Professional Documents
Culture Documents
PROGRESS PAY 19 - Kirim2
PROGRESS PAY 19 - Kirim2
PROGRESS PAY 19 - Kirim2
ANNEX - 2. KOMERSIAL
PROGRESS PAYMENT 25 APRIL 2021 - 24 MAY 2021
CLAIM
PROGRESS
19
Date Periode
25 May 2021 - 24 June 2021
PHASE - I
COMMERCIAL AREA + TOWER A
BUILDING
Owner
PT. SINDELI PROPERTINDO ABADI
Sub Contractor
PT. KARYATAMA MAKMUR PERKASA
Main Contractor
MCC - STK JO
PROYEK
STAR PROJECT - PHASE 1
ak, Pekayon, Jakarta Timur
LAIM
OGRESS
19
e Periode
21 - 24 June 2021
HASE - I
BUILDING
Owner
ROPERTINDO ABADI
Contractor
MA MAKMUR PERKASA
n Contractor
C - STK JO
MCC-STK JO
Project : PILING, STRUCTURE, ARCHITECTURE, MECHANICAL, ELECTRICAL AND PLUMBING INCLUDING LANDSCAPE WORK PACKAGES
FOR JKT LIVING STAR PHASE 1 PROJECT
Subcontractor : PT. Karyatama Makmur Perkasa
Scope of Work : Supply and Install RC Structural Works
Contract Ref : MCCSTK/JLSP1/LOA/KMP/004
Payment Cert. No. : 19
SUMMARY 合计
% of work done 17% 17% 51% 18%
1 BILL No 1 PRELIMINARY WORKS 4,008,000,000 3,748,572,760 93.53% 259,427,240 6.47% 4,008,000,000
准备工作及临时设施等(预备工作)
Sub-total Bill No. 2.1.3 14,861,904,418 14,262,855,857 96.0% 288,580,453 1.9% 14,551,436,310
Sub-total Bill No. 2.1.3 8,234,398,064 7,338,484,047 89.1% 218,512,163 2.7% 7,556,996,210
4 Sub-total for Bill No. 2.1.3 + Bill No. 2.2.3 23,096,302,482 21,601,339,903 93.53% 507,092,616 2.20% 22,108,432,520
Subbmitted By
Sub Contractor
PT. KARYATAMA MAKMUR PERKASA
GAO YUAN
Cost Control Manager
MCC-STK JO
To Date
累计付款 [3] = [1]+[2]
%
WD %
100%
75.3%
104.0%
84.1%
106.9%
97.91%
75.3%
106.9%
86.9%
92.6%
91.8%
95.72%
96.4%
90.8%
100.0%
-100.0%
87.6%
83.3%
Subbmitted By
Sub Contractor
PT. KARYATAMA MAKMUR PERKASA
GAO YUAN
Cost Control Manager
PROGRESS PAYMENT 25 MAY 2021 - 24 JUNE 2021
PRELIMINARY WORKS
Project : PILING, STRUCTURE, ARCHITECTURE, MECHANICAL, ELECTRICAL AND PLUMBING INCLUDING LANDSCAPE WORK PACKAGES
Subcontractor : PT. Karyatama Makmur Perkasa
Scope of Work : Supply and Install RC Structural Works
Contract Ref : MCCSTK/JLSP1/LOA/KMP/004
PC No. : 19
Previous Payment 已付款 This Interim Payment 本次付款 [2] To Date 累计付款
Original Contract 原合同
No
Item Description [3] = [1]+[2]
工程项目 Amount Amount %
[1] Amount % Amount %
序号 总价 (Rp) 总价 (Rp) 总价 (Rp) 总价 (Rp)
the Works for the approval of the Main-Contractor. The provision of the organisation chart and the Main-Contractor's
approval thereof shall not limit the Sub-Contractor's responsibility and obligations in respect of adequate staffing and
in the event additional staff are considered necessary to properly and effectively supervise the execution of the
Works, the Sub-Contractor shall provide such additional staff at no extra cost to the Main-Contractor.
None of the senior site supervisory staff may be changed wihout the prior approval of the Main-Contractor.
分包提供项目管理人员及其所有的费用
分包提供项目管理组织结构呈交给总包批准,如组织结构人员不能满足分包工作的责任和义务,
总包认为有必要替换或增加合格人员以适当和有效地监督工程的执行,分包必须配合,无任何增
加费用。
未经总包方同意项目管理组织结构人员不得更换。
负责自身工程范围内的设备及工具进出场费,包括:进场许可费用及场内二次转运费用以及完工 包含 包含 包含 包含
后的退场费。
Preliminary Page 6 of 36
Previous Payment 已付款 This Interim Payment 本次付款 [2] To Date 累计付款
Original Contract 原合同
No
Item Description [3] = [1]+[2]
工程项目 Amount Amount %
[1] Amount % Amount %
序号 总价 (Rp) 总价 (Rp) 总价 (Rp) 总价 (Rp)
安全措施费
D The Sub-Contractor shall allow for all costs incurred in complying with the requirements of the Environmetal, Health Include Include Include Include
and Safety specification from Main-Contractor, Construction Management (MK), SMK3 Act, and as required by law
and local goverment regulations.
