Professional Documents
Culture Documents
Structural Engineers Design Manual
Structural Engineers Design Manual
Structural Engineers Design Manual
Preface i
1. Introduction 1
1.1 General 1
1.2 Structural Design 2
1.3 Role Descriptions 3
4. Software 21
4.1 Introduction 21
4.2 Finite Element Analysis (FEA) 21
7. Serviceability 33
7.1 Introduction 33
7.2 Deflections 33
7.3 Durability 37
7.4 Vibrations 38
7.5 References and Further Reading 39
8. Design Loadings 40
8.1 Introduction 40
8.2 Design Standards 40
8.3 General Principals 41
8.4 Permanent / Dead Loads 41
8.5 Imposed / Live Loads 42
8.6 Wind Actions 43
8.7 Earthquake Load 44
8.8 Loading Calculations 46
8.9 References and Further Reading 47
10. Foundations 49
10.1 Introduction 49
10.2 General 49
10.3 Ground Investigation - Geotechnical Investigation Report 49
Table Index
Table 1 Typical Structural Property of Materials 7
Table 2 Indicative Reinforcement Rates for Concrete
Building Structures (kg/m3) 8
Table 3 Indicative Unit Weight for One-storey Steel Building
Structures (kg/m2) 9
Table 4 Typical grid dimensions 11
Table 5 Typical sizes for vertical coordination dimensions of
space 11
Table 6 Typical floor-to-floor configurations 11
Table 7 List of design documentation for a large-scale
project 15
Figure Index
Figure 1 Organisation Chart 2
Figure 2 Concept Design Phase 5
Figure 3 Preliminary Design Phase 9
Figure 4 Design Development Phase 12
Figure 5 Detailed Design Phase 14
Figure 6 Rock allowable bearing capacity for square pad
foundations with settlement not exceeding 0.5% of
foundation width (taken from BS 8004) 56
Figure 7 Design Values for Foundations on Sandstone and
Shale in Sydney Region (after Pells, 1978) 57
Figure 8 Pad on rocks 59
Figure 9 Surcharge calculations 67
Figure 10 Dynamic Foundations – General Guidelines 73
Figure 11 Span/d ratio for one-way slabs 82
Figure 12 Span/d ratio for two-way slabs (two adjacent edges
discontinuous) 83
Figure 13 Span/d ratio for two-way slabs (three edges
discontinuous, one long edge continuous) 84
Figure 14 Span/d ratio for two-way slabs (four edges
discontinuous) 85
Figure 15 Span/d ratio flat plate 86
Figure 16 Span/d ratio for simply supported beams 87
Figure 17 Span/d ratio for Continuous beams 88
Figure 18 Cross-sectional area for bars 90
Figure 19 Cross-sectional area per metre width for bar
diameters 90
Figure 20 Mesh specification 91
Figure 21 Standard Post-tensioning Duct Sizes 94
Figure 22 Tendon Profiles 95
Appendices
A Standard Calculation Summary Sheet
B Standard Details in AutoCad
C Template for Design Information
D Analysis Formulae
E Useful Design Data
F Soil and Rock Description
G Prestress Design Notes
H Water Retaining Structures – Details
This manual has been prepared to outline design procedures in order to standardise and improve the
quality of:
Design documentation;
Design approach; and
Format of structural calculations.
This manual provides direction and guidance for structural engineers on “how to design” and “where to
find useful and necessary information to carry-out design efficiently.
Refer to other GHD standard manuals for issues with regard to project management, job management,
quality management, document control, etc.
This manual will be updated periodically and suggestions for improvements are encouraged. There is a
large store of scanned references held in the N:\AU\Adelaide\Service\Structural\Technical Information,
Publications and Papers.
1.1 General
Structural engineering deals with the design of any structural system(s) for the purpose to support and
resist various loads applied to the structure directly or indirectly
Structural engineers are typically involved in the design of building and non-building structures, which
comprise of in-ground supporting systems typically called footings, main supporting structural frame,
super structure, cladding and supporting members. In addition the design of fixings and fittings
supporting non structural components may apply significant loads (gravitational or pressure induced
forces) that can form part of the design brief.
In building construction, the structural engineering field is a subset of civil engineering. In a practical
sense, structural engineering is largely the application of Newtonian mechanics to the design of structural
elements and systems that support buildings, bridges, walls (including retaining walls), dams, tunnels,
etc.
The analysis and design of structures involves the ability to assess the imposed actions on a structure
and design the components to withstand these imposed actions with a sufficient margin of safety against
the applicable limit states of design. Once this has been successfully completed, verified and
documented the construction team can safely fabricate and erect the structure and ultimately satisfy the
requirements of the Client.
Structures cover a large and varied field involving both marcro and micro design issues from concept and
scheme design through to detailed design and construction. Macro issues involve overall structure
stability and gross frame analysis whilst micro issues deal with individual component sizes and how they
are connected together.
Other areas that structural engineers can be responsible for include:
Whole of life costing i.e. durability of materials and serviceability design;
Guidance on value management involving improvement in existing design solutions for either cost,
time or functionality;
Assessment and review of existing structural systems and their ability to satisfy current limit states;
Consideration of construction/erection loads;
Inspection and verification of structural components during erection;
Reviewing fabrication and erection drawings; and
Pre-demolition inspection and guidance on appropriate demolition sequences.
The above list is by no means exhaustive. Good design practice dictates the early involvement of an
experienced structural design practitioner (5 –10 years minimum) who can guide less experienced
designers towards appropriate design objectives.
Other disciplines – disciplines (such as architectural, civil, hydraulic, electrical, mechanical, quantity
surveyor, etc.) other than the structural discipline involved with the design process.
The Client – the person or company responsible for engaging and paying for the structural engineering
service.
2.1 Introduction
Design documentation is a compilation of documents (reports, calculations, certificates, etc.) and
drawings (sketches, detailed drawings etc). It is a comprehensive written document prepared by the
design team showing how engineering theories are applied with the consideration of local regulations,
functional, economic, constructible and safe structural principals. The actual content of design
documentation varies to suit the nature of different projects and design phases. The aim of this section is
to provide engineers with an understanding of the design process and the requirements for structural
design documentation.
Note:
1. Long term Modulus of Elasticity approximately 50% of stated value.
Preliminary Drawings
Preliminary drawings in this stage shall include:
1. All key plans (smaller scale) with adequate information for initial cost estimates (reinforcement rates
& steel unit weights).
2. Necessary sections showing the configuration and sizes of proposed primary frames.
3. Preliminary foundation layout with adequate information for the initial cost estimate (reinforcement as
kg/m 3, steel as kg/m2, etc).
4. Critical details that have significant cost implications (special structural connections, strengthening to
existing structures, etc.).
5. Typical values of reinforcement rates (kg/m3) and steelwork usage (kg/m2) based on the types of
development are shown in Table 2 and Figure 3 as guidelines. The actual value to be adopted can
vary and depends very much on experience and engineering judgement. It is advised that for any
large-scale project where a variation in rate will create a significant error in job costing, that the rates
be built up from a preliminary design.
20-25 20 for portal frame 40 for portal frame 80 for portal frame
2.7 for purlin and 2.7 for purlin and girt 2.7 for purlin and girt
girt
Designer:
Is design info, arch details
& geotechnical report
available?
Compile documentation
2.7 Summary
The tables below show the structural design documentation required for each design phase:
Design Report
Design Basis
Report
Marked-up
Plans
Sketches
CAD drawings
Specifications
Calculations
QA sheets
Design
Certificates
Design Basis
Report
Marked-up
Plans
Sketches
CAD drawings
Specifications
Calculations
QA sheets
Design
Certificates
3.1 Introduction
The purpose of this section is to assist designers in presenting structured legible calculations and design
documentation.
3.2 General
Structural calculations prepared after the 50% stage (preliminary design phase) are critical documents
required to demonstrate safety and structural integrity.
A set of calculations should be separated into individual categories for each structural component.
Typically this would include the following:
Standard calculation summary sheet (see Appendix A)
QA Sheets
Contents page
Design information (see Appendix C)
Component design
– Foundation
– Substructure
– Columns and walls
– Component design shall consist of following essential portions:
Design intention/subject
Summary sketches showing component configuration and actions
Analysis results
Conclusion
Summary
– Floors and superstructures
– Stairs
– Connections
– Facades
Note: be consistent with units and clearly identify span assumptions, supports, reactions, shear
forces, bending moments and whether the load is a serviceability limit state (SLS) or ultimate limit
state (ULS). Include the ULS load factors and the combinations that are being used.
Attachments
– Design brief
– Computer outputs for a group of structures
– List of latest architectural and structural drawings
3.6 Summary
It is recommended that a summary of all the subjects covered by the calculations be included to:
Make sure the design outputs meet the requirements of design inputs,
List out the results together for self-certification and design check,
Highlight all the outstanding assumptions and have them indicated on tender / construction drawings
accordingly.
5.1 Sketches
5.2 Member design
7.3 Summary
6. Connection design
6.1 Input from output of structural analysis
6.2 Sketches of connection
6.3 Summary
7. Outstanding issues
4.1 Introduction
Application of commercial software is very common in the design development phase and detailed
design phase because it is fast, accurate and easy to check. Pre-ordination of softwares according to
their functions will make design checkers concentrate more on the design inputs and outputs without
spending too much time on the analysis process. Designers shall familiarise themselves with software in
common use through internal and external training sessions.
All current available structural software can be found on Compass (Lotus Notes) in the GALEXE
database. Software requests are managed through this database.
In applying any numerical model approximation to a real structure it is essential to understand how
well the modelling describes the real performance over time. You should be aware of what the
modelling has not adequately considered and what is the best way to take account of this in the
design.
5.1 Introduction
The main design reference for a project shall be the Structural Design Brief prepared by the JM. Design
standards and references in common use are shown in Table 9.
Part 1: General
requirements
6.1 Introduction
The structural engineer’s role is to select the appropriate structural system for a structure and ensure it is
detailed appropriately. The structural system will vary depending on various factors including:
End use/client requirements
Constructability requirements
Code requirements
Experience
Material(s) selected for construction
Durability requirements
The structural system selected will determine how the structure performs under the loadings encountered
during its service life.
Trusses are efficient in long span situations as the moment is resisted by an axial couple formed by the
chord members separated by the depth of the truss (i.e. level arm). Lighter steel members normally
make up the web members since they typically resist forces of smaller magnitude than the chords.
Trusses may be designed with either fixed or pinned connections. Pinned connections are typically used
to connect the web members to the chords although the use of rigid connections may assist in keeping
some redundancy within the structure if a connection or member were to fail. Chord members are
generally continuous to minimise the number of connections required.
Timber Gluelam
Composite beam and slab
Trusses
The selection of a structural system depends on those items mentioned above and also on:
Available space/geometry requirements
Architectural input
Client / builder requirements
Potential end user requirements;
Future use requirements
Environmental factors such as large temperature ranges, flooding risks, corrosion potential and
service life requirements
Ground conditions
Loading regimes such as high earthquake zones or cyclonic regions
Historically it is evident that the cost of labour is much greater than the cost of materials. This is apparent
when one examines old factory sheds with truss portals and riveted bridge structures. Current economic
conditions are driving labour costs higher meaning that using single deeper beam sections, although
heavier can be less expensive to fabricate, coat and erect. Ongoing maintenance costs may also favour
this approach since the surface area for coatings may also be reduced for a single member rather than
multiple smaller members. Off site prefabricated items such as precast concrete & pre assembled steel
frames can also reduce many of the additional costs associated with installation.
In the case of concrete, post tensioned/prestressed beams and slabs are the norm due to smaller steel
percentage requirements in the concrete and the advantages available in longer spans with fewer
supports. However reinforced concrete still has a major part to play in complex components, deep
beams, foundations and slabs on ground.
7.1 Introduction
AS 1170.0 Structural design actions Part 0: General principles Clause 1.4.16 defines serviceability as the
“Ability of a structure or structural element to perform adequately for normal use under all expected
actions”.
Serviceability is further described in AS 5100.1 Bridge design Part 1: Scope and general principles
(Clause 6.3.3) to include:
(a) Deformation of foundation material or a major load-carrying element of sufficient magnitude
that the structure has limitation on its use, or is a public concern.
(b) Permanent damage due to corrosion, cracking or fatigue, which significantly reduces the
structural strength or useful service life of the structure.
(c) Vibration leading to structural damage or justifiable public concern.
7.2 Deflections
Bridges: 1/400
cantilevered
members
Notes:
ii. For long span floors, consideration should be given to adopting an absolute limit for deflection, which will be more stringent
that the values quoted in table above.
In addition to the above, long term deflections for roof members shall be limited to prevent water ponding
and maintain falls to drainage outlets. A minimum fall of 1:100 is suggested.
Roofs with low pitches should be checked to ensure that water ponding does not occur.
The limits for relative horizontal deflection between adjacent frames at the eaves level of industrial
buildings due to wind loads are summarised in Figure 13.
Building clad in metal sheeting Column height / 150 Relative deflection between
without gantry cranes, no adjacent frames
Frame spacing / 200
ceilings and without internal
partitions against external walls
Building clad in metal sheeting Column height / 250 Column height /300 should be
with gantry cranes, no ceilings used for heavy crane
Frame spacing / 250
and without internal partitions
against external walls
Building with masonry walls Column height / 250 Relative deflection between
supported by steelwork adjacent frames
Frame spacing / 200
Domestic,
commercial
Industrial
7.3 Durability
7.3.1 Corrosion
AS 3600 Concrete structures is generally applicable to building type structures. Compliance with the
reinforcement stress limits and/or the reinforcement spacing of Section 8.6 (beams) and 9.4 (slabs) will
provide the requisite control over cracking commensurate with this type of structures (i.e. maximum crack
widths of approximately 0.3mm).
For bridge structures, similar provisions are provided in AS 5100.5 Bridge design Part 5: Concrete
Section 8.6 (beams) and 9.4 (slabs). As bridge structures are designed with a 100 year design life, these
provisions should be used with care and due consideration is to be given to the macro and micro-
environment.
The commentary to AS 3735 Concrete structures for retaining liquids specifies the mean crack widths for
structures that are required to retain (or exclude) liquid. Mean crack width limits of 0.1mm and 0.15mm in
tension and flexure respectively are specified where the member is continuously submerged; 0.1mm in
both tension and flexure where the member is subject to intermittent wetting and drying.
Maximum crack widths may be assumed to be 1.5 times the mean crack width.
Methods of calculating the crack widths are available in BS 8007 Design of Concrete Structures for
Retaining Aqueous Liquids, Eurocode BS EN 1992 Eurocode 2 Design of Concrete Structures and ACI
Manual of Concrete Practice 224R (to be finalised). The method proposed in BS 8110 is recommended.
7.3.3 Fatigue
Fatigue is to be considered for structural members subject to significant repetitive loading. This is
especially the case for railway bridge structures.
Fatigue requirements for steel structures are contained in Section 11 of AS 4100 Steel structures and
Section 13 of AS 5100.6 Bridge design Part 6: Steel and composite construction.
For fatigue requirements for concrete structures, refer to Section 2.5 of AS 5100.5 Bridge design Part 5:
Concrete.
7.4 Vibrations
Structures with large spans or heights may be considered for the dynamic effect caused by vibrations.
Dynamic analysis may be necessary when:
Structural steel floor spans of more than 8m
Steel portal frame spans of more than 50m
Reinforced concrete flat plate spans of more than 12m
Other types of structure spans of more than 25m
Cantilevers and masts of a height more than 10m
Core Aspect Ratio of a building (height to width) is more than 8: 1
Composite steel and post-tensioned concrete floors are extremely sensitive to vibration, particularly with
mechanical equipment loads. Structural engineers should advise the mechanical consultant to provide
vibration isolation accordingly.
Dynamic response is also influenced by structural form. The trend for lighter, stiffer floors, which follow
from consideration of static load, will bring a trend to higher natural frequencies. This should have the
effect of making the floor less likely to respond to loads moving over it, but perhaps more likely to
respond to disturbance from installed machinery.
Footfalls (pedestrian bridges, walkways, long span structures) with people loading are generally in the
range of 1.5 to 2 Hz. Therefore avoid a natural frequency of 1 to 3 Hz. AS 5100.2 Bridge Design Part 2:
Design Loads Section 12.4 says that for pedestrian bridges with resonant frequencies for vertical
vibration inside the range of 1.5Hz to 3.5Hz, the vibration of the superstructure shall be investigated as a
serviceability limit state.
