sand cu m 0.71 3213.21 2281.38
Sub Total 8358.78
Transportation 0.00
Total Labour Component ( A ) 1265.00 Total Material Component ( B ) 8358.78 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 9623.78
Rate : Nrs. 962.38 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 144.36
Total Cost: Nrs. 1106.73
Rate : Nrs. 1106.73 per sq m

Description Dry brick laying


Unit 10 sq m
9.2 edge
Respective Clause Dor Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
11.15.
kha Skilled person-day 1.00 1030.00 1030.00 Brick Nos 750.00 14.47 10852.50
Unskilled person-day 3.25 750.00 2437.50 Sand cu m 0.71 3213.21 2281.38
Sub Total 13133.88
Transportation 0.00
Total Labour Component ( A ) 3467.50 Total Material Component ( B ) 13133.88 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 16601.38
Rate : Nrs. 1660.14 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 249.02
Total Cost: Nrs. 1909.16
Rate : Nrs. 1909.16 per sq m

18
Item no
Description Dry Stone laying work
Unit 9.3 1 cu.m.
Respective Clause of Dor Labour (A) Material(B) Equipment ( c )
norms n. Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount Rate (Nrs) Amount(Nrs)
Specifications (old) Category Unit Qty. Type Unit Qty. (Nrs) Type Unit Qty. Remarks
11.16 Skilled person-day 1.00 1030.00 1030.00 stone m3 1.10 2577.88 2835.66
Unskilled person-day 3.50 750.00 2625.00 Sand cu m 0.71 3213.21 2281.38
Sub Total 5117.04
Transportation 0.00
Total Labour Component ( A ) 3655.00 Total Material Component ( B ) 5117.04 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 8772.04
Rate : Nrs. 877.20 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 131.58
Total Cost: Nrs. 1008.78
Rate : Nrs. 1008.78 per sq m
Item no
Description Filling by stones in the foundation and levelling including haulage distance up to 30 m
Unit 9.4 1 Cu M
Respective Clause of Dor Labour (A) Material(B) Equipment ( c )
norms n. Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount Rate (Nrs) Amount(Nrs)
Specifications (old) Category Unit Qty. Type Unit Qty. (Nrs) Type Unit Qty. Remarks
6.5 Skilled person-day Stone cu m 1.20 2577.88 3093.45
Unskilled person-day 1.50 750.00 1125.00
Transportation 0.00
Total Labour Component ( A ) 1125.00 Total Material Component ( B ) 3093.45 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 4218.45
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 632.77
Total Cost: Nrs. 4851.22
Rate : Nrs. 4851.22 per cu m

Item no 10
Description Stone Masonry work including full compensation for all labour, materials and other incidentals require to complete the work as per the Specifications and drawings.
It includes full compensation for using specially dressed stones on the face of walls with batter and makes provision for weep holes as necessary
A Un-coursed Rubble Masonry
Unit 1 Cu M
a ) In dry
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. (Nrs) Type Unit Qty. Remarks
38.A.a Skilled person-day 0.50 1030.00 515.00 Stone cu m 1.10 2577.88 2835.66
Unskilled person-day 1.50 750.00 1125.00 Transportation 0.00
Total Labour Component ( A ) 1640.00 Total Material Component ( B ) 2835.66 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 4475.66
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 671.35
Total Cost: Nrs. 5147.01
Rate : Nrs. 5147.01 per cu m

19
A Un-coursed Rubble Masonry
Unit 1 Cu M
10.2) In 1:4 c/s mortar
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. (Nrs) Type Unit Qty. Remarks
8 38.A.c Skilled person-day 1.50 1030.00 1545.00 Rubble cu m 1.10 2577.88 2835.66
Unskilled person-day 3.24 750.00 2430.00 Sand cu m 0.47 3213.21 1510.21
Cement bag 2.32 825.00 1914.00
Sub Total 6259.87
Transportation 0.00
Total Labour Component ( A ) 3975.00 Total Material Component ( B ) 6259.87 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 10234.87
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1535.23
Total Cost: Nrs. 11770.10
Rate : Nrs. 11770.10 per cu m
A Un-coursed Rubble Masonry
Unit 1 Cu M
10.3 In 1:6 c/s mortar
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. (Nrs) Type Unit Qty. Remarks
8 38.A.d Skilled person-day 1.50 1030.00 1545.00 Rubble cu m 1.10 2577.88 2835.66
Unskilled person-day 3.29 750.00 2467.50 Sand cu m 0.50 3213.21 1606.61
Cement bag 1.84 825.00 1518.00
Sub Total 5960.27
Transportation 0.00
Total Labour Component ( A ) 4012.50 Total Material Component ( B ) 5960.27 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 9972.77
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1495.92
Total Cost: Nrs. 11468.68
Rate : Nrs. 11468.68 per cu m

20
Unit 11
Description 11.1 In Form work Providing ,preparing , and installing , of form work including necessary support and removing, after completion Foundation & footing work
Unit using mix wooden or soft wood 10 SqM Using DOR norms
Respective Clause of Dor Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. (Nrs) Type Unit Qty. Remarks
Timber planks/ Using
1804 18.01 Skilled person-day 1.50 1030.00 1545.00 board =0.42/8 cu m 0.0525 50905.25 2672.53 timber
Unskilled person-day 2.00 750.00 1500.00 Nails kg 1.00 112.00 112.00 plank 8
strut,batten etc times &
strut ,bttern
=0.18/12 cu m 0.0150 50905.25 763.58 12 times
Sub Total 3548.10 usage

Transportation 0.00
Total Labour Component ( A ) 3045.00 Total Material Component ( B ) 3548.10 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 6593.10
Rate : Nrs. 659.31 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 98.90
Total Cost: Nrs. 758.21
Rate : Nrs. 758.21 per sq m

Item no
Description 11.2 In Form work Providing ,preparing , and installing , of form work including necessary support and removing, after completion wall work
using plywood & mix wooden or soft wood
False work is not inlcuded
Unit 10 SqM Using DOR norms
Respective Clause of Dor Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. (Nrs) Type Unit Qty. Remarks
Water Proof Using ply
Plywood 9mm wood 8
times &
1804 18.02.01 Skilled person-day 2.20 1030.00 2266.00 thick =11/8 sq m 1.3750 1495.64 2056.51
strut ,bttern
Unskilled person-day 2.20 750.00 1650.00 Nails kg 2.50 112.00 280.00 12 times
strut,batten etc usage
=0.4/12 cu m 0.0333 50905.25 1696.84
Sub Total 4033.35
Transportation 0.00
Total Labour Component ( A ) 3916.00 Total Material Component ( B ) 4033.35 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 7949.35
Rate : Nrs. 794.93 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 119.24
Total Cost: Nrs. 914.17
Rate : Nrs. 914.17 per sq m

21
Item no
Description 11.3 In Form work Providing ,preparing , and installing , of form work including necessary support and removing, after completion Lintel , Beam & slab structure work
using mix wooden or soft wood False work is not inlcuded
Unit 10 SqM Using DOR norms
Respective Clause of Dor Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. (Nrs) Type Unit Qty. Remarks
Timber planks/ Using
board 19mm thick timber
plank 6
1804 18.05 Skilled person-day 1.80 1030.00 1854.00 =0.54/6 cu m 0.0900 50905.25 4581.47
times
Unskilled person-day 2.50 750.00 1875.00 Nails kg 2.50 112.00 280.00 times
Sub Total 4861.47 usage
Transportation 0.00
Total Labour Component ( A ) 3729.00 Total Material Component ( B ) 4861.47 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 8590.47
Rate : Nrs. 859.05 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 128.86
Total Cost: Nrs. 987.90
Rate : Nrs. 987.90 per sq m
Item no 12
Description 12.1 Reinforcement for RCC work. It includes procuring steel, its bending , placing, binding and fixing in position as shown on the drawings and as directed by the Engineer
It also includes for keeping reinforcement in approved position and joining as per approved method with due allowances for wastage, overlaps , spacer bars and
annealed steel wire for binding. This applies for general bending r equirements. When the above provisions is not adequate or in order words. Specific type of
the following norms are applicable.
Unit 1 metric tonne 94540
.a)Type ( A ) for Crank type along bar ( tor steel )
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. (Nrs) Type Unit Qty. Remarks
10 40.A Skilled person-day 7.00 1030.00 7210.00 Tor Steel Mt 1.05 79000.00 82950.00
Unskilled person-day 7.00 750.00 5250.00 Binding wire kg 10.00 92.00 920.00
Sub Total 83870.00
Transportation 0.00
Total Labour Component ( A ) 12460.00 Total Material Component ( B ) 83870.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 96330.00
Rate : Nrs. 96.33 per kg
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 14449.50
Total Cost: Nrs. 110779.50
Rate : Nrs. 110.78 per kg

22
Unit 12.2 1 metric tonne
b)Type ( B ) for Plain straight bar ( tor steel ) for Common use
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. (Nrs) Type Unit Qty. Remarks
10 40.B Skilled person-day 3.50 1030.00 3605.00 Tor Steel Mt 1.05 79000.00 82950.00
Unskilled person-day 3.50 750.00 2625.00 Binding wire kg 10.00 92.00 920.00
Sub Total 83870.00
Transportation 0.00
Total Labour Component ( A ) 6230.00 Total Material Component ( B ) 83870.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 90100.00
Rate : Nrs. 90.10 per kg
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 13515.00
Total Cost: Nrs. 103615.00
Rate : Nrs. 103.62 per kg
Unit 12.3 1 metric tonne
c)Type ( C) for C type hook bar ( tor steel )
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. (Nrs) Type Unit Qty. Remarks
10 40.C Skilled person-day 5.25 1030.00 5407.50 Tor Steel MT 1.05 79000.00 82950.00
Unskilled person-day 5.25 750.00 3937.50 Binding wire kg 10.00 92.00 920.00
Sub Total 83870.00
Transportation 0.00
Total Labour Component ( A ) 9345.00 Total Material Component ( B ) 83870.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 93215.00
Rate : Nrs. 93.22 per kg
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 13982.25
Total Cost: Nrs. 107197.25
Rate : Nrs. 107.20 per kg