分包要满足总包、监理、SMK3、政府的法律和条例要求并承担所有的费用。 包含 包含 包含 包含
To Summary Preliminary Works 准备工作及临时设施等 (Page 1) 3,486,000,000 3,260,360,439 93.53% 225,639,561 6.47% 3,486,000,000 100.00%
Contract Document
合同文件
A Shall allow for all costs incurred in preparing contract document. Include Include Include Include
负责合同文件。 包含 包含 包含 包含
总包提供一套施工图纸和技术规范,分包根据工作需求准备足够数量的施工图和技术规范。 包含 包含 包含 包含
C Sub-Contractor shall prepare and submit 3 sets of shop drawing complete with Proffesional Engineer (PE) calculation 60,000,000 56,116,359 93.5% 3,883,641 6.5% 60,000,000 100.00%
and endorsement (If needed) to Main-Contractor for approval.
分包负责和准备提交三份施工方案、二次深化图设计及专业结构工程师签字盖章的详细计算,由
总包审批直至同意。
D Sub-Contractor shall prepare and submit as-built drawing (CAD & PDF) with 1 set of tracing drawing paper, 4 sets of 40,000,000 37,410,906 93.5% 2,589,094 6.5% 40,000,000 100.00%
blue-print, and 1 set coft copy (CD) to Main-Contractor and approval.
Preliminary Page 7 of 36
Previous Payment 已付款 This Interim Payment 本次付款 [2] To Date 累计付款
Original Contract 原合同
No
Item Description [3] = [1]+[2]
工程项目 Amount Amount %
[1] Amount % Amount %
序号 总价 (Rp) 总价 (Rp) 总价 (Rp) 总价 (Rp)
F Samples of materials and plant intended for incorporation into the Works are to be submitted to the Main-Contractor Include Include Include Include
for approval prior to ordering of bulk quantities.
The insertion of the name of any manufacturer or proprietary article on the Drawings or in the Specification is to be
read as an indication of the class or quality of materials and plant required: materials or plant of equal quality may be
obtained from any other source subject to the prior approval of the Main-Contractor.
按照总包及技术规范要求提供材料的样板/产品说明书。在总包审核通过后方可作为施工材料。 包含 包含 包含 包含
按照技术规范要求、分包提供4份质量保证书、保修及操作手册。 包含 包含 包含 包含
To Summary Preliminary Works 准备工作及临时设施等 (Page 2) 120,000,000 112,232,717 93.53% 7,767,283 6.47% 120,000,000 100.00%
按照总包及技术规范要求分包必须检查、检验所呈交的材料,包括不符合规定的工程材料的重新 包含 包含 包含 包含
检验。
分包要保持临时建筑的清洁、卫生、维修、维护,包括维修人工材料费用。如果分包没有按总包
的要求做,总包有权利扣除其相应的费用。
分包要提供临时排水工作包括人工和设备, 将雨水排流到总包指定的不妨碍施工的地点,保证其
施工作业面干燥不影响施工质量。(不含STP的降水工程)
Temporary Access
临时道路
D The Sub-Contractor shall allow for maintaining extrance gate, temporary roads, hardstandings, working platforms, Include Include Include Include
bridges, crossings, and the like necessary for carry out the Works and make good all damage done.
分包负责对现场已有的施工道路、大门进行维护维修。如因其施工对道路造成的损坏负责修整、 包含 包含 包含 包含
恢复。
Removal of Rubbish
垃圾清运
E Construction waste or rubbish or surplus materials and the like are to be removed from the Site by MC by Main Con by Main Con by Main Con by Main Con
Washing Bay
洗车场
F The Sub-Contractor shall allow to maintain and clean Washing Bay facility off from mud and provide labour to operate Include Include Include Include
the Washing Bay.
分包负责洗车桥的淤泥清除并提供工人在洗车场服务。 包含 包含 包含 包含
To Summary Preliminary Works 准备工作及临时设施等 (Page 3) 306,000,000 286,193,429 93.53% 19,806,571 6.47% 306,000,000 100.00%
Fire Protection
消防
A The Sub-Contractor shall allow for keeping the Site from fire hazard. The Sub-Contractor shall take all necessary Include Include Include Include
precautions including those specified by the Insurer of the Works and shall provide all necessary fire fighting
equipment to the satisfaction of the Main-Contractor.
No inflammable goods such as fuel oils, oil based paints, kerosene,thinners, cellulose lacquers, bitumen, bitumen
based products and the like shall be stored in the building under construction.
Preliminary Page 9 of 36
Previous Payment 已付款 This Interim Payment 本次付款 [2] To Date 累计付款
The Sub-Contractor shall allow for keeping the Site from fire hazard. The Sub-Contractor shall take all necessary Original Contract 原合同
No precautions including those specified by the Item Description
Insurer of the Works and shall provide all necessary fire fighting [3] = [1]+[2]
equipment to the satisfaction of the Main-Contractor.
