Professional Documents
Culture Documents
Special Questions
Special Questions
Special Questions
SPECIAL QUESTIONS
Question 1 From the following particulars, find the most profitable product mix and prepare a statement of profitability
of that product mix:-
Product A Product B Product C
Units budgeted to be produced and sold 1,800 3,000 1,200
Selling price per unit (Rs. ) 60 55 50
Requirement per unit:
Direct Materials 5 kg 3 kg 4 kg
Direct labour 4 hours 3 hours 2 hours
Variable overheads (Rs. ) 7 13 8
Fixed overheads (Rs. ) 10 12 5
Cost of direct material per kg (Rs. ) 4 4 4
Direct labour hour rate (Rs. ) 2 2 2
Maximum possible units of sales 4,000 5,000 1,500
All the three products are produced from the same direct material using same type of machines and labours. Direct
labour, which is the key factor, is limited to 18,600 hours.
Question 2 A manufacturer with an overall capacity (inter-changeable among the products) of 1,00,000 machine
hours has been so far producing a standard mix of A, B and C as 15,000 units, 10,000 units and 10,000 units
respectively. On experience, the total expenditure exclusive of his fixed charges found to be Rs. 2,09,000 and the
variable costs ratio among the products is 1 : 1.5 : 1.75 respectively per unit. The fixed charges comes to Rs. 2.00 per
unit. When the unit selling prices are Rs. 6.25 for A, Rs. 7.50 for B and Rs. 10.50 for C, he incurs loss.
He desires to change the product mix as under:-
MIX 1 MIX 2 MIX 3
A 18,000 15,000 22,000
B 12,000 6,000 8,000
C 7,000 13,000 8,000
As an accountant, which mix would you recommend ?
Question 3 A firm can produce three different products from the same raw material using the same production
facilities. The requisite labour is available in plenty at Rs. 8 per hour for all products. The supply of raw material, which
is imported at Rs. 8 per kg., is limited to 10,400 kgs for the budget period. The variable overheads are Rs. 5.60 per
hour. The fixed overheads are Rs. 50,000. The selling commission is 10% on sales.
a) From the following information, you are required to suggest the most suitable sales mix, which will maximize
the firm’s profits. Also determine the profit that will be earned at that level:-
Product market Selling price per Labour hours Raw material
demand unit (Rs. ) required per unit required per unit
(units) (Kg.)
X 8,000 30 1 0.7
Y 6,000 40 2 0.4
Z 5,000 50 1.5 1.5
b) Assume, in above situation, if additional 4,500 kgs of raw material is made available for production. Should the
firm go in further production, if it will result in additional fixed overheads of Rs. 20,000 and 25% increase in the
rates per hour for labour and variable overhaeds.
Question 4 A company produces three products. The general manager has prepared the following draft budget for the
next year.
Product A Product B Product C
No. of units 30,000 20,000 40,000
Selling price per unit (Rs. ) 40 80 20
P/V Ratio 20% 40% 10%
Raw material cost as a % of sales value 40% 35% 45%
Maximum Sales potential in Units 40,000 30,000 50,000
The company incurs Rs. 1,00,000 per annum towards fixed cost. The company uses the same raw material in all the
three products and the price of raw material is Rs. 2 per kg.
The draft budget makes full utilization of the available raw material which is in short supply. The managing director is
not satisfied with the budgeted profitability and hence he has passed on the aforesaid draft budget to you for review.
Required:
1) Set an optimal product mix for the next year and finds its profit.
2) The company has been able to locate a source for purchase of additional material 20,000 kgs at an enhanced
price. The transport cost for the additional raw material is Rs. 10,000. What is the maximum price per
kg.which can offered by the company for additional supply of raw material.
Sale value of 2500 units of A= Max cost of material + freight + other variable cost + additional fixed cost + profit
2500 units x Rs. 40 = Max. Material cost + 10000 + (2500 units x Rs. 16)
Max. material cost = Rs. 50000
Question 5 ABC Ltd. Produces three products A, B and C from the same manufacturing facilities. The cost and other
details of the three products are as follows:-
Product A Product B Product C
Selling price per unit (Rs.) 200 160 100
Variable cost per unit (Rs.) 120 120 40
Maximum production per 5,000 8,000 6,000
months in units
Maximum demand per month 2,000 4,000 2,400
in units
Fixed expenses for the month is Rs. 2,76,000. The total processing hours available for the month cannot be increased
beyond 200 hours. With these available 200 hours, only one of these three products can be produced at maximum
level.
You are required to:-
a) Compute the most profitable product-mix;
b) Compute the overall break-even sales of the company for the month based on the mix calculated in (a) above.
