Professional Documents
Culture Documents
Method Statement For Installation of Lighting Fixtures L18
Method Statement For Installation of Lighting Fixtures L18
Method Statement For Installation of Lighting Fixtures L18
PHASE III
Method Statement
Installation of Lighting Fixtures L18
List of Attachments
Ref No Title
1 Method Statement
2 Assembling Instructions
3 Detail Drawing for Lighting fixtures
4 Fixing Drawing
5 Shop Drawing
6 Inspection Test Plan ITP
7 Risk Assessment
Revision History
Rev Date Prepared By Checked By Description
00 24/March/2018 DSI JV First submission
This to advise the recipient of this document that the JV has approved this document for Implementation.
Approved By
PROJECT DIRECTOR –
Copy Right
All rights reserved. No part of this publication and referenced documents may be reproduced, stored in retrieval system, or transmitted, in
any form or by any means, electronic, mechanical, photocopying, recording or otherwise or divulged to any other party of use for any
purpose without the written permission of SACC/DSC JV Quality Management Representative.
Page 1 of 9
Table of Contents
1.0 Scope/Objectives
2.0 Purpose
3.0 Abbreviations
4.0 References
5.0 Responsibilities
a. Project Manager
b. Construction Manager
c. Discipline Manager
d. Safety Officer
e. Project Engineer
f. Site Engineer
6.0 Safety
7.0 Material’s Protection
8.0 Procedures
8.1: Material delivery, Handling and Storage
8.2: Equipment’s and Tools
8.3: Preparations
8.4: Installation of Lighting Fixtures
8.5: Inspection.
9.0 Attachments
9.1 ITP (Inspection & Test Plan)
9.2 Risk Assessment
1.0 SCOPE
The scope of this Method Statement is to define all activities and work
requirements necessary for the installation of lighting fixtures L18 in this project
and to ensure that the work / activities are in full compliance with specifications,
drawings and International Standards.
2.0 PURPOSE
The purpose of this Method Statement is to describe the Quality Control Procedure
to be followed during the installation of lighting fixture L18 in this project’s work
activities to specify the health and safety measures needed to control the risk
associated during installation.
Page 2 of 9
3.0 ABBREVIATIONS
MS : Method Statements
ITP : Inspection and Test Plan
RFI : Request for Inspection
NCR : Non-Conformance Report
DSI : Drake & Scull International
PM : Project Manager
CM : Construction Manager
PPE : Personal Protection Equipment’s
QA/QC : Quality Assurance / Quality Control
4.0 REFERENCES
5.0 RESPONSIBILITIES
Page 3 of 9
5.3 Discipline Manager :
The Discipline Manager will be responsible for the following
To ensure that the works are carried out according to the specification
and approved latest issue controlled shop drawings.
To ensure that all related quality procedures are implemented.
To give proper guidance to Project & Site Engineers regarding the
work with respect to codes and standards and as per the project
requirements and quality procedures.
To ensure that necessary testing has been carried out prior to next
phase of work.
Page 4 of 9
To provide the Project Engineer with daily progress reports and
discuss with him planned works for the next day.
To ensure that daily progress achieved is as planned and advise the
Project Engineer of any requirement for additional resources.
To ensure that all safety measures are taken care at site and all the
workers are properly trained for proper safety guidelines and
housekeeping activities in co-ordination with Safety Officer.
To ensure the good housekeeping for his workers on daily basis.
Always keep the working area clean and use proper tools.
6.0 SAFETY
The Safety Team will be responsible for the following
Prior to the commencement of any activities, the work force will
receive Tool Box Talk on the project Safety requirements.
Direct Supervisor will ensure that Personal Protection Equipment’s
are worn by site personnel at all times.
Training on scaffolding safe erection and usage will be provided
since application of this Method Statement will involve working on
the top of the scaffolding. Personnel working on the top of the
scaffolding must wear the safety harness at all times.
8.0 PROCEDURE
8.3 Preparation
a) Examine areas to receive the task for compliance with the requirements of
installation and ascertained that the area id free from any civil work.
b) Ensure that all related latest approved drawings / load schedule are available
at site for execution of the work.
c) Ensure that cable tray/ ladder are free from any sharp edges.
d) Ensure that all electricians and helpers are aware of the correct materials
handling and installation procedures to ensure the best quality of
workmanship.
e) Ensure that prior to installation of Light Fittings, all building surfaces to
which are fixed are completed and are in a suitably clean and dry condition.
Any unsatisfactory conditions are to be reported and installation shall not
proceed until corrective action has been taken.
1) Pre-installation Preparation
Page 6 of 9
1.2 INSTALLATION OF POWER SUPPLY
Page 7 of 9
b) The detailed plan and schedule for distribution of the goods from the
Warehouse to the installation area will be prepared prior to the installation
following the site conditions.