工程项目 Amount Amount %
[1] Amount % Amount %
No inflammable goods such as fuel oils, oil based paints, kerosene,thinners, cellulose lacquers, bitumen, bitumen
序号 based products and the like shall be stored in the building under construction. 总价 (Rp) 总价 (Rp) 总价 (Rp) 总价 (Rp)
分包方在施工期间,根据消防局及保险公司的有关规定,现场上必须配备充足的消防设备。分包 包含 包含 包含 包含
方应配置受过以上有过专门训练的施工人员
分包商工作地点应确保具有足够的照明,负责从总包单位提供的定点配电箱,接入至工作点位的 包含 包含 包含 包含
电线、电缆、配电箱、用电设备、照明、维护等相关工作及费用。
分包负责从总包提供的楼层给水点接入,负责相关的安装、维修费用,包括材料、人工及后续相 包含 包含 包含 包含
应工作。
在总包要求下,分包商负责工程的测量工作,提供足够数量、有合格资质的测量员担任此工作。
并配合总包、监理仔细保护和保存现场测量基准点,基准点移位或丢失,必须及时恢复;负责布
置、校验工程各部分的标高、轴线;如分包商给出的工程任何部分的位置、标高、及尺寸出现误
差或基准点的遗失均是分包商的责任,分包商应协助监理完成上述的整改。
PEST Control
现场害虫防治
E The Main-Contractor shall be repsonsible for the PEST control on Site. by MC by MC by MC by MC
总包负责现场害虫防治。 总包负责 总包负责 总包负责 总包负责
To Summary Preliminary Works 准备工作及临时设施等 (Page 4) 96,000,000 89,786,174 93.53% 6,213,826 6.47% 96,000,000 100.00%
Preliminary Page 10 of 36
Previous Payment 已付款 This Interim Payment 本次付款 [2] To Date 累计付款
Original Contract 原合同
No
Item Description [3] = [1]+[2]
工程项目 Amount Amount %
[1] Amount % Amount %
序号 总价 (Rp) 总价 (Rp) 总价 (Rp) 总价 (Rp)
Project Insurance
项目保险
A Construction All Risk by MC by MC by MC by MC
施工全险 总包负责 总包负责 总包负责 总包负责
C The Sub-Contractor shall responsible to provide insurance for his own machinery or equipment to carry out the Include Include Include Include
Works.
分包提供其施工设备、机具保险。 包含 包含 包含 包含
D The Sub-Contractor shall assist Main-Contractor to prepare all of the required documents or information to process Include Include Include Include
any kind of Insurance Claims. Any related additional expenses or cost that may incurred shall be borne by Sub-
Contractor.
分包协助总包提供办理保险索赔所需要的全部支持文件,所引起的费用由分包承担。 包含 包含 包含 包含
Compensation Claims
纠纷、索赔
E The Sub-Contractor shall responsible for any compensation claims from his own workers or subcontractors or Include Include Include Include
suppliers or any other third parties.
分包负责他的工人、分包、供应商、其他的第三方的纠纷、索赔。 包含 包含 包含 包含
分包有责任协助所有政府部门的检查并承担因其原因造成的罚款及其他费用。 包含 包含 包含 包含
Preliminary Page 11 of 36
Previous Payment 已付款 This Interim Payment 本次付款 [2] To Date 累计付款
Original Contract 原合同
No
Item Description [3] = [1]+[2]
工程项目 Amount Amount %
[1] Amount % Amount %
序号 总价 (Rp) 总价 (Rp) 总价 (Rp) 总价 (Rp)
To Summary Preliminary Works 准备工作及临时设施等 (Page 5) include include - include - include -
SUB-TOTAL 小计
Page 1 第 1页 3,486,000,000 3,260,360,439 93.53% 225,639,561 6.47% 3,486,000,000 100.00%
Page 2 第 2页 120,000,000 112,232,717 93.53% 7,767,283 6.47% 120,000,000 100.00%
Page 3 第 3页 306,000,000 286,193,429 93.53% 19,806,571 6.47% 306,000,000 100.00%
Page 4 第 4页 96,000,000 89,786,174 93.53% 6,213,826 6.47% 96,000,000 100.00%
Page 5 第 5页 include include include include
Preliminary Page 12 of 36
PROGRESS PAYMENT 25 MAY 2021 - 24 JUNE 2021
RC STRUCTURAL WORK
Project : PILING, STRUCTURE, ARCHITECTURE, MECHANICAL, ELECTRICAL AND PLUMBING INCLUDING LANDSCAPE WORK PACKAGES
Subcontractor : PT. Karyatama Makmur Perkasa
Scope of Work : Supply and Install RC Structural Works
Contract Ref : MCCSTK/JLSP1/LOA/KMP/004
PC No. : 19
Original Contract 原合同 Previous Payment 已付款 [1] This Interim Payment 本次付款 [2] To Date 累计付款 [3] = [1]+[2]
No Item Description Unit Rate Amount Qty Amount % Qty Amount % Qty Amount %
Prov. Qty Remarks 备注
工程项目 单价 总价 总价 总价 总价
序号 单位 数量 Rp Rp 数量 Rp 数量 Rp 数量 Rp
土方开挖工程量计算按照混凝土结构尺寸。土方工程单价包含土
方转运到总包指定的堆土地点, 临时道路。
A Open cut excavation for basement (refer to signed Works Order ref: Is 1.00 323,000,000 323,000,000 3,707.77 315,160,301 97.6% - - 0.0% 3,707.77 315,160,301 97.6%
MCCSTK/JLSP1/WO/KMP/001 dated 03/03/202)
筏板基础、井坑、承台、地梁的土方开挖、土方场内转运、砖胎
膜周边回填及夯实。(详见签的合同编号:MCCSTK/JLSP1/WO/
KMP/001 日期 03/03/2020)
B Excavation Works 土方开挖。 m3 58,000 Rate only 1,012.82 58,743,306 0.0% - - 1,012.82 58,743,306
C Surface Treatment for Ground Slab, Ground Beam, Tie-Beam, Pilecap, Raft m2 2,761.60 10,000 27,616,040 2,703.15 27,031,451 97.9% - - 0.0% 2,703.15 27,031,451 97.9%
Foundation, Sum Pit, Lift Pit etc. Soil Compaction as specified
按照技术规范的基础底板、梁、承台等场地平整压实 .