8.1 Introduction
This section specifies general procedures and criteria for structural design. It covers design actions and
combinations of actions. This section is applicable to the structural design of whole buildings or
structures and their elements.
The design of a building or structure shall allow for, as a minimum, the following loads/actions:
Permanent / Dead Loads
Imposed / Live Loads
Wind Loads
Snow and ice Loads
Earthquake Loads
Construction Loads
Liquid pressure
Ground water
Earth pressure
Temperature
Refer to design criteria for basic loading and check for any special requirements by the Client. Provide a
loading summary sheet at the beginning of design calculations (Section 3.7).
A building shall be designed for the loadings required by the Building Code of Australia (BCA).
The design earthquake loads shall be computed from AS 1170.4 for the appropriate structure Importance
Level.
Building and structures shall be classified as Importance Level 1,2,3 or 4. Annual Probability of
Exceedance, based on Importance Level, shall comply with Table B1.2b of the Building Code of Australia
(BCA).
Annual Probability of Exceedance for Earthquakes are tabulated below incorporating the Annual
Probability of Exceedance design events proposed by the BCA (2008).
1 1:250
2 1:500
3 1:1000
4 1:1500
The annual Probability of Exceedance relates to the annual probability that the design event will be
exceeded in 50 years in 1:500 (10% in 50 years), 1:1000 (5% in 50 years) and 1:1500 (3.3% in 50
years).
Used as a guide only, QA procedures must be followed 44
42/01012/07/44062 GHD Structural Design Manual
Revision 2
Earthquake Loads computed from AS 1170.4 are Limit State Loads.
Hazard Factor ( )
Hazard Factor Maps are produced by Geoscience Australia (GA) are reproduced in AS 1170.4. The
Hazard Factor ( ) is equivalent to an acceleration co-efficient with an annual probability of exceedance of
1:500 (i.e. a 10% probability of Exceedance in 50 years).
The site hazard factor may be obtained from AS 1170.4 Fig 3.2 (B) or as detailed in the Geotechnical
Investigation Report.
Probability Factor (Kp)
The Probability Factor (Kp) shall be taken from AS 1170.4 Table 3/1 appropriate to the structures
Importance Level and associated annual probability of Exceedance.
Site Sub-Soil Class
The site sub-soil class shall be determined from the site geology as defined in the Geotechnical
Investigation Report.
Design load combinations for Limit State ad Serviceability design shall comply with AS/NZS 1170.0.
9.1 Introduction
TBA
Concrete
Steelwork
Masonry
Timber
Aluminium
10.1 Introduction
The investigation and design of foundations is a broad subject. The guidance provided in this section is
intended to provide a basic understanding of the broad principles/design methods for relatively straight-
forward structures. It is not intended to replace Standards. However, care should also be taken in rigidly
applying Standards based methods, or presumed design values for soils/rocks.
Soil/structure interaction is complex and simplified methods may provide poor representation of actual
behaviour. GHD geotechnical engineers will be able to advise on appropriate design methods.
10.2 General
A foundation transmits structure loads to the underlying ground. Foundations must provide a factor of
safety against shear failure of the ground and be designed to keep within tolerable settlements/angular
distortion to avoid unacceptable damage to the structure (i.e. remain serviceable).
Foundations are either classified as shallow or deep foundations, and common types are:
Where a certain foundation type is not thought feasible (e.g. raft), it may be possible to improve or treat
the ground more cost effectively than adopting other more expensive foundation types (e.g. piles).
10.5.1 General
Foundation bearing pressure (qb) is the pressure exerted at the base of the foundation on the ground by
the superstructure. It is not related to bearing capacity, which is the resistance provided by the ground to
counteract the foundation bearing pressure exerted. Net foundation pressure (qn) is the net increase in
pressure at the base of the foundation, after taking into account the weight of ground permanently
removed below existing ground level. It is expressed as:
qn=qb- D
10.5.3 Calculation of Bearing Pressure for Combined Vertical and Inclined/ Horizontal Loading
Inclined and/or horizontal loading applied to a foundation in combination with vertical loading causes the
force resultant (i.e. summation of force and force direction) on the foundation base to act inclined rather
than vertical. This has an overturning effect on the foundation. The calculation of bearing pressure is
modified to take this into account by reducing the foundation width, B, (in the direction of loading) to the
“effective width”, B’:
B’=B-2e
where,
e is the eccentricity of the resultant from the centre of the base
qb=Rv/(L*B’)
This is commonly referred to as the Meyerhof bearing pressure and is represented as a rectangular
stress block across the effective width rather than triangular stress distribution over the whole footing
width.
At concept design only, preliminary sizing of pad footings with vertical loads could be based on the
presumptive bearing capacity values given in Table 20. Care should be taken in adopting presumed
bearing capacity values from international standards as the soil classification system may be different to
Australia (e.g. very soft clay in the UK has a shear strength less than 20 kPa, whereas it is less than 12
kPa in Australia).
It should be noted that the presumptive bearing capacity values only consider a factor of safety against
shear failure. They do not consider settlement. It would be advisable to seek confirmation from a GHD
geotechnical engineer. In general, foundations on soft cohesive soils and those with larger dimensions
(e.g. rafts), should have further consideration of settlements at concept stage.
Bearing soil stratum (assuming consistent soil conditions for Presumed bearing
minimum 3*footing width below footing base) capacity (kPa)
Very soft clay (min 0.75 m below ground level), cu<12 kPa Seek Seek
advice, <35 advice, <40
Firm clay (min. 0.75 m below ground level), cu=25 – 50 kPa 55 – 100 65 - 115
Stiff clay (min. 0.75 m below ground level), cu=50 – 100 kPa 100 – 185 115 – 220
Very stiff clay (min. 0.75 m below ground level), cu=100-200 kPa 185 – 350 220 - 425
Hard clay (min. 0.75 m below ground level), cu>200 kPa >350 >425
**Very loose clean sands and gravels (N<4) = 28-30 Seek Advice
**Loose sands and gravels (N = 4-10) (min. 0.75 m below ground level) 100
= 30
Medium-dense sands and gravels (N = 10-30) (min. 0.75 m below ground 180
level) = 34
Dense sands and gravels (N = 30-50) (min. 0.75 m below ground level) 300
= 38
Very dense sands and gravels (N > 50) (min. 0.75 m below ground level) >400
= 41
It is strongly advised that a GHD geotechnical engineer be consulted for appropriate values for mixed
soils such as silty or clayey sands. See below for discussion.
It is further noted that the capacity of foundations in coarse-grained soils is heavily dependent on
groundwater levels e.g. for a surface footing in sand, the dry bearing capacity is about double the
saturated bearing capacity.
It is strongly advised that a GHD geotechnical engineer be consulted for appropriate values for mixed
soils such as silty or clayey sands, or sandy silts. Many structural designers are uncertain on design
properties for mixed soils. Few mainstream geotechnical textbooks provide detailed guidance on
properties, but typically present a wide variety of soil properties and behaviour of sand and clay.
Wherever possible, grading analysis should be carried out on such mixed soils to determine the
proportion of silt/clay fines rather than relying on visual descriptions on borehole logs.
In Australia, the soils classification system (AS 1726) for silty/clayey sands (SM/SC) is very broad, and
the sand may have anywhere between 12 and 49% silt/clay fines. This is because the Australian
Standard for soil classification (AS 1726) delineates the dominant soil type (shown on borehole logs in
CAPITALS) on the basis of proportion of soil material passing the 0.075 mm sieve size. This sieve
represents the boundary between sand and silt sized soil particles. The Standard states this should be
done on a 50:50 basis. For instance, a soil with 49% clay and silt, and 51% sand, would be a clayey/silty
SAND, but a soil with 51% clay and silt, and 49% sand would be a sandy CLAY/SILT. For that example
there would be little difference in soil properties and behaviour for the two soils, which would both behave
as a fine-grained soil like clay/silt. However, the classification of a silty/clayey SAND also extends to a
soil with only 12% clay/silt and 88% sand, which would behave more as a poorly draining sand rather
than silt/clay. The challenge to designers is when the proportion of clay/silt in the sand starts to dominate
behaviour to the extent that the material basically has clay/silt properties. Adopting the DOMINANT soil
type only as the design basis may prove highly inaccurate.
The New Zealand and UK Standards both delineate dominant soil type on the basis of engineering
behaviour rather than a 50:50 proportion basis, with the difference being set at 35% clay/silt:65%
sand/gravel. Even in the 15 to 35% fines range, soil properties can be substantially different from that of
a clean sand or gravel.
Rock
The bearing capacity for rocks is significantly affected by the orientation, frequency and condition of
joints in the rock, which affect rock mass strength (ultimate bearing capacity) and stiffness (foundation
settlements). A wide variety of published presumed allowable bearing capacity values are available for
rocks, but considerable care should be taken in selecting an appropriate value, even for concept design.
A GHD geotechnical engineer should be asked for confirmation of appropriate detailed design values,
commensurate with settlement performance requirements. Some guidance is provided in Table 21, and
Figure 7.
For foundation material up to 1000 kPa allowable bearing capacity, pads should be designed as flexural
members in accordance with AS 3600.
Pad Footings on Rock
For rock over 1000 kPa either refer below or design pads to transfer load in strut/tie or shear with a
greater depth. For widely jointed rock masses with an allowable bearing capacity greater than 1000 kPa,
pads may be designed assuming a strut-tie model with nominal reinforcement in the top of the pad, as
shown in Figure 8. This relies on containment of the lateral thrust component by the rock foundation
sides. Consideration of the strain compatibility between the concrete footing and the rock should be
made.
Aside from the reduction in bearing capacity of pad footings caused by lateral and/or inclined loading,
footings should be designed against sliding based on the frictional resistance on the base and/or passive
resistance of the ground. For the latter, consideration of the following needs to be taken into account:
Potential shrinkage of the soil away from the footing
Necessary movement required to mobilise passive resistance, and the need for a suitable limiting
factor of safety
Impact on footing design if excavation was to occur adjacent to the footing, i.e. loss of passive
resistance
BS 8004 provides further guidance on parameters and calculation of resistance to sliding.
Piles should be checked for buckling, particularly long slender piles through soft soils. Where part of the
pile extends above finished ground level, that length should be designed as a column in accordance with
the relevant AS. The effective length is dependent on the lateral loading, and degree of fixity provided by
the ground and by the structure that the pile supports. The depth to the point of contra flexure varies with
soil type and strength/density.
Pile capacity
Pile capacity shall be calculated in accordance with AS 2159, unless using specialist design calculation
methods (e.g. design of rock socketed piles based on settlement criteria). Shaft friction and end bearing
contribute the geotechnical capacity. A GHD geotechnical engineer should be consulted for appropriate
design values.
Lateral Forces
Piles subject to lateral forces should be checked for moment, shear and deflection, taking into account
the stiffness of the pile and response of the ground. The following methods are available:
Hand calculations (e.g. Broms method)
Beam and spring models, using software such as Space Gass or Microstran
P-Y methods, using software such as LPILE
Finite element methods (e.g. Plaxis, Phase2)
It is strongly recommended that advice be sought from a GHD geotechnical engineer on an appropriate
soil/structure design method for each structure. Representation by linear elastic beam and spring models
can be highly inaccurate in some circumstances. The P-Y method is a slight improvement in that non-
linearity can be introduced into the springs, but the springs still work independently of each other. Finite
element methods are generally preferred but may not be warranted in all cases.
Deflection calculations should give consideration to the cracked section properties of the pile.
Pile groups subject to lateral forces should be referred to a geotechnical engineer, as the lateral capacity
of individual piles can be severely reduced if piles are less than about 6B apart (the passive support
zones start to overlap).
10.7.8 Caissons
A caisson is a structure that is sunk through the ground and becomes part of the permanent works.
Some guidance is given in BS 8004. Geotechnical design of caissons needs to consider the following:
Method of sinking the caisson
Estimates of the skin friction to overcome when sinking the caisson
Ground loss and associated movements, and the impact on adjacent structures, services and other
infrastructure
Base heave and bearing capacity
Control of groundwater
11.1 General
A retaining wall is a structure that holds back earth or rock. Retaining walls stabilise soil from downslope
movement or erosion and provide support for vertical or near-vertical grade changes. Retaining walls are
generally made of masonry, stone, concrete, steel or timber.
The most important consideration in design and installation of retaining walls is that the retained material
is attempting to move forward and downslope due to gravity and surcharge. This creates an earth
pressure behind the wall (depending on the angle of internal friction and the cohesive strength c of the
material, see Table 24). This pressure will push the wall forward or overturn it if not properly designed.
Additional horizontal hydraulic pressure on the wall, and beneath the base, shall also be considered if
any groundwater behind the wall is not dissipated by a drainage system. Proper drainage behind the wall
is critical to the performance of retaining walls. Drainage materials will reduce or eliminate the hydraulic
pressure and increase the stability of the fill material behind the wall.
11.2.1 General
Common types of retaining structures are:
Gravity wall
Cantilever wall
Sheet piling or shoring
Bored pile wall
King-post pile wall
Basement wall
Reinforced soil wall
Cut slope stabilised by ground anchors or soil nails
Table 22 Typical Presumed Unit weights of granular soil (after AS 4678 and BS 8002)
3 3
Material m: moist bulk weight (kN/m ) s: saturated bulk weight (kN/m )
In the absence of reliable data for concept design, effective shear strength parameters may be assumed
from AS 4678 (reproduced in Table 24) or BS 8002. However, the values quoted in AS 4678 should be
treated with some caution. A GHD geotechnical engineer should be asked for suitable design values.
Designers should refer to Standards, but typical surcharge allowances are as given in Table 25. A guide
to their application is provided in Figure 9.
Foundations
See
Figure 9
Where,
Ko = 1-sin normally consolidated soils only)
Ko=(1-sin OCRsin (overconsolidated soils)
Retaining walls represent a classic example of soil-structure interaction where the degree of movement
of walls by translation or rotation under the pressure of the retained soil can modify considerably the
magnitude of the pressure acting behind the walls or the resistance of the soil to movement in front of the
walls. These opposing forces are known as the active pressure (pa) and passive pressure (pp)
respectively.
Active pressures, pa, is smaller than po and only small wall outward movement (of the order 0.1-1.0% of
retaining wall height, depending on ground conditions and wall types) is necessary to mobilise pa.
Passive pressures, pp, is larger than the at-rest pressure, po, and large wall inward movement (of the
order 3-10% of wall height) is necessary to mobilise full pp.
Active pressure, pa = Ka v’
Passive pressure pp = Kp v’
Where,
Ka is the active coefficient of earth pressure
Kp is the passive coefficient of earth pressure
11.5.3 Software
Wallap - beam and spring model, or finite element
Plaxis - finite element modelling.
TEDDS - RC retaining wall design & gravity retaining wall design
Capacity tables shown in CMAA references for masonry cantilever retaining walls.
12.1 Introduction
This section is a guide for the design of foundations subjected to dynamic loads from vibrating
machinery.
k
fn
m
It follows that the greater the stiffness, the higher the natural frequency for the same mass. Common
ways of increasing natural frequency (without an undue increase in mass) include:
Increasing the depth, D, of the member – here stiffness increases by D3, but mass only increases by
a multiple of D
Providing additional bracing
Increasing the bearing contact area of the foundation
Stiffening the subsoil.
When designing foundations, the mode frequency should be ±50% of the speed of the machinery.
The common centre of gravity of the system (i.e. of the foundation and machine) is located as near
as possible to the same vertical line as the centroid of the foundation area in contact with the soil. In
any case the eccentricity in the distribution of masses should not exceed 5% of the length of the side
of the contact area.
The height difference of the centroid of the machine and foundation should be kept to a minimum but
with due consideration to operational and maintenance requirements. Where possible the combined
centre of gravity of the machine and foundation in elevation should be within the height of the
foundation. Generally foundation thickness will be a minimum of 600 mm.
To ensure reasonable stability, the width of the foundation (measured at right angles to the
crankshaft) should at least be equal to the distance from the centre of the shaft to the bottom of the
foundation.
The proportions of the foundation block should be such as to ensure stability against rocking.
structures/foundations
Machinery L
Foundation
Plan
Difference between
Machinery
concrete foundation
Elevation Longitudinal Axis of
Machinery
Notes:
Unfortunately, there is no universally correct answer for how many modes are significant for the analysis
as it varies from case to case and also depends on what is being evaluated, such as checking the
resonance, checking the transient response or checking the response against earthquake.
12.3 Design
Unless vendor data requires more restrictive vibration levels, the limiting vibration levels calculated for
selected points of the machine casing shall be as given for a Group D machine as stated in ISO 10816.