Unit 12.4 1 metric tonne


.d)Type ( D) for stirups ( tor steel )
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
10 40.D Skilled person-day 14.00 1030.00 14420.00 Tor Steel MT 1.05 79000.00 82950.00
Unskilled person-day 14.00 750.00 10500.00 Binding wire kg 10.00 92.00 920.00
Sub Total 83870.00
Transportation 0.00
Total Labour Component ( A ) 24920.00 Total Material Component ( B ) 83870.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 108790.00
Rate : Nrs. 108.79 per kg
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 16318.50
Total Cost: Nrs. 125108.50

Rate : Nrs. 125.11 per kg

23
Item no 13
Description Cement concrete work . It includes all labour and material required for mixing placing in position, vibrating , compacting , finishing , curing and all
incidentals required to product concrete of specified strength as per the specifications.
Unit 1 Cu M
13.1 Work in foundation
a ) M 10 grade ( 1 : 3 : 6 ) mix by volume

Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )


Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
11 41.A.a Skilled person-day 0.75 1030.00 772.50 Cement bag 4.40 825.00 3630.00
aggregates ( 20 -
Unskilled person-day 3.50 750.00 2625.00 40 mm ) Cu m 0.89 3344.95 2977.01
Sand Cu m 0.47 3213.21 1510.21
water lit 150.00 0.26 39.00
Sub Total 8156.21
Transportation 0.00
Total Labour Component ( A ) 3397.50 Total Material Component ( B ) 8156.21 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 11553.71
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1733.06
Total Cost: Nrs. 13286.77
Rate : Nrs. 13286.77 per cu m

cement concrete work. 13.2 ( A ) Work in foundation


b) M 15grade ( 1 : 2 : 4) mix by volume
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
11 41.A.b Skilled person-day 0.75 1030.00 772.50 Cement( nepali) bag 6.40 825.00 5280.00
aggregates ( 10 -
Unskilled person-day 3.56 750.00 2670.00 40 mm ) Cu m 0.85 3344.95 2843.21
Sand Cu m 0.44 3213.21 1413.81
water lit 205.00 0.26 53.30
Sub Total 9590.32
Transportation 0.00
Total Labour Component ( A ) 3442.50 Total Material Component ( B ) 9590.32 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 13032.82
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1954.92
Total Cost: Nrs. 14987.74
Rate : Nrs. 14987.74 per cu m

24
Work Superstructure component ( beam, slab, abutment, caps etc,, )
a) M 15grade ( 1 : 2 : 4) mix by volume

Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )


Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
11 41.B.a Skilled person-day 0.75 1030.00 772.50 Cement( nepali) bag 6.40 825.00 5280.00
aggregates ( 10 -
Unskilled person-day 4.56 750.00 3420.00 20 mm ) Cu m 0.85 3344.95 2843.21
Sand Cu m 0.44 3213.21 1413.81
water ltr 205.00 0.26 53.30
Sub Total 9590.32
Transportation 0.00
Total Labour Component ( A ) 4192.50 Total Material Component ( B ) 9590.32 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 13782.82
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 2067.42
Total Cost: Nrs. 15850.24
Rate : Nrs. 15850.24 per cu m

( b) Work Superstructure component ( beam, slab, abutment, caps etc,, )


) M 20grade ( 1 : 1.5 : 3) mix by volume

Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )


Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
Cement (Hetuada
11 41.B.b Skilled person-day 0.75 1030.00 772.50 etc) bag 8.00 825.00 6600.00
aggregates ( 10 -
Unskilled person-day 4.62 750.00 3465.00 20 mm ) Cu m 0.86 3344.95 2876.66
Sand Cu m 0.42 3213.21 1349.55
water ltr 240.00 0.26 62.40
Sub Total 10888.61
Transportation 0.00
Total Labour Component ( A ) 4237.50 Total Material Component ( B ) 10888.61 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 15126.11
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 2268.92
Total Cost: Nrs. 17395.02
Rate : Nrs. 17395.02 per cu m

25
Item no 14
Description Fabrication of gabion boxes / mattress with diapharagms including , cutting , rolling, weaving .( For Heavy class wire)
( Diapharagm is to be provided to every 1 m length. )
Unit 1 Box
Hexogonal mesh size 100*120
Mesh wire 10 Swg, Selvedge wire 8 Swg ( Heavy class wire)
( 14.1 ) Box size 2m*1m*1m
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
44.1.B.ii. For Heavy
17-1.4 Skilled person-day 0.39 1030.00 401.70 Mesh wire kg 23.43 105.00 2460.15 class wire
a
17-5 Unskilled person-day 0.20 750.00 150.00 Selvedge wire kg 2.88 105.00 302.40
Sub Total 2762.55
and 17-6 Transportation 0.00
Total Labour Component ( A ) 551.70 Total Material Component ( B ) 2762.55 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 3314.25
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 497.14
Total Cost: Nrs. 3811.39
Rate : Nrs. 3811.39 per box Rate : Nrs. 1905.69 per cu.m.
( b ) mesh wire 10Swg, selvedge wire 8 Swg
( 14.2 ) Box size 3m*1m*1m
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks

44.1.B.ii.
b For Heavy
17-1.4 Skilled person-day 0.57 1030.00 587.10 Mesh wire kg 34.08 105.00 3578.40 class wire
17-5and 17-6 Unskilled person-day 0.28 750.00 210.00 Selvedge wire kg 4.03 105.00 423.15
Sub Total 4001.55
Transportation 0.00
Total Labour Component ( A ) 797.10 Total Material Component ( B ) 4001.55 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 4798.65
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 719.80
Total Cost: Nrs. 5518.45
Rate : Nrs. 5518.45 per box Rate : Nrs. 1839.48 per cu.m.

26
( b ) mesh wire 10Swg, selvedge wire 8 Swg
(14.3 ) Box size 2m*1m*0.5m
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
44.1.B.ii.
17-1.4 c Skilled person-day 0.27 1030.00 278.10 Mesh wire kg 15.97 105.00 1676.85
For Heavy
17-5 Unskilled person-day 0.13 750.00 97.50 Selvedge wire kg 2.45 105.00 257.25 class wire
Sub Total 1934.10
and 17-6 Transportation 0.00
Total Labour Component ( A ) 375.60 Total Material Component ( B ) 1934.10 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 2309.70
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 346.46
Total Cost: Nrs. 2656.16
Rate : Nrs. 2656.16 per box Rate : Nrs. 2656.16 per cu.m.
( b ) mesh wire 10Swg, selvedge wire 8 Swg
( 14..4 ) Box size 3m*1m*0.5m
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
44.1.B.ii.
17-1.4 d Skilled person-day 0.39 1030.00 401.70 Mesh wire kg 23.43 105.00 2460.15
17-5 Unskilled person-day 0.20 750.00 150.00 Selvedge wire kg 3.46 105.00 363.30 For Heavy
Sub Total 2823.45 class wire
and 17-6 Transportation 0.00
Total Labour Component ( A ) 551.70 Total Material Component ( B ) 2823.45 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 3375.15
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 506.27
Total Cost: Nrs. 3881.42
Rate : Nrs. 3881.42 per box Rate : Nrs. 2587.62 per cu.m.
( b ) mesh wire 10Swg, selvedge wire 8 Swg
( 14.5 ) Box size 2m*1m*0.3m
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
44.1.B.ii. For Heavy
17-1.4 e Skilled person-day 0.22 1030.00 226.60 Mesh wire kg 13.00 105.00 1365.00 class wire
17-5 Unskilled person-day 0.11 750.00 82.50 Selvedge wire kg 2.28 105.00 239.40
Sub Total 1604.40
and 17-6 Transportation 0.00
Total Labour Component ( A ) 309.10 Total Material Component ( B ) 1604.40 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 1913.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 287.03
Total Cost: Nrs. 2200.53
Rate : Nrs. 2200.53

27
( b ) mesh wire 10Swg, selvedge wire 8 Swg
( 14.6 ) Box size 3m*1m*0.3m
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
44.1.B.ii.
17-1.4 f Skilled person-day 0.32 1030.00 329.60 Mesh wire kg 19.17 105.00 2012.85
Selvedge wire For Heavy
17-5 Unskilled person-day 0.16 750.00 120.00 kg 3.23 105.00 339.15 class wire
Sub Total 2352.00
and 17-6 Transportation 0.00
Total Labour Component ( A ) 449.60 Total Material Component ( B ) 2352.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 2801.60
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 420.24
Total Cost: Nrs. 3221.84
Rate : Nrs. 3221.84
Item no 15
Description Packing and filling of gabion crates with rubble stones same as dry masonry

Unit 1 Cu M
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks

17-1.4 45(38.A.a) Skilled person-day 0.30 1030.00 309.00 Rubble Stone cu m 1.10 2577.88 2835.66
17-5 Unskilled person-day 0.75 750.00 562.50
17.6 Transportation 0.00
Total Labour Component ( A ) 871.50 Total Material Component ( B ) 2835.66 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 3707.16
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 556.07
Total Cost: Nrs. 4263.24
Rate : Nrs. 4263.24
Item no 16
Description Assembling of wire crates/gabion/revetment and placing them in position including stretching, binding them together and tying down lids.(For Heavy class)
(I) Binding wire (Medium class)- 12 SWG
(16.1)Box size 2*1*1
Unit 1 Box
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
Binding wire 12 SWG
17-1.4 44.2.a Skilled person-day 1030.00 kg 0.95 100.00 95.00
17-1.5 Unskilled person-day 0.09 750.00 67.50 For Heavy
and 17-1.6 Transportation 0.00 class wire
Total Labour Component ( A ) 67.50 Total Material Component ( B ) 95.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 162.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 24.38
Total Cost: Nrs. 186.88

Rate : Nrs. 186.88 Rate : Nrs. 93.44 per cu.m.