Solution:
Limited available processing hours = 200 hours
With these available hours, only one product can be produced for maximum production quantity.
(1)
Product Production Hours Hour per unit
A 5000 kg 200 hours 1/25 hour per unit ( )
A = 2000 units
B = 1600 units
C = 2400 units
Question 6 X Ltd. supplies spare parts to an air craft company Y Ltd. The production capacity of X Ltd.
facilitates production of any one spare part for a particular period of time. The following are the cost and
other information for the production of the two different spare parts A and B:
Part A Part B
Per unit
Alloy usage 1.6 kgs. 1.6 kgs.
Machine Time: Machine P 0.6 hrs 0.25 hrs.
Machine Time: Machine Q 0.5 hrs. 0.55 hrs.
Target Price (Rs.) 145 115
Total hours available Machine P 4,000 hours
Machine Q 4,500 hours
Alloy available is 13,000 kgs. @ Rs. 12.50 per kg.
Variable overheads per machine hours Machine P: Rs. 80
Machine Q: Rs. 100
Required
(i) IDENTIFY the spare part which will optimize contribution at the offered price.
(ii) If Y Ltd. reduces target price by 10% and offers Rs. 60 per hour of unutilized machine hour,
CALCULATE the total contribution from the spare part identified above?
Question 7
The profit for the year of R.J. Ltd. works out to 12.5% of the capital employed and the relevant
figures are as under:
Required
FIND OUT by computing in detail the cost and profit for next year, whether the proposal of Sales
Manager can be adopted.
Question 9
A company can make any one of the 3 products X, Y or Z in a year. It can exercise its option only at the beginning of
each year.
Relevant information about the products for the next year is given below.
X Y Z
Selling Price (Rs. / unit) 100 120 120
Variable Costs (Rs. / unit) 60 90 70
Market Demand (unit) 3,000 2,000 1,000
Production Capacity (unit) 2,000 3,000 900
Required
COMPUTE the opportunity costs for each of the products.
Question 10
XY Ltd. makes two products X and Y, whose respective fixed costs are F1 and F2. You are given that the unit
contribution of Y is one fifth less than the unit contribution of X, that the total of F 1 and F2 is Rs.1,50,000, that the BEP
of X is 1,800 units (for BEP of X, F2 is not considered) and that 3,000 units is the indifference point between X and Y.
(i.e. X and Y make equal profits at 3,000 unit volume, considering their respective fixed costs). There is no inventory
buildup as whatever is produced is sold.
Required
FIND OUT the values F1 and F2 and units contributions of X and Y.
Question 11
AD Higher Secondary School (AHSS) offers courses for 11th & 12th standard in three streams
i.e. Arts, Commerce and Science. AHSS runs higher secondary classes along with primary and
secondary classes, but for accounting purpose it treats higher secondary as a separate
responsibility centre. The Managing committee of the school wants to revise its fee structure for
higher secondary students. The accountant of the school has provided the following details for a
year:
(i)
(ii) One teacher who teaches economics for Arts stream students also teaches commerce
stream students. The teacher takes 1,040 classes in a year, it includes 208 classes for
commerce students.
(iii) There is another teacher who teaches mathematics for Science stream students also
teaches business mathematics to commerce stream students. She takes 1,100 classes
a year, it includes 160 classes for commerce students.
(iv) One peon is fully dedicated for higher secondary section. Other peons dedicate their
15% time for higher secondary section
(v) All school students irrespective of section and age participates in annual functions and
sports activities
Required
a) CALCULATE cost per student per annum for all three streams
b) If the management decides to take uniform fee of Rs. 1,000 per month from all higher
secondary students, CALCULATE stream wise profitability
c) If management decides to take 10% profit on cost, COMPUTE fee to be charged from the
students of all three streams respectively
Question 12
Sanziet Lifecare Ltd. operates in life insurance business. Last year it launched a new term
insurance policy for practicing professionals ‘Professionals Protection Plus’. The company has
incurred the following expenditures during the last year for the policy:
Required:
i. CALCULATE total cost for Professionals Protection Plus’ policy segregating the costs into
four main activities namely (a) Marketing and Sales support, (b) Operations, (c) IT and (d)
Support functions
ii. CALCULATE cost per policy.
iii. CALCULATE cost per rupee of insured value
Question 13
SLS Infrastructure built and operates 110 k.m. highway on the basis of Built-Operate-Transfer
(BOT) for a period of 25 years. A traffic assessment carried out to estimate the traffic flow per day
shows the following figures:
An average cost of Rs.1,120 lakh has to be incurred on administration and toll plaza operation.
