Professional Documents
Culture Documents
Tanay River (Flood Control Id No. F040074LZ) - Program
Tanay River (Flood Control Id No. F040074LZ) - Program
PATRICK B. BALOT ANGIELYN C. LAPITAN ARNOLD GARRY A. PANGANIBAN RAMONITO S.M. PAZ JULIANA D. VERGARA
Engineer II Engineer II Engineer II Engineer III District Engineer
Officer-In-Charge
Office of the Assistant District Engineer
DPWH Rizal 2nd District Engineering Office
#16 Westbank Road, Manggahan Floodway, Brgy. Rosario, Pasig City
Repair and Maintenance of Flood Control and Drainage Structure Along Tanay River, FORM INFRA-03-2016
Embankment (From Roadway/Structure AS SUBMITTED 166.24 cu.m. 133,497.79 25% 33,374.45 8,343.61 41,718.06 175,215.84 1,053.99
Item 1704(1)a
Excavation) AS EVALUATED
AS SUBMITTED 197.16 cu.m. 172,501.89 25% 43,125.47 10,781.37 53,906.85 226,408.73 1,148.36
Item 1704(1)b Embankment (From Burrow)
AS EVALUATED
AS SUBMITTED 379,883.17 94,970.79 23,742.70 118,713.49 498,596.67
TOTAL OF PART I-A
AS EVALUATED
PART I-B BANK AND SLOPE PROTECTION WORKS
AS SUBMITTED 424.88 cu.m. 1,832,109.11 25% 458,027.28 114,506.82 572,534.10 2,404,643.19 5,659.58
Item 1711(1) Stone Masonry
AS EVALUATED
AS SUBMITTED 1,832,109.11 458,027.28 114,506.82 572,534.10 2,404,643.19
TOTAL OF PART I-B
AS EVALUATED
AS SUBMITTED 2,771,786.34 657,149.44 171,446.79 828,596.23 3,600,382.56
GRAND TOTAL
AS EVALUATED
say 3,000,000.00
Project : Repair and Maintenance of Flood Control and Drainage Structure Along Tanay River, Net Length : ( a ) Road N/A
(Flood Control ID No. F040074LZ) Tanay, Rizal ( b ) Bridge N/A
Project ID : N/A ( c ) Others Flood Control and Drainage Structure 33.00 L.M
Location : Tanay, Rizal Target Start Date : N/A
Station Limits : N.A Total Project Duration : 102 Calendar Days
Appropriation : P 3,600,000.00 No. of Pre-determined
: 23 Calendar Days
Source of Fund : N/A Unworkable Days
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part A : Facilities for the Engineer 1.84% 51,095.76
Part B : Other General Requirements 8.20% 227,310.47
Part C Earthwork 10.15% 281,387.83
Part J : Flood Control and Drainage
PLS. SEE FORM POW-2015-01C-00
Part I-A : Earthwork 13.71% 379,883.17
Part I-B : Bank and Slope Protection Works 66.10% 1,832,109.11
100.00% 2,771,786.34
JONAMENE G. JUAYONG ALVIN JOHN DC. FLORES CATHERINE A. TAMAYO RAMONITO SM. PAZ JULIANA D. VERGARA
Engineer II Engineer II Chief, Maintenance Section Engineer III District Engineer
Officer-In-Charge
Office of the Assistant District Engineer
FORM POW-2015-01A-00
Repair and Maintenance of Flood Control and Drainage Structure Along Tanay River,
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
***Parapet
Width 0.5 m
Height 0.6 m
Length 41 m
Area 0.30 sq.m
Volume 12.30 cu.m
Stone Masonry
Top Width 0.6 m
Heigth 5.10 m
Bottom Width 2.90 m
Length 9.00 (Actual)
Area 8.93 sq.m
Volume 80.33 cu.m
Volume Cut
Volume to Fill
Hence; Volume to fill > Volume of Cut
Unsuitable Excavation
Volume 1.50m x 3.0m x 5.0m
Volume = cu.m
DETAILED ESTIMATE
PART A - FACILITIES FOR THE ENGINEER
Item A.1.1(8) - Provision of Field Office for the Engineer ( Rental Basis)
Quantity = 3.41 mos
PART C - EARTHWORK
Item 101(1) - Removal of Structures and Obstruction
Quantity = 1.00 l.s
Approved by:
JULIANA D. VERGARA
District Engineer
Contract ID Number :
Contract Name : Repair and Maintenance of Flood Control and Drainage Structure along
Tanay River (Flood Control ID No. F040074LZ) Tanay, Rizal
Contract Location : Tanay, Rizal
BACK-UP COMPUTATION
SECTION 2 -
For Flood Control Structure:
Length = 13.00 m.