3. Installation Method
Page 8 of 9
The Lighting fixture is produced in segments and transported to construction
site disassembled, semi-assembled or fully assembled. The segments are
designed in terms of size and weight to ensure easy handling and installation by
given number of technicians. When installation takes place in higher heights, it
is recommended to use appropriate tools such a rope and pulley, or assembly
ramp (lifting platform), if available on-site. Responsible persons are trained to
handle these tools and materials as pre the EU regulations and standards.
Page 9 of 9
PRECIOSA – LUSTRY, a.s.
KAMENICKÝ ŠENOV
ČESKÁ REPUBLIKA
Assembling Instructions
Specification: 050 998 024 33 99 28 67 04 30
67 6998 024 33 99 04 28 30
Dear customer,
Thank you for your confidence expressed by buying the light fitting from our offer. This light fitting is
destined for the illumination of usual home accommodations. Our exceptional technology having almost
three hundred years tradition of chandelier production in the North Bohemian region is the best guarantee of
the highest quality of this light fitting.
The electrical installation, the connection of the light fitting to the electrical network and its
suspending has to be made by the authorised firm only observing all the valid standards and safety
regulations.
Don’t provide the light fitting with the light sources having the higher power input than prescribed.
Before starting the assembly of light fitting you have to make sure whether the supply of electric
current from the ceiling is not under the voltage. These conditions have to be observed during all
the time of assembly. We advise to suspend the ceiling light fitting adequately high in order to avoid
in advance the possibility of injury e.g. strike the head against it.
The repeated connection under the voltage can be made only when the light fitting is provided with
all the light sources.
Company Preciosa - Lustry, a.s. has no responsibility for the unprofessional connection !
• We recommend to use the fine gloves of cloth for assembling of light fitting in order to avoid the
loss of its gloss.
PRECIOSA – LUSTRY, a.s.
KAMENICKÝ ŠENOV
ČESKÁ REPUBLIKA
Make sure before starting the assembly of light fitting that the power supply form ceiling is not under
1. voltage. Observe it during all the time of assembly.
Unpack the single parts of the light fitting from the cartons and boxes.
Install the ceiling fixings according to the drawing delivered by the light fitting manufacturer. Verify in
an adequate manner that the load-bearing capacity of individual fixings reaches the minimum value
stipulated by the light fitting manufacturer. Prepare the supply cable according to the drawing
delivered by the light fitting manufacturer. The cross-section of the cable used and its insulation shall
correspond with the power demand of the light fitting and safety requirements.
If the light fitting is equipped with the connection for the dimming signal (1-10 V, DALI, etc.), prepare a
corresponding cable according to the drawing.
Install the ceiling frame on the prepared ceiling fixings.
Connect LED drivers with the input from the ceiling and with the conductors from LED modules under
the ceiling frame.
Install a load-bearing plate with a sheet metal cover.
Fix the little frames of spotlights into the openings in the sheet metal cover and the load-bearing plate
and fasten the LED modules into them.
2. Insert stranded wires, on which hang glass rods, into the cable holders, screwed into the load-bearing
plate.
Install the stranded wires gradually from the centre outwards. The individual stranded wires are
numbered. Maintain the correct placement of stranded wires.
The placement of these suspensions corresponds with the attached sketch.
PRECIOSA – LUSTRY, a.s.
KAMENICKÝ ŠENOV
ČESKÁ REPUBLIKA
The maintenance of the metallic parts of the light fitting – the holders, the cords, the coupling
parts:
Clean the metallic parts of the light fitting directly without their removing from the light fitting.
Use the dry and soft duster for cleaning the metallic parts.
The metallic parts may be also cleaned by the moister duster, use the lukewarm detergent bath.
Don’t use in any case the solvents or technical benzine for cleaning the metallic parts.
When cleaning the different parts than stainless ones avoid using of the alcoholic agents that could make the
change of the shade of varnish applied on the part.
For cleaning the surfaces of stainless steel use the agents defined directly for it. The alcohol and the technical
benzine may be used.
When the stainless cords are released from the cord holders that are screwed into the upper and the bottom
circular frame then insert it again into the holder in order to be stretched.
In the case that you want to remove the cord from the cord holder than press the piston of the cord holder by
means of the screwdriver toward the circular frame and in this way you release the cord attached in the cord
holder.
The producer retains the right to make the small variances of making the light fitting without notice.
Producer: Seller:
PRECIOSA - LUSTRY, a.s.