On the basis of the vehicle specifications (i.e. weight, size, time saving etc.), the following
weights has been assigned to the passing vehicles:
Note – Concession period is a period for which an infrastructure is allowed to operate and
recovers its investment.
Question 14
A cast iron foundry is importing forged steel moulds for making its castings. The moulds are of
four different sizes A, B, C and D and the CIF values are US $ 4,140, 4,760, 6,340 and 7,875,
respectively. Customs duty may be assumed at 45% and clearing charges 5% of CIF value. The
number of castings that can be made out of each mould is: A 2,000, B 2,000, C 1,800, and D
1,500.
The weight of each casting out of A is 300 kg., B 400 kg., C 500 kg., and D 700 kg. The casting
suffer a normal rejection of 10%. You are required to calculate the average cost of mould per
tonne of saleable casting. (For conversion assume US $1 = Rs. 8.)
Solution
Concept
Case 1 When Ram purchases goods from john and sells in India (Ram is Buyer)
Case 2 When Ram purchase goods in India and Sells to John (Ram is Seller)
Buyer shall always be responsible after goods reach port of buyer’s country.
If terms are CIF it means buyer shall be responsible till goods reach port of buyer’s country.
Free on Board means seller shall be free from responsibility once goods reach port of seller country.
If terms are CIF
Seller is responsible for any loss till goods reach port of buyer’s country.
In Given Question terms are CIF, it means Seller is responsible for any loss till goods reach port of buyer’s country. So
we need to calculate Landed Cost = CIF + Custom Duty (import)
A B C D TOTAL
CIF Values (US $) 4,140 4,760 6,340 7,875 23,115
Customs duty & clearing charges (50%)
2,070 2,380 3,170 3,937.50 11,557.50
Total Cost (US$) 6,210 7,140 9,510 11,812.50 34,672.50
Cost in Rupees (1$ = Rs. 8) 49,680 57,120 76,080 94,500 2,77,380
--- A (Assumed)
Number of castings 2,000 2,000 1,800 1,500 -
Less 10% normal rejections 200 200 180 150 -
Number of saleablecastings 1,800 1,800 1,620 1,350 -
--- B (Assumed)
Weight of each casting (Kg) 300 400 500 700 -
----- C (Assumed)
Weight of saleable castings (in tonnes)
– D (Assumed) 540 Tonnes 720 Tonnes 810 945 Tonnes 3,015 Tonnes
Tonnes
The average cost of mould per tonne of saleable casting is, therefore, Rs.91.3 approx.
Question 15
PREPARE the priced stores ledger on FIFO method and STATE how would you treat the shortage in stock taking.
Stores Ledger of AT Ltd. for the month of September, 20X8 (FIFO Method)
MRR no. Units (Rs.) (Rs.) no. Units (Rs.) (Rs.) Units (Rs.) (Rs.)
1 2 3 4 5 6 7 8 9 10 11 12
1-9-X8 -- -- -- -- -- -- -- -- 25 6.50 162.50
4-9-X8 -- -- -- -- 85 8 6.50 52 17 6.50 110.50
6-9-X8 26 50 5.75 287.50 -- -- -- -- 17 6.50 110.50
50 5.75 287.50
Question 16
A Factory produces two products “A” & “B” from a single process. The Joint processing costs during a particular month
are:
Direct Material Cost Rs.30,000
Direct Labour Cost Rs.9,600
Variable Overheads Rs.12,000
Fixed Overheads Rs.32,000
Sales: A – 100 units @ Rs.600 per unit; B – 120 units @ Rs.200 per unit.
Apportion Joint Costs on the basis of:
(i) Physical Quantity of each product
(ii) Contribution Margin method
(iii) Determine Profit or Loss under both the methods
Special Point - Contribution of One Product Coming Negative so how to distribute Fixed cost
Concepts
(i) Physical Quantity of each product
According to this method, The joint costs is to be distributed on the basis of weight or on the basis of quantity of
various joint products i.e. Joint cost is distributed in ratio of quantity manufactured.
Solution
W. Note 1:- Calculation of Total Joint cost
DMC Rs.30,000
DLC Rs.9,600
Variable Overheads Rs.12,000
Total Variable Cost Rs.51,600
Fixed Overheads Rs.32,000
Total Joint Cost Rs.83,600
Note:- In practical life, if contribution of any product comes negative then entity should choose another method
because this method is not suitable.
But since we are supposed to solve this question, we will treat negative contribution as zero contribution.
