Professional Documents
Culture Documents
Substation Control and Protection Project
Substation Control and Protection Project
Substation Control and Protection Project
Project
EPRI
EPRI EL-1813
System Requirements Specification Project 1359-1
Interim Report
Keywords: April 1981
Substation Instrumentation
Control System
Protective Relaying System
AC Protections
Prepared by
Westinghouse Electric Corporation
Pittsburgh, Pennsylvania
SISTWBIIIIM Of THIS poconon IS mmm
EL-1813
Research Project 1359-1
Prepared by
Prepared for
EPRI authorizes the reproduction and distribution of an or any portion of this report and the preparation
of any derivative work based on this report, in each case on the condition that any such reproduction,
distribution, and preparation shall acknowledge this report and EPRI as the source
NOTICE
This report was prepared by the orgamzation(s) named below as an account of work sponsored Py the
Electric Power Research Institute. Inc. (EPRI) Neither EPRI, members of EPRI, the orgamzation(s) named
below, nor any person acting on their behalf, (a) makes any warranty or representation, express or
implied, with respect to the accuracy, completeness, or usefulness of the information contained m this
report, or that the use of any information, apparatus, method, or process disclosed in this report may not
infringe privately owned rights, or (b) assumes any liabilities with respect to the use of. or for damages
resulting from the use of, any information, apparatus, method, or process disclosed m this report.
Prepared by
Westinghouse Electric Corporation
Pittsburgh, Pennsylvania
ABSTRACT
This specification evolved during Phase I of EPRI Project RP 1359-1. This project
involves the design and implementation of a microprocessor-based, integrated protec
tion and control system for transmission class substations. In order to define the
scope of the system, a list of possible functions was generated and the requirements
for each function were defined after extensive consultation with Host Utility
personnel and with other utility Advisors. A list of general system requirements and
design criteria was also generated. This specification has served as the starting
point in the development of more detailed functional specifications and in the
translation of these into implementation specifications. The requirements listed
here, are considered to be design goals whose feasibility and practicality will be
tested during the design and implementation of the system.
iii
EPRI PERSPECTIVE
PROJECT DESCRIPTION
PROJECT OBJECTIVE
This project is divided into different phases. This report was developed under
Phase I of RP1359-1, which covered the development of the system requirements and
trade-off studies for selection of a system architecture and top-level system
design.
PROJECT RESULTS
The intent was to define the requirements in a strict form to allow compliance
with the requirements to be tested. However, this was not possible to do at all
times. Rather than eliminating a requirement for lack of a good test criteria,
the requirement was included to serve as a flag for further requirements that will
be made at a later date. The requirements were reviewed for consistency and
examined to determine technical feasibility. However, in a complex system such as
the one defined in this report, errors were unavoidable. In spite of these, the
publication of this report provides an opportunity, which otherwise would be
impossible, for feedback to the project group from a larger audience.
v
' -!>.
ACKNOWLEDGMENTS
Many people have contributed to the development of these specifications during the
last two years, and their efforts are hereby acknowledged with gratitude.
Howard R. Petrie and his associates Steve Leveckis and Carlos H. Castro representing
the Host Utility, Public Service Electric and Gas Co. of New Jersey, contributed to
the initial definition of functions and to subsequent discussions and evaluation of
functional requirements.
Five Advisory Utilities have contributed original suggestions and critical review
comments through their designated representatives. These are:
The EPRI Project Manager Stig L. Nilsson has provided valuable suggestions and
comments, and has also given direction and motivation during the development of these
specifications.
John S. Deliyannides
Frank G. Willard
Mladen Kezunovic
Bob j. Masterson
Mike J. McGarry
John F. Reuther
Milt Sackin
Tom H. Schwalenstocker
Eric A. Udren
vii
CONTENTS
Section Page
1. INSTALLATION 1-1
2. ENVIRONMENTAL 1-2
3. OPERATING PERSONNEL 1-3
4. MAINTENANCE AND TESTING 1-5
5. EXPANSION, ADDITION, AND MODIFICATION 1-6
6. DESIGN 1-7
7. DOCUMENTATION 1-10
8. RELIABILITY 1-11
ix
SUMMARY
One of the major activities during Phase I of Project RP 1359-1 was the development
of functional specifications for a substation protection and control system. The
procedure used to generate such a specification was as follows: An initial list of
general requirements and functions was prepared by a joint effort of Westinghouse and
the Host Utility. This information was transmitted to five Utility Advisors for
their review. Each advisory Utility was visited and discussions on the functional
requirements were held. Following these discussions and a review of written comments
by the Advisors, the requirements were combined and regrouped into the form that
appears in this document. General requirements cover the areas of installation,
environment, operating personnel, maintenance and testing, expansion and
modifications, design, documentation and reliability. Twenty-six functions are
described individually. Included for each function is a functional description, an
input and output list, and a set of requirements.
