Repair Rubble Concrete of FCD Tanay Revetment 30 FInal

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 45

DPWH Rizal 2nd District Engineering Office

#16 Westbank Road, Manggahan Floodway, Brgy. Rosario, Pasig City


FORM INFRA-03-2016
Repair/Maintenance of Tanay River Retvement 12 Brgy. Tandang Kutyo Tanay,Rizal

SUMMARY OF APPROVED BUDGET FOR THE CONTRACT


Contract Duration: 66 Calendar Days
ESTIMATED TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION VAT TOTAL COST
DIRECT COST % VALUE COST
AS EVALUATED
PART I FACILITIES FOR THE ENGINEER
AS SUBMITTED 35,691.50 10% 3,569.15 1,963.03 5,532.18 41,223.69
AS EVALUATED
PART II OTHER GENERAL REQUIREMENTS
AS SUBMITTED 324,748.84 25% 39,709.24 18,222.90 57,932.16 382,680.98
CIVIL,MECHANICAL,ELECTRICAL AND SANITARY /PLUMBING AS EVALUATED
PART III
WORKS AS SUBMITTED
AS EVALUATED
PART A EARTHWORK
AS SUBMITTED 20,673.70 25% 5,168.43 1,292.11 6,460.54 27,134.24
AS EVALUATED
PART C FINISHING AND OTHER CIVIL WORKS
AS SUBMITTED 52,038.01 25% 13,009.50 3,252.38 16,261.88 68,299.89
AS EVALUATED
PART J FLOOD CONTROL AND DRAINAGE
AS SUBMITTED
AS EVALUATED
PART I-A EARTHWORK
AS SUBMITTED 285,397.95 25% 71,349.49 17,837.37 89,186.86 374,584.80
AS EVALUATED
PART I-B BANK AND SLOPE PROTECTION WORKS
AS SUBMITTED 1,984,979.46 25% 496,244.86 124,061.22 620,306.08 2,605,285.54
AS EVALUATED
TOTAL
AS SUBMITTED 2,703,529.46 629,050.67 166,629.03 795,679.69 3,499,209.13
say 2,000,000.00

Preparation and Submission: Evaluation: Approval:

Prepared by: Checked/Submitted by: Evaluated by: Recommending Approval: Approved:

JENI LOU B. ORACION PATRICK B. BALOT ROCHELLE V. ARMENDARES MANOLITO S. FABIAN WILFREDO L. RACELIS
Engineer II Engineer II Engineer II Officer-In-Charge District Engineer
Office of the Assistant District Engineer
DPWH Rizal 2nd District Engineering Office
#16 Westbank Road, Manggahan Floodway, Brgy. Rosario, Pasig City
FORM INFRA-03-2016
Repair/Maintenance of Tanay River Retvement 12 Brgy. Tandang Kutyo Tanay,Rizal

APPROVED BUDGET FOR THE CONTRACT


Contract Duration: 66 Calendar Days

ESTIMATED TOTAL MARK-UP TOTAL INDIRECT


ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
DIRECT COST COST
% VALUE
PART I FACILITIES FOR THE ENGINEER
Provision of Field office for the Engineer AS SUBMITTED 2.86 mos. 35,691.50 10% 3,569.15 1,963.03 5,532.18 41,223.69 14,437.50
Item A.1.1(8)
(Rental Basis) AS EVALUATED
AS SUBMITTED 35,691.50 3,569.15 1,963.03 5,532.18 41,223.69
TOTAL OF PART A
AS EVALUATED
PART II OTHER GENERAL REQUIREMENTS
AS SUBMITTED 2.00 each 7,538.80 25% 1,884.70 471.18 2,355.88 9,894.68 4,947.34
Item B.5 Project Billboard / Signboard
AS EVALUATED
AS SUBMITTED 1.00 l.s 237,468.30 10% 23,746.83 13,060.76 36,807.58 274,275.87 274,275.87
Item B.7(2) Occupational Safety and Health Program
AS EVALUATED
AS SUBMITTED 1.00 l.s 23,430.89 0% - 1,171.54 1,171.54 24,602.44 24,602.44
Item B.9 Mobilization/ Demobilization
AS EVALUATED
AS SUBMITTED 1.00 l.s 25,664.14 25% 6,416.03 1,604.01 8,020.04 33,684.18 33,684.18
Item B.17 Temporary Diversion of Waterway
AS EVALUATED
AS SUBMITTED 324,748.84 39,709.24 18,222.90 57,932.16 382,680.98
TOTAL OF PART B
AS EVALUATED
PART III CIVIL,MECHANICAL,ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORK
AS SUBMITTED 1.00 l.s 20,673.70 25% 5,168.43 1,292.11 6,460.54 27,134.24 27,134.24
Item 101(1) Removal of Structures and Obstruction
AS EVALUATED
AS SUBMITTED 20,673.70 5,168.43 1,292.11 6,460.54 27,134.24
TOTAL OF PART A
AS EVALUATED