(iii)
Profit & Loss Under above methods
St. showing Profit & Loss as per Physical unit method
Particulars Product A Product B
Sales Rs.60,000 Rs.24,000
Less Share in Joint Cost Rs.38,000 Rs.45,600
Profit Rs.22,000 Rs.21,600
Question 17
GZ Ld. pays the following to a skilled worker engaged in production works. The following are the employee benefits
paid to the employee:
Solution
First of all we need to understand meaning and implication of lines given in question so we can
understand each point from practical point of view
Line Given in Question Its meaning & Implication
Transport Allowance as Rs.50 per day of If employees comes to Office then he shall be
Actual Work paid Rs.50 per day. This 50 rupees shall be
paid even if it is Sunday, it is holiday. It also
means that If employee does not come on any
day in office then he shall not be paid this
Rs.50
Overtime Line (Read from Question) If worker works for more than 9 hours in a day
then he shall be eligible for overtime payment.
Overtime rate = Twice the hourly rate (Basic
salary Plus DA)
Overtime = Actual time worked – 8 hours
Working on holiday (Read From Question) Holiday Means Sunday and Public Holiday e.g.
15th August.
Overtime rate = Double per day basic Rate
Condition = Works at least 4 hours.
Above Pymt shall be added in Basic as given in
Question.
Earned Leave & Casual Leave. These are paid Company allow some leaves in year for which
leaves salary is not deducted. It means if a worker
takes CL then his salary shall not be deducted.
Required Calculations
1. Overtime Rate per hour = Twice the hourly rate (Consider basic & DA)
( )
=2x = 2 x Rs.160 = Rs.320
( )
Question 18
AP Ltd. received a job order for supply and fitting of plumbing materials. Following are the details related with the
job work:
Direct Materials
AP Ltd. uses a weighted average method for the pricing of materials issues.
Purchases:
ANSWER :-
Question 19
M Ltd. produces a product-X, which passes through three processes, I, II and III. In Process-III a by-product arises,
which after further processing at a cost of Rs.85 per unit, product Z is produced. The information related for the
month of August 2020 is as follows:
Process-I Process-II Process-III
Normal loss 5% 10% 5%
Materials introduced (7,000 units) 1,40,000 - -
Other materials added 62,000 1,36,000 84,200
Direct wages 42,000 54,000 48,000
Direct expenses 14,000 16,000 14,000
Production overhead for the month is Rs.2,88,000, which is absorbed as a percentage of direct wages.
The scrapes are sold at Rs.10 per unit
Product-Z can be sold at Rs.135 per unit with a selling cost of Rs.15 per unit No. of units produced:
Process-I- 6,600; Process-II- 5,200, Process-III- 4,800 and Product-Z- 600 There is not stock at the beginning and end
of the month.
You are required to PREPARE accounts for:
(i) Process-I, II and III
(ii) By-product process.
Question 20
Arnav Electronics manufactures electronic home appliances. It follows weighted average Cost method for inventory
valuation. Following are the data of component X:
Question 21
The Following data related to the manufacture of a standard product during the month of April 2020:
Particulars Amount (Rs.)
Raw Materials 1,80,000
Direct Wages 90,000
Machine Hours worked (hours) 10,000 Hours
Machine hour rate (per hour) Rs.8
Administration Overheads (general) 35,000
Selling Overheads (Per Unit) Rs.5
Units Produced 4,000 units
Units Sold 3,600 units
Selling Price per unit Rs.125
You are required to prepare a cost sheet in respect of the above showing:
(i) Cost per unit
(ii) Profit for the month
Requirement No. 2
Particulars Total Cost (Rs.) Units Cost Per Unit (Rs.)
www.purushottamaggarwal.com Call 95 8280 8296 Page 16.22
Cost & Management Accounting CA Purushottam Sir
Question 22
Arnav Inspat Udyog Ltd. has the following expenditures for the year ended 31st March, 20X8:
Amount realized by selling of scrap and waste generated during manufacturing process – Rs.86,000/-
From the above data you are requested to PREPARE Statement of cost for Arnav Ispat Udyog Ltd. for the year ended
31st March, 20X8, showing (i) Prime cost, (ii) Factory cost, (iii) Cost of Production, (iv) Cost of goods sold and (v) Cost
of sales.
Answer:
Statement of Cost of Arnav Ispat Udyog Ltd. for the year ended 31st March, 20X8:
Notes: GST paid of purchase of raw materials would not be part of cost of materials as it is eligible for input credit.
Question 23
An English willow company who manufactures cricket bat buys wood as its direct material. The Forming department
processes the cricket bats and the cricket bats are then transferred to the Finishing department where stickers are
applied. The Forming department began manufacturing 10,000 initial bats during the month of December for the first
time and their cost is as follows:
CALCULATE:
Solution
Equivalent Units
Input Units Output Units Material Conversion cost
Details Particulars
% Units % Units
Unit Introduced 10,000 Finished output 8,000 100 8,000 100 8,000
Closing W-I-P 2,000 100 2,000 25 500
Total 10,000 Total 10,000 10,000 8,500
Total 42,400
Question 24
Hill manufacturing Ltd uses process costing to manufacture Water density sensors for hydro
sector. The following information pertains to operations for the month of May.