The list of functions and requirements presented here is a long wish list of all that
could possibly be implemented in such a system. It is realized that any one
installation would only contain a subset of these functions and features. The list,
however, has served as the starting point of detailed design considerations during
the process of translating functional requirements into implementation details.
S-l
SECTION I
INSTALLATION
1.1. The following functions shall be designed so that they can be implemented,
if desired, in a stand-alone mode. As much as is practical, they shall be
physically packaged separately from one another and shall be able to inter
face directly to substation apparatus such as pt's, cpd's, ct's, trip
coils, breaker auxiliary contacts, dc supplies, etc., independently of
other system functions or equipment:
1.2. For ease of maintenance, especially during inclement weather, indoors loca
tion is preferred for cortplex control devices. It is normal practice to
functionally test all control equipment during scheduled maintenance or
unscheduled repairs.
1.3. Maximum shipping dimensions shall be limited to permit movement through the
control house opening. For this R&D project, all panels can be assembled
in the factory on a common base and shall clear an opening of 2.0m high by
1.75m wide.
1.4. Panels shall be rigid and designed for easy field handling and skidding on
base; proper support points shall be provided for lifting by crane without
distortion of panels.
1.5. Equipment components and modules shall be sized to allow one man to handle
them.
1.6 Special control cables (e.g., fiber optic cables) shall be designed for
direct burial.
1.7 Special control cables supplied by the contractor must withstand cable
pulling forces of 50 kg and a minimum bending radius of 12 cable diameters.
[Pulling force will be larger if such cables are available.]
1-1
2. ENVIRONMENTAL
- ^
2.2 Equipment installed in the control house will be exposed to 0° TO 55°C tem
perature variations with up to 95% non-condensing relative humidity, with a
maximum wet-bulb temperature of 35°C. Equipment installed in the other
locations of a substation must operate within -40° to +650C temperature
range and up to 95% non-condensing relative humidity. Cabinet heaters may
be used to prevent condensation where more serious humidity problems are
anticipated. Maximum rate of temperature change shall not exceed 20°C per
hour.
2.3 The seismic qualifications of the control equipment shall conform to pre
vailing national standards according to its location of installation and
service.
2.5 All control equipment shall withstand adverse EMI, radiated or conducted,
without misoperation or failure, in the following defined environments:
A. ANSI C37.90a-1974
B. Conducted fast transient
C. Portable RF transmitters
D. Transient electromagnetic fields (EPRI-1359-2) for switchyard
located equipment only.
2.6 All system hardware which performs critical protective relaying functions
shall conform to ANSI C37.90-1978. Critical protection functions are
numbers 1, 2, 3, 4, 12, 13, 14, plus parts of 16, 17, 18, 19.
1-2
3. OPERATING PERSONNEL
3.1 Display of equipment status and analog readings, and control of devices
shall be centralized. A CRT for displaying one-line diagrams and tables
is the preferred operator interface device during local substation manual
operation. A mimic-bus of the substation may be used optionally. For
stand-alone equipment, readouts and controls must be located at an
appropriate height for ease of viewing and manipulation by the average
operator. Controls shall be protected to prevent accidental operation.
3.2 Any operator shall have access to information at the station such as
metering, equipment status, passive sequence-of-events logs, alarms,
counters, etc.
3.4 For individual points or groups of points of the types listed in 3.3 above,
the user shall be given one category of local operators, plus 3 categories
of remote masters. He shall be able to program the system so that none,
all, or any combination of these 4 categories can control each point or
group of points. In the functional requirements, such points or groups are
characterized as operable by designated operators. Relay setting changes
shall require a more secure entry procedure.
3.5 Means shall be provided for programming of priorities for each of the 4
categories, in case more than one attempts to control the same point.
3.6 Some qualifying procedure such as code or password shall be used to iden
tify a local operator.
3.7 Local control may be initiated through the operator's console interface,
but backup electrical control of circiut breakers and switches must be pro
vided such that no single failure will affect both normal and backup
positions.
3.9 Any operator action (remote or local) shall be recorded as an event for
sequence-of-events and related logs. The operator or remote master iden
tity shall be included in the logging. This does not apply to passive
access to data as described in 3.2 above.
1-3
C. Stored on non-volatile medium and changed by programmer through soft
ware system modification or regeneration. (e.g., tables in mass
memory).
3.11 Relay settings and other fixed operational parameters may be Class (A),
(B), or (C) as desired by user. They may be divided so that some of each
type are used, depending on likelihood of field setting changes. Variable
operational parameters such as limits and set points shall be Class (D).
Adaptive or self-settings are Class (E).
3.13 Optionally, all Class (E) settings which directly dictate some automatic
control action shall be logged when that action is taken. As a further
option a Class (E) setting may be logged whenever it changes, for
diagnostic purposes.
1-4
4. MAINTENANCE AND TESTING
4.1 Means shall be provided for testing each subsystem including the optical
links.