These limits of this class of machine are as per Table 26:
< 10 Hz s 100 µm s 23 µm
The engineer’s attention is drawn to clause 3.4.2 of CP 2012-1, which stipulates desirable frequency
ratios between the forcing frequencies and the natural frequencies of the foundation/machine system.
These ratios shall be targeted where possible. However, if the damped forced response analysis
indicates that calculated levels of vibration are acceptable, then the frequency ratios shall be taken as for
machines of a `lesser importance', as indicated in clause 3.4.2 of CP2012-1.
13.1 Introduction
Columns shall be designed to resist axial forces and bending moments caused by design loads and
additional bending moments produced by slenderness effects.
Columns are defined as either short or slender, and braced or unbraced.
For short braced columns with small bending moments the design axial strength may be taken as
0.75xNu and the bending moments disregarded (AS 3600 Clause 10.3.3). Refer also to Warner Rangan
Hall Faulkes section 22.5.3.
Used as a guide only, QA procedures must be followed 77
42/01012/07/44062 GHD Structural Design Manual
Revision 2
Slender columns are designed with additional bending moments taken into account by multiplying the
largest design bending moment by the moment magnifier; depending on the method of analysis for
determining the axial forces and bending moments.
From a constructability and cost viewpoint it is usual to size columns based on a reinforcement ratio of 1
– 1.5%. If architectural requirements require minimal section sizes it maybe better to increase concrete
strengths.
Square columns are usually the most efficient solution in terms of load carrying capability followed by
circular columns. Blade columns may have architectural planning advantages e.g. car parks.
For detailing purposes it is recommended that the least number of larger diameter bars is used to reduce
congestion of reinforcement splices and junctions. Four sided columns should ideally have multiples of
four bars and circular columns a minimum of six bars.
13.4 Walls
Walls subject to in-plane vertical forces may be designed as columns or by simplified methods of AS
3600 Clause 11.5.
In-plane horizontal forces shall also be designed for in accordance with AS 3600 Clause 11.6.
Walls designed as columns commonly do not always require the restraint provisions of vertical
reinforcement, refer AS 3600 Clause 11.7.4.
Walls subject principally to horizontal forces perpendicular to the wall may be designed as slabs.
14.1 Introduction
The purpose of this section is to enable preliminary sizing for insitu reinforced concrete members to be
obtained with little effort but reasonable accuracy. It should not take the place of detailed design.
14.2 General
Reinforced concrete (RC) in-situ elements could be adopted considering the following:
High strength for compression and bending;
Good fire rating;
High construction quality;
Durability;
Easy to adapt to odd shapes; &
Generally well skilled tradespersons and world class equipment throughout Australia.
However, adoption of RC in-situ maybe not so advisable considering:
High costs;
Local unavailability;
Difficulty in concrete placement;
High self weight;
Time delay before load-bearing;
Tight schedule; &
Lack of skilled labour.
14.5 Detailed design (Strength – moment and shear; Deflection – short-term &
long-term; Crack – flexural & shrinkage)
14.5.1 Software
GHD Validated Spreadsheets (N:\Global\Apps Resources\GHD Spreadsheets)
Slab 3.2 for slab design (strength, deflection & crack)
TEDDS
Microstran for beam & column design (strength & deflection)
Space Gass for beam and column design (strength & deflection)
Sam for section subject to biaxial and uniaxial bending (strength & deflection)
Rapt (prestressed & RC members)
AS 3600 – 2009
CIA, Recommended Practice, Reinforcement Detailing Handbook for Reinforced and Prestressed
Concrete.
Warner, R. F., Rangan, B. V., Hall, A. S., Faulkes, K.A. 1998. Concrete Structures. Longman,
Melbourne, 1998.
15.1 Introduction
The purpose of this section is to enable preliminary sizing for prestressed concrete members. It should
not take the place of detailed design.
15.2 General
Advantages of using prestressed concrete include:
Common throughout Australia;
Could be designed in-house or by subcontractor;
Increase clear span;
Thinner slabs;
Lighter structures;
Reduced cracking and deflections;
Reduce storey height;
Watertightness;
Effect of restraint to floor shortening
Floors must be able to shorten to enable the prestress to be applied to the floor.
Due to the stiffness of cores, prestressing of slabs between stiff core walls maybe ineffective
because the slab cannot compress and the prestress forces are held within the cores and not the
slab.
15.3 Materials
Parabolic
Type of floor Total imposed Span / depth ratio Min slab thickness
loading (kPa) (mm)
10.0 30
10.0 34
STD-To be advised
Designers can obtain a copy of GHD Standard Details (N:\AU\Brisbane\Projects\14\0156106\Project
Tools\Standard Structural blocks) for reference.
16.1 Introduction
The purpose of this section is to enable preliminary sizing for steel members and provide preliminary
information on connection types to be obtained with little effort but reasonable accuracy. It should not
take the place of detailed design.
16.2 General
Structural steel is adopted mainly because of its high strength and labour saving factor. A minimum mass
solution does not necessarily result in a minimum cost solution. Connection detailing and fabrication of
components should be simplified as much as possible. Generally shop welding and field bolting are the
most economical form of connections.
Fire protection in the form of fire spray or fire-proof box-up is used where a fire resistance is a
requirement.
Tubes are available in a variety of grades. Circular (CHS), square (SHS) and rectangular hollow sections
(RHS) to, AS 1163 are available with a yield stress of 250, 350MPa or 450MPa. For larger tubes,
specialist advice should be obtained as to the grade, suitability for structural work, and welding
requirements.
16.4 Frames
Typical steel frames used are:
Portal Frames (single storey)
Sway Frames (multi storey)
Braced Frames
Space Frames
Generally an elastic analysis is sufficient to be carried out on a frame to find design moments and forces.
A second order analysis incorporating P- and non-linear analysis effects is available in most analysis
software. This is particularly useful for analysis of sway frames and also enables direct calculation of
member forces and moments in braced frames without the need to apply the amplification factors noted
in AS 4100 clause 4.4.2.
Plastic Analysis
Where serviceability and sway deflection requirements are not critical, a plastic analysis and design can
provide slightly lighter frames and members. Although there is no in-house software dealing with plastic
analysis, relevant literature can be consulted for methods to be used e.g. Limit state design of portal
frame buildings – Australian Institute of Steel Construction (AISC).
It should be noted that AS 4100 has some special requirements for plastic analysis and design, see
Clause 4.5.
For a continuous beam or cantilever beam, it is possible that maximum shear and bending occur at the
same location. The shear capacity in this case shall be checked considering the presence of bending
moment.
16.6 Connections
Connections should be designed for the loads and moments induced by the connecting members. Care
should be taken to ensure that:
The design reflects the assumptions made in the analysis e.g. full moment connections, pinned
connections etc
The size of member is adequate for the connection configuration
A variety of connections may be used, some of which are listed in Table 30:
Splices in long members should be made to keep lengths as near to standard rolled lengths as possible
to reduce wastage (refer to Onesteel online for availability and structural lengths). They should also be
positioned at points of minimum moment. Splices should be designed and checked for the forces and
moments at the position the splice occurs. Dimensions to splices should be clearly marked on the
drawings. It is possible to avoid bulky moment splices by the inclusion of a hinge at the splice position
and then designing the splice for shear only. (Check deflections if this procedure is adopted).
Many of the system options will provide equal performance in the field. The system chosen will depend
on many factors including location, material supply, available equipment, labour and cost. Typical
systems include:
16.8.1 For steel floor or roof beams, with a depth of d and a span of L;
Case 1: Non composite UB L/d = 15~18
Case 2: Composite, UB L/d = 18~21
Case 3: All for UC L/d = 21~24
Case 4: Plate girder, WB L/d = 10~12
Case 5: Cantilever beam L/d = 7
16.8.2 For truss roof structures, with an effective depth of d (from the centre of top chord to
centre of bottom chord) and a span of L;
Case 1: Pitch roof truss, Pratt, Howe or Find L/d = 4~7 (L = 6~12 m)
Case 2: Mansard truss L/d = 7~8 (L = 15~30 m)
Case 3: Parallel chord truss (Pratt or Howe Lattice Girder) L/d = 15~25 (L = 6~50 m)
Case 4: Portal Frame (with haunches) L/d = 55 (rafter)
L/d = 50 (column)
Haunch Length = L/10
Haunch Depth = 2 rafter depth
Case 5: Space truss L/d = 20~24 (L 50 m)
16.8.3 For braced columns, calculate the column load N* and check the sectional size based on
following formula:
N* x 0.5 x fy x Ag
Where,
= 0.9
Ag = section area
16.9.2.1 Software
Microstran for beam & column design (strength & deflection)
Space Gass (strength, deflection & connection)
LimCon (connection design)
Standard calculation (TEDDS)
– Steel beam analysis and design (strength, deflection, no angles)
– Steel column design (strength)
– Comprehensive pad design (fixed and pinned base)
GHD verified Excel spreadsheet (N:\Global\Apps Resources\GHD Spreadsheets)
17.1 Introduction
The purpose of this section is to enable preliminary sizing for masonry members. It should not take the
place of detailed design.
17.2 General
Concrete masonry is a generic term covering many building systems that incorporate blocks of many
different shapes, sizes and strengths. It includes:
Decorative face masonry such as coloured, polished, textured or split blocks;
Plain blocks used as the load-bearing leaf in cavity construction and non load-bearing partitions;
Reinforced corefilled blockwork in large building panels and retaining walls; and
Mixed construction consisting of unreinforced, corefilled and reinforced blockwork.
Concrete masonry is adopted for the following advantages:
Non-repetitive construction;
Reasonable load bearing capacity for low-rise commercial and industrial buildings;
Effective resistance to horizontal loads; and
Less expensive than reinforced concrete
Preliminary check:
Check wall thickness based on sizing limits (refer Section 17.3)
Design charts in Design of Concrete Masonry Buildings by CMAA
Design charts in Reinforced Concrete Masonry Cantilever Retaining Walls by CMAA
Capacity tables, Figure 26, Figure 27 and Figure 28).
Detailed design
AS 3700- Masonry Structures
TEDDS
GHD verified structural spreadsheets (N:\Global\Apps Resources\GHD Spreadsheets)
18.1 Introduction
The purpose of this section is to facilitate preliminary sizing for timber members and provide preliminary
information on connection types. It should not take the place of detailed design
18.2 General
Specifying a hardwood does not necessarily mean it is a durable outdoor timber; the class of timber will
ensure durability. Remember certain hardwoods have very high shrinkage levels that can result in
warping, twisting and joint separation.
18.3 Sizing
18.3.1 For bearers and joists, with a joist spacing of 450 mm, depth of d and a span of L;
Case 1: Simply-supported bearers L/d = 10~15
Case 2: Continuous bearers L/d = 12~17
Case 3: Simply-supported joists L/d = 20~25
Case 4: Continuous joists L/d = 25~30
Figure 30 Bearers
19.1 Introduction
The combination of reinforced concrete and steel systems forms the basis of composite construction.
Composite slab construction generally consists of a cold-formed steel profiled floor deck, which acts as
the permanent formwork system for the concrete slab during construction. The decking spans in one
direction across supports and can be propped or unpropped depending on the span and depth of wet
concrete supported.
In its final state, the profiled steel decking acts as bottom reinforcement with additional top steel in the
form of mesh and bars provided to allow for continuity and to control cracking.
Where steel beams are used to support the decking, they may also be designed compositely to provide a
more economical solution. Apart from larger fully composite steel framed buildings, profiled decking is
also commonly used as “lost formwork” in positions where conventional timber forms cannot be removed
following casting of the slab eg. suspended ground floor slabs on walls or beams.
Note that for smaller jobs the option of non-composite construction should also be considered as studs
are expensive and can make erection more difficult.
It is therefore important to select a structural arrangement that takes full advantage of the permanent
formwork system. Commonly for a rectangular grid this takes the form of secondary beams spaced at
regular intervals that allow the metal sheeting to span without props.
Primary beams span the full distance between columns in the opposite direction. In unequal rectangular
grids, the secondary beams should span the longer distance.
Be aware of the preliminary mechanical services design as large penetrations in steel beams can cause
problems and should be avoided eg. avoid putting a deep, heavily loaded beam across the path of an AC
run if possible.
19.3 Sizing
The beams are designed elasticity for construction loads, wet concrete and self-weight; continuity may
be used where applicable. Deflection must be assessed and added to the working deflection in the final
composite state.
In the final state the beams are checked as simply supported composite elements under the working
loads. Stresses induced in the steel beam during construction remain and must be taken into account
when the final check is made. Steel flange stress often governs for an unpropped beam design and to
help this Grade 350 steel can be specified.
To reduce dead load deflections use pre-cambered beams.
Propped Construction
For continuously propped arrangements the beam is assumed to be unstressed during construction and
therefore the system is checked in the final state to withstand all the loads by composite action. Again
the elements are designed as simply supported.
If an alternative propping arrangement is used eg single prop at midspan, it may be possible to use the
stresses induced in the structure during the construction phase to advantage for the structure in its final
composite unpropped state.
Shear Connectors
Shear connectors facilitate composite action between the steel beam and concrete slab. These are fixed
to the beam either by:
Profiled sheeting on site, or
In the fabrication shop.
19.4.3 Software
OneSteel
Lysaght W-dek Design
Lysaght Bondek Design
20.1 Introduction
The section describes the design of flexible pavements subjected to the heavy loads.
Normal 175
4 10 20 4 10 20
load (kg)
Notes:
i. The Table has been based on average axle loads, from typical tow-axle forklift trucks
ii. Axel loads are average, maximum fully laden axle loads
For point load, a load factor is used and correction has to be made if the loaded area is small
compared with slab thickness.
For distributed loads, one design objective is to limit tensile stresses in the top of slab in aisle ways
so that cracks will not occur.
151-200 3.5
201-250 4.0
100 SL62 24
125 SL62 24
150 SL72 24
175 SL82 28
200 SL82 28
225 SL92 32
250 SL92 32
275 SL92 36
300 SL92 36
21.1 Introduction
There are two major categories of precast concrete:
Structural elements
– Slab systems (hollowcore slab, plank)
– Beams (single T beams, double T beams)
– Walls (tilt-up walls, precast wall)
– Cores
– Columns
Non-structural elements
– Facade
Consider the following key items when doing detailed design:
Material: The correct materials must be specified to achieve the quality of finish and colour required.
Size, colour and quality of the aggregate may need to be specified to obtain the final appearance.
Design for the strength and serviceability requirements of AS3600 and the Precast Concrete Handbook
(NPCAA & CIA) or use manufacturers’ design charts (Figure 38, Figure 39, , Figure 40, Figure 41, Figure
42 , Figure 43, Figure 44 , Figure 45, Figure 46, Figure 47 and Figure 48).
21.2.1 Sizing
It is normal for the manufacturer to participate in the design process with the design team as well as
providing advice on costing. The design of hollowcore floors is usually undertaken in two stages:
Preliminary design – the general layout, the overall dimensions of the planks and the typical details
are selected to suit the building requirements; and
Final design – the details of the planks such as strand pattern connections, embedded items are
decided and the shop drawing produced.
For the purpose of conceptual design, size of hollowcore plank could be chosen from:
Live load capacity table (uniform area load, refer Figure 38, Figure 39, Figure 40, Figure 41, Figure
42, Figure 43); and
Equivalent load distribution method chart (FTP method, refer Figure 44, Figure 45, Figure 46 and
Figure 47).
Note that propping requirements may impose loads onto floor slabs and need to be reviewed.
22.1 Introduction
This section is intended to be further developed to include all aspects of design outlined in Key Issues,
below. Initially, it addressed only structure serviceability and joints, issues considered most likely to lead
to unsatisfactory performance in concrete water retaining structures.
The other issues raised, while important to the outcome of design and construction of a water retaining
structure do not, in GHD’s opinion, have the same immediate (negative) impact on a structure, and on its
fitness for purpose. That is not to say the other issues are not important, and their impacts on a structure
need to be considered.
There have now been additions made to this guide to include many of the other design aspects, such as
concrete quality and mix design, minimisation of cracking, estimation of peak temperatures, design for
earthquake, etc.
The types of water retaining structures that are required to be designed are (generally) those at sewage
treatment plants and those at water treatment plants
The principal difference is that water treatment plants are essentially above ground and sewage
treatment plants are below ground but there are some common requirements for these structures.