D Remove surplus excavated material from site (off site) 土方外运 ls 1.00 N/A -
E Filling with selected excavated material from stockpile, deposited and m3 2,302.46 96,585 222,383,099 - - 0.0% - - 0.0% - - 0.0%
compacted as specified
土方回填及素土夯实工程。
Cut of pile heads including bending rebar for incorporation into raft
foundations and pile caps 截桩头:
F Cut off pile heads size 500mm x 500mm and remove to nominated location no 807.00 187,000 150,909,000 925.00 172,975,000 114.6% - - 0.0% 925.00 172,975,000 114.6%
桩尺寸 500mm x 500mm 截桩头包括运至场内指定地点
Anti-termite Treatment
G Prepare and apply anti-termite treatment complete with guarantee as m2 3,287.00 17,000 55,879,000 4,553.02 77,401,331 138.5% - - 0.0% 4,553.02 77,401,331 113.7%
specified
按照技术规范要求白蚁防治工程
A Raft foundation 筏板基础 m2 1,475.92 20,000 29,518,400 1,532.30 30,646,000 103.8% - - 0.0% 1,532.30 30,646,000 106.5%
B Pile caps 承台 m2 267.71 20,000 5,354,240 379.00 7,580,000 141.6% - - 0.0% 379.00 7,580,000 157.9%
C Basement Slab 半地下室 m2 1,496.50 20,000 29,930,000 952.27 19,045,364 63.6% - - 0.0% 952.27 19,045,364 76.6%
D Tie-Beam 基础梁、连系梁 m2 119.07 20,000 2,381,400 220.82 4,416,436 185.5% - - 0.0% 220.82 4,416,436 166.9%
Note 说明:
Ready Mixed Concrete supply by Main Contractor 混凝土甲供:
the temponary price in BOQ will be changed according as follows:
BOQ 清单里暂定的混凝土单价将按以下进行调整:
1. Sub-Con's price Rp173,000/m3 when concrete supply by concrete supplier
外购商品混凝土
C Reinforcement concrete foundation in generator, diesel fuel tank, pump, m3 44.61 173,000 7,717,887 38.74 6,265,212 81.2% - - 0.0% 38.74 6,265,212 81.2%
gondola, lightning rod
发电机,柴油罐,泵 ,擦窗机,避雷针混凝土基础
Reinforcing steel complete with tie wires and fixing accessories as specified
钢筋工程
A General reinforcing bars, stirrups, and links in Raft foundation 筏板基础 kg 631,820.90 1,800 1,137,277,611 328,960.90 592,129,624 52.1% - - 0.0% 328,960.90 592,129,624 52.1%
B Ditto, Column 柱 kg 395,759.25 1,800 712,366,650 436,451.82 785,222,270 110.2% 4,327.76 8,180,968 1.1% 440,779.58 793,403,238 111.4% Annex1-F2
C Ditto, Shear Wall/Core Wall 剪力墙/核心筒 kg 145,023.78 1,800 261,042,805 132,485.59 238,312,854 91.3% 2,593.05 4,828,695 1.8% 135,078.64 243,141,549 93.1% Annex1-F3
D Ditto, Pile Cap 承台 kg 60,580.18 1,800 109,044,320 29,208.17 52,574,706 48.2% - - 0.0% 29,208.17 52,574,706 48.2%
E Ditto, Tie-Beam 连系梁 kg 43,542.53 1,800 78,376,558 21,233.07 38,219,523 48.8% - - 0.0% 21,233.07 38,219,523 48.8%
F Ditto, Beam 梁 kg 534,001.69 1,800 961,203,034 605,829.04 1,090,492,277 113.5% 5,799.60 10,439,280 1.1% 611,628.64 1,100,931,556 114.5% Annex1-F6
G Ditto, Slab 板 kg 409,597.87 1,800 737,276,158 211,365.50 380,457,893 51.6% 2,122.52 3,820,544 0.5% 213,488.02 384,278,437 52.1% Annex1-F7
H Dittto, Retaining Wall Basement 地下室支护墙 kg 58,580.71 1,800 105,445,274 41,479.17 74,662,497 70.8% - - 0.0% 41,479.17 74,662,497 70.8%
I Ditto, Exterior Wall 外墙 kg 45,156.52 1,800 81,281,733 22,104.07 39,787,320 48.9% 5.32 9,583 0.0% 22,109.39 39,796,903 49.0% Annex1-F9
J Ditto, Ramp and Parapet Ramp 坡道及坡道护墙坡道 kg 13,236.57 1,800 23,825,831 22,043.18 39,677,729 166.5% - - 0.0% 22,043.18 39,677,729 166.5%
