Professional Documents
Culture Documents
PID (Photogrammetry)
PID (Photogrammetry)
PID (Photogrammetry)
TEAM MEMBERS
1
Contents
1.0 INTRODUCTION .......................................................................................................... 3
1.1 Inception Report Purpose .............................................................................................. 3
1.2 Project Objectives and Scope ........................................................................................ 3
1.3 Project Organization ....................................................................................................... 4
1.4 Project Mobilization and Accomplishments ........................................................................ 5
2.0 Planned Objectives, Results and, Activities ......................................................................... 5
2.1 Component 1 ........................................................................................................................ 5
3.0 Project Work Plan ................................................................................................................ 6
3.1 Work plan schedule .............................................................................................................. 6
3.2 Responsibility chart ............................................................................................................. 7
4.0 Implementation Issues ......................................................................................................... 8
4.1 Start-up Issues ...................................................................................................................... 8
4.2 Implementation Issues ......................................................................................................... 8
4.3 Sustainability Issues ............................................................................................................. 8
5.0 APPENDIX .......................................................................................................................... 9
5.1 Attachment 1; showing the project organization chart ........................................................ 9
5.2 Attachment 2; Bar chart showing project time log ............................................................ 10
5.3 Attachment 3; Risk log....................................................................................................... 10
5.4 Attachment 4; shows the project cost log. ......................................................................... 13
5.5 Attachment 5; Quality log .................................................................................................. 13
5.6. Attachment 6; shows the HR log ...................................................................................... 15
5.7. Attachment 7; List of persons contacted/ being contacted................................................ 16
5.8. Attachment 8; project terms of reference .......................................................................... 16
2
1.0 INTRODUCTION
Over the past few years, the use of 3D digitization and modelling for 3D modelling of cultural
heritage has become increasingly common. The most commonly used technologies include
surveys, CAD tools, and traditional photogrammetry with control points. These approaches
are, however, time-consuming and can be costly, and therefore may be impractical for large-
scale sites. Photogrammetry is one of the most cost-effective approaches for gathering physical
information about an object, because data can be collected using a consumer-level digital
camera. The digital camera can be used to obtain digital imagery which is processed to come
up with photogrammetric products like a 3D model, orthophotos etc. Laser scanner technology
can also be used to produce 3D models but given its high cost, transport difficulties, time
investment, and the complexity of data management, photogrammetry becomes a preference.
This project aims to create a 3D model of two historic buildings on our campus using
photogrammetric methods. The historic buildings in question are the Department of Music,
Dance and Drama at School of Liberal and Performing Arts and the Department of Science and
Vocational Education at the School of Education. They are some of the oldest buildings at
Makerere University dating back to 1928 and 1923 respectively.
It helps in identifying areas that need extra consideration or changes. Discovering potential
issues or risks at this early stage is extremely important for a project in terms of both time and
budget efficiency.
The Inception report can be a useful tool for budgeting more accurately, with a better overview
of the requirements and an understanding of potential risks.
• To identify the appropriate photogrammetry techniques and software that can be used
for 3D modelling and visualization of buildings.
• To collect and process the required data using photogrammetry technology.
3
• To develop a 3D model of the building using the processed data.
• To evaluate the accuracy and precision of the 3D model.
• To create visualizations of the 3D model and assess its usefulness for various
applications such as architecture, construction, and heritage preservation.
Scope
preservation applications.
Project manager; manages the production of the required deliverables. He is the team leader
and therefore a top decision-maker.
The human resource manager; is in charge of the human resource (project team) planning,
ensure to maintain the efficiency of the members. All the other roles are accountable to him.
4
The risk assessment officer; identifies, analyzes, and responds to risk throughout the life of a
project and in the best interests of meeting project objectives.
Quality manager; ensures that the project satisfies the needs for which it is undertaken. It
includes quality planning, assurance, and control.
Monitoring and evaluation; monitoring assesses and aims to improve the performance of the
project. Evaluation is concerned with the relevance, effectiveness, efficiency, impact, and
sustainability of what has been done.
Technical officers; are in charge of the technical onsite and offsite activities to be done during
the project’s lifetime. They also serve as hardware and software experts.
The finance and procurement manager; ensures that the project team completes the project
within an approved budget. There are four project cost management processes: resource
planning cost estimating, cost budgeting, and cost control
2.1 Component 1
Objective; To utilize photogrammetric methods to produce three-dimensional models of
the department of music and drama building at the School of Liberal and Performing Arts and
the Department of Science and Vocational Education at the School of Education.