4.5 Test points, LED indicators, or card extenders shall be provided for all
equipment to facilitate troubleshooting. Routine adjustments shall be
accomodated without card withdrawal.
4.6 Sufficient test points shall be provided for localizing equipment trouble
to the card level. Use of indicators (e.g. LED's to indicate failure) is
highly desirable.
4.8 Maintenance personnel shall have the capability of switching between regu
lar and backup SCADA communication channels.
4.10 Data test patterns shall be built in or shall be programmable within each
communication interface to facilitate troubleshooting.
4.13 The system shall be so designed that given sufficient hardware redundancy,
it shall be possible to arrange the primary and backup protection subsystem
so that during repair or scheduled maintenance of either subsystem, the
other subsystem can be operating and providing protection.
4.14 Diagnostic Software and test algorithms shall be provided to exercise the
processing elements on a regular basis. Test failures will be alarmed.
1-5
5. EXPANSION/ ADDITION, AND MODIFICATION
5.3 The substation computer shall have sufficient capacity to handle the ulti
mate substation requirements with minimum additional equipment and
rewiring.
5.5 Control equipment shall be of modular design and shall utilize plug-in con
nections to simplify equipment additions or removals with minimum rewiring.
5.6 Maximum use of the distributed processor approach shall be made. Any
control operation or data processing shall be performed at the lowest prac
tical level of hierarchy consistent with sound engineering design prin
ciples to minimize dependence on communication channels and to improve
response time.
1-6
6. DESIGN
6.1 All control equipment shall be designed to operate from the station battery
source. Battery voltage may vary from 84% to 116% of nominal value. The
contractor shall specify the battery drain current of each subsystem
supplied. Initial design shall be for 125 Vdc nominal. 48 Vdc and 250 Vdc
are also frequently encountered.
6.2 Any filtering and surge protection required to meet environmental specifi
cation above shall be the responsibility of the contractor. Filtering with
capacitors in excess of 1 microfarad is not acceptable on continuously
grounded equipment.
6.4 Contractor's equipment shall be supplied with fuse or circuit breaker pro
tection and an on/off switch for each module or subsystem to completely
isolate the equipment from the dc supply. Loss of power or functionality
shall be alarmed.
6.7 The analog input subsystems shall accept and digitize voltage samples of up
to 2.5 p.u., and current samples of at least 40 p.u. Values in excess of
these full-scale limits shall not cause erratic program outputs or misop
eration of functions.
6.11 A means shall be provided to mask input relay bounce on opening, closing,
or both. Bounce on closing shall be masked by providing a time-delayed
dropout of adjustable period after the contact closes. Bounce on opening
shall be masked by providing a time-delayed pickup of adjustable period
after the contact opens. Dropout or pickup delay shall be adjustable 0 to
30 ms.
6.12 Contact input voltage supply may be different than battery voltage to
system.
1-7
6.13 Tripping outputs shall carry up to 30A for Is. Output drivers shall reset
automatically in 12 ms after fault disappears.
6.14 Low level control outputs (e.g. BFI, Reclose initiate, etc.), shall carry
3A continuously and shall be capable of interrupting 0.5A inductive at 125
Vdc. Fault-related outputs shall automatically reset after fault
disappears.
6.17 Equipment should meet all relevant industry standards in effect at time of
manufacture.
6.18 The design shall be made as fail-safe as is practical. This means that the
supplier shall approach the hardware and software design in such a way that
the more probable or foreseeable failure modes produce passive or secure
behavior of control and data outputs. However, specific outputs in
response to particular failures may be called for elsewhere in this
document, or by the user at time of system specification.
6.20 The design shall minimize the probability of a single component failure
causing a cascading component failure or subsystem misoperation.
6.22 Control equipment shall not issue spurious outputs in the event of power
failure. The equipment shall execute an orderly restart upon restoration
of power.
6.23 No failure in one hardware subsystem shall cause a failure in another hard
ware subsystem.
A. Line Protection
B. Bus Protection
C. Transformer Protection
D. Breaker Failure and Ground Fault Protection
E. Shunt Reactor Protection
6.25 Facilities for manual switchover to and from the secondary system shall be
provided.
1-8
6.27 Communications links between primary and backup may be provided for redun
dancy of input sources and control outputs depending on equipment con
figuration design.
6.30 Contractor shall minimize the use of special function hardware. Special
functions should be performed by software whenever possible.
6.33 Isolating test switches shall be supervised through the use of covers or
supervisory interlocking blades.
6.36 Sufficient space and support shall be provided at the external connection
points to accomodate wires and cables which enter the equipment from the
top and/or bottom.
6.38 Discrete components and integrated circuits shall be "off the shelf" items
supplied by more than one manufacturer.
6.39 All processor control memories shall be equipped with failure detection
means (e.g. check sum on control ROMs).
