Professional Documents
Culture Documents
18 Productivity Rates
18 Productivity Rates
C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Elec, Pl = Plumber
PRODUCTIVITY RATES
k. Corner Flashing & Trims, etc 1 E + 3 H Rm/Day 80
l. 4m x 4m double Sliding Door 1 E + 3 H No. 1
m. Wall or Roof opening + Frames (1.0m x 1.0m) 1 E + 3 H No. 8
n. Ridge Ventilator 1 E + 3 H No./Day 6
o. Gutter / Down Spout 1 E + 3 H Rm/Day 70
6 MOISTURE THERMAL CONTROL
WATER PROOFING & DAMP PROOFING
Polythene Sheet
a. Polytheen under footings 1 C + 1 H M2/Day 200
b. Polytheen under slab 1 C + 1 H M2/Day 1000
c. Polytheen under tie beams 1 H Rm/Day 200
Bitumin Paint
2
a. Cold Bituminous Painting 1 H M /Day/Coat 100
b. Hot Bituminous Painting 2 H M2/Day/Coat 60
Bituminous Membrance
2
a. Bituminous Membrance + Protection Board 1 C + 1 H M /Day 30
SEALERS
Construction Joint
a. Flexel Board 1 C + 1 H RM /Hr 18
b. Sealant 1 H RM /Hr 7
8 FINISHES
PLASTER
Internal Plaster
a. Ceiling Plaster 1 M + 1 H M2/Day 10
b. Wall plaster up to 3m Height 1 M + 1 H M2/Day 20
c. Wall plaster 3m to 6m Height 1 M + 2 H M2/Day 17
d. Wall plaster above 6m Height 1 M + 2 H M2/Day 15
e. Fixing of Plaster Mesh 1 C + 1 H Rm/Day 90
f. Fixing of Corner beed 1 M + 1 H Rm/Day 30
External Plaster
a. Wall plaster up to 3m Height 1 M + 1 H M2/Day 20
b. Wall plaster 3m to 6m Height 1 M + 2 H M2/Day 18
c. Wall plaster above 6m Height 1 M + 2 H M2/Day 15
TILES
Mosaic
a. Floor Mosaic Tiles 1 M + 1 H M2/Day 15
b. Mosaic Skirting 1 M + 1 H Rm/Day 40
c. Mosaic Steps (Riser & Tread) 1 M + 1 H Rm/Day 14
d. Mosaic Polishing 1 Po + 1 H M2/Day 100
Ceramic
2
a. Fixing of Ceramic Wall Tiles (Glue Type) 1 M + 1 H M /Day 10
b. Grouting of Ceramic Wall Tiles 1 M + 1 H M2/Day 30
c. Fixing of Ceramic Wall Tiles (Cement Mortar Type) 1 M + 1 H M2/Day 8
d. Fixing of Ceramic Floor Tiles 20 x 20cm 1 M + 1 H M2/Day 12
e. Fixing of Ceramic Floor Tiles 30 x 30cm 1 M + 1 H M2/Day 15
f. Fixing of Ceramic Floor Tiles 50 x 50cm 1 M + 1 H M2/Day 20
g. Grouting of Ceramic Floor Tiles 1 M + 1 H M2/Day 40
h. Ceramic Skirting 1 M + 1 H Rm/Day 30
PVC Tiles
a. PVC Tiles 1 M + 1 H M2/Day 35
b. PVC Skirting 1 M + 1 H Rm/Day 40
Marble
a. Marble Wall 1 M + 1 H M2/Day 6
b. Marble Floor 1 M + 1 H M2/Day 15
c. Marble Skirting 1 M + 1 H Rm/Day 30
d. Marble Steps (Riser & Treads) 1 M + 1 H Rm/Day 10
Floor Screed (50mm)
a. Floor Screed (50mm) 1 M + 1 H M2/Day 50
b. Cement Skirting 1 M + 1 H Rm/Day 25
Wooden Skirting
C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Elec, Pl = Plumber
PRODUCTIVITY RATES
a. Timber 1 C + 1 H Rm/Day 100
Thershold
a. Thershold 1 M Rm/Day 10
False Ceiling
a. False Ceiling ‐ Suspended Type 1 C + 1H M2/Day 30
Dry Wall Partition
a. Dry wall Partition 1 C + 1H M2/Day 20
PAINTING & WALL COVERINGS
Tyrolene (Cullamix)
a. Tyrolene over plastered surface 1 M + 1 H M2/Day/Coat 100
2
b. Tyrolene over block wall 1 M + 1 H M /Day/Coat 100
Normal Paint
a. Primer 1 P M2/Day/Coat 200
b. Stucco (Putty) 1 P M2/Day/Coat 80
2
c. Emulsion Paint 1 P M /Day/Coat 100
d. Oil Paint 1 P M2/Day/Coat 60
Epoxy Painting
2
a. Epoxy Painting 1 P + 1 H M /Day/Coat 50
9 MECHANICAL
COPPER & PVC PIPES
Copper & PVC Pipes
a. 1/2" to 1" Copper Pipe (Hot water) 1 Pl + 1 H Rm/Day 12
b. 1/2" 1 1/2" PVC Pipe 1 Pl + 1 H Rm/Day 20
c. 2" to 3" PVC Pipe 1 Pl + 1 H Rm/Day 75
d. 3" to 6" PVC Pipe 1 Pl + 1 H Rm/Day 60
PLUMBING FIXTURES
Plumbibg Fixtures
a. Shower Tray 1 Pl + 1 H Nos. / Day 2
b. Kitchen Sink 1 Pl + 1 H Nos. / Day 2
c. Urinals + Partition 1 Pl + 1 H Nos. / Day 3
d. Wash Basin 1 Pl + 1 H Nos. / Day 2
e. W/C Asian 1 Pl + 1 H Nos. / Day 2
f. W/C Western 1 Pl + 1 H Nos. / Day 2
g. Bidet 1 Pl + 1 H Nos. / Day 2
h. Booster Pump 1 Pl Nos. / Day 1
i. Manhole 60cm to 90 cm 1 M + 1 H Nos. / Day 2
PLUMBING APPLIANCES
Plumbing Appliances
a. Water Heater 1 Pl + 1 H Nos. / Day 2
10 ELECTRICAL
ELECTRICAL
Race Ways
a. Conduits 1 El + 1 H Rm/Day 50
b. Trunking 1 El + 1 H Rm/Day 50
Conductors & Crounding
a. Laying Cables 1 El + 2 H Rm/Day 150
Wiring
a. Wiring 1 El + 1 H Rm/Day 300
Boards
a. D.B's 1 El + 1 H Nos. / Day 2
b. M.D.B's 1 El + 1 H Nos. / Day 1
C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Elec, Pl = Plumber