Control of cracking
Satisfactory joint performance
Quality of concrete and concrete placement (porosity, voids, boney areas)
Life Cycle Performance
Ease and cost of construction
Durability
Resistance to contained liquid over the long term, both in terms of leakage, and degradation of the
structure.
Ability of owner/operator to maintain structure
The Code Commentary further elaborates on the code philosophy, and provides background to the
rationale adopted.
Note that while the Code does cover all aspects of serviceability, it really only gives coverage to flexural
strength. This means that a working stress approach is mandated for serviceability and flexural strength,
but designers must use current limit state provisions from AS 3600 for shear strength.
22.10.1 Overview
An overview of serviceability issues for concrete water retaining structures is listed below. More detailed
discussion is in the following sections.
AS3735 Section 3.1, serviceability dominates, check for strength
Relate Section 3 provisions to Commentary
Minimum reinforcement ratios set on the basis that cracks must be controlled in both width and
distribution
Key provision is to limit crack widths by limiting reinforcement stresses
Reinforcement must be considered in conjunction with a defined jointing rationale
Avoid joints wherever possible
Practical maximum regular structure size without expansion/contraction joints 50m x 50m, 50m
diameter
Quality foundation required
Design of rectangular tanks or sumps not explicitly covered in Code
Provide effective underdrains to control hydrostatic loads and assist in leak detection
For large steel stresses, the effect of tension stiffening is small, and a reduction in spacing for a given bar
size and stress leads to a REDUCTION in crack widths.
Conversely, for small steel stresses, the effect of tension stiffening is large, and a reduction in bar
spacing for a given bar size and steel stress leads to an INCREASE in crack widths (because at small
steel stresses, better control of stress distribution leads to less cracks, but those that do occur are
larger).
In the case of temperature or shrinkage strains, increasing strain subjects the concrete to increasing
stress until the cracking strength of the section is reached. Further increase in stress is accompanied by
a decrease in section rigidity as the crack propagates. A point is eventually reached where the crack
propagation stops because the section reaches a rigidity capable of relieving the stress without further
deformation.
The section rigidity reduces to a value where stress cannot increase further, as there is no restraint to
strains which generate the stress.
The basic import of all of this is to carefully consider restraint on a structure, and reinforce the structure
accordingly. There is a tendency to take the reinforcement reduction factor of 25% in the Code as a
potential cost saving measure, and to justify using it by inserting joints.
In GHD’s experience, it has often been preferable to delete joints, treat the structure as fully restrained,
and reinforce accordingly. Often, better quality control can be maintained on reinforcement and concrete
placement than joint installation.
This also relates to temperature stresses that a structure will experience in service. In Melbourne and
Southern regions where daily and annual temperature variation can be substantial, no reductions should
be made. In Brisbane and tropical climates, the daily and annual temperature variation is much smaller,
and reinforcement reductions are possible.
22.11 Waterstops
It has been common practice for 10 to 15 years to use hydrophilic waterstops which sit on the upper
surface of the base slab. Wall kickers on the base slab are no longer commonly used.
Provided the contractor seals the bottom of the form to prevent the grout leaking from the concrete, the
use of hydrophilic waterstops is now the preferred construction method.
In slabs, it is recommended that rearguard water stops be placed on sill beams. Sometimes, if the
designer specifies a no-fines concrete underdrainage layer, a fibre cement sheet can be embedded into
the surface of the no fines, and the rearguard can be placed on that.
This means there is a transition from a PVC rearguard waterstop system beneath the slab to a
hydrophilic system above the slab. The connection between the two can be done with either a vertical
mitred PVC waterstop or a hydrophilic waterstop over the depth of the slab.
If there are expansion joints, then a PVC system must be used in slab and walls.
Examples of typical details used for waterstops and joints are illustrated in Appendix H.
22.12 Joints
Given that movement joints in water retaining structures are often the source of major leaks, these joints
should be avoided wherever possible.
In most cases, this requires the designer to consider designing and detailing reinforcement for a fully
restrained structure, with consequent significant quantities of reinforcement to carry thermal and
shrink/swell loads.
When you add the serviceability (strain) load cases within the structure itself to externally applied actions
in larger structures, stresses in sections can quite quickly become extreme.
A functioning and effective network of underdrains linked to pits outside the main structure can assist in
reducing or preventing external hydrostatic loads. For constantly full structures, this may not be an
issue, but nearly all structures need to be emptied for maintenance, and substantial damage can occur
when structures are emptied (buoyancy loads).
Perhaps just as importantly, if the structure is leaking, flowing underdrains can reveal the leak and even
quantify the extent of leakage.
23.1 Introduction
This section provides guidance in selecting bulk solids container geometry and components, references
in determination of loads and procedures in structural design.
23.2 General
Bulk solid container structures include bins, silos, bunkers and dump hoppers. They are typically used for
the storage of bulk materials in mining, agricultural, food and chemical industries.
Calculate initial frictional forces on vertical walls as per Clause 6.2.2 of the code. These will increase
linearly with depth.
Determine initial normal pressures on hopper walls using Clause 6.2.3.3. of the code.
Where applicable, also calculate initial forces on container closures. These forces are initial pressure
on the flat-bottomed bin and horizontal shearing tractions acting outwards from the centre of the bin.
Calculate frictional tractions on hopper walls from initial material load from Clause 6.2.3.4. of the
code.
Hard lumpy material can increase hopper wall loads when dumped into the bin. Where insufficient
material is left in the hopper, local effect due to impact load on hopper wall needs to be investigated
using Clause 6.2.3.5. of the code.
The procedures are then repeated from the beginning to determine the loads induced by flow during
symmetrical discharge. Methods of determining these flow loads are in Clause 6.3.
Figure 51 shows pressures and tractions on the container wall and hopper from the bulk solids during
both filling and discharging. Abrupt increase of load is observed at the transition from container wall
to hopper.
6.2.2 Eccentrically Filled and Discharged
For special cases of eccentrically filled and discharged bins, initial and flow loads on bin walls are
calculated in accordance with Clauses 6.4 and 6.5 respectively.
6.2.3 Other Normal Service Loads
Other normal service loads acting on a bin and its support are covered in Clauses 6.6 to 6.12 in AS
3774. These loads include the following:
Loads on gates and feeders from stored material. Consideration should be taken for the increased
loads due to large drop height and rapid fill rates.
0.5
1.0
1.5
Effective Depth (m)
2.0
2.5
3.0
3.5
4.0
4.5
Norm al wall pressure - Filling Wall traction - Filling
Norm al wall pressure - Discharging Wall traction - Discharging
23.10 Maintenance
To avoid problems with bulk solid containers in service, regular inspection should be carried out
according to a preventative maintenance plan. Factors in determining the frequency of inspection include
the type of container and bulk solids, nature of current defects, type and frequency of overloading, future
use, degree of difficulty of repairs, environment, and consequence of failure.
23.11 References
AS/NZS 1170.2-2002 “Structural design actions – Wind actions”
AS 1170.4-2007 “Structural design actions – Earthquake actions in Australia”
AS/NZS 2312-2002 “Guide to protection of structural steel against atmospheric corrosion by the use of
protective coatings”
AS 3600-2009 “Concrete Structures”
24.1 Introduction
24.1.4.3 Construction
Construction durability tasks include the below:
Develop optimum materials technical performance
QA/QC focusing on durability critical issues
Site trials relevant for all materials
Contractor’s method statements
Materials evaluation
Critical durability construction processes
Cathodic protection and prevention systems
Corrosion monitoring systems
Troubleshooting construction difficulties
Resolution of technical noncompliance and any disputes
Review to confirm acceptable durability has been achieved prior to issue of works practical
completion certificate
Buildings, including exterior façade and below water level basement levels
Bridges
Elevated Viaducts
Tunnels
Wharf
Water
Water Tanks
Water Treatment Plants
Wastewater Treatment Plants
Pump Stations
Desalination Plants
Dams
24.2.3.1 AS 5100 Definition of Design Life Words (check present day Standard)
Serviceability Limit States include:
– Permanent damage due to corrosion, cracking or fatigue, which significantly reduces the
structural strength or useful service life of the structure.
End of Service Life is Defined to occur when:
– Deterioration progresses to a level that makes the structure unsafe or unserviceable.
– The level of maintenance necessary to maintain the functionality of the structure becomes
uneconomical.
24.2.3.2 AS 4997: Definition of Design Life Words (check present day Standard)
The period for which a structure or structural element remains fit for use for its intended purpose with
appropriate maintenance.
Condition at end of design life:
– Adequate strength to resist ultimate loads
– Be serviceable
– Further deterioration Inadequate structural capacity
Concrete structures need individual assessment to be durable.
Environment 2 Within permanent Permanent bodies of water including oceans, rivers, drains,
water estuaries, lakes etc.
Environment 3 Natural ground The local soils below the peak of the water table. A region
below water table of these soils will be subject to season wetting and drying
with the rise and fall of the water table.
Environment 4 Natural ground The local soils above the peak of the water table. However,
above water table still subject to contamination and wetting due to flood
waters, irrigation and precipitation.
Environment 5 Specified fill above Fill with no PASS or significant residual salts (e.g. no
water table chlorides, no sulphates) and neutral pH.
Potential for contamination by saline ground/flood waters.
Environment 6 Intertidal and splash The region surrounding the mean saline water level subject
saline zone to changes in the water level. Includes tidal movement,
waves, seasonal variations, frequent flooding and splashing
from water traffic.
Environment 7 Spray saline zone Region immediately above the intertidal and splash saline
zone. Only considered in locations where wave action
generates spray.
a) AS2312:2002, Guide to the protection of structural steel against atmospheric corrosion by the use of
protective coatings.
b) AS2159 Supp1-1996, Steel piling.
c) German Gas and Water Works Engineers Association Soil Corrosivity Assessment Technique.
d) Langelier Saturation Index, and Ryznar Stability Index: Scaling tendency.
24.5.1 General
This section outlines typical potential durability issues for reinforced concrete elements.
A general overview of reinforced concrete durability issues is separately available from MTG. The
general overview is reviewed and those project specific potential durability issues for reinforced concrete
elements are taken into account at detailed design.
b) Cracks as thin as 0.1 mm can allow the penetration of moisture under piezometric head. The rate of
flow will depend on the piezometric head, thickness of section and tortuosity of the crack.
c) Where cracks form at an early age some level of sealing will occur due to a process known as
autogenous self-healing. This process will occur at early age and after water filling a Tank. The
extent of such self-healing is difficult to predict being dependent on a number of factors including the
crack width, cement binder type, rate of flow, water composition, time of water flow through the
crack, etc. However, self-healing can be confirmed by core sampling and examination of the
retrieved concrete core, and/or observation of water leakage through cracks over time (i.e. whether
self-healing seals the crack).
d) Where flow through cracks exceeds acceptable limits cracks, the crack may be sealed by a variety of
methods.
24.5.6.1 General
The thermal/restraint and shrinkage modelling of concrete early age behaviour completed can result in
additional reinforcement recommended above reinforcement ratios compliant to design by Australian
Standards to limit predicted crack widths less than specific values (e.g. say less than 0.3 mm width for
general structural concrete and 0.1 mm width for water retaining structure). The thermal/restraint
modelling is completed to approaches given in Concrete Society Technical Reports, Construction
Industry Research and Information Association publications and GHD’s in house experience. Risk
management decisions are considered when relevant, such as suggestions to include additional
reinforcement based on the reduced likelihood of crack widths greater than specific values.
24.5.6.3 Concrete Thermal/Restraint and Shrinkage Crack Formation Highest Risk Positions
The hydration reaction that takes place when cement is mixed with water is exothermic and the volume
of concrete will expand and contract as it heats up and then cools back down to the ambient
temperature. If the concrete is restrained (unable to move freely) in certain locations, this expansion and
contraction may result in the concrete cracking. Commonly the highest risk locations for crack formation
are:
a) Wall vertical cracks from restraint by prior cast floor, primarily forming from the floor base up the wall
and between prior cast wall segments.
b) Floor slab cracks from restraint by prior cast floor segments, forming from the prior cast floor
perpendicular inwards and between prior cast parallel floor segments
c) Roof cracks from restraint by prior cast walls, forming from the walls perpendicular inwards and
between parallel walls.
d) Mass foundation cracks from restraint by the base, or prior cast base and adjacent vertical elements.
The widths, location and occurrence of these cracks can be predicted using concrete Thermal/Restraint
and Shrinkage Modelling and can be controlled by a range of measures (e.g. suitable placement of
reinforcement).
b) Reinforcement can be used to control crack widths to less than the design limits, after the pour
sequence is finalised by the project team (i.e. input from designers, construction staff, durability
consultant, premix supplier on concrete mixes, etc.).
c) Concrete placement temperature kept as low as practically possible via interaction with the project
team and chosen premix supplier.
The concrete thermal/restraint behaviour and crack risk assessment completed at Detailed Design stage
is a guideline only. The concrete thermal/restraint behaviour and crack risk assessment must be re-
assessed after the final construction sequence is confirmed.
To resolve uncertainty from design assumptions to actual construction environmental conditions and
selected method of construction the Specification is recommended to include a requirement for the
Contractor to complete a Thermal/Restraint and Shrinkage Crack Risk Assessment. The Contractor
would need to take appropriate actions to achieve the target acceptable concrete crack width.
24.5.7.1 General
Vertical and horizontal construction joints in reinforced concrete will create restraint for the concrete
element cast against prior cast concrete. The concrete pour sizes will be selected to practically minimise
the number of construction joints.
c) A sloped fall inwards for all below floor thickened sections (e.g. ring beam below external wall inner
face) instead of a vertical inner thickened face will provide reduced floor base restraint and reduce
the need for construction joints.
24.6.1 General
This section outlines typical potential durability issues for metal elements.
The MTG Current Practice Guideline on Steel Corrosion gives a general overview of durability issues
and is separately available from MTG. The general overview is reviewed and those project specific
potential durability issues for metal elements are taken into account at detailed design.
b) In general, proprietary brand products have an acceptable record of service for specific intended
service life, so long as the correct grade of material is selected for the exposure conditions.
24.6.4 Fasteners
The category of fasteners includes fasteners for roofing/cladding, holding down bolts, structural steelwork
and mechanical/electrical works. Fasteners are susceptible to the general atmospheric and aqueous
corrosion. However, there are three other important corrosion issues related to their application that
should be addressed specifically.
a) Galvanic corrosion can occur when dissimilar metals are in physical contact in the same electrolyte.
To avoid this problem the design should provide for appropriate fixing materials and insulators
specified for the given element.
b) Crevice corrosion can occur along interfaces where two elements are joined. For example, where
beams are butted against one another, or between the head of a bolt and the surface of a beam
web. These areas are susceptible to increased times of moisture residency and the formation of
concentration cells where depleted oxygen levels can promote localised corrosion. This problem can
be alleviated by the careful design of joints, material selection and the use of insulation between
joints.
24.6.5.3 Internal
The main durability issues for the internal surfaces of MSCL pipes are corrosion and wear. The following
can all cause premature failure of the internal coating system and pipe:
a) Cracks or debonded cement lining.
b) Exposure conditions.
c) Galvanising grades as appropriate.
d) Coating systems.
24.7.1 General
This section outlines potential durability issues for rubbers/elastomers, protective coatings, sealants and
adhesives.
24.7.2 Rubbers/Elastomers
Rubber materials are typically used as gaskets, o-rings and seals in the desalination plant. The types of
rubbers typically used are ethylene propylene diene monomer (EPDM), Nitrile (NBR) and Viton.
24.7.2.1 Loads
Rubber gaskets can be mechanically damage by over tightening of flanges. The use of torque wrenches
and controlled operational procedures will increase the durability of these materials.
24.7.2.2 UV Degradation
Rubber materials exposed to UV can degrade and thus must either contain UV stabilisers, pigments or
carbon black evenly dispersed in the compounds.
The rubber type and grade selected shall resist deterioration in the conditions of operation.
24.7.2.4 Temperature
Rubber materials selected must be suitable for the temperature of operation. Long term exposure of
rubber to elevated temperatures can cause degradation. Effects shall be evaluated prior to material
selection.
24.7.3.1 Standards
For potable water tanks, the internal coating must have AS/NZS 4020 approval and appropriate
conditioning procedures followed.
AS 2312 Guide to the Protection of Structural Steel against Exterior Atmospheric Corrosion shall be
followed where applicable. Specifications for each coating system will be required. APAS (Australian
Paint Approvals Scheme) can be used.
Surface preparation is essential to the durability of all coatings. For coating of metals, AS1627 should be
followed.
24.8.1 General
This section outlines typical potential durability issues for waterproofing of reinforced concrete structures.