K Ditto, Pit lift, Sewagepit,Grease Trap, Balok dudukan roof tank, lift separator kg 36,171.21 1,800 65,108,174 1,452.13 2,613,835 4.0% - - 0.0% 1,452.13 2,613,835 4.0%
beam
井坑,污水坑,润滑脂分离器,屋顶水箱的梁架,电梯的梁间隔
材
L Ditto, Reinforcement concrete foundation in generator, diesel fuel tank, kg 6,509.05 1,800 11,716,293 8,617.83 15,512,100 132.4% - - 0.0% 8,617.83 15,512,100 132.4%
pump, gondola, lightning rod
发电机,柴油罐,泵 ,擦窗机,避雷针混凝土基础
M Ditto, Emergency & Retail Staircase 消防楼梯及商业区楼梯 kg 29,640.00 1,800 53,352,000 17,166.33 30,899,391 57.9% 490.70 883,255 1.7% 17,657.03 31,782,646 59.6% Annex1-F13
N Wiremesh 钢筋网片 (34.76kg/2.1mx2.4m) ### m2 4,500 Rate Only 52,584.73 236,631,304 352.24 1,585,080 52,936.97 238,216,384 Annex1-F14
To Summary 2.1.3.3 Rebar Works 钢筋工程 kg 2,409,620 4,337,316,441 2,241,064.52 3,617,193,323 17,768.29 29,747,404 2,258,832.81 3,646,940,727
93.00% 0.74% 93.74%
Note 说明:
Aluminium Formwork syupply by Main Contractor 铝合金模板甲供:
the temponary formwork price in BOQ will be changed according as follows:
BOQ 清单里暂定的模板单价将按以下进行调整:
1. Sub-Con's price Rp153,000/m2 when used timber formwork 木模板价格
2. Sub-Con's price Rp 80,000/m2 when used aluminium formwork 铝合金模板价格
M Foundation in generator, diesel fuel tank, pump, gondola, lightning rod m2 295.16 153,000 45,158,728 218.21 32,125,043 71.1% - - 0.0% 218.21 32,125,043 71.1%
发电机,柴油罐,泵 ,擦窗机,避雷针混凝土基础
N Emergency & Retail Staircase 消防楼梯及商业区楼梯 m2 437.00 153,000 66,861,000 246.31 37,306,482 55.8% 24.92 3,621,499 5.4% 271.22 40,927,981 61.2% Annex1-D11
Basement - 4th Floor, Roof
O Extra over for Gutter 200 x 70 ( Tower A Basement) m2 1.00 153,000 rate only - - 0.0% - - - -
To Summary 2.1.3.4 Formworks 模板工程 68,822 7,555,488,143 73,503.15 7,841,689,284 103.8% 1,633.16 236,121,908 3.1% 75,136.31 8,077,811,191 106.9%
106.80% 2.37% 109.18%
Original Contract 原合同 Previous Payment 已付款 [1] This Interim Payment 本次付款 [2] To Date 累计付款 [3] = [1]+[2]
No Item Description Unit Rate Amount Qty Amount % Qty Amount % Qty Amount %
Prov. Qty Remarks 备注
工程项目 单价 总价 总价 总价 总价
序号 单位 数量 Rp Rp 数量 Rp 数量 Rp 数量 Rp
2.2.3.1 Earthworks 土方工程
Note : Excavation
Earthworks 土方 is measured net, any allowance for working space
should be included in the unit rates. Excavation works shall include
moving excavated soil to designated stockpile location as per Main-
Contractor's Instruction and temporary access road.
土方开挖工程量计算按照混凝土结构尺寸。土方工程单价包含土方转运
到总包指定的堆土地点, 临时道路。
A Excavation for Sewage Treatment Plant (STP), commencing from m3 344.30 58,000 19,969,516 - - 0.0% - - 0.0% - 0.0%
bottom of basement excavation 污水处理池 的土方开挖。
B Excavation for Pit Lift, commencing from bottom of basement m3 22.00 58,000 1,276,000 - - 0.0% - - 0.0% - 0.0%
excavation
井坑 的土方开挖。
C Excavation for Pile Caps, commencing from bottom of basement m3 535.16 58,000 31,039,338 - - 0.0% - - 0.0% - 0.0%
excavation 承台的土方开挖。
D Surface Treatment for Ground Slab, Ground Beam, Tie-Beam, m2 1,896.00 10,000 18,960,000 3,546.88 35,468,810 187.1% 17.12 171,234 0.9% 3,564.00 35,640,044 188.0%
Pilecap, Raft Foundation, Sum Pit, Lift Pit etc. Soil Compaction as
specified
按照技术规范的基础底板、梁、承台等场地平整压实 .