Particulars Units
Beginning WIP, May 1 16,000
Started in production during May 1,00,000
Completed production during May 92,000
Ending work in progress, May 31 24,000
The beginning work in progress was 60% complete for materials and 20% complete for
conversion costs. The ending inventory was 90% complete for material and 40% complete for
conversion costs.
CALCULATE:
(i) Using the FIFO method, the equivalent units of production for material.
(ii) Cost per equivalent unit for conversion cost.
Solution
Introduced
Closing W- I-P 24,000 90 21,600 40 9,600
1,16,000 Total 1,16,000 1,04,000 98,400
Total
Question 25
‘Healthy Sweets’ is engaged in the manufacturing of jaggery. Its process involve sugarcane
crushing for juice extraction, then filtration and boiling of juice along with some chemicals and
then letting it cool to cut solidified jaggery blocks.
The main process of juice extraction (Process – I) is done in conventional crusher, which is then
filtered and boiled (Process – II) in iron pots. The solidified jaggery blocks are then cut, packed
and dispatched. For manufacturing 10 kg of jaggery, 100 kg of sugarcane is required, which
extracts only 45 litre of juice.
Following information regarding Process – I has been obtained from the manufacturing
department of Healthy Sweets for the month of January, 2020:
Sugarcane Rs.50,000
Labour Rs.15,000
Overheads Rs.45,000
Sugarcane introduced for juice extraction (1,00,000 Kg) Rs.5,00,000
Direct Labour Rs.2,00,000
Overheads Rs.6,00,000
Solution
(i) Statement of Equivalent Production
% Units % Units
Amount Amount
(Rs.) (Rs.)
Question 26
Smile company produces two main products and a by-product out of a joint process. The ratio of
output quantities to input quantities of direct material used in the joint process remains consistent
on yearly basis. Company has employed the physical volume method to allocate joint production
costs to the main products. The net realizable value of the by- product is used to reduce the joint
production costs before the joint costs are allocated to the main products. Details of company’s
operation are given in the table below. During the month, company incurred joint production
costs of Rs. 10,00,000/- The main products are not marketable at the split off point and thus
have to be processed further.
Particulars Product-A Product-B By product
Monthly output in kg. 60,000 1,20,000 50,000
Selling price per kg. Rs. 50 Rs. 30 Rs. 5
Process costs Rs. 2,00,000 Rs. 3,00,000
FIND OUT the amount of joint product cost that Smile company would allocate to the product-B
by using the physical volume method to allocate joint production costs?
Solution
Calculation of Net joint costs to be allocated:
Therefore, amount of joint product cost that Smile company would allocate to the product-B by
using the physical volume method to allocate joint production costs:
Question 27
‘Buttery Butter’ is engaged in the production of Buttermilk, Butter and Ghee. It purchases
processed cream and let it through the process of churning until it separates into buttermilk and
butter. For the month of January, 2020, ‘Buttery Butter’ purchased 50 Kilolitre processed cream
@ Rs. 100 per 1000 ml. Conversion cost of Rs. 1,00,000 were incurred up-to the split off point,
where two saleable products were produced i.e. buttermilk and butter. Butter can be further
processed into Ghee.
All 20 tonne of butter were further processed at an incremental cost of Rs. 1,20,000 to yield 16
Kilolitre of Ghee. There was no opening or closing inventories of buttermilk, butter or ghee in
January, 2020.
Required:
(i) SHOW how joint cost would be apportioned between Buttermilk and Butter under Estimated
Net Realisable Value method.
(ii) ‘Healthy Bones’ offers to purchase 20 tonne of butter in February at Rs. 360 per kg. In case
‘Buttery Butter’ accepts this offer, no Ghee would be produced in February. SUGGEST
whether ‘Buttery Butter’ shall accept the offer affecting its operating income or further process
butter to make Ghee itself?
The operating income of ‘Buttery Butter’ will be reduced By Rs. 3,60,000 in February if it sells 20
tonne of Butter to ‘Healthy Bones’, instead of further processing of Butter into Ghee for sale.
Thus, ‘Buttery Butter’ is advised not to accept the offer and further process butter to make Ghee
itself.
Question 28
NN Manufacturing company uses joint production process that produces three products at the
split off point. Joint productions costs during September were Rs. 8,40,000. Product information
for September was as follows:
Assume that product C is treated as a by-product and the company accounts for the by-product
at net realizable value as a reduction of joint cost. Assume also that Product B&C must be
processed further before they can be sold. FIND OUT the total cost of Product A in September if
joint cost allocation is based on net realizable values?