Waterproofing of cracks in reinforced concrete structure due to concrete thermal/restraint and shrinkage
is covered in the Reinforced Concrete section which includes sealing of cracks with proprietary products.
This section looks at potential durability issues of waterproofing of joints in construction.
24.8.2 Waterstops
Waterstops are typically PVC or hydrophilic material embedded in concrete joints and some waterstops
allow movement of the joints. Multiple waterstops are often utilised to minimise the risk of water leakage.
Waterstops are unlikely replaced during the service life of the structures therefore appropriate material
must be assessed for likelihood of moisture and contaminant penetration through the joint causing
degradation of the waterstops.
Particular issues to be considered include, but are not limited to, access and joint preparation
requirements for satisfactory installation including water ponding test.
24.8.4 Sealants
Sealants are generally used as waterproofing barrier in additional to waterstops to minimise the risk of
water leakage. Suitable sealants must be selected to take up joint movements and likelihood of moisture
and contaminant penetration through the joint causing degradation of the sealant and loss of
waterproofing barrier. Sealants are expected replaced during the service life of the structures and
therefore consideration must be given to how and when all sealants will be replaced or injected.
Particular issues to be considered include, but are not limited to, access and joint preparation
requirements for satisfactory resealing including water ponding test, and specific requirements for
exposure to chemical spills in affected areas.
[check if the new structure is classified as “post-earthquake recovery structure” before list out all the
parameters]
Structure classification [?]
Acceleration coefficient [?]
Site factor [?]
Importance level [1.25 or 1.00?]
2 .5 Geotechnical loads
[lateral earth pressure: as recommended by GIR]
For all the structure design, the individual load cases will be combined in accordance with relevant load
combination specified in AS 1170. Following load cases shall apply [delete inapplicable ones]:
Case 4 1 1 0.7 1
3 .2 Serviceability limits
Following deflection limits are suggested for the serviceability limit states:
Load G Q Ws Imposed
case Dead
Case 2 ?? ?? ?? ??
5. Geotechnical information
Refer to Geotechnical Investigation Report prepared by [??? on ???].
5 .1 Subsoil condition
CA NTIL EV&S
'iw
c b—4 a
L I' L -
Wx2
Wa
Mmax 7
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
Frjp Izçjg
cwrved—raight I—
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
° W(&+/8a2b+/2ab3b3)
24E1
dmaxfJ(' +Ja) _______________________
2W
___ I/A J/Q
a b— c— ____ ____
L. L
N
i aj
______
RAW
4.— curved .4strai'ht f_-
CA NTIL EV&S
'iw
c b—4 a
L I' L -
Wx2
Wa
Mmax 7
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
Frjp Izçjg
cwrved—raight I—
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
° W(&+/8a2b+/2ab3b3)
24E1
dmaxfJ(' +Ja) _______________________
2W
___ I/A J/Q
a b— c— ____ ____
L. L
N
i aj
______
RAW
4.— curved .4strai'ht f_-
CA NT/LEVERS
9 w I 2W
________L________ b
-I ________L 'I
M _T()_2] Mmax = w( 4)
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
1 IIi
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
llWp—j
°'C 60E1 W(2#SOo2b,4Oab2-H/b)
/SbI dmox 60E1
dmax Jf(i+ i7)
IA a b— a
L L s.j
Mx IX Mx = MC
M,,,x— P a
No shears
A[ I
w/z
IA B
T L L
RB
// —
T
N
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
R8
W
RA=RB T 94 R5
_ 012
2°I'ZL/
2/ when x1—
ien .;—
RAfl\ 'RB
_______ RB
When xa
djmt2n(2n)d#n2(242m]
When xo
dmax j.j (8?_4Lb2#b3) d4where mx/L and naa/L
Steel Designers' Manual - 6th Edition (2003)
L 84
p8
M Mx = Wx( 2)
A4nqx. —O•/28WL — WL/6
when x,=0•5774L
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
II
= WIS
.x;. I R8
RA=RB =
RB 2W/S
4,dmcx Jdmax
0.0/304 wi! WL5
dinax 60(1
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
51
when x =05/PJL
AA'F
T.—a b
BA
-F a
L
"A B
A5
RR8 wft
j dc,s i,dmax.
d, ur=ëi(85,7aLL4c2L4I) —3iffk1
Steel Designers' Manual - 6th Edition (2003)
£k"\
M- '"cx. 6 Mmcx _(_m# 'j)
N iW,en x—
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
NRa
'A=B= W/2
Wm
R8 —
lOab# 5b2)
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
_____ RB
z_
RA[ when x= a/i—
— R8—w/2 _______IA
4/max.
B .7
dmxJi(/5a2#2Oabi'.5b2)
Steel Designers' Manual - 6th Edition (2003)
L
pa
V A4nc P
M,,,— T
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
I I I I
I IB
'4—R8— . RA-R8-P
J/nax. J/nax.
°;nax.
PL3 -
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
a>c
"C ,,Ppib*Zc)
L
Pc(b#2a)
MD— L
I I
— Pb/L Po/L
P(b *)
LH
L
always occurs within Pot central deflection
00774 L of tfie centre of the beo,n odd the values for each P
When ba, derived from the formula
d PL3rsa Ia i7
centre 48E1L L (LII in the adjacent diagram.
This value is a/ways with/n
S % of the maximum value.
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
RAI
MC=ME
I
Steel Designers' Manual - 6th Edition (2003)
I
=P
Mmax r
dmax = 304(1
PL
/9 P1!
dmczx. 23PL3
648(1
dp
JB
A*C
MC Mf —
PL
MD
— — 2P
768(1
4/PL3
din ax. — SJPL
dinax.
Bending moment, shear and deflection
SPL
1083
Steel Designers' Manual - 6th Edition (2003)
'9
When n is odd.
MDME!fL Mmax —
(nL /) p1
When n is even.
R8
'4 B("')'%
A4 —A8 "2P
;,2'max.
6JPL
dmax. 1000E%
When n is odd
PL3 r i7r it /
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
When n /5 even
dmaxiuu,p4,. . nft_ :# )J
TOTAL LOAD
Value otn A C k
2 0 250O 0.1250 O• 0/05
S
4
0.3333
03750
0/I/I
0.1250
00118
00/24
5
6
Q.4
04/67
01200
O•IZSO
0.0/26
OO/27
7 O4286 0/224 0•0/28
8 0•4375 0•1250 00/28
9 04444 0/236 00l29
/0 O•4500 0.1250 0•0/29
Steel Designers' Manual - 6th Edition (2003)
L '.1
A CI BA MA(,
a
L
+ b—I ___________'M8
1 MA
®M4>M5
MA
Al8
Al4 — MB
A4 A5 M/L
As shown
ML2
For anti-clockwise moments dmcxaii —y
KiI
the deections are reversed ____________________________
2nd degree_parabola. W
L
'°1
Complement of parabola.
Mx -i (m4-2m#m) Mx (mJm2#4m1_2m4)
— Mmq .LfL
RAflJ R ______
/6
A4—R5—W/2 ,IA_R8_W/z
dmqx
w unit /oao'
/W.unFt /oaoç
C A 0 B CADBfl
L NH A5
- MA=MB=-
RD
L,
AAI
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
—4..',,
rTA
_
d4f(
RA=RBWN
dc=o_4(jn3,Ln2_ i) fC
(s-)
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
wL2 N
/6(1
Where
boo w— unit
/W.unit
CiA
-HNI
BAD
'1QH- L
0 BE
—j O•5774L
IQH
L
_4J4 A
Max. upward deflection is at 0.
NIA
___ W(L#N)(LN)
m.x/L ,,1.N/L
Steel Designers' Manual - 6th Edition (2003)
8(J/LT—/N BEAMS
H
-- b-
L -4
WL
MA=MB
EN
WL
MC
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
4B WI? = = w/2
—.10g/L .—O s8L—.12/L p—
____ I /dflfl
= WI! -J Wa / I
'-jvl
V4—a-4..—b- "+ c—4 'Ak—- L— -
in
MA
B/JILT-/N BEAMS
LA L
8 A C ___
M
MA ___________M8 MA V NMB
- WL 7/Qx 9x ) M- SWL
-
RB
R8
R=O.SW R8=O7W RA=RB=W/2
—4J•22LF—O S6L —Ø22L
WI! — 1.4W!!
max. - 384E1
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
when x, = 0• 525L
La- b—+_aJ
L—4 ____C
F I.
MA M8 (SL44aL_402) MA = M8 -WL//6
M=WL/48
R8 W/2 A = R3 W/Z
JRB
. L/2 —H ¼
O-WL3
364(1
Steel Designers' Manual - 6th Edition (2003)
B(//LT-/N BEAMS
2W/a
fwTw/a
L ____ L
b
MAV NMa
MA MA =-J'2(Jo/obL)
M3
mAC.
Mx =P.X+M3- 2W(x.-bP
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
InCB.Mx RB.X#M5
AB W/2
A = (/OL—sLa42a)
____ I /d____
____ , prO,,
2
4 —
dmax = Wa /
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
-Y HJ
W/2
—a I
W/a
b
L
-f
W/2
I.
W
L
b
.1
1NMB MA
MB
MA Maz_R(4L_3a) MA — _!10L_15#502)
M3 _lOL2(5L4t
= = W/2
= (/oL-/sLa'#8a)
R = '/5L —ec)
dmax = (/SL—Ma)
Steel Designers' Manual - 6th Edition (2003)
BUILT—/N BEAMS
parabolic total /oao W con,c*ment
parabo/p
JRa
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
r
Any symmetrical load W
A ______
symmetrical diagram
rA
2br
a rb
2 -2br----—-
NMB
aab r&_
MA = M8 —A,JL
where A5 is the area of the 'free'
bending moment diagram
CM. f(Ja—L)M8c -M(3b-L)
When
A
RB '4I
A =R8 = W/2 = P8 = slope of moment diagram
M#M M#M
Eab
- - I The fic.re shown
A, is ha/f the bending
* + moment diagram
fr- X, - C 1* and +7
H-X--- LareC.GI When '2/L = in,
A5x —AIX1 M. L2m2(/_m)2(1_2m)
lmaxatC ZET 2E%
Where A' is the area of the fixing For ant/clockwise moments
moment diagram reverse the deflect/ons
Steel Designers' Manual - 6th Edition (2003)
BUILT—/N BEAMS
p p
4mcx p9
dinax = /92
I.— X
dC—
— __
Po3b3
El
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
d _ZPa2b3 WñQnX=
"3EI(3L2a)2 JL-Za
p p p p
MA—MB—
Pa MA/ \MB
- __Pa(L-q) MA=MB=_JPLh6
L
MC MD = P02,'L MC =MD =
RAfl
LJ AI I
PA=P'P
II
dmax PL
= /30(a)7
Steel Designers' Manual - 6th Edition (2003)
BUILT—/N BEAMS
p
______
fA C
P
D
p p
Irg
'.—L/y —1--L/j —.—L/j. l,L/3 P.-L/3L2
MA MB MA LF- 5N M8
MA =M8 = — 2PL/9 MA =M = —/9PL/72
MC =MD = PL/p MD =1/
AL I
PArJ__LJA
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
RA = JP/2
S PL3 4/PL3
dmax 548?1
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
p pp PPpp
II
A C D +
£ +
BL 34C D E 1I
PB
L/4--L/4 L/4 L/4 L/L/4 +L/4 +L/4 4L14
2P
— PL3
dmax —
96(1 max. = 96(1
Steel Designers' Manual - 6th Edition (2003)
BUILT—/N BEAMS
p pp p ppppppp
A CVt
L/5 +Lg +L,/s+L4
P 4 (n-i) forces
I I
B
sôcev,naLJ,
MAMALNMB
M52PL/5
MA P1,'/)
MA=MB=—
MD wM — PL/5
AArL
HJ
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
'A B=2'°
-
Y1F,ennisoø6 ,I / /
dmax.=1000
13PL3
El
Cimox 114-4c (,ji
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
Whennis even,
EfIiiiitiIII
•:.:i••
COLUMN
LOAD PER SA4NW
O...o.&. ,.
n CONTINUOUS BEAM
}d L/n#-+-L/n4L/n+-L/-#L1-+-44
L
4;.' •O4•4•.
-
L. - When n >10, consider the load .nitorrrdy oYstiibuted
The load on the outside stringers is carried c'/rect/y by the supports
The continuous beam Is assumed to be horizontal at each support
The reaction at the supports for each s,oan = W/2. but the maximum
shear force in any span of tM continuous beam = V/J.IAW
The value of the fixing moment at each support = — B. WL
The value of the maximum positive moment for each span = C. W4
The value of the maximum deflection for each span —0'0O26
Value ofn A B C
2 02500 00625 0•0 625
3 0•3333 0074/ 00370
4 03750 0078/ 00469
S 04000 0-0800 0•0400
6 04/67 Qc// 0•0439
7 04286 0O8/5 00408
B Q•4375 00820 00 430
9 04444 00823 004/3
10 04500 00825 00425
Steel Designers' Manual - 6th Edition (2003)
/w W
A C B ___ a C
-f-b
MA
—--_J P8 1
P3 =f RAi4J[8n2(4n)]
x/Lm P3 Hn2( fl)
LA'max.
dmax.— WL3
- ____
/W
A C B BA
L
b .f- c—.J
Web L°'
MA
'P MA7tS
MA=— MA =— d2-c2)(29c2_c12)
AI
J2 (o - n 2)
-____
L R8=r5—
= f (n'-n-pi.e) Where and r3 are the simple
support reactions for the beam
(MA being considered positive)
a, d=J42/n3(3n?-6b5
When x a.
dj[2p4—p3n (n-6n,'.8)+
_________ pn2(jn2_8n #6)]
Steel Designers' Manual - 6th Edition (2003)
PROPPED CANTILEVERS
W/2 W/2
1'
CU BA
—f— a -H
L
MA
'9:4
RB
Vx i(9_rn2)
= (2i."#soi. 42) A PB =
p8 = (2L2_30L#40')
- OO0/WL3
El
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
When x=0•598L
W/? W/2
-L
RB
MA
3WL
MA
#MmaxO0454 WL
[When x 0 283L]
=4W
T RB = * p_L
A- /3W
B - 32
- 0•0047WL'
dmax (I —ii
When x=O•447L When x=0404L
Steel Designers' Manual - 6th Edition (2003)
PROPPED CANT/LEVERS
a
_____
L
C BA
A a _____
iR8 L A5
___S___
I
0•577b
0/28 Wa
MA
MA
_________________ JL
BQt we en
CandA, Mx=R5.x-j!('x-b) M5=R5.x -
=_ j9(si.2_j,2)
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
(JaL/5aL#2OL2)
#Mmox when xb# fI/-
W P5 A8 = (t+SaL2)
2W
2W W
__________
C
____________ -
____ a " b—' 4—a______
.. L b____I
L R3
H0577aH 0/28 Wa
f—x —
Wab
H042Jb—
MA
When ,n=a/L 2
3m#2 I
MC=AB.b MA=_f/0L2-3b2)
Between AandC RA I
=RAW52/a2
_______________
}.—x--H \ IRS
Between C and B \
N
I
Vx=RA_Wrc24Z
PROPPED CANTILEVERS
W.iw4,
fAA 51 CD
1. L
I Wa2
M5=—2M— F
c-'3'L
8TN
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
.jwap
d0 WL4f2(ep#4?q#dp3(p#i)J
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
- Omax. —
54(1
IJA
'1. L
8+ CD
1.