1-9
7. DOCUMENTATION
7.1 All equipment shall be supplied with the following hardware documentation:
7.2 All software documentation shall be of high quality, and supplier shall
certify that it corresponds to the software actually shipped. The documen
tation shall include but shall not be limited to the following information:
1-10
8. RELIABILITY
The reliability and availability estimates for the chosen hardware configuration
shall be based on constituent MTBF's derived from one of the following methods:
B. Failure rates taken by comparison of the devices in the designed modules with
those as in (A) for which measured data exists using suitable multiplier
based on comparative complexity and stress level.
C. Where neither of the above methods are available, calculations shall be made
using the procedures given in MIL-HDBK-217B or 217C.
In all cases, this data shall be extrapolated to the upper temperature limit of
the design specifications.
1-11
SECTION II
FUNCTIONS
I. FUNCTION DESCRIPTION
For a fault anywhere along the protected transmission line, initiate high
speed tripping of circuit breakers at each terminal.
For the initial design, three-phase tripping will be provided for all
faults. Design shall allow for future addition of phase selection and
single- or selective-pole tripping output.
2-1
LINE FAULT PROTECTION (Cont'd)
Inputs
1 .6 Loss-of-channel indication.
Outputs
Initially, one trip output per breaker. Design will allow for
future addition of independent pole tripping for single-pole
operation (i.e. three outputs for each of the 4 breakers).
2-2
LINE FAULT PROTECTION (Cont’d)
1. Performance
2-3
LINE FAULT PROTECTION (Cont’d)
2-4
LINE FAULT PROTECTION (Cont'd)
1.2 Characteristics
2-5
LINE FAULT PROTECTION (Cont'd)
2. Operating Personnel
2.3 Optional indicators on the host module shall show trip type.
2-6
LINE FAULT PROTECTION (Cont'd)
3.2 Store the essential results of each calculation (after every new
set of sanples). Following the fault, dump this record as a
testing and optional production feature.
2-7
2. TRANSFORMER FAULT PROTECTION
I. FUNCTION DESCRIPTION
2-8
TRANSFORMER FAULT PROTECTION (Cont'd)
1. Inputs
2. Outputs
2-9
TRANSFORMER FAULT PROTECTION (Cont'd)
1. Performance
..
2-10
TRANSFORMER FAULT PROTECTION (Cont'd)
A. Sudden-pressure relay.
C. Overtemperature contact.
1.2 Characteristics
2-11
TRANSFORMER FAULT PROTECTION (Cont’d)
2. Operating Personnel
D. Inrush restraint.
2.2 Optional indicators on the host module shall show trip type.
2-12
3. BUS FAULT PROTECTION
I. FUNCTION DESCRIPTION
2-13
BUS FAULT PROTECTION (Cont'd)
1. Inputs
2. Outputs
2-14
BUS FAULT PROTECTION (Cont'd)
1. Performance
1.1.3 The design should allow for future use of linear couplers
and low-energy electronic ct's (ECT's).
1.1.6 For utilities who reclose at high speed for bus faults,
single-pole tripping for bus faults may be considered in
the future.
1.2 Characteristics
1.2.2 The maximum operating time shall not exceed 16 ms, unless
a surge arrestor is included in the bus zone. In that
case, operating time may be up to 24 ms.
2. Operating Personnel
2-15
BUS FAULT PROTECTION (Cont’d)
2.2 Optional indicators on the host module shall show trip type.
2-16
4. BREAKER FAILURE AND FAULT PROTECTION
I. FUNCTION DESCRIPTION
2-17
BREAKER FAILURE AND FAULT PROTECTION (Cont’d)
1. Inputs
1.4 Breaker "a" and "b" contact status, consolidated for three inde
pendent poles if used.
1.5 Breaker failure initiate (BFI) inputs from primary and secondary
relaying functions for zones on both sides of the breaker. May
be pre-identified as line, bus, or transformer protection
initiation. Also, an adjacent-breaker failure initiation may be
needed for future cascaded-B.F. applications.
2. Outputs
2-18
BREAKER FAILURE AND FAULT PROTECTION (Cont'd)
1. Peformance
1.1 Initiation of the function shall be from all functions which are
trying to trip this breaker except manual or supervisory control.
Initiation for breaker failure on other adjacent breakers may be
optionally provided.
2. Operating Personnel
2-19
BREAKER FAILURE AND FAULT PROTECTION (Cont'd)
2.4 Optional indicator on the host module shall show B.F. trip type.
2-20
5. AUTOMATIC SWITCHING SEQUENCES
I. FUNCTION DESCRIPTION
2-21
AUTOMATIC SWITCHING SEQUENCES (Cont'd)
■-
1. Inputs
2. Outputs
2-22
AUTOMATIC SWITCHING SEQUENCES (Cont’d)
1. Performance
A. Automatic sequencing.
2. Operating Personnel
2-23
AUTOMATIC SWITCHING SEQUENCES (Cont’d)
2-24
6. LOCAL CONTROL OF VOLTAGE AND VAR FLOW
v..