5
Result; Three-dimensional models of the department of music and drama building at the
School of Liberal and Performing Arts and the Department of Science and Vocational
Education at the School of Education
Activities;
• Photo acquisition
• Processing of photographs
• 3D Model generation
• Texturing and Visualization
Week 4 • Reconnaissance
27/03/2023 to • Getting familiar with the suitable instruments and software
01/04/2023
Week 5 • Conduct the photo acquisition (capturing overlapping digital
03/04/2023 to photographs)
08/04/2023
6
Week 6 • Processing of photographs (using Photomodeler or any other
10/10/2023 to appropriate software)
15/04/2023
Week 7 • 3D Model generation
17/04/2023 to
22/04/2023
Week 8 • Texturing and Visualization
24/04/2023 to
29/04/2023
Week 9 • Final results report
01/05/2023 to
06/05/2023
To be specified • Supervision by client
by client • Presentation of results to client
To be specified • Presentation to department supervisor
by the
department
7
4.0 Implementation Issues
8
5.0 APPENDIX
9
5.2 Attachment 2; Bar chart showing project time log
A gantt chart is a bar chart that illustrates the project schedule. It shows the work completed
over a period of time in relation to the time planned for the work
ACTIVITY 28th to 3rd to 8th April 10th to 15th 19th to 26th 1st to 6th
30th April April May
March
Reconnaissance
Fieldwork
Data processing
Data analysis
Documentation
A risk can be defined as an uncertain event or condition that, if it occurs, has the potential to
cause harm, loss, or damage to an organization's assets, operations, reputation, or even financial
health. Risks can arise from internal and external factors and can be classified as strategic,
operational, financial, or reputational.
Risk management involves systematically analyzing potential risks, evaluating the likelihood
and potential impact of each risk, and implementing strategies to mitigate or eliminate those
risks. The goal of risk management is to enable organizations to make informed decisions about
risks and to implement measures to reduce or avoid the likelihood and impact of negative
events.
i. Risk factors
ii. Likelihood of the risk happening
iii. The impact of the said risk on the overall progress of the project
iv. Mitigation of the risks
10
RISK REGISTER
RISK LOG:
11
4 Errors in data Low Severe Technical Carrying out
collection officers independent
checks
5 Theft of equipment Low Severe Technical Safety measures
Officers
6 Conflicts within the Moderate Moderate Human Counselling
group Resource sessions
7 Illness of team Low Low Monitoring and Designated
members evaluation substitutes
officer
8 Slow internet High Moderate Project Manager Alternative
sources of
internet
9 Accidents on site Low Severe Project Manager Use of
protective gear
10 Conflicting schedules high severe Project manager Effective
between the project communication
manager and the prior to the
client meeting
11 Conflicting schedules high high Project manager Effective
among project communication
members
12 Adverse climatic High High Risk Manager -
conditions e.g., rain,
too much sunshine
13 Lack of high severe Monitoring and Regular
accountability on the evaluation evaluation of
part of team members manager project activities
14 Miscommunication High high Communication Regular physical
among members manager meetings
12
5.4 Attachment 4; shows the project cost log.
PROJECT COST LOG
A project budget is an estimate of the expenses to be incurred during the period when the project
is being executed. It shows the cash flow of the project.
PROPOSED BUDGET
TOTAL 450000
Quality control in project management is the process of ensuring that a project meets its defined
quality standards. It involves identifying the quality requirements for the project, setting quality
objectives, and monitoring the project's progress to ensure that these objectives are met.
A quality assurance plan is a document drafted by the team with an aim of ensuring that the
accomplished task meets all the criteria making it of the best quality possible. The checks are
carried out essentially by filling the activity checklist for each item at the start and end of every
activity.
13
QUALITY OBJECTIVES
Specification Measure
Delivery to scope. A complete accurate three-dimensional model of The Department
of Music Dance and Drama (The School of Liberal and Performing
Arts)
Delivery on time All project activities should be fully completed and the
deliverables ready within the above specified time/ period.
Delivery on budget All expenses on the project should be within the anticipated
budget.
Adherence to project All the necessary field data collection and analyses should be
methodology carried out using the specified methods.
ACTIVITY CHECKLIST
14
Conduct the photo Pending The photo acquisition will Pending
acquisition (capturing be carried out after
overlapping digital reconnaissance.
photographs)
Compilation and final Pending This will be the final step Pending
presentation after data has been
analysed and processed
15
17/03/2023 Finalized consolidation of each Project Manager and HR Pending
member’s responsibility
17/03/2023 Keeping track of the assigned HR Ongoing
roles
Photogrammetry specialist
16