Solution
Product A can be sold at the split-off point, because the question says that "Products B and C
must be processed further before they can be sold." Since product A is not included in that, we
know that Product A can be sold at the split-off point. Furthermore, the cost to process Product A
after the split-off point is Rs. 150,000, whereas the additional revenue to be earned by processing
it further is only Rs.75,000 (Rs.50 increase in selling price per unit multiplied by the 1,500 units
produced during September). Therefore, Product A will not be processed further, and we use the
sales value at split-off for A for allocating the joint costs. The sales value at the split-off for A is
Rs. 100 × 1,500 units, or Rs.1,50,000.
Since Product B must be processed further, we use its net realizable value for the joint cost
allocation. The net realizable value of Product B is Rs.5,25,000 (Rs.175 selling price after further
processing × 3,000 units produced) – Rs.1,50,000 in further processing costs = Rs.3,75,000.
Product C, the by-product, must also be processed further to be sold. The net realizable value of
Product C is Rs. 75,000 (Rs. 50 sales price after further processing × 4,500 units produced – Rs.
1,50,000 in further processing costs = Rs. 75,000.
Joint production costs total Rs. 8,40,000. Since the by-product C is accounted for as a reduction
to the joint costs, the joint costs to be allocated are Rs. 7,65,000 (Rs. 8,40,000 minus the Rs.
75,000 NRV of Product C), to be allocated between Product A (sales value Rs. 1,50,000) and
Product B (net realizable value Rs. 3,75,000). So, the total on which the allocation of the joint
costs is based is Rs. 1,50,000 + Rs. 5,25,000. Product A represents 28.571% of Rs. 5,25,000).
the total 3,75,000 = (Rs. 1,50,000 ÷ Rs. 5,25,000).
Since Product A has no further processing costs, the total cost of Product A is equal to its
allocated joint costs, which are 28.571% of the net joint costs of Rs. 7,65,000, or Rs. 2,18,568.
Question 29
GAP Limited operates a system of standard costing in respect of one of its products which is
manufactured within a single cost centre. Following are the details.
Budgeted data:
B 40 30 1200
Inputs 100 2400
Normal loss 20
Output 80 2400
Actual data:
Actual output - 80 units.
Question 30
Following data is extracted from the books of XYZ Ltd. for the month of January, 2020:
(i) Estimation-
Particulars Quantity (kg.) Price (Rs.) Amount (Rs.)
Material-A 800 ? --
Material-B 600 30.00 18,000
Normal loss was expected to be 10% of total input materials.
Question 31
Paras Synthetics uses Standard costing system in manufacturing of its product ‘Star 95 Mask’.
The details are as follows;
During the month of August, 2020 10,000 units of ‘Star 95 Mask’ were manufactured.
Details are as follows:
Direct material consumed 5700 meters @ Rs. 58 per meter
Direct labour Hours ? @ ? Rs. 2,24,400
Variable overhead incurred Rs. 1,12,200
Variable overhead efficiency variance is Rs. 2,000 A. Variable overheads are based on Direct
Labour Hours.
You are required to calculate the missing data and all the relevant Variances.
Question 32
Prisha Limited manufactures three different products and the following information has been
collected from the books of accounts:
Products
A B C
Sales Mix 40% 35% 25%
Selling Price Rs.300 Rs.400 Rs.200
Variable Cost Rs.150 Rs.200 Rs.120
Total Fixed Costs Rs.18,00,000
Total Sales Rs.60,00,000
The company has currently under discussion, a proposal to discontinue the manufacture of
Product C and replace it with Product E, when the following results are anticipated:
Products
A B E
Sales Mix 45% 30% 25%
Required:
(i) CALCULATE the total contribution to sales ratio and present break-even sales at existing
sales mix.
(ii) CALCULATE the total contribution to sales ratio and present break-even sales at
proposed sales mix.
(iii) STATE whether the proposed sales mix is accepted or not?