2-25
LOCAL CONTROL OF VOLTAGE AND VAR FLOW (Cont'd)
1. Inputs
2. Outputs
1. Performance
1.4 If station has more than one type or size of reactive device, a
priority procedure shall be established for selection of bus
voltage to be adjusted, and reactive device to be used.
2. Operationg Personnel
A. Control setpoint.
B. Control bandwidth.
C. Control bias & time delay.
D. Load compensation.
E. Transformer ratings for parallel operation and permissable
deviation of loadings.
2-27
7. LOCAL MAN-MACHINE SUBSYSTEM
I. FUNCTION DESCRIPTION
This function enables the local operator to display and enter data, to per
form manual operations and to initiate and monitor diagnostic and main
tenance test functions. These operations are itemized below:
1. Data Display
2. Data Entry
2-28
LOCAL MAN-MACHINE SUBSYSTEM (Cont'd)
1. Inputs
2. Outputs
/-
v.
2-29
LOCAL MAN-MACHINE SUBSYSTEM (Cont'd)
1. Performance
2-30
LOCAL MAN-MACHINE SUBSYSTEM (Cont'd)
1.11 After the operate command is given, the correct operation shall
be confirmed using checks such as:
1.14 Optionally, locally recorded data which was not sent to the
master and was about to be overwritten.
2. Operating Personnel
2-31
LOCAL MAN-MACHINE SUBSYSTEM (Cont'd)
3.4 System shall permit display os SCADA tables on the local display
device.
8. REVENUE METERING
Sample voltage and current signals and compute real and reactive power.
Integrate these values to obtain kWh, KVARh and demand readings. kVAh
should be provided if needed.
/■
2-33
REVENUE METERING (Cont’d)
1. Inputs
2. Outputs
2.1 kW, kVAR, kVA, kWh, kVARh, )d7Ah and demand records (to be stored
in a non-volatile memory).
2-34
REVENUE METERING (Cont'd)
1. Performance
2-36
9. REMOTE SCADA INTERFACE
/'
2. Responses to master
2-37
REMOTE SCADA INTERFACE (Cont'd)
1. Inputs
2. Outputs
2-38
REMOTE SCADA INTERFACE (Cont'd)
1. Performance
1.1 Communications
■v .
2-39
REMOTE SCADA INTERFACE (Cont’d)
2-40
REMOTE SCADA INTERFACE (Cont'd)
.
parameters, etc. When such information is
received it shall be stored and the appropriate
processing program shall be called.
A. Circuit breakers
B. Disconnect switches
C. Control test point
D. Station Local/Remote plus individual control
point Local/Remote
E. Synchrocheck status
F. Lockout status
G. Alarm indications for station equipment
H. All controlled devices and circuits
I. Selected uncontrolled devices
J. Failure indications from selected station
circuits
K. Failure of supervisory control subsystems
L. Safety tags.
2-41
REMOTE SCADA INTERFACE (Cont'd)
A. Bus volts
B. Line watts, vars, amperes
C. Transformer watts, vars, amperes
D. Calibration points (10% or 90% of full
scale)
E. Frequency (optionally)
F. Other analog data such as temperatures, gas
flow, etc.
G. Synchrocheck slip frequency, or voltage and
phase
2-42
REMOTE SCADA INTERFACE (Cont'd)
2• Operating Personnel
2-43
10. TIE-TRIPPING
The function may also be used for alarm only, or can alarm as advance
warning before a trip.
2-44
TIE-TRIPPING (Cont'd)
1. Inputs
1.1 Voltage signal samples from one phase of bus or line, for fre
quency measurement, if used.
1.2 Samples of voltage and current for tie line, to compute direc
tion and magnitude of power flow. Alternatively, load flow may
be obtained from another function which computes it. Current,
if used, from up to 4 three-phase ct sets.
2. Outputs
V.
2-45
TIE-TRIPPING (Cont’d)
1.2.1 The function shall monitor power out on the tie in con
junction with below-normal frequency and shall trip if
limits on both are exceeded.
2-46
11. LOAD SHEDDING
Optionally, the shed loads can be automatically restored after system fre
quency returns to normal.
2-47
LORD SHEDDING (Cont'd)
1. Inputs
2. Outputs
2-48
LOAD SHEDDING (Cont'd)
1. Performance
2. Operating Personnel
2.4 Any operator should be able to determine which steps have been
implemented and which lines or feeders have been dropped to meet
target shedding at any point in the sequence.
/-
2-49
12. SHUNT REACTOR PROTECTION (Cont'd)
1. FUNCTION DESCRIPTION
2-50
SHUNT REACTOR PROTECTION (Cont'd)
1. Inputs
1.1 Samples of currents from 3-phase bushing ct's for each reactor
bank.