28
(16.2)Box size 3*1*1
Unit 1 Box
Respective Clause of Labour (A) Material(B) Equipment ( c )
dolidar Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
Specifications Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
Binding wire 12 For Heavy
17-1.4 44.2.b Skilled person-day 1030.00 SWG kg 1.30 100.00 130.00 class wire
17-1.5 Unskilled person-day 0.13 750.00 97.50 Transportation 0.00
Total Labour Component ( A ) 97.50 Total Material Component ( B ) 130.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 227.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 34.13
Total Cost: Nrs. 261.63 Rate : Nrs. 87.21 per cu.m.
(16.3)Box size 2*1*0.5
Unit 1 Box
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Norms n. Category Unit Qty. Rate (Nrs) Amount Type Unit Qty. Rate (Nrs) Amount Type Unit Qty. Rate Amount(Nrs) Remarks
Specifications
(Nrs) (Nrs) (Nrs)
Binding wire 12 For Heavy
17-1.4 44.2.c Skilled person-day 1030.00 SWG kg 0.70 100.00 70.00 class wire
17-1.5 Unskilled person-day 0.07 750.00 52.50 Transportation 3.50
Total Labour Component ( A ) 52.50 Total Material Component ( B ) 73.50 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 126.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 18.90
Total Cost: Nrs. 144.90
Rate : Nrs. 144.90 Rate : Nrs. 144.90 per cu.m.
(16.4)Box size 3*1*0.5
Unit 1 Box
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
Binding wire 12
17-1.4 44.2.d Skilled person-day 1030.00 SWG kg 0.95 100.00 95.00 For Heavy
17-1.5 Unskilled person-day 0.09 750.00 67.50 class wire
and 17-1.6 Transportation 0.00
Total Labour Component ( A ) 67.50 Total Material Component ( B ) 95.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 162.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 24.38
Total Cost: Nrs. 186.88
Rate : Nrs. 186.88 Rate : Nrs. 124.58 per cu.m.

29
(16.5)Box size 2*1*.3
Unit 1 Box
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
Binding wire 12
17-1.4 44.2.e Skilled person-day 1030.00 SWG kg 0.65 100.00 65.00
17-1.5 Unskilled person-day 0.06 750.00 45.00 For Heavy
and 17-1.6 Transportation 0.00 class wire
Total Labour Component ( A ) 45.00 Total Material Component ( B ) 65.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 110.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 16.50
Total Cost: Nrs. 126.50
Rate : Nrs. 126.50
(16.6)Box size 3*1*.3
Unit 1 Box
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
Binding wire 12
17-1.4 44.2.f Skilled person-day 1030.00 kg 0.90 100.00 90.00
SWG
17-1.5 Unskilled person-day 0.09 750.00 67.50 For Heavy
and 17-1.6 Transportation 0.00 class wire
Total Labour Component ( A ) 67.50 Total Material Component ( B ) 90.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 157.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 23.63
Total Cost: Nrs. 181.13
Rate : Nrs. 181.13

30
Item no 17
Description Fabrication of gabion box including , cutting , rolling, weaving .( For Medium class wire )
( Diapharagm is to be provided to every 1 m length. )
Unit 1 Box
Hexogonal mesh size 100*120
( b ) Mesh wire 10 SWG, Selvedge wire 8 SWG ( Medium class wire)
( 17.1) Box size 2m*1m*1m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
44.1.B.ii.a
17-1.4 Skilled person-day 0.39 1030.00 401.70 Mesh wire kg 23.43 100.00 2343.00
17-5 Unskilled person-day 0.20 750.00 150.00 Selvedge wire kg 2.88 100.00 288.00 Medium
Sub Total 2631.00 class wire
and 17-6 Transportation 0.00
Total Labour Component ( A ) 551.70 Total Material Component ( B ) 2631.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 3182.70
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 477.41
Total Cost: Nrs. 3660.11
Rate : Nrs. 3660.11
( b ) mesh wire 10Swg, slavage wire 8 Swg
( 17..2 ) Box size 3m*1m*1m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
44.1.B.ii.b
17-1.4 Skilled person-day 0.57 1030.00 587.10 Mesh wire kg 34.08 100.00 3408.00 Medium
17-5and 17-6 Unskilled person-day 0.28 750.00 210.00 Selvedge wire kg 4.03 100.00 403.00 class wire
Sub Total 3811.00
Transportation 0.00
Total Labour Component ( A ) 797.10 Total Material Component ( B ) 3811.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 4608.10
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 691.22
Total Cost: Nrs. 5299.32
Rate : Nrs. 5299.32
( b ) mesh wire 10Swg, slavage wire 8 Swg
( 17.3 ) Box size 2m*1m*0.5m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
44.1.B.ii.c
17-1.4 Skilled person-day 0.27 1030.00 278.10 Mesh wire kg 15.97 100.00 1597.00 Medium
17-5 Unskilled person-day 0.13 750.00 97.50 Selvedge wire kg 2.45 100.00 245.00 class wire
Sub Total 1842.00
and 17-6 Transportation 0.00
Total Labour Component ( A ) 375.60 Total Material Component ( B ) 1842.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 2217.60
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 332.64
Total Cost: Nrs. 2550.24
Rate : Nrs. 2550.24

31
( b ) mesh wire 10Swg, slavage wire 8 Swg
17.4Box size 3m*1m*0.5m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
44.1.B.ii.d
17-1.4 Skilled person-day 0.39 1030.00 401.70 Mesh wire kg 23.43 100.00 2343.00
17-5 Unskilled person-day 0.20 750.00 150.00 Selvedge wire kg 3.46 100.00 346.00 Medium
Sub Total 2689.00 class wire
and 17-6 Transportation 0.00
Total Labour Component ( A ) 551.70 Total Material Component ( B ) 2689.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 3240.70
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 486.11
Total Cost: Nrs. 3726.81
Rate : Nrs. 3726.81
( b ) mesh wire 10Swg, slavage wire 8 Swg
( 17.5 ) Box size 2m*1m*0.3m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
44.1.B.ii.e
17-1.4 Skilled person-day 0.22 1030.00 226.60 Mesh wire kg 13.00 100.00 1300.00 Medium
17-5 Unskilled person-day 0.11 750.00 82.50 Selvedge wire kg 2.28 100.00 228.00 class wire
Sub Total 1528.00
and 17-6 Transportation 0.00
Total Labour Component ( A ) 309.10 Total Material Component ( B ) 1528.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 1837.10
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 275.57
Total Cost: Nrs. 2112.67
Rate : Nrs. 2112.67

( b ) mesh wire 10Swg, slavage wire 8 Swg


( 17.6 ) Box size 3m*1m*0.3m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. Type Unit Qty. Remarks
44.1.B.ii.f
Medium
17-1.4 Skilled person-day 0.32 1030.00 329.60 Mesh wire kg 19.17 100.00 1917.00 class wire
17-5 Unskilled person-day 0.16 750.00 120.00 Selvedge wire kg 3.23 100.00 323.00
Sub Total 2240.00
and 17-6 Transportation 0.00
Total Labour Component ( A ) 449.60 Total Material Component ( B ) 2240.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 2689.60
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 403.44
Total Cost: Nrs. 3093.04
Rate : Nrs. 3093.04

32
Item no 18
Description Assembling of wire crates/gabion/revetment and placing them in position including stretching, binding them together and tying down lids. ( For Medium class wire )
(I) Binding wire ( Medium class)- 12 SWG
(18.1)Box size 2*1*1
Unit 1 Box
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
Binding wire
17-1.4 44.2.a Skilled person-day 1030.00 12swg kg 0.95 100.00 95.00 Medium
17-1.5 Unskilled person-day 0.09 750.00 67.50 class wire
and 17-1.6 Transportation 0.00
Total Labour Component ( A ) 67.50 Total Material Component ( B ) 95.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 162.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 24.38
Total Cost: Nrs. 186.88
Rate : Nrs. 186.88
(31.2.2)Box size 3*1*1
Unit 1 Box
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
Binding wire
17-1.4 44.2.b Skilled person-day 1030.00 12swg kg 1.30 100.00 130.00 Medium
17-1.5 Unskilled person-day 0.13 750.00 97.50 Transportation 6.50 class wire
Total Labour Component ( A ) 97.50 Total Material Component ( B ) 136.50 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 234.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 35.10
Total Cost: Nrs. 269.10
(18.3)Box size 2*1*0.5
Unit 1 Box
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
Binding wire
17-1.4 44.2.c Skilled person-day 1030.00 12swg kg 0.70 100.00 70.00 Medium
17-1.5 Unskilled person-day 0.07 750.00 52.50 Transportation 0.00 class wire
Total Labour Component ( A ) 52.50 Total Material Component ( B ) 70.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 122.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 18.38
Total Cost: Nrs. 140.88
Rate : Nrs. 140.88

33
(18.4)Box size 3*1*0.5
Unit 1 Box
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
Binding wire
17-1.4 44.2.d Skilled person-day 1030.00 12swg kg 0.95 100.00 95.00 Medium
17-1.5 Unskilled person-day 0.09 750.00 67.50 class wire
and 17-1.6 Transportation 0.00
Total Labour Component ( A ) 67.50 Total Material Component ( B ) 95.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 162.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 24.38
Total Cost: Nrs. 186.88
Rate : Nrs. 186.88
(18.5)Box size 2*1*.3
Unit 1 Box
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
Binding wire
17-1.4 44.2.e Skilled person-day 1030.00 12swg kg 0.65 100.00 65.00 Medium
17-1.5 Unskilled person-day 0.06 750.00 45.00 class wire
and 17-1.6 Transportation 0.00
Total Labour Component ( A ) 45.00 Total Material Component ( B ) 65.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 110.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 16.50
Total Cost: Nrs. 126.50
Rate : Nrs. 126.50
(18.6)Box size 3*1*.3
Unit 1 Box
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Specifications Norms n. Category Unit Qty. Rate (Nrs) Amount Type Unit Qty. Rate (Nrs) Amount Type Unit Qty. Rate Amount(Nrs) Remarks
(Nrs) Binding wire (Nrs) (Nrs)
17-1.4 44.2.f Skilled person-day 1030.00 12swg kg 0.90 100.00 90.00 Medium
17-1.5 Unskilled person-day 0.09 750.00 67.50 class wire
and 17-1.6 Transportation 0.00
Total Labour Component ( A ) 67.50 Total Material Component ( B ) 90.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 157.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 23.63
Total Cost: Nrs. 181.13
Rate : Nrs. 181.13