M
'1
84 'C 0
4I
q
Tfl
- 8 =-
— dmax I0'O
Ido
= j4p2,pq#Jp #Jq) a#b)#a2(2# VJ
d,n0x '-dmax"
27(1
Steel Designers' Manual - 6th Edition (2003)
PROPPED CANT/LEVERS
W/2
+
AB na/L *7/q
Wa
W'?Qn X< a,
tl =(9,r?x —/2nx# /2x— 4xg2)
+Mmax occurs whQn
A r—\
NB
A -(4L?#ZaL— az) (4L2 #4aL—JoT
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
R8 W—
W
I w
a —+—b —+-—a —4
L kO.4/SLtq
—L——-——--R8
MA7Z
I—
MA
32 A Bj A477(2/1!#4aL 4a2)
/ A8
—
Steel Designers' Manual - 6th Edition (2003)
PROPPED CANT/LEVERS
!F051
coIr4oleraQnt of parabola
SWL — SWL
M .('/Om-ZOm#7m) Mx =(-4om+8om-om4I7m)
#My,OO888WL,when X #Mmax*O0399WL,whQn x —
0 •3965L 02343L
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
A6
7W
B—
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
MA
F9 7PL
7(%
dmax'OOOPJ2
ft3
A3=f3b#2L) RAPR5
Steel Designers' Manual - 6th Edition (2003)
PROPPED CANT/LEVERS
Pp P
'4
ACDE
¼+V4+L/4 +-/4
MA MA
MA = — ISPL
D "E7
/7PL JJPL
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
PAL
4P 2P P AJ3 J2
Lj
dx 00152
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
dmax00209 zr
P P P P PP P
AC D EB* .4C DEFBA
L/L/3 Lb
MA MA
/9PL
MA=— 48
M0 -.96
M ....SJPL
£ 288
PROPPED CANILEVEPS
pppp P PPPP Pp
D E F19 forces B
L/4tL/4tL/44L/
MA
JSPL
MAE7ZTJ
PL(,,?l)
MA=— -— MA= 8n
Ad /S7PL
rT(— 5/2
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
P8
RAEL (5n2-4n-i)
RB = (34z_4fl#/)
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
whennis
GO•OZZl !or9e, dmax. /85(1
Any symmetrical load W
JA ____
I.
AreaR L AreoS'B
a=L
MA
VAr000 X
M-
If AArea of free B.MDiagram ® _r—
a>O423L
cO423L
a< O423L
A8
M1 9(2_6n#sn')
P82
=!—
L MCA (2— 6n# Pn?3ni
-Sn
It'B
dmax occurs at point corresponding L
to Xon M diagram, the area A In Case!, R — SM/ZL
being equal to the area 0 CaseS, A= M/L
Vmax = Area SXx
Steel Designers' Manual - 6th Edition (2003)
W\ —OO6J
0•096
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
W, —0.100 VA —0100 VA
ooeo O•OZS o 0080 0
o — — o
W 0.0s0 W
0•101 0101
o 0 0 0
o.o5o W\ 0.o50
0075
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
—0•117 W\
0073 0054
o "II 0
00P4
VA _______________
— 0049 W1 —0054
0
6
#00/4
0074
0 01 0
Steel Designers' Manual - 6th Edition (2003)
1W
This material is copyright - all rights reserved. Reproduced under licence from The Steel Construction Institute on 12/2/2007
To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.org/
Steel Designers' Manual - 6th Edition (2003)
1. INTRODUCTION
1.1 Introduction
1.2 History of Prestressed Concrete
1.3 Definitions
3. PRESTRESSING COMPONENTS
3.1 Prestressing Steel
3.2 Prestressing Ducts
3.3 Live End Anchorages
3.4 Dead End Anchorages
3.5 Coupling Anchorages
3.6 Flat Jacks
3.7 Prestressing Companies
6. DESIGN DETAILING
6.1 Introduction
6.2 Post-tensioned Slabs
6.3 Multi-strand Post-tensioning
7. CONSTRUCTION
7.1 Construction Operations
7.2 Safety Precautions
1. INTRODUCTION
1.1 Introduction
The first person clearly to define the purpose of prestressing, as inducing compressive forces
in the tensile zone of a beam, was the Austrian engineer J. Mandl in 1896. His aim was to
reduce the tensile stresses in the concrete under load, and thus utilise the strength of the
concrete as much as possible. The idea was further developed by the German engineer
Koenen.
In these proposals, the loss of prestress due to elastic shortening was taken into account, but
the effects of shrinkage and creep were ignored, and mild steel was tensioned to the stresses
permitted for reinforced concrete. However, this initial tensioning stress was to low and
shrinkage and creep soon reduced the prestressing force to zero.
Freyssinet claims 1904 as the year when prestressing was born. He resolved to substitute
“permanently acting forces for the elastic forces developed in the reinforcement”. In 1912
Freyssinet encountered difficulties due to creep when he built the bridge at Veurdre; but he
was unable to follow up the problem before 1926. From this investigation he concluded that
high-strength steel should be used for tensioning; this in turn led to effective prestressing by
the introduction of “permanently acting forces”.
In the 1920’s, RH Dill in the USA recognised that high strength wire could be used to produce
a satisfactory prestressed member. The first engineer to use the properties of high-strength
strands initially in construction, before Freyssinet, was Torroja in 1925. Another pioneer, the
French engineer Coyne successfully employed tensioned high-strength steel cables for
anchoring dams in 1928. However, only Freyssinet persevered with his idea of introducing
prestressing.
Freyssinet carried out the first successful practical designs in prestressed concrete in Europe
in the 1930’s, when the time-dependent creep and shrinkage behaviour of concrete was
better understood. After World War 2, Freyssinet designed a number of successful and highly
acclaimed bridges in France, which led to wide acceptance of prestressed concrete.
1.3 Definitions
By definition, a prestressing system is one that will pre-compress the member in such a way
that when it is subsequently subjected to load, the tensile stresses induced by the applied
loads are either eliminated or counteracted to a desired degree.
There are two basic forms of prestressing, namely ‘pre-tensioned’ and ‘post-tensioned’. In
both cases, a prestressing force is usually applied by means of tendons, which comprise
high-strength wire, strand or bar. The term ‘post-tensioned’ is frequently misapplied in the
same manner as the term ‘pre-tensioned’. In the correct sense, these terms should be applied
only to the steel, and not to the member or the concrete.
q In pre-tensioning, the tendons pass through the mould, or moulds for a number of
similar members arranged end to end, and are tensioned between external anchor
blocks, by which the tension is maintained while the concrete is poured. When the
concrete has hardened sufficiently the ends of the tendons are gradually released
from the anchor blocks. During this operation, known as transfer, the force in the
tendons is transferred to the concrete by bond stress. The length required at each
end of a member to transmit the full tendon force to the concrete is termed the
‘transmission length’.
q In post-tensioning, the concrete member is cast incorporating ducts for the tendons.
When the concrete has hardened sufficiently, the tendons are tensioned by jacking
against one or both ends of the member, and are then anchored by means of
anchorages that bear against the member or are embedded in the concrete.
The level of prestress adopted in the design can have a significant influence on the cost.
Frequently the most economical design is achieved by using limited prestressing, which does
not prevent cracking under the full service design load, but which is sufficient to control
deflections and crack widths and hence achieve good service load behaviour. Hence,
depending on the level of the applied prestress force, the member can be classified as being
either ‘fully prestressed’, or ‘partially prestressed’.
q In a fully prestressed member, there is sufficient prestress to ensure that there is no
cracking of the concrete under the applied service load. In the British Standard, this is
classified as either a ‘Class 1’ type structure if there is zero tensile stress, or ‘Class 2’
if the tensile stress is limited so that there is no visible cracking of the structure.
q In a partially prestressed member, tensile cracking is allowed to occur, with crack
control being provided by bonded tendons and often supplementary reinforcement. In
the British Standard, this is classified as a ‘Class 3’ type structure.
‘External post-tensioning’ refers to the practice where the prestressing tendons are placed
on the outside of the physical cross section of the structure. The prestressing forces are
transferred to the structure at the anchorages and at ‘deflectors’. The use of external post-
tensioning has major applications in the design of long-span bridges, and in the strengthening
of existing structures.
2. REVIEW OF PRESTRESSING PRINCIPLES
iii. Post-tensioned floors can save construction time by permitting early removal of
formwork and reduced back propping.
There are virtually no disadvantages, though there are certain restrictions. Prestressing
requires high quality throughout – of design, detailing, materials and workmanship.
In the design of reinforced concrete beams, it is assumed that the tensile strength of the
concrete is negligible, and the tensile forces created by the bending moments are resisted by
reinforcement. Cracking and deflections are essentially irrecoverable. The reinforcement
exerts no forces on the member on its own account.
In prestressed concrete, the primary purpose of the prestressing is to apply a force to the
concrete either by bond or by means of special anchoring devices. Hence, the whole of the
concrete can be made to act structurally. The prestressing steel is used actively to preload
the member and cracking and deflections are recoverable.
However, it should be noted that under overload conditions, as soon as the flexural tensile
strength of the concrete has been overcome, prestressed concrete behaves in a similar
manner to reinforced concrete, and at the ultimate load, the tensile and compressive
resistances required to withstand these conditions are the same for both the reinforced and
prestressed members.
At the anchorages, the prestressing cable exerts a concentrated axial load in the
direction of the tendon. If the anchorage is located eccentrically relative to the
centroid of the beam, then the horizontal component of the prestressing force will also
result in an applied moment.
Consider the case of a simply supported beam with a parabolic cable profile, with
eccentricity e1 at midspan, and anchorage end eccentricities eo above the centroid of
the beam. The resulting equivalent loads for the beam are indicated below:
2.2.2 Benefits of Prestressing
The benefits of prestressing can best be demonstrated by way of an example.
Consider two rectangular beams of identical dimensions. The first beam is a
reinforced concrete section with 3-N28 bars. The second beam is fully prestressed
with a single tendon, comprising 4-15.2 diameter strands. The area of the
reinforcement and prestressing has been selected to give the same ultimate bending
moment capacity for each member.
The key results for each of the beams, subject to an applied service state bending
moment of 200 kN-m, are illustrated below:
From the above results, it is evident that the prestressed concrete section requires
less than 1/3 the amount of steel compared with the equivalent reinforced concrete
section. It must, however, be recognized that the difference in initial cost is not
proportional to the difference in weights of the steel. High-strength steel is required
for the prestressing steel, and thus the unit cost is higher than for the reinforcement in
the concrete beam.
Another key benefit of prestressing is evident - the effective moment of inertia of the
partly cracked prestressed section is almost 3 times that of the reinforced section, as
the majority of the concrete section is effective for the prestressed element. This
results in a substantially stiffer element, with a corresponding reduction in deflections
and potential cracking.
2.3 Applications of Prestressing
Bridges and floor slabs account for a large percentage of prestressed structures, but there are
many other general and specialised applications that are sometimes overlooked.
In bridge construction, the advantages are obvious. For large spans, low rises and small
structural depths which would be impractical in reinforced concrete can be achieved, whilst for
shorter spans, construction depths are less so that there is improved appearance, lighter
foundations and greater durability.
The prestressing of building frames and floor slabs achieves considerable reductions in dead
loading with savings in foundation costs; reduces the number of columns, giving more
flexibility in planning, reduces cracking; and reduces the deflection of beams and slabs.
The prestressing of marine structures gives a longer life, due to the higher durability of
prestressed concrete. Railway sleepers are now almost entirely of prestressed concrete; and
tanks and other liquid containers, eliminates cracking, seepage and leaks. Pipes, poles,
masts, towers and other tall structures are often axially prestressed in order to resist bending
in any direction.
Specialist applications include the stressing of industrial ground slabs, roads and runways to
prevent cracking. In nuclear power station construction, the reactor pressure vessels are
typically prestressed because of increased safety characteristics.
By controlling the amount of prestress, a structure can be made either rigid or flexible without
affecting its ultimate strength. A flexible structure is obviously more resilient and can absorb
considerable energy before failure due to impact and thus show improved performance under
seismic and dynamic conditions. Examples of such structures include fender-piles of wharfs
or jetties. Alternatively, a very rigid structure is more suitable to resist heavy vibrations.
Casting beds are commonly set up employing the abutment method, where the
abutments are placed a substantial distance apart, thus permitting a number of similar
units to be cast end-to-end around continuous strands tensioned against the anchorages
at each end of the casting bed. This is known as the “long line” process.
The prestressing wires or strands pass through the ends of the casting bed formwork and
end abutments. The strands are then stressed and the forms subsequently filled with
concrete. After the concrete has attained the specified strength, the strands are gradually
released at the abutment positions and the strands are severed at the ends of the
member. The prestress is transferred into the member by the elastic shortening of the
concrete.
During this operation, known as transfer, the force in the strands is transferred to the
concrete by bond stress. The length required at each end of a member to transmit the full
tendon force to the concrete is termed the ‘transmission length’.
In the manufacturing process, the frictional weight of the concrete member on the casting
bed may prevent longitudinal shortening, until the member is lifted. During this period,
shrinkage or thermal cracking may occur unresisted by the prestress since the member
has not shortened and is effectively not prestressed. Similarly, in lifting the member from
the casting bed, the initial lifting force may cause cracking. Special care must therefore be
taken to ensure that the bond between the concrete and the casting bed is readily broken.
Pre-tensioned strands, by nature of their being stressed before concreting, must be
straight between points of support. Where a profiled strand is required, it is possible to
deflect the strands using ‘hold-downs”. These can be attached to the soffit, or thrust down
from above. In order to avoid high friction forces developing at the change in direction at
the hold-downs, rollers or shoes can be used.
It should be noted that the use of deflected strands is not commonly adopted in Australia.
q Segmental Construction. Precast lengths of beam are lifted into place and
supported on temporary falsework, after which joints are poured in-situ. Joints
may be either spaced and grouted, using special grout, or adjacent surfaces may
be match-cast, and coated with an epoxy glue immediately prior to offering the
surfaces into contact. In either case, the consequences of imperfect matching
must be allowed for, and the effects of possible loss of prestress must be
considered.
The wire is typically low relaxation, stress relieved, super grade. The term low relaxation
refers to how much the strain relaxes in the strands under constant load. The term super
grade refers to the strength of the wire itself.
The vast majority of strands used are 12.7mm diameter. The use of 15.2mm strand is
normally used for large beams, or slabs with a span greater than about nine or ten
metres. Although 12.7mm diameter strand has a higher strength per unit weight when
compared to 15.2mm strand, the latter is more economical where it leads to a reduction in
the number of tendons and a subsequent reduction in anchorage costs. In many
situations this may not be possible, particularly for shorter span slabs, where the
maximum tendon spacing is typically limited to 8 times the slab thickness.
Post-tensioned tendons are encapsulated within the concrete in a duct that is usually
manufactured in corrugated steel with a wall thickness of between 0.3 and 0.5mm. The ducts
are normally supplied in 4-6 m lengths, and are then coupled on site.
For enhanced corrosion protection and fatigue resistance of the tendons, the use of
corrugated high strength polyethylene ducts is recommended.
The ducting can be installed with or without the tendons in place prior to concreting. If the
tendons are not installed prior to concreting, it is recommended that temporary stiffeners,
such as flexible polythene tubing, be installed to ensure any accidental damage or slurry
penetration will not restrict later installation of the tendons.
For a post-tensioned member, the ducts are grouted with a cement-based grout after the
stressing operations are completed. Grouting has two major objectives:
i. To protect the steel against corrosion; and
ii. To effect the bond between the prestressing steel and the concrete.
Care must be taken to ensure that grout tubes are provided, and venting allowed for ensuring
that all the air within the ducts will be removed during the grouting process.
Details of the Structural Systems ‘Type M1’ anchorage are illustrated below:
As the number of strands increases, then so too must the size of the jack.
Several other ‘Live end’ anchorage types are also available. The type of stressing
anchorage and tendon configuration selected will vary depending on the application.
Note must be taken of the physical dimensions of the anchor. These dimensions are
dictated by the load capacity of the tendons and are not restricted to a proprietary system.
Care must also be taken in preparing any design to ensure that the particular jack
required for the system chosen can actually be inserted in the space provided.
Refer to specialist prestressing supplier brochures for details of the full range of available
anchorages.
Dead end anchorages are embedded in the structure and so take advantage of the bond
between the strand and concrete. Most systems comprise either the ‘bulb-type’’ (onions) or
the ‘swage-type’ anchorage.
The ‘bulb-type’ anchorage is an economical system suitable for any number of strands. It
transfers the force from the tendon by a combination of the bond of the strand and the
deformed bulb.
The 'swage' type anchor is suited to cases where the tendon force must transfer to the
concrete right at the swage plate. The strand must be debonded between the swage plate
and the duct.
The ‘bulb’ type anchor provides a more gradual transfer of the stressing force into the
concrete. It is also a ductile anchor.
3.4.2 Multi Strand Systems
The “Structural Systems” multi-strand ‘dead end’ anchorages are designed to the same
principles as the mono-strand anchorages, varying only in size and number of strands as
illustrated below:
Couplers are used to give continuity to the tendons, which due to their length or the
construction methodology cannot be installed or tensioned as one unit. The first-stage of the
tendon is stressed and anchored in the normal way and the dead end of the second-stage
tendon is then assembled around it.
Couplers are expensive but their cost can be offset against savings in formwork,
reinforcement and sliding bearings required with an expansion joint. Construction joints in
prestressed slabs would normally be no further apart than about 40 metres.
