Professional Documents
Culture Documents
RAN - Installation MoP-v01 - Safaricom Ethiopia - V1.1 - 08122021
RAN - Installation MoP-v01 - Safaricom Ethiopia - V1.1 - 08122021
RAN - Installation MoP-v01 - Safaricom Ethiopia - V1.1 - 08122021
Installation Document
Function TI Manager
Approver Arvin Ramballee/Adel Moneim
Change History
material, including documentation and any related computer programs, is protected by copyright controlled by
Nokia. All rights are reserved. Copying, including reproducing, storing, adapting or translating, any or all of this
material requires the prior written consent of Nokia. This material also contains confidential information, which may
not be disclosed to others without the prior written consent of Nokia.
This document details the Method of Procedure (MOP), including work tasks and checks required, to
successfully install 2G, 3G, LTE, and SRAN SBTS. This document will be used during Safaricom Telecommunications
Ethiopia PLC deployment on RAN Scope.
This document is generated by Nokia and to be shared with Safaricom for consultation purposes. This
document and information contained within shall not be shared or distributed outside of Nokia without prior written
consent.
If there are any concerns or changes required to this MOP, this should be raised to the identified MOP contacts
in this document within 2 working days of discovery.
IMPORTANT WARNING
Purpose of this Method of Procedure document is to summarize the scope of installation and to provide the
guidelines for auxiliaries and connectivity between the different network elements in subject project, this
document does not focus on the Hardware installation itself, that’s why the installation teams must use Nokia
Hardware installation manuals together with this MoP document to be able to complete the site installation as
per Nokia standards and customer requirements.
It’s mandatory that the installation team members are trained on the installation of Nokia hardware and other
network elements related to the scope of this project, the installation teams must hold all necessary
certificates required to complete the work onsite as per Nokia requirements, standard practice and country
regulations, certificates such as but not limited to; Nokia PTID, electrical works, work at hight, telecom cabling &
fibre works, …, etc.
Please find attached Templates for TSSR. There are different templates for New Build & Colo.
This document describes the Nokia RAN to meet SFC forecasted network deployment and expansion for the initial
664 sites.
This will give an overview of the SRAN solution proposed by Nokia. The proposed Single RAN Solution to Safaricom
Telecommunications Ethiopia PLC. comprises of Airscale Base Station that is a versatile software-defined, multi-
technology, high-capacity base station on the market. It will help SFC Ethiopia build a simplified Network using
Single RAN equipment which allows for significant OPEX savings.
Note:
1. All cables to enter from bottom of Radio modules.
2. Jumpers to be routed with cable ties and chained properly.
3. Jumpers should be supported by tie connectivity on pole to avoid stress on connector due to wind.
However, Roof top & Green Field solution will remain valid for these sites.
DC DB would be deployed on a portion of Co-Located sites with Ethiotel. These Site’s will be without without DC
power cabinet. On these sites, DC will be provided by sharing party.
The DC feed will be power the DC DB, and from the DC DB the site will be powered. Below will be assumptions for
these sites:-
• Feed will be supplied to us from a single LVD(set to 43.5V or above, Safaricom will take responsibility of the LVD)
• The DB will supply power to the FCOB, Mw, BB , site switch, site light and FPFH(RRH’s) (Invertor may be added)
• Site Light will be DC LED (Not more than 400w) not AC as per RF
Canopy poles will be used to mount the DB and the FCOB. Site light will be mounted to the inside of the canopy.
Canopy poles will be used to mount the DB. The FCOB will be mounted to the JST stack. Site light will be mounted
to the inside of the canopy.
Note: 2xFCOB stacked on top of each other in the case of IXR. If the site required the SAS-K router, 1 x FCOB will
be used.
Alarm card used in this project will be FSEE. This alarm could be fixed with FMAA bracket as shown below.
Purpose of this Method of Procedure document is to summarize the scope of installation and to provide the
guidelines for auxiliaries and connectivity between the different network elements in subject project, this
document does not focus on the Hardware installation itself, that’s why the installation teams must use Nokia
Hardware installation manuals together with this MoP document to be able to complete the site installation as
per Nokia standards and customer requirements.
It’s mandatory that the installation team members are trained on the installation of Nokia hardware and other
network elements related to the scope of this project, the installation teams must hold all necessary
certificates required to complete the work onsite as per Nokia requirements, standard practice and country
regulations, certificates such as but not limited to; Nokia PTID, electrical works, work at hight, telecom cabling &
fibre works, …, etc.