34
Item no 19
Description Laying, fitting of hume pipe having a length 1 m or more. It includes all operations required to complete the work up to a trench depth of 2.2 m below
the ground level and the jointing of pipes with 1:2 cement sand mortar.
Unit 1M
(A) R c c hume pipe NP 2
(A)For one or 1st pipe
(A1) pipe having 150 mm dia
Respective Clause Labour (A) Material(B) Equipment ( c )
Dolidar
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
Norms n.
of Specifications Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
15-5 47.a Skilled person-day 1030.00 Rcc Hp Np2 mtr 1.00 570.00 570.00 1st pipe
15-6 Unskilled person-day 0.075 750.00 56.25
Transportation 0.00
Total Labour Component ( A ) 56.25 Total Material Component ( B ) 570.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 626.25
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 93.94
Total Cost: Nrs. 720.19
Rate : Nrs. 720.19

(32.1.4) pipe having 300 mm dia


Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
15-5 47.a Skilled person-day 1030.00 Rcc Hp Np2 mtr 1.00 1260.00 1260.00 1st pipe
15-6 Unskilled person-day 0.15 750.00 112.50 Transportation 0.00
Total Labour Component ( A ) 112.50 Total Material Component ( B ) 1260.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 1372.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 205.88
Total Cost: Nrs. 1578.38
Rate : Nrs. 1578.38

(32.1.6) pipe having 450 mm dia


Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
15-5 47.a Skilled person-day 1030.00 Rcc Hp Np2 mtr 1.00 1852.00 1852.00 1st pipe
15-6 Unskilled person-day 0.15 750.00 112.50 Transportation 0.00
Total Labour Component ( A ) 112.50 Total Material Component ( B ) 1852.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 1964.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 294.68
Total Cost: Nrs. 2259.18

35
(A4) pipe having 600 mm dia
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
15-5 47.a Skilled person-day 1030.00 Rcc Hp Np2 mtr 1.00 2740.00 2740.00 1st pipe
15-6 Unskilled person-day 0.25 750.00 187.50
Transportation 0.00
Total Labour Component ( A ) 187.50 Total Material Component ( B ) 2740.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 2927.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 439.13
Total Cost: Nrs. 3366.63
Rate : Nrs. 3366.63
(A5) pipe having 900 mm dia
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
15-5 47.a Skilled person-day 1030.00 Rcc Hp Np2 mtr 1.00 5835.00 5835.00 1st pipe
15-6 Unskilled person-day 0.35 750.00 262.50 Transportation 0.00
Total Labour Component ( A ) 262.50 Total Material Component ( B ) 5835.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 6097.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 914.63
Total Cost: Nrs. 7012.13
Rate : Nrs. 7012.13
Item no 19 b
Description Laying, fitting of hume pipe having a length 1 m or more. It includes all operations required to complete the work up to a trench depth of 2.2 m below the ground level
and the jointing of pipes with 1:2 cement sand mortar.
Unit 1M
(A) R c c hume pipe NP 2
(b)For every sbusequent pipe having a length of minimum 1 m
(B1) pipe having 1 2
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
Rcc Hp Np2 every
47.b sbusequen
15-5 Skilled person-day 0.005 1030.00 5.15 mtr 1.00 570.00 570.00 t pipe
15-6 Unskilled person-day 0.020 750.00 15.00 Cement bag 0.01 825.00 8.25
Jute kg 0.50 76.00 38.00
Bitumen kg 0.10 78.10 7.81
Sub Total 624.06
Transportation 0.00
Total Labour Component ( A ) 20.15 Total Material Component ( B ) 624.06 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 644.21
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 96.63
Total Cost: Nrs. 740.84
Rate : Nrs. 740.84

36
(B2) pipe having 300 mm dia
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) every
Remarks
Rcc Hp Np2 sbusequen
15-5 47.b Skilled person-day 0.02 1030.00 20.60 mtr 1.00 1260.00 1260.00 t pipe
15-6 Unskilled person-day 0.10 750.00 75.00 Cement bag 0.015 825.00 12.38
Jute kg 1.00 76.00 76.00
Bitumen kg 0.20 78.10 15.62
Sub Total 1364.00
Transportation 0.00
Total Labour Component ( A ) 95.60 Total Material Component ( B ) 1364.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 1459.60
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 218.94
Total Cost: Nrs. 1678.53
Rate : Nrs. 1678.53
Description Laying, fitting of hume pipe having a length 1 m or more. It includes all operations required to complete the work up to a trench depth of 2.2 m below the ground level
and the jointing of pipes with 1:2 cement sand mortar.
Unit 1M
(B3) pipe having 450 mm dia
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
Rcc Hp Np2
every
47.b sbusequen
15-5 Skilled person-day 0.02 1030.00 20.60 mtr 1.00 1852.00 1852.00 t pipe
15-6 Unskilled person-day 0.10 750.00 75.00 Cement bag 0.015 825.00 12.38
Jute kg 1.00 76.00 76.00
Bitumen kg 0.20 78.10 15.62
Sub Total 1956.00
Transportation 0.00
Total Labour Component ( A ) 95.60 Total Material Component ( B ) 1956.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 2051.60
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 307.74
Total Cost: Nrs. 2359.33
Rate : Nrs. 2359.33

37
Unit 1M
(B4) pipe having 600 mm dia
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount Rate (Nrs) Amount(Nrs)
Specifications Norms n. Category Unit Qty. Type Unit Qty. (Nrs) Type Unit Qty. Remarks
Rcc Hp Np2
every
47.b sbusequent
15-5 Skilled person-day 0.05 1030.00 51.50 mtr 1.00 2740.00 2740.00 pipe
15-6 Unskilled person-day 0.20 750.00 150.00 Cement bag 0.06 825.00 49.50
Jute kg 2.50 76.00 190.00
Bitumen kg 0.50 78.10 39.05
Sand cu m 0.01 3213.21 32.13
Sub Total 3050.68
Transportation 0.00
Total Labour Component ( A ) 201.50 Total Material Component ( B ) 3050.68 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 3252.18
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 487.83
Total Cost: Nrs. 3740.01
Rate : Nrs. 3740.01

(B5) pipe having 900 mm dia


Labour (A) Material(B) Equipment ( c )
Respective Clause of Dolidar Amount (Nrs) Amount Remarks
Specifications Norms n. Category Unit Qty. Rate (Nrs) Type Unit Qty. Rate (Nrs) Type Unit Qty. Rate (Nrs) Amount(Nrs)
(Nrs) every
Rcc Hp Np2 sbusequent
15-5 47.b Skilled person-day 0.15 1030.00 154.50 mtr 1.00 5835.00 5835.00 pipe
15-6 Unskilled person-day 0.50 750.00 375.00 Cement bag 0.12 825.00 99.00
Jute kg 4.00 76.00 304.00
Bitumen kg 1.00 78.10 78.10
Sand cu m 0.01 3213.21 32.13
Sub Total 6348.23
Transportation 0.00
Total Labour Component ( A ) 529.50 Total Material Component ( B ) 6348.23 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 6877.73
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1031.66
Total Cost: Nrs. 7909.39
Rate : Nrs. 7909.39

38
Item no 19.C
C) R c c hume pipe NP 3
(a)For one or 1st pipe
(c.1) pipe having 150 mm dia
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
15-5 47.a Skilled person-day 1030.00 Rcc Hp Np3 mtr 1.00 1310.00 1310.00 1st pipe
15-6 Unskilled person-day 0.075 750.00 56.25 Transportation 65.50
Total Labour Component ( A ) 56.25 Total Material Component ( B ) 1375.50 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 1431.75
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 214.76
Total Cost: Nrs. 1646.51
Rate : Nrs. 1646.51

(C2) pipe having 300 mm dia


Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
15-5 47.a Skilled person-day 1030.00 Rcc Hp Np3 mtr 1.00 3140.00 3140.00 1st pipe
15-6 Unskilled person-day 0.15 750.00 112.50 Transportation 0.00
Total Labour Component ( A ) 112.50 Total Material Component ( B ) 3140.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 3252.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 487.88
Total Cost: Nrs. 3740.38
Rate : Nrs. 3740.38

(B) R c c hume pipe NP 3


(a)For one or 1st pipe
(C3) pipe having 450 mm dia
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
15-5 47.a Skilled person-day 1030.00 Rcc Hp Np3 mtr 1.00 4500.00 4500.00 1st pipe
15-6 Unskilled person-day 0.15 750.00 112.50 Transportation 0.00
Total Labour Component ( A ) 112.50 Total Material Component ( B ) 4500.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 4612.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 691.88
Total Cost: Nrs. 5304.38
Rate : Nrs. 5304.38