Solution
(i) Calculation of Contribution to sales ratio at existing sales mix:
Products Total
A B C
Selling Price (Rs.) 300 400 200
Less: Variable Cost (Rs.) 150 200 120
Contribution per unit (Rs.) 150 200 80
P/V Ratio 50% 50% 40%
Sales Mix 40% 35% 25%
Contribution per rupee of sales (P/V Ratio × Sales Mix) 20% 17.5% 10% 47.5%
Present Total Contribution (Rs. 60,00,000 × 47.5%) Rs. 28,50,000
Less: Fixed Costs Rs. 18,00,000
Present Profit Rs. 10,50,000
Present Break-Even Sales Rs. 37,89,473.68
(Rs. 18,00,000/0.475)
Products
A B E Total
Selling Price (Rs.) 300 400 300
Less: Variable Cost (Rs.) 150 200 150
Contribution per unit (Rs.) 150 200 150
P/V Ratio 50% 50% 50%
Sales Mix 45% 30% 25%
Contribution per rupee of sales 22.5% 15% 12.5% 50%
(P/V Ratio x Sales Mix)
Proposed Total Contribution Rs. 32,00,000
(Rs. 64,00,000 × 50%)
Less: Fixed Costs Rs. 18,00,000
Proposed Profit Rs. 14,00,000
www.purushottamaggarwal.com Call 95 8280 8296 Page 16.36
Cost & Management Accounting CA Purushottam Sir
(iii) The proposed sales mix increases the total contribution to sales ratio from 47.5% to 50% and
the total profit from Rs. 10,50,000 to Rs. 14,00,000. Thus, the proposed sales mix should be
accepted.
Question 33
K Ltd. produces and markets a very popular product called ‘X’. The company is interested in
presenting its budget for the second quarter of 2020. The following information are made
available for this purpose:
(i) It expects to sell 1,50,000 bags of ‘X’ during the second quarter of 2020 at the selling
price of Rs.1,200 per bag.
(ii) Each bag of ‘X’ requires 2.5 mtr. of raw – material ‘Y’ and 7.5 mtr. of raw – material ‘Z’.
(iii) Stock levels are planned as follows:
(iv) ‘Y’ cost Rs.160 per mtr., ‘Z’ costs Rs.30 per mtr. and ‘Empty Bag’ costs Rs.110 each.
(v) It requires 9 minutes of direct labour to produce and fill one bag of ‘X’. Labour cost is Rs.
70 per hour.
(vi) Variable manufacturing costs are Rs.60 per bag. Fixed manufacturing costs Rs.40,00,000
per quarter.
(vii) Variable selling and administration expenses are 5% of sales and fixed administration
and selling expenses are Rs.3,75,000 per quarter.
Required
(i) PREPARE a production budget for the said quarter in quantity.
(ii) PREPARE a raw – material purchase budget for ‘Y’, ‘Z’ and ‘Empty Bags’ for the said
quarter in quantity as well as in rupees.
(iii) COMPUTE the budgeted variable cost to produce one bag of ‘X’.
Solution
(i) Production Budget of „X‟ for the Second Quarter
Particulars Bags (Nos.)
Budgeted Sales 1,50,000
Add: Desired Closing stock 33,000
Total Requirements 1,83,000
Less: Opening stock (45,000)
(ii) Raw–Materials Purchase Budget in Quantity as well as in Rs. for 1,38,000 Bags of „X‟
Particulars „Y‟ „Z‟ Empty Bags
Mtr. Mtr. Nos.
Production Requirements 2.5 7.5 1.0
Per bag of ‘X’
Requirement for 3,45,000 10,35,000 1,38,000
Production (1,38,000 × (1,38,000 × (1,38,000 × 1)
2.5) 7.5)
Add: Desired Closing Stock 78,000 1,41,000 84,000
Total Requirements 4,23,000 11,76,000 2,22,000
Less: Opening Stock (96,000) (1,71,000) (1,11,000)
Quantity to be purchased 3,27,000 10,05,000 1,11,000
Cost per mtr./Bag Rs.160 Rs.30 Rs.110
Cost of Purchase (Rs.) 5,23,20,000 3,01,50,000 1,22,10,000
Particulars
(Rs.)
Raw – Material
Y 2.5 mtr @160 400.00
Z 7.5 mtr @30 225.00
Empty Bag 110.00
Direct Labour (Rs.70× 9 minutes / 60 minutes) 10.50
Variable Manufacturing Overheads 60.00
Variable Cost of Production per bag 805.50
Question 34
Woolmark Ltd. manufactures three types of products namely P, Q and R. The data relating to a
period are as under:
Particulars P Q R
Machine hours per unit 10 18 14
Direct Labour hours per unit 4 12 8
Direct Material per unit (Rs.) 90 80 120
Production (units) 3,000 5,000 20,000
Currently the company uses traditional costing method and absorbs all production overheads on
the basis of machine hours. The machine hour rate of overheads is Rs. 6 per hour. Direct labour
hour rate is Rs. 20 per hour.
The company proposes to use activity based costing system and the activity analysis is as under:
Particulars P Q R
Batch size (units) 150 500 1,000
Number of purchase orders per batch 3 10 8
Number of inspections per batch 5 4 3
Required
(i) CALCULATE the cost per unit of each product using traditional method of absorbing all
production overheads on the basis of machine hours.