Below is the Radio and System module hardware required for initial 664 sites with 2G+3G+4G
The power input for AirScale is -48V DC with the permitted range of -40.5V to -57V. The positive input is always at
0V. I_lugs and Thimbles would be used during installation.
• System Module (AirScale): 16mm2 separate DC cables -- MCB 32A / per one Arscale SM
• DC 10 mm2 between FPFH and RFMs (configurable outputs from FPFH – 40A per each RRH and max length
of 10m)
• MW ODUs with dedicated DC Cable (coaxial not PoE) powered directly from bottom rectifier
• NOTE: Rectifier new one- to be connected to AC Breaker 63A 4P MCB with 40kA SPD
- 10m of 10mm2 power cable can be used for the FPFH to RRH
- 10m of 10mm2 power cable can be used for the FPFH to RRH
- 38m of 16mm2 power cable can be used for the FPFH to RRH
- 10m of 10mm2 power cable can be used for the FPFH to RRH
- 50m of 16mm power cable can be used for the FPFH to RRH
If the Rect-FPFH lengths is <10m(Option1) and <20m(Option 2) the below will apply.
Labelling
Please add specification of grounding resistance to be checked before power-on of the equipment
Sites would be accessed after getting approval from respective owner of site.
CABLE CLAMPS:
4.2.1 Self-Assessment
Self-Assessment is work done check, which a member of the Subcon installation team will perform of their own
work as agreed in the contracted statement of Work.
Checklist
• TI Checklist
• HSE Checklist
• Site Integration Checklist
Photo proof
✓ (Physical or Tool e.g; NDPc)
✓ General Photo of site and Tower (5)
✓ Photo of Cable Trays (2)
✓ Photo of clamps on cable ladder (2)
✓ Photo of AirScale (2)
✓ Alarm Box (with/out cover) (2)
✓ PIX Krone (Ext Alarm) (1)
✓ Circuit Breaker (showing dc cable connected) (2)
✓ Tx backhaul cable towards TX INU and Airscale FCOB (2) – include the label
✓ AirScale FCOB (2)
✓ FCOB grounding cable – plinth and grounding point (2)
✓ RRH (2)
✓ RRH grounding cable – plinth and grounding point (3)
✓ FPFH (with/out cover) (2)
✓ FPFH grounding cable – plinth and grounding point (2)
✓ Screenshot of FPFH final settings should be added.
✓ Flyleads on all sectors (3)
✓ Antenna per sector showing Flylead connected (3)
✓ Coverage photo per sector (3)
✓ Electrical Tilt on all sectors (3)
✓ Mechanical tilt using the Tiltmeter on all sectors (3)
✓ Mechanical bracket on all sectors (3)
Note: Every photo should have date, time & location stamp. Total of 49 photos.
When to do SA
The Self-Assessment checklist will be completed by the installation team when on-site after completion of the
installation work.
Submission
• The checklist is uploaded during TalonView collaboration and NDP-D Site Forge
Guidelines
• Mandatory for all service suppliers for all sites. To be done when the installation job is finalized, right
before the team leaves the site.
The Site Quality Assessments are conducted on random basis according to the Site Quality Assessment Plan.
Every Service Supplier (SeS) working on every site must have their company Health and
Safety file with them. They must possess an updated Nokia HSE Passport ID as proof of compliance.
The following items must be defined in the SeS Health & Safety File
• Project Scope of Work
• Health and Safety Specifications
• Risk Matrix Methodology & Baseline Risk Assessment
• Appointments in accordance with Occupational Health and Safety Act
• Procedures in accordance with Occupational Health and Safety Act
• Safe Work Instructions
• Registers and Checklist of Tools and Equipment
• Health and Safety Plans
• Incident and Reporting in accordance with Occupational Health and Safety Act
As a general Health & Safety rule, Nokia have come up with regulations on the proper rigging and hoisting of
equipment (RF antenna, transmission links, RF modules......etc.) being done during network rollout. Strict
Compliance on these regulations must be observed always. Failure to do so will have corresponding sanctions.
Nokia laid out clear non-negotiable standard for working at height. Please ensure the following:
• Riggers who work at height need to be trained and carry copy of certification
• Be medically fit to climb.
• Use proper fall protection devices (full body harnesses, shock absorbing double lanyard, positioning belt,
fall arrestor to use while ascending or descending, rigger helmet, safety shoes, gloves and a pouch to carry
tools) and anchor at strong anchor points.
• Need supervision on ground.