39
(C4) pipe having 600 mm dia
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
15-5 47.a Skilled person-day 1030.00 Rcc Hp Np3 mtr 1.00 6200.00 6200.00 1st pipe
15-6 Unskilled person-day 0.25 750.00 187.50 Transportation 0.00
Total Labour Component ( A ) 187.50 Total Material Component ( B ) 6200.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 6387.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 958.13
Total Cost: Nrs. 7345.63
Rate : Nrs. 7345.63
(C5) pipe having 900 mm dia
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
15-5 47.a Skilled person-day 1030.00 Rcc Hp Np3 mtr 1.00 12172.00 12172.00 1st pipe
15-6 Unskilled person-day 0.35 750.00 262.50 Transportation 0.00
Total Labour Component ( A ) 262.50 Total Material Component ( B ) 12172.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 12434.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1865.18
Total Cost: Nrs. 14299.68
Rate : Nrs. 14299.68
Item no 19 D
Description Laying, fitting of hume pipe having a length 1 m or more. It includes all operations required to complete the work up to a trench depth of 2.2 m below the ground level
and the jointing of pipes with 1:2 cement sand mortar.
Unit 1M
(B) R c c hume pipe NP 3
(b)For every sbusequent pipe having a length of minimum 1 m
(D1) pipe having 150 mm dia
Respective Clause Dolidar Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
of Specifications Norms n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
every
47.b sbusequen
15-5 Skilled person-day 0.005 1030.00 5.15 Rcc Hp Np3 mtr 1.00 1310.00 1310.00 t pipe
15-6 Unskilled person-day 0.020 750.00 15.00 Cement bag 0.01 825.00 8.25
Jute kg 0.50 76.00 76.00
Bitumen kg 0.10 78.10 7.81
Sub Total 1402.06
Transportation 0.00
Total Labour Component ( A ) 20.15 Total Material Component ( B ) 1402.06 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 1422.21
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 213.33
Total Cost: Nrs. 1635.54
Rate : Nrs. 1635.54

40
(B2) pipe having 300 mm dia
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs
Specifications n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) ) Remarks

47.b every
sbusequ
15-5 Skilled person-day 0.02 1030.00 20.60 Rcc Hp Np3 mtr 1.00 3140.00 3140.00 ent pipe
15-6 Unskilled person-day 0.10 750.00 75.00 Cement bag 0.015 825.00 12.38
Jute kg 1.00 76.00 76.00
Bitumen kg 0.20 78.10 15.62
Sub Total 3244.00
Transportation 0.00
Total Labour Component ( A ) 95.60 Total Material Component ( B ) 3244.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 3339.60
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 500.94
Total Cost: Nrs. 3840.53
Rate : Nrs. 3840.53

(D3) pipe having 450 mm dia


Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs
Specifications n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) ) Remarks

47.b every
sbusequ
15-5 Skilled person-day 0.02 1030.00 20.60 Rcc Hp Np3 mtr 1.00 4500.00 4500.00 ent pipe
15-6 Unskilled person-day 0.10 750.00 75.00 Cement bag 0.02 825.00 12.38
Jute kg 1.00 76.00 76.00
Bitumen kg 0.20 78.10 15.62
Sub Total 4604.00
Transportation 0.00
Total Labour Component ( A ) 95.60 Total Material Component ( B ) 4604.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 4699.60
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 704.94
Total Cost: Nrs. 5404.53
Rate : Nrs. 5404.53

41
(D4) pipe having 600 mm dia
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs
Specifications n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) ) Remarks
Rcc Hp Np3

47.b every
sbusequ
15-5 Skilled person-day 0.05 1030.00 51.50 mtr 1.00 6200.00 6200.00 ent pipe
15-6 Unskilled person-day 0.20 750.00 150.00 Cement bag 0.06 825.00 49.50
Jute kg 2.50 76.00 190.00
Bitumen kg 0.50 78.10 39.05
Sand cu m 0.01 3213.21 32.13
Sub Total 6510.68
Transportation 0.00
Total Labour Component ( A ) 201.50 Total Material Component ( B ) 6510.68 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 6712.18
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1006.83
Total Cost: Nrs. 7719.01
Rate : Nrs. 7719.01

(D5) pipe having 900 mm dia


Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs
Specifications n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) ) Remarks

47.b every
sbusequ
15-5 Skilled person-day 0.15 1030.00 154.50 Rcc Hp Np3 mtr 1.00 12172.00 12172.00 ent pipe
15-6 Unskilled person-day 0.50 750.00 375.00 Cement bag 0.12 825.00 99.00
Jute kg 4.00 76.00 304.00
Bitumen kg 1.00 78.10 78.10
Sand cu m 0.01 3213.21 32.13
Sub Total 12685.23
Transportation 0.00
Total Labour Component ( A ) 529.50 Total Material Component ( B ) 12685.23 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 13214.73
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1982.21
Total Cost: Nrs. 15196.94
Rate : Nrs. 15196.94

42
Item No
Description of Item
Semi-grouting works including compaction ( Ref norms of Dor Item no 15-21(a) in Open oven For Patch work only
( 5 cm thickness )
Unit 10 sq M
Respective Clause of Dor Labour (A) Material(B) Equipment ( c )
norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs)
Specifications (old) Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) Remarks
15.21 Skilled person-day Bitumen kg 35.00 78.10 2733.50
Roller
Unskilled person-day 1.20 750.00 900.00 kerosine app. 100.00 70.00 machine hrs 0.07 1102.50 77.18
Fire wood ( in open oven) kg 72.00 18.00 1296.00 Sprayer hrs 0.07 1821.75 127.52
Aggregate 38-40mm Cu M 0.60 3344.95 2006.97
Aggregate 12mm Cu M 0.15 3344.95 501.74
Total Labour Component ( A ) 900.00 Sub Total 6608.21 Total Equipment Component ( C) ) 204.70
Transportation 0.00
Total Material Component ( B ) 6608.21
Sub Total (A+B+C ) : Nrs. 7712.91
Nrs. 771.29 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1156.94
Total Cost: Nrs. 8869.85
Rate : Nrs. 886.98 per sq m
Item No
Description : Premix carpeting work including compactions For Patch work only

making arrangements for traffic in accordance with clause G 12 of the specification except for initial treatment to shoulders and construction of diversions

providing all materials to be incorporated in the work including all royalties fees, rents where necessary and all leads along the lead route
Unit : 1 cu m In norms unit is in sq.m. Now calculate is in cu.m. there for (10m2 *.02m thick =.2 m3 then 1m3/.20 m3 =5 times)
Equipment ( c
Respective Clause of Dor norms Labour (A) Material(B) )
Specifications (old)
Remarks
Category Unit Qty. Rate (Nrs) Amount Type Unit Qty. Rate (Nrs) Amount Type Rate Amount(Nrs
8-10 t Unit Qty.
Due to m3
(Nrs) (Nrs) (Nrs) )
4,2 15.24.khSkilled person-day Bitumen kg 77.00 78.10 6013.70 roller hrs 0.50 1102.50 551.25 unit
multiply by
Fire wood in open Sprayer above 5
Unskilled person-day 4.50 750.00 3375.00 oven kg 180.00 18.00 3240.00 hrs 0.50 1821.75 910.88 times
6 mm agg cu m 0.58 3213.21 1847.60
12mm agg. cu m 0.38 3344.95 1254.36 Half of
coarse sand. According
cu m 0.48 3213.21 1526.27 to 15.24.ka
kerosene. LS 7.70 100.00 770.00 Agg.qty
multiply by
Sub Total 14651.93 5 times
transportatin 0.00
Total Labour Component ( A ) 3375.00 Total Material Component ( B ) 14651.93 Total Equipment Component ( C) 1462.13
Sub Total (A+B+C ) : Nrs. 19489.05
Rate : Nrs. 19489.05 per cu m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 2923.36
Total Cost: Nrs. 22412.41
Rate : Nrs. 22412.41 per cu m

43
Item no 20
Description Fabricated Gabion boxes by Meachine weaving Mechanically Selvedged double twist wire mesh all complete work.
( Diapharagm is to be provided to every 1 m length. )
Unit 1 Box
Hexogonal mesh size 100*120
3.9/3/2.4 Heavy galvanized(ZN)
( 20.1 ) Box size 2m*1m*1m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs
Specifications n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) ) Remarks
Readymade
Gabion Box Box 1.00
Area 11 m2 2541.00
Sub Total 2541.00
Transportation 0.00
Total Labour Component ( A ) 0.00 Total Material Component ( B ) 2541.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 2541.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 381.15
Total Cost: Nrs. 2922.15
Rate : Nrs. 2922.15 per box Rate : Nrs. 1461.08 per cu.m.

( 20.2 ) Box size 3m*1m*1m


Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs
Specifications n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) ) Remarks
Readymade
Gabion Box Box 1.00
Area 16 m2 3696.00
Sub Total 3696.00
Transportation 0.00
Total Labour Component ( A ) 0.00 Total Material Component ( B ) 3696.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 3696.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 554.40
Total Cost: Nrs. 4250.40
Rate : Nrs. 4250.40 per box Rate : Nrs. 1416.80 per cu.m.

44
(20.3 ) Box size 1.5m*1m*1m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs
Specifications n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) ) Remarks
Readymade
Gabion Box Box 1.00
Area 8 m2 1848.00
Sub Total 1848.00
Transportation 0.00
Total Labour Component ( A ) 0.00 Total Material Component ( B ) 1848.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 1848.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 277.20
Total Cost: Nrs. 2125.20
Rate : Nrs. 2125.20 per box Rate : Nrs. 1416.80 per cu.m.
( 20. 4 ) Box size 2m*1m*0.5m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs
Specifications n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) ) Remarks
Readymade

Gabion Box Box 1.00


Area 7.5 m2 1732.50
Sub Total 1732.50
Transportation 0.00
Total Labour Component ( A ) 0.00 Total Material Component ( B ) 1732.50 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 1732.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 259.88
Total Cost: Nrs. 1992.38
Rate : Nrs. 1992.38 per box Rate : Nrs. 1992.38 per cu.m.
( 20.5 ) Box size 3m*1m*0.5m
Respective Clause of Dolidar Labour (A) Material(B) Equipment ( c )
Norms Rate (Nrs) Amount Rate (Nrs) Amount Rate Amount(Nrs
Specifications n. Category Unit Qty. (Nrs) Type Unit Qty. (Nrs) Type Unit Qty. (Nrs) ) Remarks
Readymade
Gabion Box Box 1.00
Area 11 m2 2541.00
Sub Total 2541.00
Transportation 0.00
Total Labour Component ( A ) 0.00 Total Material Component ( B ) 2541.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 2541.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 381.15
Total Cost: Nrs. 2922.15
Rate : Nrs. 2922.15 per box Rate : Nrs. 1948.10 per cu.m.