Top Width = 0.60 m.
Bottom Width = 3.70 m.
Height = 6.40 m.
Volume (FCS) = (length) x (area of flood control structure)
= 13.00 m x [ 0.50 x (0.60 m + 3.70 m) x 6.40 m]
Volume (FCS) = 178.88 cu.m.
Volume 2 = 178.88 cu.m.
Total Volume = 424.88 cu.m.
Prepared by:
JONAMENE G. JUAYONG
Engineer II
Contract ID Number : N/A
Contract Name : Repair and Maintenance of Flood Control and Drainage Structure along
Tanay River (Flood Control ID No. F040074LZ) Tanay, Rizal
Contract Location : Tanay, Rizal
Calendar Days = (est. amount) x (ref. duration per km of road) Mobilization / Demobilization
+
Duration
given ref. amount
= (P 3,600,000.00) x (34 days)
+ 10days
P 1,769,002.74
Calendar Days = 79 C.D.
Prepared by:
JONAMENE G. JUAYONG
Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)
Project : : Repair and Maintenance of Flood Control and Drainage Structure along
Location : Tanay, Rizal
Item No. : B.7(1)
Description : Occupational Safety and Health Program
Source to Site Unit Cost/ Hauling Cost/ Unit Price Unit Cost /
(km) x cu.m./km cu.m. (Quarry) cu.m.
Common Borrow 36.00 x 10.00 360.00 150.00 510.00
Cost of Fine Aggregates (Sand) 36.00 x 10.00 360.00 475.00 835.00
Cost of Coarse Aggregates (Gravel, G3/4) 36.00 x 10.00 360.00 850.00 1,210.00
Cost of Natural Gravel (Gravel Fill) 36.00 x 10.00 360.00 630.00 990.00
Cost of Class A Boulders (Stones 15-25 kg) 36.00 x 10.00 360.00 700.00 1,060.00
Note: P20/cu.m./km. as per supplier / 15km free hauling (Crownmix)
Prepared by:
JONAMENE G. JUAYONG
Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)
B.1
Minor Tools (10% Labor) 29.25
Item No. / Description : A.1.1(8) - Provision of Field Office for the Engineer (Rental Basis)
Unit of Measurement : month
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : -
Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)
Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS
For Removal
a. Construction Foreman 1 0.63 103.15 64.98
b. Labor 2 0.63 57.39 72.31
Removal
a. Dumptruck (12 yd3) 3 0.63 1,420.00 2,683.80
b. Backhoe (0.80 cu.m.) 1 0.63 1,537.00 968.31
Prepared by:
Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)
Labor
For Removal
a. Construction Foreman 1 0.63 103.15 64.98
b. Labor 2 0.63 57.39 72.31
Equipment
Removal
Materials
F.1
Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)
Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)
B.1
Minor Tools (10% Labor) 33.27
Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)
Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)
B.1
For Spreading and Compaction:
a. Walk Behind Roller 1 1.00 359.78 359.78
b. Water Truck (16000 L) 1 0.25 4,738.38 1,184.60
c. Backhoe (0.80 cu.m.) 1 1.00 2,788.49 2,788.49
Minor Tools (10% Labor) 53.92
F.1
Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 803.04
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
Overhead, Contingencies & Miscellaneous (OCM)
H.1 15% of G.1 120.46
- As Submitted
Overhead, Contingencies & Miscellaneous (OCM)
H.2 of G.2
- As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 80.30
I.2 Contractor's Profit (CP) - As Evaluated of G.2
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 50.19
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,053.99
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2)
Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)
Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)
Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)
Handling of Materials
a. Laborer 8 1.00 57.39 459.12