E Remove surplus excavated material from site (Off Site) 土方外运 ls 1.00 N/A
F Filling with selected excavated material from stockpile, deposited and m3 3,036.26 96,585 293,257,172 973.26 94,002,139 32.1% - - 0.0% 973.26 94,002,139 32.1%
compacted as specified 土方回填工程及素土夯实。
Cut of pile heads including bending rebar for incorporation into pile
G capsoff
Cut 截桩头:
pile heads 500 mm x 500 mm and remove from site no 308.00 187,000 239.00 44,693,000 77.6% - - 0.0% 239.00 44,693,000 77.6%
57,596,000
500 mm x 500 mm 截桩头包括运至场内指定地点堆放
Anti-termite Treatment 白蚁防治工程
H Prepare and apply anti-termite treatment complete with guarantee as m2 3,993.76 17,000 67,893,837 8,598.23 146,169,854 215.3% 347.77 5,912,131 8.7% 8,946.00 152,081,985 224.0%
specified 按照技术规范要求白蚁防治工程
Sand bed 100mm thick including compation under:
砂垫层,厚度=100mm,包括下部的压实:
I Pile caps 承台 m2 466.36 38,000 17,721,832 793.95 30,170,100 170.2% - - 0.0% 793.95 30,170,100 170.2%
J STP 污水处理池 m2 344.30 38,000 13,083,476 - - 0.0% - - 0.0% - - 0.0%
K Basement Slab 地下室 m2 1,539.03 38,000 58,483,178 1,732.68 65,841,692 112.6% - - 0.0% 1,732.68 65,841,692 112.6%
L Tie-Beam 连系梁 m2 205.70 38,000 7,816,638 506.61 19,251,366 246.3% 17.12 650,689 8.3% 523.74 19,902,055 254.6%
To Summary 2.2.3.2 Reinforcement Concrete Works 混凝土工程 937,636,118 973,703,041 28,245,110 1,001,948,151
Note :
Formworks rates stated above shall comprise of different types of
system formworks such as (Aluminum Formworks, Table Form
Formworks, Conventional Formworks & etc)
The breakdown of the payment shall be as per following claim and
subject to assessment :
Concrete m3 100%
Vibrated Reinforced Concrete 90%
Post Concrete / Making Good Defects 5%
Structural Water Ponding Test 5%
Rebars kg 100%
Laying of Rebars 95%
Cleaning of Rebars 5%
Formworks m2 100%
Erection and Installation of Formworks 70%
Formworks Dismantling 25%
Housekeeping and Cleaning upon Handling Over which shall be done 5%
within one month of Formwork Dismantling at each floor
A1 Lean Concrete fc'15 Mpa Raft foundation m2 20,000 1,532 1,532 1,532 30,646,000 1,532 1,532 1,532 30,646,000
A2 Lean Concrete fc'15 Mpa Pile caps m2 20,000 379 379 379 7,580,000 379 379 379 7,580,000
A3 Lean Concrete fc'15 Mpa Basement Slab m2 20,000 952 952 952 19,045,364 952 952 952 19,045,364
A4 Lean Concrete fc'15 Mpa Tie-Beam m2 20,000 221 221 221 4,416,436 221 221 221 4,416,436
B1 Concreting fc'40 Mpa Column m3 173,000 825 774 774 141,834,713 825 774 774 141,834,713
B2 Concreting fc'40 Mpa Shear Wall/Core Wall m3 173,000 296 270 270 50,749,118 296 270 270 50,749,118
B3 Concreting fc'35 Mpa Column m3 173,000 427 386 386 73,093,303 427 386 386 73,093,303
B4 Concreting fc'35 Mpa Shear Wall/Core Wall m3 173,000 253 228 228 43,350,383 253 228 228 43,350,383
B5 Concreting fc'30 Mpa Raft foundation m3 173,000 3,004 3,004 3,004 519,748,610 3,004 3,004 3,004 519,748,610
B6 Concreting fc'30 Mpa Column m3 173,000 131 - - 20,440,763 156 - - 24,225,207
B7 Concreting fc'30 Mpa Shear Wall/Core Wall m3 173,000 94 - - 14,682,531 164 - - 25,549,881
B8 Concreting fc'30 Mpa Pile Cap m3 173,000 346 346 346 59,863,190 346 346 346 59,863,190
B9 Concreting fc'30 Mpa Tie-Beam m3 173,000 44 44 44 7,679,470 44 44 44 7,679,470
B10 Concreting fc'30 Mpa Beam m3 173,000 1,489 1,172 1,172 252,172,311 1,506 1,172 1,172 254,783,240
B11 Concreting fc'30 Mpa Slab m3 173,000 3,714 2,981 2,981 629,859,569 3,745 2,981 2,981 634,719,838
B12 Concreting fc'30 Mpa Retaining Wall Basement m3 173,000 413 413 413 71,420,663 413 413 413 71,420,663
B13 Concreting fc'30 Mpa Exterior Wall m3 173,000 792 - - 123,263,108 792 - - 123,374,745
B14 Concreting fc'30 Mpa Ramp and Parapet Ramp m3 173,000 145 145 145 25,113,237 145 145 145 25,113,237
B15 Concreting fc'30 Mpa Pit lift, Sewagepit,Grease Trap, Balok m3 173,000 9 9 9 1,635,629 9 9 9 1,635,629
dudukan roof tank, lift separator beam.
B16 Concreting fc'30 Mpa Reinforcement concrete foundation in m3 173,000 39 13 13 6,265,212 39 13 13 6,265,212
generator, diesel fuel tank, pump,
gondola, lightning rod.
B17 Concreting fc'25 Mpa Emergency & Retail Staircase m3 173,000 107 83 83 18,019,405 110 83 83 18,495,916
B1 Concreting fc'40 Mpa Column m3 173,000 608 274 268 99,404,028 628 276 271 102,437,936
B2 Concreting fc'40 Mpa Shear Wall/Core Wall m3 173,000 58 13 13 9,255,859 58 13 13 9,255,859
B3 Concreting fc'30 Mpa Pile Cap m3 173,000 479 - - 74,591,199 479 - - 74,591,199
B4 Concreting fc'30 Mpa Tie-Beam m3 173,000 168 37 36 26,748,955 168 37 36 26,748,955
B5 Concreting fc'30 Mpa Beam m3 173,000 763 318 317 124,297,256 809 318 317 131,470,316
B6 Concreting fc'30 Mpa Slab m3 173,000 2,591 1,032 1,032 421,257,485 2,696 1,051 1,051 437,962,643
B7 Concreting fc'30 Mpa Retaining Wall Basement m3 173,000 544 187 187 87,938,495 544 187 187 87,938,495
B8 Concreting fc'30 Mpa Ramp and Parapet Ramp m3 173,000 30 - - 4,732,292 37 - - 5,722,808
B9 Concreting fc'30 Mpa GWT m3 173,000 270 168 168 44,951,628 270 168 168 44,951,628
B10 Concreting fc'30 Mpa Pit lift, Sewagepit,Grease Trap, Balok m3 173,000 12 - - 1,931,433 12 - - 1,931,433
dudukan roof tank, lift separator beam.