1.2 Samples of current from single neutral ct for each reactor bank.
2. Outputs
V,.-
2-51
SHUNT REACTOR PROTECTION (Cont'd)
1. Performance
V, I. FUNCTION DESCRIPTION
2-53
TRANSFER TRIPPING (Cont'd)
1. Inputs
2. Outputs
2-54
TRANSFER TRIPPING (Cont’d)
1. Performance
1.3 On dual-channel systems, alarm for trip signal from one receiver
only. On loss of one channel, alarm and enable tripping on
receipt of trip signal from the other channel. Optional disable
feature for latter function.
1.4 User shall have the following supervision options for received
transfer-trip command:
A. No supervision
B. Enabling for 500 ms after a sudden current or voltage change
C. Residual overcurrent
D. Overreaching distance relaying function
E. Any combination of B, C, and D
2. Operating Personnel
2-55
14. PILOT AND TRANSFER-TRIP CHANNEL MONITORING
I. FUNCTION DESCRIPTION
:
The blocking-type relaying used with this channel will not suffer a
reduction in security from frequent channel testing. Since the
relaying processor performs the testing it can abort the test sequence
at any sign of a disturbance requiring possible relay action.
Therefore, dependability is not degraded either.
The above test can be executed periodically, say once a day, automati
cally by the processor; or it can be manually initiated.
3. For FSK carrier channels, there may be logic at the receiving end
which enables tripping (permissive) for 150 ms on loss-of-channel.
The security hazard is thus slightly increased, in that an external
(Zone 2) fault occurring in this 150 ms window may lead to false
tripping. Utilities must evaluate their concern about experiencing
such a trip. New, more secure schemes will be sought, if possible.
2-56
PILOT AND TRANSFER-TRIP CHANNEL MONITORING (Cont'd)
II. Inputs
2. Outputs
2-57
PILOT AND TRANSFER-TRIP CHANNEL MONITORING (Cont'd)
1. Performance
1.1 General
*>
2-58
PILOT AND TRANSFER-TRIP CHANNEL MONITORING (Cont'd)
2. Operating Personnel
I. FUNCTIONAL DESCRIPTION
This function shall record and indicate sequence-of-events data from the
protection systems, from substation apparatus, from control functions, and
from local and remote operators. All such events are time-tagged and
stored. Upon request from an operator or automatically on occurrence of
fault, the sequence-of-events files are displayed or printed locally and/or
transferred to SCADA master or any other remote data terminal which inter
faces to the substation control system.
A list of events which may be logged is developed in advance for each pro
tection function.
In addition to generating entries for the events list, this function shall
update limited panel indications provided on protection processors, if
desired by a particular user.
2-60
INDICATION AND SEQUENCE-OF-EVENTS RECORDING (Cont'd)
1. Inputs
2. Outputs
2-61
INDICATION AND SEQUENCE-OF-EVENTS RECORDING (Cont'd)
1. Performance
1.7 The event storage and operator indication facilities shall each
offer the options of being reset by the local operator, or over
a telemetering interface, or automatically after hard-copy
logging or sequence-of-events, or after a preset time delay.
•*'•'**
2-62
INDICATION AND SEQUENCE-OF-EVENTS RECORDING (Cont'd)
1.10 Beginning of the fault condition shall be tagged with date and
time with a resolution of 1 ms. The time differences among all
analog wave forms and digital events ultimately displayed on
user's display or recording device, shall not be more than 1 ms
from actual time relationship.
2. Operating Personnel
2-63
16. LOAD MONITORING AND OUT-OF-STEP PROTECTION
I. FUNCTION DESCRIPTION
When machines on the power system are slipping out of synchronism, imple
ment a splitting or islanding of the system which separates out-of-step
machines and which balances the load and generation as closely as possible
within each island. The out-of-step protection function at a given line
terminal must determine that the electrical center of a swing has fallen
within a zone around the line-impedance locus; it then implements one of
the control strategies given below. Distinguish between symmetric and
unbalanced conditions to facilitate continued unbalanced-fault protection
during swings.
2-64
LOAD MONITORING AND OUT-OF-STEP PROTECTION (Cont'd)
1. Inputs
2. Outputs
2-65
LOAD MONITORING AND OUT-OF-STEP PROTECTION (Cont'd)
1. Performance
2-66
LOAD MONITORING AND OUT-OF-STEP PROTECTION (Cont'd)
2-67
LOAD MONITORING AND OUT-QF-STEP PROTECTION (Cont’d)
b. Trip for 135% for 30 min, 185% for 15 min, 200% for 2
min.
1.3.5 On lines with tapped loads, one end may be preferred over
the other when trip becomes necessary, so interface to
other substation control system through master, or
through conventional transfer-trip channel. Back up
channel failure with local trip.
2. Operating Personnel
2-68
17. AUTOMATIC RECLOSING
I. FUNCTION DESCRIPTION
The majority of faults on transmission lines are temporary and will dissi
pate if the line is deenergized for 0.25 - 0.5 s. Logic is thus provided
to execute a delay after high-speed clearing of line faults, to initiate
reclosing of the breaker, and finally to limit the number of unsuccessful
reclosing attempts.