45
Item 21 Providing
Kerb in roadside
and laying of M20 precast cement concrete Kerb 35cm * 20 cm * 30 cm ( H*B*L) with 12 mm thick 1:3 cement sand mortar bedding and joints
including foundation excavation levelling but excluding foundation concrete for foundation or sand gravel material, all complete as per Drawing and
Technical Specifications.

unit for 400 Rm


Labour (A) Material(B) Equipment ( c ) Remarks
Category Unit Qty. Rate (Nrs) Amount (NType Unit Qty. Rate (Nrs) Amount (N
Type Unit Qty. Rate (NrAmount(Nrs)
Precast / cast in situ
concrete block of /20
Ref: Clause Concrete ( 0.35 m
*0.20 m * 0.30 m
1401 A, of Skilled md 3 1030.00 3090 1330 374.53 498124.9
(H*B*L))
SS DoR &
Unskilled md 16 750.00 12000 coarse sand m3 1.2 3213.21 3855.852
S.N. 14.1 of
Norms DoR cement ton 0.52 16500 8580
water lt 200 0.26 52
Sub Total 510613
Transportation 0
Total Labour Component ( A ) 15090 Total Material Component ( B ) 510613 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 525702.752
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 78855.4128
Total Cost: Nrs. 604558.165
Rate : Nrs. 1511.39541 per m

Rate : Nrs. 1511.4 per m 1314.25688 without over head

Item 22 Plum concreting


Providing and laying Plum concrete ( Boulder mixed concrete) as per Drawing and Specifications 60% M 20 concrete and 40%
A) boulders/stones Using Mechanical Aids.

unit 10 m2
Labour (A) Material(B) Equipment ( c ) Remarks
Category Unit Qty. Rate (Nrs)Amount (Type Unit Qty. Rate (Nrs) Amount T
( ype Unit Qty. Rate (NAmount(Nrs)
Ref: Clause 20-40mm
2421 of SS
DoR & S.N. Skilled md 3 1030 3090 agg m3 3.45 3344.95 11540
Concre
Concre
24.21(I) of Unskilled md 30 750.00 22500 10-20mm agm3 1.56 3344.95 5218.12 te te
Norms DoR
5-10mm aggm3 0.72 3213.21 2313.51 vibrato
mixer hr 6 362 2172
coarse sand m3 3 3213.21 9639.63 r hr 6 50 300
cement ton
2.5 16500 41250
boulder stonm34.4 2577.877 11343
Sub Total 81304
Transportation 0
Total Labour Component ( A ) 25590 81304 Total Equipment Component ( 2472
Sub Total (A+B+C ) : Nrs. 109366
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 16404.9

46
Total Cost: Nrs. 125770.9
Rate : Nrs. 12577.09 per m

Rate : Nrs. 12577.089754 per m

47
Providing and laying Plum concrete ( Boulder mixed concrete) as per Drawing and Specifications 60% M 15 concrete and 40% boulders/stones
22.B
without machine
unit 1 m2
Labour (A) Material(B) Equipment ( c ) Remarks
Ref: Clause
2421 of SS Category Unit Qty. Rate (Nrs) Amount (NType Unit Qty. Rate (Nrs) Amount (NType Unit Qty. Rate (NrAmount(Nrs)
DoR & S.N.
24.21(II) of
Norms DoR
Skilled md 1 1030 1030 20-40mm aggm3 0.156 3344.95 521.8122
Unskilled md 4 750 3000 10-20mm aggm3 0.072 3344.95 240.8364
5-10mm agg m3 0.299 3213.21 960.7498
coarse sand m3 0.299 3213.21 960.7498
cement ton 0.185 16500 3052.5
boulder stone m3 0.44 2577.877 1134.266
Sub Total 6870.914
Transportation 0
Total Labour Component (A) 4030 (B) 6870.914 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 10900.9139
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1635.13708
Total Cost: Nrs. 12536.051
Rate : Nrs. 12536.051 per m3

Rate : Nrs. 12536.051 per m3


Item no 23
Laying and fixing of Geo-Textile all complete as per specification.
Providing and laying of a geotextile filter between pitching and embankment slopes as per Drawing and Technical Specifications.

unit 300 sq m
Ref: Clause Labour (A) Material(B) Equipment ( c ) Remarks
2404 of SS Category Unit Qty. Rate (Nrs) Amount (NType Unit Qty. Rate (Nrs) Amount (N
Type Unit Qty. Rate (NrAmount(Nrs)
DoR & S.N. Skilled md 1 1030 1030 0
24.5 of Norms Unskilled md 2 750 1500 Geo textile m2 360 72 25920
DoR ton 0 0
lt 0
Sub Total 25920
Transportation 0
Total Labour Component ( A ) 2530 Total Material Component ( B ) 25920 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 28450
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 4267.5
Total Cost: Nrs. 32717.5
Rate : Nrs. 109.058 per m2

Rate : Nrs. 109.058333 per m2

48
Item 24 painting work on road

24.A
Road marking with hot applied Thermoplastic compound with reflectorizing glass beads on bituminous surface with all complete as
technical specification.
unit 400 m2
Labour (A) Material(B) Equipment ( c ) Remarks
Ref: Clause 1504 of SS Category Unit Qty. Rate (Nrs) Amount (Nrs)Type Unit Qty. Rate (Nrs) Amount (NrsType Unit Qty. Rate (Nrs)Amount(Nrs)
DoR & S.N. 15.9 of
Norms DoR Skilled md 2 1030 2060 thermoplastic ltr 930 509.00 473370 road
marking
machine hr 10
Unskilled md 4 750 3000 glass bed kg 100 150 15000 881 8810
0 0
0 0 trollley hr 10 1182 11820
Sub Total 488370
Transportation 0
Total Labour Component ( A ) 5060 Total Material Component ( B ) 488370 Total Equipment Component ( C) ) 20630
Sub Total (A+B+C ) : Nrs. 514060
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 77109
Total Cost: Nrs. 591169
1477.9225

Rate : Nrs. 1477.9225 per m2

24.B

Providing required material and Painting lines, dashes, arrows etc. on roads in two coats on work with ready
mixed road marking paint conforming to NS 408/ IS 164 on bituminous surface, including cleaning the surface of
all dirt, dust and other foreign matter, demarcation at site and traffic control as per Drawing and Technical
Specifications.
unit 10 m2
Labour (A) Material(B) Equipment ( c ) Remarks
Category Unit Qty. Rate (Nrs) Amount (Nrs)Type Unit Qty. Rate (Nrs) Amount (NrsType Unit Qty. Rate (Nrs)Amount(Nrs)
Ref: Clause 1503 of SS Skilled md 1 1030 1030 enamel paint lt 1.48 509.00 753.32
DoR & S.N. 15.7 of
Norms DoR
Unskilled md 2 750 1500 0
0 0
0 0
Sub Total 753.32
Transportation 0
Total Labour Component ( A ) 2530 Total Material Component ( B ) 753.32 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 3283.32
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 492.498
Total Cost: Nrs. 3775.818
Rate : Nrs. 377.5818 per m2

Rate : Nrs. 377.5818per m2

49
per cu.m.

per cu.m.

50
per cu.m.

per cu.m.

per cu.m.

51
Remarks

Remarks

52
SUMMARY OF ROAD RATE ANALYSIS

TARKESHWOR MINICIPALITY
Offce of theMunicipal Executive
Dharmsthali , Kathmandu, State No.3
SUMMARY OF RATE ANALYSIS
(Fiscal Year - 2077/078)
F.Y. 2075/2076 F.Y. 2076/077 F.Y. 2077/078

Page
Item no. Description of Work Unit Users Rate
(Excluding
Contractor Users Rate
Rate (Including (Excluding
Contractor
Rate (Including
Users Rate
(Excluding
Contractor
Rate (Including nos.
Remarks

Overhead) Overhead) Overhead) Overhead) Overhead) Overhead)

1.0 Site Clearance


1.1 Site Clearance - Clearing and grubbing etc all complete work
Sq M 28.00 32.20 30.00 34.50 30.00 34.50 1
1.2 Surface dressing work Sq M 7.00 8.05 7.50 8.63 7.50 8.63 1
1.3 Stripping of top soil work Cu M 560.00 644.00 600.00 690.00 600.00 690.00 1
2.0 Excavation work
2.1 Excavation in roadway and drain
a) Ordinary Soil Cu M 360.50 414.58 386.25 444.19 386.25 444.19 2
b) Hard Soil Cu M 432.60 497.49 463.50 533.03 463.50 533.03 2
c) Ordinary Rock Cu M 1442.00 1658.30 1545.00 1776.75 1545.00 1776.75 2
2.2 Exavation for structures
a) Ordinary Soil Cu M 721.00 829.15 772.50 888.38 772.50 888.38 3
b) Hard Soil Cu M 1442.00 1658.30 1545.00 1776.75 1545.00 1776.75 4
c) Ordinary Rock Cu M 2884.00 3316.60 3090.00 3553.50 3090.00 3553.50 4
3.0 Filling work with or with out compaction
3.1 Construction of roadway in embankments Cu M 180.25 207.29 193.13 222.09 193.13 222.09 5
3.2 Construction of roadway in embankments with hard soil cuttings Cu M 612.85 704.78 656.63 755.12 656.63 755.12 5
3.3 Compaction of filling material with Rolling Cu M 21.21 19.36 21.21 24.39 21.21 24.39 6
4.0 Sub grade work
4.1 Scarifying existing granular/bituminuous road surface Cu M 144.20 165.83 154.50 177.68 154.50 177.68 6
4.2 Subgrade construction with treated materials Cu M 497.09 571.65 528.75 608.06 528.75 608.06 6
4.3 Subgrade construction without treated materials Cu M 167.59 192.73 173.29 199.28 173.29 199.28 7
4.4 Prepration of Subgrade for rehabilitaion works ( filing or cutting depth
10cm to 20cm thick)
4.4 A 108.15 124.37 115.88 133.26 115.88 133.26
In Common soil Sq M 7
4.4 B 216.30 248.75 231.75 266.51 231.75 266.51
In Gravel & boulder mixed soil Sq M 7
5.0 Sub Base (Gravelling work)
Carrying out the construction operation of gravel material for
sub-base work
5.1 Local Gravel with compaction . Cu M 2802.28 3222.62 2804.63 3225.32 2804.63 3225.32 8
5.2 Gravel quarry from (Tikabhairav, Bhakunde site) Cu M 3469.38 3989.79 3471.73 3992.49 3471.73 3992.49 8
5.3 Local Gravel without compaction . Cu M 2619.86 3012.84 2622.21 3015.55 2622.21 3015.55 9
6.0 Brick Masonry work with all necessary operations .