Standard coupler components exist for all mono-strand slab tendons, and a full range for all
multi-strand systems.
The compressive force required to prestress concrete need not necessarily be produced by a
steel tendon, but can be obtained by the application of an external force. One way of applying
such a force is the “flat jack”, devised originally by Freyssinet, which is relatively cheap and
simple. Large numbers can therefore be employed where required, even if they are not
recoverable. The amount of movement obtainable, however, is limited.
In principle, the flat jack consists of a flattened metal canister that is inserted into a joint in the
structure and inflated as required by a fluid under high pressure. The shape may be elliptical,
although circular jacks are more usual. Rectangular jacks with rounded corners are also
available.
There are several proprietary prestressing systems in use in Australia. Details of the major
prestressing companies are indicated below:
1. Structural Systems
2. VSL Australia Pty. Ltd.
3. Austress Freyssinet
4. GENERAL DESIGN THEORY
All prestressed concrete members must be designed to ensure an adequate degree of safety
and serviceability at all relevant limit states. The usual approach is to design based on the
most critical limit state and then to check that the remaining limit states will not be reached.
It is important to ensure that the design is not, however, totally controlled by one limit state
alone, as this may suggest an uneconomical design. The design should attempt to optimise
all aspects of the structure. This can only be achieved if the designer has a total
understanding of the member’s behaviour, and is able to progressively refine the design to
ensure an optimal solution.
The member must have sufficient strength to support, without collapse an “ultimate
load”, which should represent the greatest load that might occur under the most
unfavourable conditions.
b) The cracking of the concrete should not adversely affect the appearance or
durability of the member.
In assessing the likely behaviour of a prestressed concrete member, flexural cracking must be
limited. The requirements of AS3600 Clause 8.6.2 are noted below:
4.1.1 Behaviour of Uncracked Section
In the uncracked range of behaviour, concrete stresses remain relatively small, so that the
short-term response of the concrete to stress changes is nearly linear and elastic. Under the
effect of permanent stresses due to prestress and dead load, considerable creep occurs in
the concrete and significant additional long-term deformations occur.
Consider a post-tensioned beam with a curved cable profile.
At midspan it has an applied force ‘P’ at an eccentricity from the centroid of the cross-section
of ‘e’. The extreme concrete fibre stresses can be calculated using simple linear elastic
theory. For the combined effect of the prestress and an applied moment ‘M’, the resulting
stresses are given by:
For the uncracked section, the section properties are normally based on the gross concrete
sections. The effects of reinforcing steel can be included by determining the section
properties based on a transformed section, but this is generally not necessary.
For statically determinate members, the longitudinal stresses due to prestress depend only on
the magnitude and the eccentricity of the prestressing tendon. This is not necessarily true for
statically indeterminate beams, due to potential hyperstatic reactions. This is discussed in
Section 4.6.
In the uncracked section there is negligible change in magnitude of the prestressing force as
the external load is applied. This property is beneficial when fatigue resistance is a design
consideration. A fully prestressed design is thus particularly appropriate for structures
subjected to large repeated live loading.
4.1.2 Behaviour of Cracked Section
As the applied moment increases above the cracking load in a bonded prestressed member,
cracks develop and extend progressively into the section. This behaviour is different to that of
a typical reinforced concrete beam without prestress. In the latter case, the cracks form
suddenly and immediately extend well into the section. As the applied moment increases, the
lever arm remains almost constant, with the increase in moment capacity resulting from an
increase in stress in both the concrete and reinforcement. For prestressed concrete
members, significant increase in moment capacity occurs through the progressive increase in
the lever arm, as opposed to an increase in force in the tendon.
The general flexural theory for a cracked prestressed section is illustrated below:
Under the action of prestress alone, prior to the application of any external moment, the strain
in the concrete at the tendon level is εce (compressive), and the strain in the tendon is εpe
(tensile). The applied moment induces a tensile strain εcp in the concrete at the level of the
tendon. Assuming perfect bond, the same change in strain must occur in the tendon. The
resulting strain in the tendon is therefore:
Similarly, the strain in the reinforcement can be expressed in terms of the top fibre concrete
strain and the neutral axis depth as follows:
For normal design applications in the working stress range, the concrete stresses are
primarily in the lower linear region of the stress-strain curve (stresses less than 0.45 f’c). For
the above section, the compressive force in the concrete is given by:
These expressions allow the internal forces to be determined. By equating the total
compressive and tensile forces within the section, a relationship between εo and dn is
obtained. For an assumed value of dn, the corresponding internal moment of resistance can
be determined and compared against the applied moment. An iterative trial and error
approach can then be used to determine the correct neutral axis depth.
4.1.3 Ultimate Limit State
As the applied moments increase, the concrete’s performance becomes non-linear. The
stress in the tendon, which increases steadily after cracking, now increases more rapidly, the
depth of the neutral axis reduces, and the extreme concrete fibre stress increases. At this
stage, a prestressed member behaves similar to a reinforced concrete section.
The ultimate capacity is reached when the tendon is stressed to its ultimate strength, or when
the compressive strain capacity of the concrete is reached. For under-reinforced beams,
failure is initiated by yielding of the tendon. The associated large tensile strains result in
increased crack widths and the neutral axis depth reduces. The increased concrete stresses
acting on the reduced compressive area ultimately result in a compression failure of the
concrete. The large steel strains produce visible cracking and considerable deflection of the
member before the failure load is reached.
In an over-reinforced member, failure occurs when the compressive strain limit of the
concrete is reached. This type of failure occurs suddenly with little warning.
The general flexural theory for determining the ultimate capacity of a prestressed concrete
member is similar to that described in Section 4.1.2 for a cracked section.
For normal strength concrete up to 50 MPa, AS3600 adopts the value εu = 0.003. It is
possible to construct the concrete compressive stress block by using a linear variation in
strain above the neutral axis and assuming a suitable stress-strain relationship. It is found that
the calculated moment capacity is not very sensitive to the parameters chosen to define the
shape of the concrete stress block.
In AS3600, use is made of the equivalent rectangular stress block, in which the nonlinear
stress distribution is replaced by a uniform stress of magnitude 0.85 f’c which acts over an
area bounded by the edges of the section and a line parallel to the neutral axis located at a
distance γ dn below the extreme compressive fibre.
In assessing the stress in bonded tendons at ultimate, AS3600 Clause 8.1.5 permits the use
of a conservative, empirical expression to evaluate the stress σpu:
where:
While the above equation may lead to a simpler calculation, in some circumstances a more
accurate analysis may be necessary, requiring an iterative trial and error approach similar to
that described in Section 4.1.2.
In most practical situations the actual stress-strain curve for the prestressing steel can be
better approximated by an idealised bi-linear, elastic-plastic distribution in which the ‘yield’
stress for the tendon is taken as the 0.2% offset stress.
Where greater accuracy is required, the following equation provides a smooth transition from
the elastic curve to the strain-hardening curve, and closely represents the actual stress-strain
curve.
Where the exponent ‘n‘ can be chosen to properly simulate the actual transition from the
elastic part of the curve to the strain-hardening part after yielding.
The ‘trial and error’ approach for determining the ultimate flexural capacity of a prestressed
concrete beam has been adopted in the GHD ‘Excel’ computer program “Prestressed Beam”.
This program uses the latter more accurate stress-strain curve for the prestressing tendons,
as well as a non-linear stress-strain relationship for the concrete.
Other than in the design of major bridges, the use of un-bonded tendons is not generally
recommended or adopted in Australia.
4.2 Design for Shear
Shear failure is an ultimate load condition. Its influence on the behaviour of a prestressed
member at service load is not usually significant. The types of cracking that occur in a
prestressed concrete beam at ultimate load are illustrated in the figure below.
In regions of negligible shear, flexural cracks occur at the extreme tensile face when the
tensile strength of the concrete is exceeded. These cracks, located in region ‘1’ in the figure
above, extend vertically into the section.
In the adjacent region ‘2’, both the shear force and the bending moment are large, and the
cracks initiate as vertical cracks in the tensile face. As they extend upwards with increasing
load, they become inclined under the influence of the shear force. These cracks are referred
to as ‘flexure shear’ cracks.
In region ’3’, where the shear force is high but the bending moment is relatively small, inclined
cracks initiate in the web of the beam if the principal tensile stress reaches the tensile
strength of the concrete. These cracks are referred to as ‘web-shear’ cracks and are most
likely to develop in beams with thin webs and high prestress.
The direct stress due to the prestressing force and applied moment varies with depth. The
value of the tensile stress is determined as follows:
As the section is uncracked, distribution of shear stress across the section can be calculated
using the classical equation:
The resulting principal tensile stress can be determined using the Mohr circle, and is given by:
The shear force required to produce shear cracking can then be determined by equating the
maximum principal tensile stress to the tensile strength of the concrete. In AS3600 the
principal tensile strength of the concrete is taken as:
The corresponding shear force Vt is found by setting the principal tensile stress (determined
using the Mohr circle equation) equal to the concrete tensile strength.
The maximum principal tensile stress does not necessarily occur at the centroidal axis, where
the maximum vertical shear stress occurs. For Ι-sections, the junction of the flange and web
is frequently the critical location. It is therefore necessary to determine the stresses at
numerous depths within the section.
Within the section, the direct stress ‘σ ‘ depends on the value of the applied moment, which in
turn is related to the shear force. A trial and error calculation is therefore required to
determine the value of Vt. This involves an iterative procedure in which the applied loads on
the beam are proportionally increased (or decreased), until the corresponding maximum
principal tensile stress within the section, determined using the above equations, reaches the
principal tensile strength.
The above process will be demonstrated by way of any example during the two-day course,
using the ‘excel’ spreadsheet program “Shear Capacity of Prestressed Beams”.
The ultimate shear strength at web-shear cracking is given in AS3600 as:
Vuc = Vt + Pv
where: Pv = the vertical component of the prestressing force at the section
The force Pv usually adds to the shear resistance provided by the concrete. As the slope of
the tendon is liable to be near its maximum value in regions prone to web-shear cracking, the
contribution of the vertical component of the tendon force can be significant. In unusual
cases, the vertical component of force may subtract from the shear resistance of the
concrete.
4.2.2 Flexure-Shear Cracking
In the zone of the beam subject to ‘flexure-shear’ cracking, inclined cracks develop as an
extension of the vertical cracks initiated by flexure. In AS3600, the resistance to ‘flexure-
shear’ fracture is assumed to comprise of three components, which add together to give an
estimate of the total shear resistance:
§ the vertical component of the prestressing force in the tendon, Pv, as described in
Section 4.2.1.
§ a crack initiation force, which is that value of shear force which corresponds to
the bending moment that would cause a crack to open at the section, it being
assumed that the crack already exists. The bending moment adopted for this
case is taken as the de-compression moment, Mo, and the shear force
corresponding to this moment, Vo. For the case of a simply supported beam, the
value of V can be taken as Vo = [Mo / M * ] V *.
§ A crack propagation force, which is the additional shear force after cracking until
failure of the section occurs. This is taken to be equal to the shear resistance
determined for an equivalent reinforced concrete beam, allowance being made
for both prestressed and non-stressed steel.
The ultimate shear strength at ‘flexure-shear’ cracking is given in AS3600 Clause 8.2.7 as:
φ Vu = φ (Vuc + Vus)
The above analysis assumes that the shear reinforcement yields before crushing of the
concrete in the web occurs. An upper limit Vu.max is therefore set on the value of Vu, as given
in Clause 8.2.6:
The initial prestressing force applied to the live anchorage is transmitted along the tendon, but
decreases as a consequence of instantaneous and long-term losses.
The losses can be classified as follows:
q Instantaneous Losses
These losses are due to:
a) Friction along the duct;
b) Draw-in of the anchorage wedges
c) Elastic shortening of the concrete
– µ (α tot + Β Lx)
Px = Po e
The friction coefficients depend on various factors such as the condition of the duct inner
surface, the condition of the strand external surface and the tendon layout.
4.4.2 Draw-in of the Anchorage Wedges
A loss of prestress occurs when the load is transferred from the stressing jack to the
anchorage of the tendon. When the strands are ‘locked off”, there is a small slip (or draw-
in) of the strands through the jack before the anchorage wedges “bite” into the strand and
hold it firm. The slip is normally about 6mm (dependant upon the jacking system used).
The movement in the strand is in the opposite direction to the tensioning process and is
opposed by the same friction mechanism as opposed the initial tensioning, (ie. µ and Β
are the same). Hence the friction loss profile is effectively modified by a “mirror image”
profile near the jack (ie. the slope of the ‘draw-in’ line is the same as the friction loss line,
but in the reverse direction).
The energy dissipated in the strand is given by:
KE = δ Ep A p
The point where the friction overcomes the ‘draw-in’ can be determined by equating the
energy dissipated in the strand to the area enclosed by the two friction loss lines.
For pre-tensioned members the loss of force in the tendon at transfer is given by:
∆P = Ap σcp . Ep / Ec
For post-tensioned members, all the tendons are not stressed simultaneously. Assuming
that all tendons experience a uniform shortening and are stressed one after the other in a
unique operation, the loss of force in the tendons can be determined using the following
expression, where ‘n’ is the number of tendons:
∆P = n – 1 . Ap σcp . Ep / Ec
2n
For a single tendon, all the elastic shortening occurs while the tendon is still attached to
the jack. No loss to prestress due to elastic shortening therefore occurs. For several
tendons, the loss tends to half the product of the modular ratio and the stress in the
adjacent concrete.
In most cases the loss due to elastic shortening is relatively minor compared with losses
from other sources.
4.4.4 Losses due to Concrete Shrinkage
As the concrete shrinks with time so the prestressing steel undergoes a corresponding
shortening which results in a loss of the prestressing force. With pretensioned members
the loss is based on the total ultimate shrinkage strain, while for post-tensioned members
only the shrinkage strain that occurs after stressing is taken into account.
The loss in prestress in the tendons due to shrinkage of the concrete is given by:
∆P = Ep . εcs . Ap
The design shrinkage strain ( εcs ) can be estimated from shrinkage data provided in
AS3600. The shrinkage is dependent upon the environment in which the member is
drying and the exposed surface area of the member from which moisture is lost (as
measured by the hypothetical thickness, th). For normal strength concrete, AS3600
suggests that the design shrinkage at any time after the commencement of drying can be
estimated from:
εcs = k1 εcs.b
where εcs.b is a basic shrinkage strain which in the absence of measurement, can be
taken to be 850x10-6; k1 describes the development of shrinkage with time and is
determined by interpolation from Figure 6.1.7.2 in AS3600.
In the absence of more detailed calculations and provided that the sustained stress in the
concrete at the level of the tendons at no time exceeds 0.5 f’c, the loss in prestress in the
tendons due to creep of the concrete is given by:
∆P = Ep . εcc . Ap
φcc = k2 k3 φcc.b
In the absence of tests, the basic creep factor (φcc.b ) may be taken as the values given in
Table 6.1.8.1. The factor k2 depends on the hypothetical thickness, th, the environment
and the time after loading and is given in Figure 6.1.8.2(A). The factor k3 is a function of
the age at first loading and may be determined from Figure 6.1.8.2(B) in the Standard.
In the absence of detailed test data, AS3600 Clause 6.3.4 allows the basic relaxation (Rb)
of a tendon, for Australian manufactured material, to be taken as 1% for low relaxation
wire, 2% for low relaxation strand, and 3% for alloy steel bars. The basic relaxation is the
assumed relaxation 1000 hours after stressing, for a prestress level of 0.7 f’c, and an
average temperature of 20oC.
R = k4 k5 k6 Rb
where, k4, k5 and k6 are coefficients to account for the duration of the prestressing force,
the level of the stress in the tendon, and the average annual temperature.
As the force in the tendon will gradually reduce due to the loss in prestress from the long-
term effects of creep and shrinkage in the concrete, the long term relaxation of the
strands is modified as a percentage of theses losses.
In pre-tensioned members, the tendon forces are transmitted by bond between the tendon
and the concrete. In a post-tensioned member, the forces are transmitted through bearing
type anchorages. These mechanisms are entirely different, and are considered separately. In
both systems, highly concentrated forces occur, and these must be safely dispersed into the
structure.
The most critical time in the life of an anchor is during stressing. The concrete strength at
transfer is usually specified as less than the full design compressive strength for the member,
and the highest stresses occur during prestressing, which is before any deferred loss of
prestress occurs.