2-69
AUTOMATIC RECLOSING (Cont'd)
1. Inputs
A. Pilot trip
B. Zone 1 trip; high-set trip
C. Zone 2 trip
D. Single- versus multi-pole trip, pilot
E. Bus trip; single- versus multi-pole trip
2. Outputs
2-70
AUTOMATIC RECLOSING (Cont'd)
1. Performance
A. Live-bus, dead-line
B. Dead-bus, live-line
C. Synchrocheck (live line and bus)
1.6 Test and folow breakers at a given station will require dif
ferent supervising checks and time-delay sequences. Each
breaker shall be subject to an individually selected sequence.
2-71
AUTOMATIC RECLOSING (Cont'd)
1.9 When the line remains continuously energized with the reclosing
enabled for a time period in excess of the reset time delay,
then the logic shall proceed from the EOS state to a ready-for-
reclosing (normal) state. No other means of leaving the EOS
state shall be provided. If an automatic trip occurs while the
logic is still in EOS state, no automatic reclosing shall
follow.
1.13 EOS state implies only that no automatic reclosing can occur.
All closing initiation from outside the reclosing function,
including local or remote manual closing, shall still be
possible when automatic reclosing is in EOS.
2-72
AUTOMATIC RECLOSING (Cont’d)
2. Operating Personnel
2-73
18. MONITORING AND CONTROL OF BREAKERS AND SWITCHES
I. FUNCTION DESCRIPTION
Check for sustained pole disagreement and flashover of open devices using
auxiliary contacts, currents, and phase or residual voltages. Optionally
execute controlled-breaker or backup-breaker tripping for certain pole
disagreements and flashovers. Provide logic and delays for single-pole
tripping applications.
2-74
MONITORING AND CONTROL OF BREAKERS AND SWITCHES (Cont'd)
1. Inputs
1.3 Trip and close commands from automatic control devices and
programs (relaying, reclosing,etc.).
1.5 Current flow data as available for each controlled and/or moni
tored switching device (including raw samples or phase-position
data for zero-crossing trip option).
1.7 Auxiliary "a" and "b" contacts; separately from each pole if
available.
1.8 Device status contacts such as low air pressure, low gas
pressure, etc.
2. Outputs
2-75
MONITORING AND CONTROL OF BREAKERS AND SWITCHES (Cont'd)
1. Performance
2-76
MONITORING AND CONTROL OF BREAKERS AND SWITCHES (Cont'd)
A. Nonvolatile
B. Non self-resetting
C. Electrically resettable by operators unconditionally, or
only if certain predetermined conditions are satisfied.
1.15 Each breaker and motor-operated switch shall have its own indi
vidual lockout and lockout reset capability. Protection func
tions which gang-trip shall lockout breakers as desired via
tripping and lockout tables. Lockouts shall be individually
cleared before reclosing of each device.
2-77
19. SYNCHRONISM CHECKING AND SYNCHRONIZER CLOSING
I. FUNCTIONAL DESCRIPTION
B. Evaluates slip frequency across the open breaker contacts versus a pre
set limit to determine safety of closing.
F. Aborts the closing attempt after a preset time limit, with message or
alarm to designated operators.
2-78
SYNCHRONISM CHECKING AND SYNCHRONIZER CLOSING (Cont'd)
1. Inputs
1.2 Initiating and abort signals from local or remote operator, for
synchronizer closing.
2. Outputs
2-79
SYNCHRONISM CHECKING AND SYNCHRONIZER CLOSING (Cont'd)
1. Performance
2. Operating Personnel
2.2 Means shall be provided for setting of voltage, phase, and slip-
frequency tolerances, plus breaker closing delay.
2-80
20. OSCILLOGRAPHY
I. FUNCTIONAL DESCRIPTION
2-81
OSCILLOGRAPHY (Cont'd)
1. Inputs
2. Outputs
2-82
OSCILLOGRAPHY (Cont'd)
1. performance
1.5 The user shall have, via programming, options for first-level
storage use:
1.6 All saved tables of data are time-tagged for correlation with
SOE log (1 ms resolution).
1.8 If storage is full and another fault occurs before data can be
transferred to high-level processor, the user shall have the
option at SYSGEN of;
C. keeping the old data for a preselected time period and then
releasing the store for new data.
2-83
OSCILLOGRAPHY (Cont’d)
'"V
1.9 Optionally, programs shall be provided to equalize the data with
respect to data-acquisition unit input filters, and to plot it
off-line, on some suitable host facililty. Also optionally,
this may be done at the substation by the substation computer.
1.12 Saved data at the second level of storage shall be available for
local dump or for telemetering to remote location, if not
locally processed.
2. Operating Personnel
2-84
21. LINE FAULT LOCATION ESTIMATION
I. FUNCTIONAL DESCRIPTION
Utilize raw voltage and current signal data, stored during line faults by
the oscillography function, to calculate apparent physical distance from
relaying location to the fault. Location data is thus provided for tem
porary as well as permanent faults. Calculation is performed after the
fault by programs in the station computer or another host machine which
receives oscillography data.