Page 53
SUMMARY OF ROAD RATE ANALYSIS

6.1 In 1:4 c/s mix ratio Cu M 15408.72 17720.03 15731.22 18090.91 15731.22 18090.91 15

Page 54
SUMMARY OF ROAD RATE ANALYSIS

6.2 In 1:6 c/s mix ratio Cu M 15021.52 17274.75 15355.12 17658.39 15355.12 17658.39 16
7.0 Plastering work
12.5 mm th. plastering with cement sand mortar on brick walls of
concrete surfaces.
a) In 1:4 c/s mix ratio Sq M 352.50 405.37 368.63 423.93 368.63 423.93 16
b) In 1:6 c/s mix ratio Sq M 344.51 396.19 360.94 415.08 360.94 415.08 17

8.0 8.1 Pointing work in cement sand mortar on brick & stone wall with all
169.83 195.30 179.56 206.49 179.56 206.49
necessary operations in 1:3 c/s mix ratio Sq M 17
9.0 Other costruction work
9.1 Dry brick/ stone soling.
a) Flat Brick Sq M 953.88 1096.96 962.38 1106.73 962.38 1106.73 18
b) On edge Brick Sq M 1636.89 1882.42 1660.14 1909.16 1660.14 1909.16 18
C Stone soling work (15cm thick ) Sq M 852.70 980.61 877.20 1008.78 877.20 1008.78 19
Stone filling in the foundations and levelling including haulage
4143.45 4764.97 4218.45 4851.22 4218.45 4851.22
D distance up to 30 m. Cu M 19
Structural work in Road way
10.0 Retaining / protection wall work
Stone Masonry Work Un-coursed Rubble Masonry
10.1 In Dry wall Cu M 4365.66 5020.51 4475.66 5147.01 4475.66 5147.01 19
10.2 In Stone wall 1:4 c/s mix ratio Cu M 10004.99 11505.74 10234.87 11770.10 10234.87 11770.10 20
10.3 In Stone wall 1:6 c/s mix ratio Cu M 9732.71 11192.62 9972.77 11468.68 9972.77 11468.68 20
11.0 Formwork with timber /ply wood as material .
Providing preparing and instaling form work and removing after
completion work
11.1 Foundation & footing work Sq M 638.81 734.63 659.31 758.21 659.31 758.21 21
11.2 wall work Sq M 768.53 883.81 794.93 914.17 794.93 914.17 21
11.3 Lintel , Beam & slab structure work Sq M 833.95 959.04 859.05 987.90 859.05 987.90 22
12.0 Reinforcement for Rcc work ( Tor Steel )
12.1 Type ( A ) for Crank type along bar ( tor steel ) Kg 102.77 118.19 96.33 110.78 96.33 110.78 22
12.2 Type ( B ) for Plain straight bar ( tor steel ) for common use Kg 96.96 111.50 90.10 103.62 90.10 103.62 23
12.3 Type ( C) for C type hook bar ( tor steel ) Kg 99.86 114.84 93.22 107.20 93.22 107.20 23
12.4 Type ( D) for stirups ( tor steel ) Kg 114.39 131.55 108.79 125.11 108.79 125.11 23
13.0 Cement Concrete Work.
13.1 A) In foundation
a) M 10 Grade ( 1:3:6 ) mix by volume. Cu M 11396.61 13106.11 11553.71 13286.77 11553.71 13286.77 24
b) M 15 Grade ( 1:2:4 ) mix by volume. Cu M 12904.72 14840.43 13032.82 14987.74 13032.82 14987.74 24
13.2 In superstructural components ( beam,slab, abutment, caps etc.)
a) M 15 Grade ( 1:2:4 ) mix by volume. Cu M 13604.72 15645.43 13782.82 15850.24 13782.82 15850.24 25.0
b) M 20 Grade ( 1:1.5:3 ) mix by volume. Cu M 14970.61 17216.20 15126.11 17395.02 15126.11 17395.02 25

Page 55
SUMMARY OF ROAD RATE ANALYSIS

14.0 A Gabion Wall work


Fabrication of gabion boxes including rolling, cutting and weaving.
Mesh wire-10swg selvedge wire 8 swg , Hexagonal mesh size -
100*120 mm with partition
14.1 Using Heavy class wire
a) Box sizes 2m*1m*1m Box 3329.57 3829.01 3314.25 3811.39 3314.25 3811.39 26
b) Box sizes 3m*1m*1m Box 4820.97 5544.12 4798.65 5518.45 4798.65 5518.45 26
c) Box sizes 2m*1m*0.5m Box 2321.14 2669.31 2309.70 2656.16 2309.70 2656.16 27
d) Box sizes 3m*1m*0.5m Box 3391.63 3900.37 3375.15 3881.42 3375.15 3881.42 27
e) Box sizes 2m*1m*0.3m Box 1923.16 2211.63 1913.50 2200.53 1913.50 2200.53 27
f) Box sizes 3m*1m*0.3m Box 2816.00 3238.40 2801.60 3221.84 2801.60 3221.84 28
15.0 Packing and filling of gabion crates with rubbles stones. Cu M 3648.66 4195.96 3707.16 4263.24 3707.16 4263.24 28
16.0 16 Assembling of wire crates/gabion/revetment and placing them in
position.
Using heavy class wire
Binding wire 12 swg.
16.1 Box sizes 2m*1m*1m Box 160.85 184.98 162.50 186.88 162.50 186.88 28
16.2 Box sizes 3m*1m*1m Box 224.90 258.64 227.50 261.63 227.50 261.63 29
16.3 Box sizes 2m*1m*0.5m Box 124.71 143.41 126.00 144.90 126.00 144.90 29
16.4 Box sizes 3m*1m*0.5m Box 160.85 184.98 162.50 186.88 162.50 186.88 29
16.5 Box sizes 2m*1m*0.3m Box 108.95 125.29 110.00 126.50 110.00 126.50 30
16.6 Box sizes 3m*1m*0..3m Box 155.70 179.06 157.50 181.13 157.50 181.13 30
17.0 Fabrication of gabion boxes including rolling, cutting and weaving.
Mesh wire-10swg selvedge wire 8 swg , Hexagonal mesh size -
100*120 mm with partition
Using Medium class wire

17.1 Box sizes 2m*1m*1m Box 3198.02 3677.72 3182.70 3660.11 3182.70 3660.11 31
17.2 Box sizes 3m*1m*1m Box 4630.42 5324.98 4608.10 5299.32 4608.10 5299.32 31
17.3 Box sizes 2m*1m*0.5m Box 2229.04 2563.40 2217.60 2550.24 2217.60 2550.24 31
17.4 Box sizes 3m*1m*0.5m Box 3257.18 3745.76 3240.70 3726.81 3240.70 3726.81 32
17.5 Box sizes 2m*1m*0.3m Box 1846.76 2123.77 1837.10 2112.67 1837.10 2112.67 32
17.6 Box sizes 3m*1m*0.3m Box 2704.00 3109.60 2689.60 3093.04 2689.60 3093.04 32
18.0 Assembling of wire crates/gabion/revetment and placing them in
position.
Using Medium class wire
Binding wire 12 swg.
18.1 Box sizes 2m*1m*1m Box 160.85 184.98 162.50 186.88 162.50 186.88 33
18.2 Box sizes 3m*1m*1m Box 231.60 266.33 234.00 269.10 234.00 269.10 33
18.3 Box sizes 2m*1m*0.5m Box 121.10 139.27 122.50 140.88 122.50 140.88 33
18.4 Box sizes 3m*1m*0.5m Box 160.85 184.98 162.50 186.88 162.50 186.88 31
18.5 Box sizes 2m*1m*0.3m Box 108.95 125.29 110.00 126.50 110.00 126.50 34
18.6 Box sizes 3m*1m*0..3m Box 155.70 179.06 157.50 181.13 157.50 181.13 34