B11 Concreting fc'30 Mpa Reinforcement concrete foundation in m3 173,000 16 3 3 2,466,653 16 3 3 2,466,653
generator, diesel fuel tank, pump, gondola,
lightning rod.
B12 Concreting fc'25 Mpa Emergency & Retail Staircase m3 173,000 32 15 15 5,190,138 32 15 15 5,190,138
C1 Break FWK Pile caps m2 160,000 700 700 700 112,045,808 700 700 700 112,045,808
C2 Break FWK Basement Slab m2 160,000 - - - - - - - -
C3 Break FWK Tie-Beam m2 160,000 1,033 1,033 1,026 165,274,151 1,033 1,033 1,026 165,274,151
D1 Timber FWK Column Basement - 4th Floor, Roof m2 153,000 3,662 3,611 1,578 542,369,471 3,811 3,735 1,592 563,145,647
D2 Timber FWK Shear Wall/Core Wall Basement - 4th Floor, Roof m2 153,000 654 654 89 95,781,481 654 654 89 95,781,481
D3 Timber FWK Beam Semi Basement - 4th Floor, Roof m2 153,000 5,786 5,786 2,482 859,952,077 6,021 5,969 2,482 892,111,481
D4 Timber FWK Slab Semi Basement - 4th Floor, Roof m2 153,000 11,245 10,736 6,042 1,661,177,334 11,798 11,280 6,144 1,742,055,023
D5 Timber FWK Retaining Wall Basement m2 153,000 3,950 3,950 1,249 583,740,132 3,950 3,950 1,249 583,740,132
D6 Timber FWK Ramp and Parapet Ramp m2 153,000 330 322 322 50,080,985 363 355 355 55,207,220
D7 Timber FWK GWT m2 153,000 1,654 1,654 975 247,830,613 1,654 1,654 975 247,830,613
D8 Timber FWK Pit lift, Sewagepit,Grease Trap, Balok dudukan roof tank, m2 153,000 147 147 65 21,929,796 147 147 65 21,929,796
lift separator beam
D9 Timber FWK Emergency & Retail Staircase Basement - 4th Floor, Roof m2 153,000 245 245 118 36,537,699 245 245 118 36,537,699
D10 Timber FWK Gutter m' 153,000 323 323 224 48,709,435 323 323 224 48,709,435
VO Previous Payment [1] This Interim Payment [2] To Date [3] = [1]+[2]
SN Description Unit Remarks
Qty Rate Amount Qty Amount % Qty Amount % Qty Amount %
1 Work with Internal Memo/ EI/ SI/ Other Instructions
1.2 Jalan Masuk Ketempat Pekerjaan, Jalan beton Sementara Dan Pengalihan Lalu
Lintas Sementara.
进场路口、临时道路及临时交通改道
a Extension of temporary access road from main gate to rebar yard (FC' 20 Mpa)
新道路打混凝土
a.1 Casting concrete (inclusive materials) m3 161.42 787,525 127,122,848 161.42 127,122,848 100% - - 0% 161.42 127,122,848 100%
a.2 Urugan pasir tebal=100mm, termasuk pemadatan m2 66.49 33,206 2,207,791 66.49 2,207,791 100% - - 0% 66.49 2,207,791 100%
砂垫层,厚度=100mm,包括下部的压实
a.3 Bekisting kayu 模板 (tinggi 20cm) m2 27.32 107,100 2,925,972 27.32 2,925,972 100% - - 0% 27.32 2,925,972 100%
Temporary of access road @ from gate to existing access road , Concrete FC'
b
30 Mpa supply by MC
b.1 Labour only for Casting of temporary of access road m3 190.13 121,100 23,024,743 190.13 23,024,743 100% - - 0% 190.13 23,024,743 100%
1.3 Additional sand bag for protection of slop near by rebar yard area 护坡工程
1 Galian tanah 挖土 m3 227.74 50,265 11,447,461 227.74 11,447,461 100% - - 0% 227.74 11,447,461 100%
2 Bronjongan karung tanah ( Slope Protection of side fence ) m3 300.79 369,038 111,002,977 300.79 111,002,977 100% - - 0% 300.79 111,002,977 100%
Part I Sub Total for Part I 1,366,379,160 1,175,189,284 86% 56,703,080 4% 1,231,892,364 90%
2 Work without Internal Memo/ EI/ SI/ Other Instructions
1 Waterproofing integral for Tower Crane foundation (Pile Cap) at Tower A 混凝 m3 21.31 139,400 2,970,963 21.31 2,970,963 100% - - 0% 21.31 2,970,963 100%
土防水
C Pile Cap 承台 m3 73.15 618,000 45,206,243 73.15 45,206,243 100% - - 0% 73.15 45,206,243 100%
D Tie-Beam 基础梁、连系梁 m3 0.85 618,000 525,757 0.85 525,757 100% - - 0% 0.85 525,757 100%
I DAYWORK LABOUR
1 Memperbaiki pintu sisi barat ( Repair west door ) day 4.00 3.00 180,000 2,160,000 12.00 2,160,000 - - 12.00 2,160,000 ###
- Request date 2020-03-10
6 Instal Collecting Well Between Tower A and Tower B 7/16/2020 Daywork Request 06/4
