Professional Documents
Culture Documents
Pipework
Pipework
Pipework
9.1 Objective
This Method Statement serves to document the procedure for the fabrication,
installation, welding and testing of the pipework system.
Material
(a) Condensate pipe
(b) In situ polyurethane mixture
(c) Cement solvent
(d) Welding rods
(e) G. I. sheet
(f) Bolts and nuts
(g) HILTI® flush anchors M10 size
(h) Hanger rods
(i) Support bracket
Machinery
(a) Tools and equipments
(b) Chain blocks or other lifting equipment
9.4 Submission
All sample pipe and associate accessories shall be submitted to the respective
consultant for approval prior to installation works.
9.5 Manufacturing
Aboveground & underground chilled water pipe shall be G.I pipe class ‘C’ c/w poly –
urethane pre-insulated type (CFC free). All pipes shall end-capped to protect against
introduction of dirt or water. All delivery to site shall be check for rust, welding,
insulation or any deformities.
9.6 Transportation, Storage and Handling
Pipe shall be transported to site via lorries and pipes shall be hoisted to the respective
level via cranes. Fittings shall be transported in casings and shall be hoisted to the
respective level via the crane. Utilization of chain block during installation shall be
used if necessary. All pipes if possible shall be stored inside the building. If in the
event that external storage is inevitable, pipes shall be duly covered and raised up
above ground.
9.7 Installation
Pipe Supports
Vertical run pipes shall be fastened to the building floor slabs at each level.
The additional brackets will be provided at middle height of each level if
necessary.
Pipe Sizes (mm) Rod Diameter (mm) Max. hanger Space (mm)
Up to 25 10 2000
32 to 50 10 3000
65 to 80 15 3000
100 15 3600
Types of Pipe Support are as indicated in Equipment and Piping Installation Detail.
Calculation shall determine the support spacing, size and type. These shall be in
compliance to the specifications. There shall be minimum 2 support per length of
pipe. Trapeze type support shall be used where more that two pipes are running side
by side in parallel. Expansion type anchor bolts shall be correctly selected and
installed to prevent overloading. Positions of anchor-bolts are marked on the slab
above prior to drilling. Anchor-bolts are tightened together with the mild steel channel
(where required). The hangar rod and the clevis hangars are than bolted onto the
channel. The pipe is then lifted (large pipe using chain block) to sit onto the clevis
hangar.
Pipe risers to be anchored shall be via sleeve to pipe and wedge to sleeve and channel
method as indicated in Equipment and Piping Installation Detail. Pipe risers to be
guided only shall be as indicated in Equipment and Piping Installation Detail.
Pipe running on ground level shall be installed as indicated in Equipment and Piping
Installation Detail.
9.7.5 Insulation
As pipes are pre-insulated, site insulation works shall be limited to joints and elbows.
Site insulation works shall be carried out only after completion, inspection, pressure
test and approval of the joint. All site insulation for pipes shall be jacketed first and
subsequently the polyurethane compound is poured it. The work sequence of
polyurethane insulation as below:
9.7.6 Penetration
All pipe penetration through floors and compartment walls shall be installed with the
appropriate fire seal and installation shall be verified by the fire seal supplier.
a) All galvanized pipes passing through walls, floors shall be filled with pipe
sleeves of 1.0mm galvanized sheet metal, and shall be minimum one nominal
diameter larger than the service pipe.
b) Installation shall be done during the formwork activity or coordinated during
the brick work erection.
c) Where pipes penetrate floors and firewalls, the annular space between the
sleeve and the pipe shall be filled with mineral rock-wool and for fire-wall to
caulk with approved fire stopper at both ends.
Pressure test shall be carried out over the whole system at 1.5 times the operating
pressure or minimum 150psi and hold for 24 hours.
Quality Control shall start from fabrication offsite, delivery until installation.