Page 56
SUMMARY OF ROAD RATE ANALYSIS

18 A Gabion wall all complete work ( including fabrication , packing stone & assembling of wire crates with using
Heavy class wire as above specification)
18A 1 Unit per Box from
items no
a) Box sizes 2m*1m*1m ( 2 m3 ) 10626.90 12220.93 10891.08 12524.74 10891.08 12524.74 14,15,16
Box
b) Box sizes 3m*1m*1m ( 3 m3 ) 15998.56 18398.34 16181.77 18609.03 16181.77 18609.03
Box
c) Box sizes 2m*1m*0.5m ( 1 m3 ) 6090.90 7004.54 6161.76 7086.03 6161.76 7086.03
Box
d) Box sizes 3m*1m*0.5m ( 1.5 m3 ) 9025.48 10379.30 9122.77 10491.19 9122.77 10491.19
Box
18A2 Unit per Cu. m.
a) Box sizes 2m*1m*1m 5313.45 6110.47 5445.54 6262.37 5445.54 6262.37
Cu M
b) Box sizes 3m*1m*1m 5332.85 6132.78 5393.92 6203.01 5393.92 6203.01
Cu M
c) Box sizes 2m*1m*0.5m 6090.90 7004.54 6161.76 7086.03 6161.76 7086.03
Cu M
d) Box sizes 3m*1m*0.5m 6016.98 6919.53 6081.85 6994.12 6081.85 6994.12
Cu M
19 Hume pipe work
Laying fitting and fixing of hume pipe having a length of 1 m of
more.
Rcc Hume pipe - NP2
A For one or first pipe.
a1 Pipe having 150 mm diameter. R.m 595.50 684.83 626.25 720.19 626.25 720.19 35
a2 Pipe having 300 mm diameter. R.m 1303.00 1498.45 1372.50 1578.38 1372.50 1578.38 35
a3 Pipe having 450 mm diameter. R.m 1869.00 2149.35 1964.50 2259.18 1964.50 2259.18 35
a4 Pipe having 600 mm diameter. R.m 2785.00 3202.75 2927.50 3366.63 2927.50 3366.63 36
a5 Pipe having 900 mm diameter. R.m 5801.00 6671.15 6097.50 7012.13 6097.50 7012.13 36
19.b b For every subsequent pipe having a length of minimum 1m

b1 Pipe having 150 mm diameter. R.m 615.67 708.02 644.21 740.84 644.21 740.84 36
b2 Pipe having 300 mm diameter. R.m 1390.74 1599.35 1459.60 1678.53 1459.60 1678.53 37
b3 Pipe having 450 mm diameter. R.m 1956.74 2250.25 2051.60 2359.33 2051.60 2359.33 37
b4 Pipe having 600 mm diameter. R.m 3107.90 3574.09 3252.18 3740.01 3252.18 3740.01 38
b5 Pipe having 900 mm diameter. R.m 6561.67 7545.92 6877.73 7909.39 6877.73 7909.39 38
19 c Rcc Hume pipe-Np3
Laying fitting and fixing of hume pipe having a length of 1 m of
more.
For one or first pipe.
c1 Pipe having 150 mm diameter. R.m 1362.90 1567.34 1431.75 1646.51 1431.75 1646.51 39
c2 Pipe having 300 mm diameter. R.m 3093.00 3556.95 3252.50 3740.38 3252.50 3740.38 39
c3 Pipe having 450 mm diameter. R.m 4392.00 5050.80 4612.50 5304.38 4612.50 5304.38 39
c4 Pipe having 600 mm diameter. R.m 6080.00 6992.00 6387.50 7345.63 6387.50 7345.63 40
c5 Pipe having 900 mm diameter. R.m 11838.00 13613.70 12434.50 14299.68 12434.50 14299.68 40

Page 57
SUMMARY OF ROAD RATE ANALYSIS

19 D For every subsequent pipe having a length of minimum 1 m

d1 Pipe having 150 mm diameter. R.m 1358.67 1562.47 1422.21 1635.54 1422.21 1635.54 40
d2 Pipe having 300 mm diameter. R.m 3180.74 3657.85 3339.60 3840.53 3339.60 3840.53 41
d3 Pipe having 450 mm diameter. R.m 4479.74 5151.70 4699.60 5404.53 4699.60 5404.53 41
d4 Pipe having 600 mm diameter. R.m 6402.90 7363.34 6712.18 7719.01 6712.18 7719.01 42
d5 Pipe having 900 mm diameter. R.m 12598.67 14488.47 13214.73 15196.94 13214.73 15196.94 42
20.0 A Gabion Wall work ( Machine made maccaferi Box )
Fabricated Gabion boxes by Meachine weaving Mechanically
Selvedged double twist wire mesh all complete work. Hexogonal
mesh size 100*120 Gabion of 3 mm mesh and 3.9 salvegde with
2.4 mm lacing of Heavy galvanized(ZN)
A.1 Using Heavy class wire
a) Box sizes 2m*1m*1m Box 2090.70 2404.31 2541.00 2922.15 2541.00 2922.15 44
b) Box sizes 3m*1m*1m Box 2918.70 3356.51 3696.00 4250.40 3696.00 4250.40 44
c) Box sizes 1.5m*1m*1m Box 1676.70 1928.21 1848.00 2125.20 1848.00 2125.20 45
d) Box sizes 2m*1m*0.5m Box 1469.70 1690.16 1732.50 1992.38 1732.50 1992.38 45
e) Box sizes 3m*1m*0.5m Box 2090.70 2404.31 2541.00 2922.15 2541.00 2922.15 45
A2 Gabion wall all complete work ( including fabrication , packing
stone & assembling of wire crates with using Heavy class wire as above
specification)
Unit per Box
a) Box sizes 2m*1m*1m ( 2 m3 ) Box 9388.03 10796.23 9955.33 11448.63 9955.33 11448.63
b) Box sizes 3m*1m*1m ( 3 m3 ) Box 13864.69 15944.40 14817.49 17040.12 14817.49 17040.12
c) Box sizes 1.5m*1m*1m ( 1.5 m3 ) Box 7149.70 8222.15 7408.75 8520.06 7408.75 8520.06
d) Box sizes 2m*1m*0.5m ( 1 m3 ) Box 5118.36 5886.12 5439.66 6255.61 5439.66 6255.61
e) Box sizes 3m*1m*0.5m ( 1.5 m3 ) Box 7563.70 8698.25 8101.75 9317.01 8101.75 9317.01
A3 Unit per Cu. m.
a) Box sizes 2m*1m*1m ( 2 m3 ) Cu M 4694.01 5398.12 4977.66 5724.31 4977.66 5724.31
b) Box sizes 3m*1m*1m ( 3 m3 ) Cu M 4621.56 5314.80 4939.16 5680.04 4939.16 5680.04
c) Box sizes 1.5m*1m*1m ( 1.5 m3 ) Cu M 4766.46 5481.43 4939.16 5680.04 4939.16 5680.04
d) Box sizes 2m*1m*0.5m ( 1 m3 ) Cu M 5118.36 5886.12 5439.66 6255.61 5439.66 6255.61
e) Box sizes 3m*1m*0.5m ( 1.5 m3 ) Cu M 5042.46 5798.83 5401.16 6211.34 5401.16 6211.34

Page 58
SUMMARY OF ROAD RATE ANALYSIS

Road constructin work


21 Kerb in roadside
Providing and laying of M20 precast cement concrete Kerb 35cm * 20
cm * 30 cm ( H*B*L) with 12 mm thick 1:3 cement sand mortar
bedding and joints including foundation excavation levelling but 1314.26 1511.40 1314.26 1511.40 46
excluding foundation concrete for foundation or sand gravel material,
all complete as per Drawing and Technical Specifications. rm
22.0 Plum concreting
22.1 Providing and laying Plum concrete ( Boulder mixed concrete) as per
Drawing and Specifications 60% M 15 concrete and 40% 93694.00 107748.10 109366.00 125770.90
boulders/stones Using Mechanical Aids. 46
22.2 Without machine used 10900.91 12536.05 10900.91 12536.05 46
23.0 Laying and fixing of Geo-Textile
Providing and laying of a geotextile filter between pitching and
94.83 109.06 94.83 109.06
embankment slopes as per Drawing and Technical Specifications. 47
24.0 paintaing work on road 0.00 0.00

Supplying and applying Thermoplastic road marking paint incluing


A 1285.15 1477.92 1285.15 1477.92
cleaning, wastering,brooming ect all complete
48
Double coat enamel paints/ readymade emulsion paint including
B 328.33 377.58 328.33 377.58 48
supply all complete

Page 59
SUMMARY OF ROAD RATE ANALYSIS

25.0 Road Construction work


Scarifying existing granular/bituminous road surface for carrying out the
required operations necessary to complete the work. This includes handling,
25.1 salvaging, stacking and disposing of scarified material up to a lead of 100 m
sqm 28.85 33.17 30.90 35.54 30.90 35.54 49
along the lead route.

25.2 Preparation of sub-grade for rehabilitation or other similar works 30.21 30.21 50
cum 25.14 28.90 26.27 26.27
(filling or cutting depth of 10 to 20 cm) in:

Providing, laying, spreading, watering, leveling and compaction of


25.3 natural sand gravel sub base grading as per table 12.1 of standard cum 3509.96 4034.44 3510.56 4037.14 3510.56 4037.14 51
specification

Providing, laying, spreading, watering, leveling and compaction of


25.4 cum 3890.32 4471.63 3889.72 4473.18 3889.72 4473.18 51
crusher run materials for base course lead up to 10m.

Providing and spraying bituminous tack coat MC30/MC70 including


25.5 cleaning the road surface using wire, brushes, broom etc before ltr 155.16 178.35 161.25 185.44 161.25 185.44 52
applying prime coat. (@0.60lit/sqm)

Providing and spraying bituminous prime coat MC30/MC70 including


25.6 cleaning the road surface using wire, brushes, broom etc before ltr 155.16 178.35 161.25 185.44 161.25 185.44 53
applying prime coat.

25.7 Providing, mixing, laying and compaction of premixed carpet cum 15323.9161 17613.6966 15840.72 18216.83 15840.72 18216.83 53

25.8 Providing and laying sand seal (for 10sqm) sqm 127.324448 146.34994 130.96 150.60 130.96 150.60 54

25.9 Providing, mixing, laying asphalt concrete with compaction cum 17866.48 20536.1788 18266.77 21006.78 18266.77 21006.78 55

Providing, laying, spreading, watering, leveling and compaction of


25.10 natural sand gravel sub base grading as per table 12.1 of standard cum 3512.02 4036.80 3511.61 4038.35 3511.61 4038.35 56
specification (Gravelling)

26.0 Rate Analysis for Water Supply and Sanitation Project 57 to 79

Page 60

You might also like