The average stress behind the anchor plate, allowing for a deduction for the
trumpet size, is calculated at the time of transfer. The allowable value for this stress
is given in AS3600 Clause 12.3 as follows:
Cast-in proprietary anchors will generally transfer higher forces than external plates
of similar area due to the transmission of forces along the anchor. Proprietary
anchorages are generally designed on the basis of full-scale tests in accordance
with AS1314. The tests often indicate that the code limit is conservative.
q Bursting Stresses
In the end anchorage zone of a post-tensioned member, the concentrated
anchorage force is dispersed until a linear stress distribution is achieved across the
overall cross-section. The length of the dispersion zone is approximately equal to
the width or depth of the member. As the longitudinal compressive stresses fan out
in curved trajectories away from the anchorage, a bursting tensile force is produced
perpendicular to the tendon axis.
Maximum bursting usually occurs directly behind the anchorage, and for a
prestressed member with a single anchorage, can be represented as follows:
The transverse stresses occurring along the line of the anchor force vary with the
distance from the anchor head. These stresses are both compressive and tensile
as shown, forming a moment couple.
The tensile bursting force can be calculated using the empirical formula given in
AS3600 Clause 12.2.4, which has been shown to give reliable results:
T = 0.25P (1 - kr)
The formula varies slightly from experimentally derived results in regions of low kr,
but this is not significant in most practical cases.
For multiple anchorages, the same principle used for a single anchorage can be
adopted by dividing the member into a series of symmetrically loaded equivalent
prisms. Each prism is then treated individually using the empirical formula noted
previously.
The design of the anchorage zone should also consider the possibility of the
tendons being stressed separately. During the stressing operation higher splitting
forces can occur than in the final condition with all anchors stressed. The design
must allow for the corresponding anchorage / symmetrical prism geometry at the
time of stressing. It may be necessary to specify a sequence of stressing in order to
avoid placing additional reinforcement in the anchorage zone.
q Spalling Stresses
For anchorage zones where the tendon is highly eccentric to the member
centreline, or for multiple anchorages spaced widely apart, tensile ‘spalling’ forces
may occur at the loaded concrete surface. This surface tensile cracking between
anchorages is additional to the bursting stresses that occur directly behind the
anchorage.
The magnitude of the tensile spalling force can be calculated using a concrete
beam analogy that considers a free-body of the anchorage zone. This approach is
described in more detail below.
The integration of the stress distribution is equal to the total force in all the tendons.
Using the free-body, one can determine the bending moment diagram through the
depth of the member. The bursting moments are taken as positive, whereas the
spalling bending moments are negative. The bending moment is divided by a
suitable estimate of the ‘lever-arm’ depth to obtain a corresponding tensile force.
Some de-bonding occurs with time over a short length from the end of the strands / wires,
and it is therefore assumed that a completely unstressed zone of length 0.1 Lp develops
at the end of the tendon.
Where the strand or wire is untensioned, the development length is taken as not less than
1.5 times the value given in Table 13.3.2. AS 3600 does not permit the use of plain wire
for pre-tensioned work (Clause 19.3.1.3).
Prestressing offers larger spans with reduced structural depth, resulting in larger column-free
areas. Positive deflection and crack control and, if necessary, crack-free watertight slabs offer
the designer the opportunity to overcome some of the limitations of reinforced concrete and
structural steel.
A column grid spacing of between 8m and 10m usually results in the most economical
structure while maintaining architectural flexibility.
It is generally uneconomical to vary the prestress level in every span. If the following
points are given consideration then a constant amount of prestress may be used
efficiently throughout the length of the structure with resultant cost savings:
§ End spans approximately 80% the length of interior spans;
§ Cantilevers approximately 30% the length of interior spans;
§ Expansion joints, where necessary, located at ¼ points within a span;
§ Tendon length should be limited to a maximum of 60 metres;
§ The use of tendons shorter than 8 metres is generally not economical;
The above points are not always possible, but will generally lead to greater economy
where used.
q Flat Plate
The recent increase in formwork price has encouraged the use of flat plate structures.
They are best suited to square grids with a span of 7m to 9m. The increase in
concrete, reinforcement and prestress must be offset by the formwork cost savings.
The depth of a flat plate is generally dictated by punching shear requirements.
Thinner slabs or longer spans can be achieved by providing shear heads.
Loadings Span/Depth Prestress Reinforcement
Carpark – 2.5 kPa 38 – 42 1.6 – 2.0 MPa 3 – 4 kg/m2
Retail – 4.0 kPa 35 – 38 1.6 – 2.0 MPa 4 – 5 kg/m2
q Flat Slab
These are more efficient than flat plates for spans greater than 8m. Drop panels are
typically 30-35% of column grid. This is a widely used system as it maintains a flat
soffit, simple formwork, as well as flexibility for services reticulation.
The drop panels increase the flexural stiffness of the floor as well as improving its
punching shear capacity. The system provides the thinnest floors and can lead to
overall floor height reductions. The economic span range is up to 12m.
Loadings Span/Depth Prestress Reinforcement
Carpark – 2.5 kPa 42 – 47 1.8 – 2.2 MPa 3 – 4 kg/m2
Retail – 4.0 kPa 38 – 42 1.8 – 2.4 MPa 4 – 5 kg/m2
Office Buildings 0.5 – 1.0 kPa 3.0 kPa (0.8 – 1.0) x swt
Shopping Centres 0.5 – 2.0 kPa 4.0 kPa (0.9 – 1.1) x swt
Residential 2.0 – 3.0 kPa 1.5 kPa swt + 50% of
Buildings (brick partition walls) partition loads
For structures designed for relatively large partition and superimposed dead loads, care is
required at the time of stressing due to the absence of the partition loads. The problem
can be avoided by stressing in stages as the superimposed load is applied
Although AS3600 does not specify a maximum spacing of tendons, the recommendations
of AS1481 Clause 4.13.2.5, that the tendon spacing not exceed 8 times the slab
thickness, is considered appropriate and should be adhered to.
Precast pre-tensioned floor systems have many advantages over conventional post-tensioned
insitu suspended slabs.
When precast is being considered for any project it is essential that all facets ranging from the
detailing, manufacturing, erection and finishes are taken into consideration. This will ensure
that the final solution utilised satisfies not only the architectural and structural requirements,
but also economics and buildability of the project.
There are numerous precast pre-tensioned floor systems available in Australia. The systems
most currently in use are:
5.2.2 Ultrafloor
5.2.3 Transfloor
5.2.4 Solid Slabs
5.2.5 Tee-Beams
5.4 Tanks
6.1 Introduction
The design details adopted for any structure can have significant effects on the speed and
quality of construction. Detailing should be standardised and as simple as possible.
Congested areas, in particular, should be carefully assessed and appropriately detailed.
The design stage is the best time to allow for the site requirements.
The design of post-tensioned slab systems is covered in some detail in Section 4.1. The
following points should be considered in arriving at the final project detailing:
6.2.1 Formwork
Dimensions of beams and slabs should be based on standard formwork sheet sizes to
minimise formwork cutting. In particular, the distance between beams should permit
standard form ply sheets to be used (i.e. 1200mm / 1800mm module).
Changes in the level of the soffit form should be minimised as much as possible. Where
the slab is required to be thickened to accommodate a set down in the top of the slab, the
soffit of the set down area should extend to between the bands to simplify the formwork.
For wide shallow band beams, with a beam / slab depth ratio of less than 2, the side
forms should be vertical rather than sloping as this simplifies construction of the
formwork. For deeper band beams, the side forms are normally splayed to minimise the
potential shrinkage differential between the slab and the beam, which could otherwise
result in transverse cracking of the slab between the band beams.
6.2.2 Reinforcement
The most common on-site problem with post-tensioned structures involves clashes
between the reinforcement and tendons, which are unfortunately often only picked up on
site, potentially leading to delays. The following general recommendations should be
followed:
ii. The reinforcement should be detailed so that the bottom bars can be placed
first followed by the prestressing tendons, and then the top bars.
iii. The reinforcement should be detailed using standard bar lengths as far as
practicable. Ideally, bent bars and stirrups should be kept to the same size and
shape where feasible.
iv. Open ligatures should be detailed. This allows the tendons to be laid in position
following the placement of the bottom layer of reinforcement, rather than having
to be threaded through closed ligs. If closed ligatures must be used, it is
preferable to use a ‘U’-shaped lig with cogged ends, and a separate closer bar.
v. The bottom layer of slab reinforcement should not extend too far into the band
beam as this could clash with the tendons.
vi. Edge beams should not be to narrow. Transverse slab tendons (with
associated bursting reinforcement) can provide an obstacle to the longitudinal
tendons in the edge beam. Slab anchorages are typically up to 300mm long,
and consequently a narrow edge beam can be very difficult to prestress. A
minimum edge beam width of approximately 1000mm is therefore generally
adopted. Also, check that the top reinforcement does not interfere with the
anchorages.
vii. The reinforcement required in the anchorage zones must be carefully detailed
to avoid congestion, and to ensure ease of placement, particularly where it
coincides with reinforcement in columns and other beam reinforcement.
6.2.3 Tendons
Where possible, use only mono-slab systems throughout the project. Avoid the use of
tendons larger than 6-12.7mm or 5-15.2mm strands, as the larger jacks are difficult to
handle on site. Obvious exceptions apply to large transfer beams, where an
uneconomically large number of tendons would be required.
For overall economy, the designer should always attempt to minimise the number of
tendons by maximising the tendon spacing - the maximum tendon spacing should be
limited to 8 times the slab thickness. For less highly stressed slabs, tendons comprising
12.7 mm-diameter strands are generally more cost effective, provided they are spaced at
the maximum allowed. For thicker, more highly stressed slabs, it may necessary to
substitute 15.2 mm-diameter strands to maintain the maximum tendon spacing.
The cost of prestressing depends primarily on the length of the tendons. Short tendons
are relatively expensive in comparison with long tendons as the fixed costs per tendon,
such as the number of anchorages required and the stressing operation, which is
independent of the length, are prorated over a lesser tonnage. A practical slab and beam
length for single end stressing is approximately 35m, and for tendons stressed from both
ends, 60m.
In flat slabs, transverse tendons should be located below the longitudinal primary tendons
(ie. a 20mm reduction in drape). This avoids weaving tendons at the columns.
Tendons should not be located close to columns as they may clash with the column
reinforcement. This problem is often exacerbated where the column reinforcement
terminates in the slab, and the cogs fan out into the slab or band beam. Preferably, the
tendons should be located a minimum of 600mm either side of the column. This will
ensure that the tendons achieve their maximum drape over the line of the supports.
It is recommended that tendons always be independently supported and kept separate
from reinforcing. Where slab tendons cross wide ban beams, ensure adequate support is
provided to the tendon.
Standard anchorage recess sizes and dimensions should be detailed wherever possible.
Beware of clashes of tendon high points with holding down bolts and baseplates, or
services blockouts.
A minimum cover of 25mm should be specified to the duct – this prevents the concrete
from popping off when high-pressure grout is pumped into the ducts.
6.2.7 Joints
The required construction joint layout will be determined to a large extent by the area of
concrete the builder can finish in a day. Commonly, the maximum area is about 1200 to
1600 square metres. Construction joints are commonly formed using standard coupling
anchorages.
[To be Expanded]
For building elements with multi-strand post-tensioning, the detailing requirements can be
more onerous due to the increased number and size of tendons. This will generally result in
greater congestion of tendons and reinforcement, and therefore requires greater attention to
detail to ensure that potential on-site problems are prevented.
Since the stresses applied to the concrete immediately behind the anchorage bearing
plate are considerable, the arrangement of the bearing plates must provide a minimum
edge distance. The minimum required distance of the bearing plates to the concrete
edges, and to adjacent anchorage bearing plates is dependent on:
§ the post-tensioning force to be transmitted
§ the concrete strength
§ the bearing plate dimensions
§ the reinforcing steel behind the bearing plate
Specific requirements are generally provided in the technical literature supplied by the
various prestressing companies.
For tendons of greater length, it is normal practice to stress from both ends.
When only the duct is placed prior to concreting, supports must resist buoyancy forces.
Post-tensioned concrete relies for its structural adequacy and serviceability performance on
correct detailing and on-site operations. This involves the interaction of all the structural
elements (concrete, reinforcement and post-tensioned tendons), and the timely execution of
the on-site activities. The timing of the stressing operations is important to the achievement of
the required construction cycle.
The forces at the anchorages are very high. Consequently, the concrete
strength is critical in this zone. For the same reason, the reinforcement tends
to be congested in the vicinity of the anchorages, which makes compaction
more difficult. Good reinforcement detailing by the designer, and careful
consideration, by the reinforcement fixer, of the sequence in which the
reinforcement is to be placed is important.
Personnel, Qualifications
Pre-pour Inspections
The consulting engineer should carry out a pre-pour inspection of the post-
tensioning system. This entails a detailed inspection of the prestressing and
reinforcement, and importantly the anchorage reinforcement. This should
ideally only be carried out once the site supervisor has checked the
installation against the workshop drawings and is satisfied that the works
have been completed, and is ready for a final inspection.
Concreting
Care must be taken during concreting. Ducts must not be damaged or
displaced, either by poker vibrators, or by concrete being dropped from an
excessive height.
It is important that the concrete, particularly in the anchorage zones, is
properly placed and compacted. The majority of problems encountered
during the stressing process occur due to inadequate quality control at this
stage.
If the strands have been installed in the ducts before pouring the concrete,
there is a risk of grout leaking into the duct and the tendon becoming
immovable thereby preventing stressing. In order to avoid this problem, it is
recommended that the duct be flushed with water in order to wash out any of
the cement paste that might have leaked into the duct. In addition, the
strands should be moved within the duct, within about an hour of the
concreting operation being completed. This movement will break any bonding
that might have commenced between the tendon and the duct as a result of
the ingress of cement paste.
Concrete test cylinders should be cast at the same time as pouring the slab /
beams, so that the strength can be checked before tensioning takes place.
These cylinders are additional to the normal quality control testing
requirements. These should be site cured using the same procedures
adopted for the structure. These concrete cylinders will need to be tested
before stressing of the tendons is permitted.
Tensioning Procedures
Prior to commencing tensioning, check that the following items have been
completed:
i. The strength of the concrete has attained the specified value. This
can only be checked by testing the prepared concrete cylinders. Do
not assume that elapsed time since casting is a sufficient assurance
of adequate strength.
Working Area
The area around the stressing anchors and passive anchors should be
fenced off from the general working area.
If the area behind the anchors cannot be adequately secured in any other
way, the necessity for erecting rigid screens as safety barriers should be
considered. An alternative is to fix an anchor-ring to the jack or structure by a
chain.
Stressing Equipment
During the entire stressing operation, the equipment should be checked for
possible malfunctions, leakages, pipe failures etc. The jacks should be
cleaned, threads oiled, and protective wrapping removed just prior to use.
Working Area
No personnel are to be allowed to access behind the anchors from the time
the stressing has commenced, until the full load has been transferred to the
anchorage.
Stressing Records
Stressing records must be maintained for all tendons. These records are to
be prepared by the prestressing subcontractor, and should include details of
the stressing force, and measured extensions of the strands. If the actual
extensions deviate from those calculated by more than +10% of the
theoretical value, the designer should be informed. Care should be taken
when restressing (if required) to ensure that the wedges do not clamp at the
same point on the strand.
The projecting tendon ends must not be cut after the jacking has been
completed, until the consulting engineer has reviewed the stressing records,
and given permission.
The operations involved in tensioning and de-tensioning prestressing tendons are not
dangerous provided that sufficient care is taken. Prestressing steel, when tensioned, does
however contain a considerable amount of stored energy, which in the event of any failure of
the prestressing steel, anchorage, or jack, may be released violently.
[To be expanded ]
Appendix H
Water Retaining Structures – Details
© GHD 2010
This document is and shall remain the property of GHD. The document may only be used for the purpose
for which it was commissioned and in accordance with the Terms of Engagement for the commission.
Unauthorised use of this document in any form whatsoever is prohibited.
Document Status
2 L. Smit C. Spencer
(Software,
Prestressed
Concrete)
J. Pautasso
(Concrete)
I. Round
(Standard
Technical Spec)
J. Yip
(Water Retaining
Structures)
R. Chohan
(Water Retaining
Structures)
S. Elward
(Water Retaining
Structures)
G. Tomlinson
(Water Retaining
Structures)
R. Paull
(Durability)
L. Milst
(FEA Guidelines)
P. Vatin
(FEA Guidelines)
S. Konstanty
(Dynamic
Foundations/Bin
Design/Material
Flow)
Y. Kumai
(Design Loading)
T. Kershaw
(Bin
Design/Material
Flow)