(ii) CALCULATE the cost per unit of each product using activity based costing principles.
Solution
Particulars of Costs P Q R
(Rs.) (Rs.) (Rs.)
Direct Materials 90 80 120
Direct Labour [(4, 12, 8 hours) x Rs. 20] 80 240 160
Production Overheads [(10, 18, 14 hours) x Rs. 6] 60 108 84
Cost per unit 230 428 364
Products P Q R
Production (units) 3,000 5,000 20,000
(Rs.) (Rs.) (Rs.)
Direct Materials (90, 80, 120) 2,70,000 4,00,000 24,00,000
Direct Labour (80, 240, 160) 2,40,000 12,00,000 32,00,000
Machine Related Costs @ Rs. 1.80 per hour
(30,000, 90,000, 2,80,000) 54,000 1,62,000 5,04,000
Setup Costs @ Rs. 9,600 per setup
(20, 10, 20) 1,92,000 96,000 1,92,000
Inspection Costs @ Rs. 4,800 per
inspection 4,80,000 1,92,000 2,88,000
(100, 40, 60)
Purchase Related Costs @ Rs. 750 per
Workings
Particulars P Q R Total
A. Production (units) 3,000 5,000 20,000
B. Batch Size (units) 150 500 1,000
C. Number of Batches (A÷B) 20 10 20 50
D. Number of Purchase Order per batch 3 10 8
E. Total Purchase Orders [C x D] 60 100 160 320
F. Number of Inspections per batch 5 4 3
G. Total Inspections [C x F] 100 40 60 200
Particulars P Q R
A. Machine Hours per unit 10 18 14
B. Production (units) 3,000 5,000 20,000
C. Total Machine Hours [A x B] 30,000 90,000 2,80,000
Cost Pool % Overheads Cost Driver Basis Cost Cost Driver Rate
Driver
(Rs.) (Units) (Rs.)
Setup 20% 4,80,000 Number of batches 50 9,600 per Setup
Inspection 40% 9,60,000 Number of inspections 200 4,800 per Inspection
Purchases 10% 2,40,000 Number of purchases 320 750 per Purchase
MachineHours 30% 7,20,000 Machine Hours 4,00,000 1.80 per Machine Hour
Question 35
BABYSOFT is a global brand created by Bio-organic Ltd. The company manufactures three
ranges of beauty soaps i.e. BABYSOFT- Gold, BABYSOFT- Pearl, and BABYSOFT- Diamond.
The budgeted costs and production for the month of December, 2020 are as follows:
Diamond
Production of soaps (Units) 4,000 3,000 2,000
Resources per Unit: Qty Rate Qty Rate QtyRate
- Essential Oils 60 ml Rs. 200 / 100 ml 55 ml Rs. 300 / 100 ml 65 ml
Rs. 300 / 100
ml
- Cocoa Butter 20 g Rs. 200 / 100 g 20 g Rs. 200 / 100 g 20 g Rs. 200 / 100 g
- Filtered Water 30 ml Rs. 15 / 100 ml 30 ml Rs. 15 / 100 ml 30 ml Rs. 15 / 100 ml
- Chemicals 10 g Rs. 30 / 100 g 12 g Rs. 50 / 100 g 15 g Rs. 60 / 100 g
- Direct Labour 30 Rs. 10 / hour 40 Rs. 10 / hour 60 Rs. 10 / hour
minutes minutes minutes
Bio-organic Ltd. followed an Absorption Costing System and absorbed its production overheads,
to its products using direct labour hour rate, which were budgeted at Rs. 1,98,000.
Now, Bio-organic Ltd. is considering adopting an Activity Based Costing system. For this,
additional information regarding budgeted overheads and their cost drivers is provided below:
Particulars (Rs.) Cost drivers
Forklifting cost 58,000 Weight of material lifted
Supervising cost 60,000 Direct Labour hours
Utilities 80,000 Number of Machine operations
The number of machine operators per unit of production are 5, 5, and 6 for BABYSOFT- Gold,
BABYSOFT- Pearl, and BABYSOFT- Diamond respectively.
(Consider (i) Mass of 1 litre of Essential Oils and Filtered Water equivalent to 0.8 kg and 1 kg
respectively (ii) Mass of output produced is equivalent to the mass of input materials taken
together.)
Unit Costs:
BABYSOFT- BABYSOFT- BABYSOFT-
Gold (Rs.) Pearl (Rs.) Diamond (Rs.)
Direct Costs:
- Direct Labour 5.00 6.67 10.00
(10x30) (10x40) (10x60)
60 60 60