2-85
LINE FAULT LOCATION ESTIMATION (Cont'd)
1. Inputs
2. Outputs
1. Performance
1.4 Distance estimation shall be tagged with date and time; and
shall be made available to local or remote interfaces as desired
by user (unless executed on host machine).
2-87
22. DATA LOGGING
I. FUNCTION DISCRIPTION
Format and output all information which is to be printed locally (if local
printing option exists) and prepare information to be transmitted to
masters for printout of reports at remote control centers. Because of the
obvious functional similarity, tabular CRT displays are also included in
this function.
2-88
DATA LOGGING (Cont’d)
1. Inputs
2. Outputs
2-89
DATA LOGGING (Cont'd)
1. Performance
2. Operating Personnel
2.3 Designated operators shall be able to select any point for trend
computation.
2.4 It shall not be possible for any operator to delete any item in
an existing log or record (i.e., no cleanup of logs).
w ■*
2-90
DATA LOGGING (Conf d)
2-91
23. ALARMING
I. FUNCTION DESCRIPTION
The alarming program shall be able to route each alarm to the responsible
local or remote operator.
2-92
ALARMING (Cont'd)
1 . Inputs
2. Outputs
2-93
ALARMING (Cont'd)
1. performance
2-94
ALARMING (Cont'd)
- Reactor alarms
protection trouble
fire
loss of oil flow
high oil temperature
low oil level
hot spot or winding temperature
pressure relief
gas detector
tank vacuum
out of service
- Line protection trouble
- Bus protection trouble
- Revenue metering trouble
- Line loading high
- Line loss
- Line peak MW and MVAR
- Loss of guard
- Carrier failure
- Automatic control system operation failure
- Unbalanced ac potential
- Synch, closure failure
- Unauthorized penetration of substation property
- Emergency generator running
- Sump level high
- Sewerage ejection pump failure
- Ac transducer trouble
2. Operating Personnel
2-95
ALARMING (Cont1d)
2-96
24. INFERENTIAL MEASUREMENT CHECK
I. FUNCTIONAL DESCRIPTION
Confirm that each ac signal transducer (cvt, ct, or other primary connected
device), and its interfaces to the substation control system, are func
tioning correctly and are calibrated. In a centralized data-base system,
look for consistency of readings collected from transducers around the
substation. For example, the instantaneous or rms currents passing to or
from a selected phase of a bus section should sum to zero. If they do not,
an alarm warns the operator that one of the transducers or data links is
malfunctioning. In some cases, it may be possible to identify the par
ticular element by observing unbalanced phase measurements at a give
location.
2-97
INFERENTIAL MEASUREMENT CHECK (Cont'd)
1. Inputs
1.1 Rms voltages, with relative phase position data from all three
phases of all potential transducers in the station.
1.2 Rms currents, with relative phase position data, from all three
phases of all current transformers in the station.
1 .3 Data from the breaker and switch monitoring function on the sta
tes of all such devices in the station.
2. Outputs
" ■>
2-98
INFERENTIAL MEASUREMENT CHECK (Cont'd)
1. Performance
2-99
25. TRANSFORMER OVERLOAD MONITORING
I. FUNCTION DESCRIPTION
Also, accept inputs from partial discharge detector and gas analyzer.
2-100
TRANSFORMER OVERLOAD MONITORING
1. Inputs
2. Outputs
2.1 Alarms
2-101
TRANSFORMER OVERLOAD MONITORING (Cont'd)
1. Performance
1.3 Loss of oil flow and/or loss of cooling fans should automati
cally change transformer rating.
1.4 Optionally, time left to reach a hot spot temperature for which
transformer life expectancy should be considered, if present
loading continues, shall also be presented to operators.
1.7 Trips caused by the overload monitoring function shall not cause
lockout, but shall only interrupt load.
2. Operating Personnel
2-102
26. SELF-CHECKING
I. FUNCTION DESCRIPTION
The self-checks fall into two categories. The first group consists of
direct tests on processor hardware, using periodically-executed test
programs and external monitoring devices. These tests form the processor-
oriented self-checking.
Processor Oriented:
A. Instruction test
B. Memory checksum
C. Output-to-input loopback test
D. Dead-man or processor-bus fault detector
Application Oriented:
A. A/D calibration check using a fixed input reference source on one
channel
B. Voltage-signal limit check, and check for balance among phases
C. Current-signal balance check among phases
D. Phase sequence and polarity check
2-103
SELF-CHECKING (Cont'd)
1. Inputs
1 .3 Looped-back outputs
2. Outputs
2.1 Alarms
2-104
SELF-CHECKING (Cont'd)
1. Performance
A. Processor hardware
B. Control software (ROM)
C. Trip output continuity
D. Correctness of input sources
2-105
SELF"CHECKING (Cont'd)
2. Operating Personnel
2-106