6.1 Workers/ Lobour man/day 2.00 16.00 25,000 800,000 32.00 800,000 - - 32.00 800,000
6.2 Anxiliary Materials Ls 1.00 1.00 200,000 200,000 1.00 200,000 - - 1.00 200,000
8 Repair door & STP installation plastic 8/13/2020 Daywork Request 08/3
8.1 Workers/ Lobour (wellding) man/day 2.00 8.00 30,000 480,000 16.00 480,000 - - 16.00 480,000
8.2 Workers/ Lobour man/day 3.00 4.00 25,000 300,000 12.00 300,000 - - 12.00 300,000
4.1 - dated 2020-03-30, from 2020/03/18 ~ 2020-04-18 pc/day 15.00 30.00 100,000 45,000,000 450.00 45,000,000 - - 450.00 45,000,000 ###
4.2 - dated 2020-04-16, from 2020/04/18 ~ 2020/05/18 4/16/2020 Daywork Request for Equipment pc/day 15.00 30.00 100,000 45,000,000 450.00 45,000,000 - - 450.00 45,000,000 ###
5 Rental of Excavator
5.1 Rental of Excavator 5/11/2020 Daywork Request for Equipment hr 1.00 156.00 500,000 78,000,000 156.00 78,000,000 - - 156.00 78,000,000 ###
7 Payment 5
7.1 Rent Iron Plate 5/19/2020 4 pcs/ 1 day day 4.00 1.00 3,000,000 12,000,000 4.00 12,000,000 - - 4.00 12,000,000 ###
8 Sent Steel Plat 7/19/2020 Daywork Request 06/5 pcs 4.00 1.00 3,000,000 12,000,000 4.00 12,000,000 - - 4.00 12,000,000
Sub-Total for Rental of equiment & machine 212,600,000 212,600,000 - 212,600,000 ###
III MATERIAL
1 solar for mobile crane servce履带吊用柴油 ltr 11,000 35,200,000 3,200 35,200,000 - - 3,200 35,200,000 ###
2 Peminjaman bahan bakar minyak Solar ltr 11,000 4,400,000 400 4,400,000 - - 400 4,400,000 ###
- Request date 2020-03-17 ( 200 Liters )
- Request date 2020-04-02 (200 Liters )
3 Water Tank for site office 6/20/2020 2 pcs pcs 2.00 1.00 650,000 1,300,000 2.00 1,300,000 - - 2.00 1,300,000 ###
4 Using Sand & Cement by MCC 6/11/2020 Sands/m3 m3 5.00 1.00 350,000 1,750,000 5.00 1,750,000 - - 5.00 1,750,000 ###
Cement /Zak m3 9.00 1.00 69,600 626,400 9.00 626,400 - - 9.00 626,400 ###
5 Plat Strip 0x75, L=6m' 6/29/2020 Daywor Request 06/1 btg 1.00 1.00 350,000 350,000 1.00 350,000 - - 1.00 350,000
6 For Safety Raill and water instalation 7/14/2020 Daywor Request 06/3
- Pipe 3/4" pcs 21.00 1.00 25,000 525,000 21.00 525,000 - - 21.00 525,000
- Pasir m3 3.00 1.00 350,000 1,050,000 3.00 1,050,000 - - 3.00 1,050,000
- Pipa PVC btg 7.00 1.00 110,000 770,000 7.00 770,000 - - 7.00 770,000
- Pipa PVC 1/2' btg 1.00 1.00 200,000 200,000 1.00 200,000 - - 1.00 200,000
- Kran air pcs 4.00 1.00 50,000 200,000 4.00 200,000 - - 4.00 200,000
- Knee (T join) pcs 1.00 1.00 80,000 80,000 1.00 80,000 - - 1.00 80,000
- Sok Kran pcs 2.00 1.00 80,000 160,000 2.00 160,000 - - 2.00 160,000
- Besi Hollow 50x50x3 btg 3.00 1.00 320,000 960,000 3.00 960,000 - - 3.00 960,000
8 Steel Pipe 3/4" 7/23/2020 Daywor Request 06/7 m3 9.00 1.00 60,000 540,000 9.00 540,000 - - 9.00 540,000
9 Request for Material on July 23, 2020 7/23/2020 Datwork Request 08/1
- Shock drat dalam piece 1.00 1.00 50,000 50,000 1.00 50,000 - - 1.00 50,000
- Pipa Clipsa piece 10.00 1.00 35,000 350,000 10.00 350,000 - - 10.00 350,000
- Shock pipe 1 inch piece 4.00 1.00 20,000 80,000 4.00 80,000 - - 4.00 80,000
- Shock pipe 1 1/4 inch piece 1.00 1.00 20,000 20,000 1.00 20,000 - - 1.00 20,000
- Sand m3 1.00 1.00 300,000 300,000 1.00 300,000 - - 1.00 300,000
- 'PVC Pipe piece 3.00 1.00 55,000 165,000 3.00 165,000 - - 3.00 165,000
- Steker 3 Phase 32 Amp piece 1.00 1.00 150,000 150,000 1.00 150,000 - - 1.00 150,000
10 Request for Material on Augst 13, 2020 8/13/2020 Datwork Request 08/4
- Cable NYYHY 4x2,5 mm, Exs Jembo m' 120.00 1.00 30,000 3,600,000 120.00 3,600,000 - - 120.00 3,600,000
11 Request for Material on Septt 20, 2020 9/20/2020 Datwork Request 09/1
- Hollow 50x50 m' 113.00 1.00 45,000 5,085,000 113.00 5,085,000 - - 113.00 5,085,000
IV OTHERS
一级箱到二级箱主电缆线100米(规格4*50)