Nový Svět 915
471 14 Kamenický Šenov
Česká Republika
3.1 Visual Inspection of Lighting Fixture Installation Spec.Section 16500 Visual Check Confirm the installation is as per the approved shop drawing WIR I W W
Visual Inspection of wall mounted & Floor
3.2 Spec.Section 16500 Visual Check Confirm the installation is as per the approved shop drawing WIR I W W
mounted receptical installation
H=Hold Point / W=Witness Point / S=Survellance Point /T=Test Point /DR= Document Review / DS= Document Submittal / DA = Document Approval/I=Visual Inspection
Page 1
HAZARD IDENTIFICATION AND RISK ASSESSMENT
SHEET FOR
LIGHTING FIXTUREL L18
PROJECT : JODP
Risk Assessment Risk Assessment
Item Process Hazard (No Controls) Controls (With Controls)
P S R P S R
1.cuts 1. Use PPE gears at all times, wear gloves and safety goggles
2.abrasion 2. Supervisor to inspect hand tools prior to commence work.
3.broken bones 3. Proper housekeeping should be done after finish the activity
4.Blunt cutting 4. Damaged tools to be disposed of.
Use of 5. Tools to be kept clean and clear of grease
tools
hand or 6. Check the condition for all power and electrical tools before
5. Tools used for
power start the job
1 the wrong 4 3 A 2 2 C
tools and
purpose. 7. Hammerheads to be secure and undamaged.
sharp
6. Inappropriate 8. If work carried out near highly flammable materials or
edge tools
use of power explosive dusts, spark free tools to be used.
tools. 9. If the work is on near to electrical apparatus, properly
7. Screwdrivers insulated and nonconductive tools to be used.
with split handles.
1.Slip
1. Use proper PPE at all times during this activity.
Wiring of 2. skin cuts
2 3 2 A 2. Close Supervision by the Foremen 2 2 D
Cables causing from fast
3.Use cotton hand gloves when working with cable pulling
cable pulling
1. Personal Protective Equipment’s such as Full Body Harness,
Hand Gloves Safety goggles etc will be used as applicable.
2. Proper working Platform will be prepared under the
Working on 1 Fracture. supervision of Scaffold Foreman/Inspector
3 4 3 A 2 2 D
scaffolding 2.falling hazard 3. Platforms will be inspected and Scaff Tag posted
4. Access ladder will be in place
5. Overloading of Platform will not be permitted
6. Walk way will be maintained at all times
Page 1 of 5
HAZARD IDENTIFICATION AND RISK ASSESSMENT
SHEET FOR
LIGHTING FIXTUREL L18
PROJECT : JODP
Risk Assessment Risk Assessment
Item Process Hazard (No Controls) Controls (With Controls)
P S R P S R
7. Housekeeping will be done on daily basis.
Page 2 of 5
HAZARD IDENTIFICATION AND RISK ASSESSMENT
SHEET FOR
LIGHTING FIXTUREL L18
PROJECT : JODP
Risk Assessment Risk Assessment
Item Process Hazard (No Controls) Controls (With Controls)
P S R P S R
Manipulati
ng with
our
1. The transport of our Chandeliers its
chandelier 1.Injury resulting
components and parts is managed only
s its in manipulating
by the trained responsible person from
componen with heavy
PRECIOSA LIGHTING
6 ts objects in heights, 4 3 A 3 2 C
2. The bellow area is secured so that
and tools possible fall down
others are not endangered
on and work
scaffolding related injuries
,
lifting
platform
Page 3 of 5
HAZARD IDENTIFICATION AND RISK ASSESSMENT
SHEET FOR
LIGHTING FIXTUREL L18
PROJECT : JODP
Risk Assessment Risk Assessment
Item Process Hazard (No Controls) Controls (With Controls)
P S R P S R
Hanging
our
chandelier 1.Injury resulting
s or in manipulating 1. We are using sufficient number of
its with heavy manpower as well as lifting equipment
7 componen objects in heights, 3 2 B
and safety wires 3 2 C
ts to fixing possible fall down 2. The chandelier, frames or the
points and work components are secured while our
under the related injuries technicians fix it and secure it with
fault nuts, suspension tubes or wires.
ceiling
When completing this Performa you must take due consideration of local site conditions, including adjacent operations and premises.
_____________________________________________________________________
Probability (P) X Severity (S) = Risk Risk Level ® P/S Conclusions
1 = Unlikely 1 = Negligible S1 S2 S3 S4 A = Hazard MUST be avoided (or level of risk reduced significantly & reliably by controls)
2 = Low 2 = Minor Injury P1 X X D C B = Hazard SHOULD be avoided (or level of risk reduced significantly & reliably by controls)
3 = Medium 3 = Severe Injury P2 X D C B C = Risk to be controlled as far as reasonably practicable
4 = High 4 = Fatal P3 D C B A D = Risk is controlled as far as reasonably practicable
P4 D B A A X = Normal PPE to be worn as dictated by ACC policy
Page 4 of 5
HAZARD IDENTIFICATION AND RISK ASSESSMENT
SHEET FOR
LIGHTING FIXTUREL L18
PROJECT : JODP
Risk Assessment Risk Assessment
Item Process Hazard (No Controls) Controls (With Controls)
P S R P S R
Page 5 of 5