PART C FINISHING AND OTHER CIVIL WORKS

AS SUBMITTED 263.22 l.s 52,038.01 25% 13,009.50 3,252.38 16,261.88 68,299.89 259.48
Item 1027(1) Cement Plaster Finish
AS EVALUATED
AS SUBMITTED 52,038.01 13,009.50 3,252.38 16,261.88 68,299.89
TOTAL OF PART C
AS EVALUATED
PART J FLOOD CONTROL AND DRAINAGE
PART I-A EARTHWORK
AS SUBMITTED 175.00 sq.m 1,847.47 25% 461.87 115.47 577.33 2,424.79 13.86
Item 1700(1) Clearing and Grubbing
AS EVALUATED
Embankment (From Roadway/Structure AS SUBMITTED 206.45 cu.m. 129,969.40 25% 32,492.35 8,123.09 40,615.44 170,584.84 826.29
Item 1704(1)a
Excavation) AS EVALUATED
AS SUBMITTED 168.40 cu.m. 68,409.59 25% 17,102.40 4,275.60 21,378.00 89,787.59 533.17
Item 1704(1)b Embankment (From Burrow)
AS EVALUATED
AS SUBMITTED 285,397.95 71,349.49 17,837.37 89,186.86 374,584.80
TOTAL OF PART I-A
TOTAL OF PART I-A
AS EVALUATED
PART I-B BANK AND SLOPE PROTECTION WORKS
AS SUBMITTED 423.96 cu.m. 1,984,979.46 25% 496,244.86 124,061.22 620,306.08 2,605,285.54 5,890.12
Item 1711(1) Stone Masonry
AS EVALUATED
AS SUBMITTED 1,984,979.46 496,244.86 124,061.22 620,306.08 2,605,285.54
TOTAL OF PART I-B
AS EVALUATED
AS SUBMITTED 2,703,529.46 629,050.67 166,629.03 795,679.69 3,499,209.13
GRAND TOTAL
AS EVALUATED
say 2,000,000.00

Preparation and Submission: Evaluation:


Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

JENI LOU B. ORACION PATRICK B. BALOT ROCHELLE V. ARMENDARES


Engineer II Engineer II Engineer II
DPWH Rizal II District Engineering Office
#16 Westbank Road, Manggahan Floodway, Brgy. Rosario, Pasig City
FORM POW-2015-01-00
DATE: May 22,2023
PROGRAM OF WORK / BUDGET COST

Project : Repair/Maintenance of Tanay River Retvement 12 Brgy. Tandang Kutyo Tanay,Rizal Net Length : ( a ) Road N/A
( b ) Bridge N/A
Project ID : N/A ( c ) Others Flood Control and Drainage Structure 20.50 L.M
Location : Tanay, Rizal Target Start Date : Upon Release of NTP
Station Limits : N.A Total Project Duration : 66 Calendar Days
Appropriation : P 2,000,000.00 No. of Pre-determined
: 30 Calendar Days
Source of Fund : FY 2023 RA 11936 Regular 2023 CURRENT Unworkable Days

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I : Facilities for the Engineer 1.32% 35,691.50
Part II : Other General Requirements 12.01% 324,748.84
Civil,Mechanical Electrical, Sanitary/Plumbing
Part III :
Works
Part A : Earthwork 0.76% 20,673.70
Part C : Cement Plaster Finish 1.92% 52,038.01
Part J : Flood Control and Drainage
PLS. SEE FORM POW-2015-01C-00
Part I-A : Earthwork 10.56% 285,397.95
Part I-B : Bank and Slope Protection Works 73.42% 1,984,979.46
100.00% 2,703,529.46

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 600,174.51 A. Total Direct Cost 2,703,529.46
2. Materials 1,617,093.56 B. OCM and Profit 629,050.67
3. Rental Equipment 486,261.38 C. Value Added Tax 166,629.03
4. Mobilization/ Demobilization D. Total Construction Cost 3,499,209.13
SEE ATTACHED 5. OCM and Profit 629,050.67 E. Eng'g & Administrative Overhead, %
6. Value Added Tax 166,629.03 F. RROW Acquisition
7. EAO, 3.5% G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10. TOTAL ESTIMATED COST 3,499,209.15 H. TOTAL ESTIMATED COST 3,499,209.13
say 3,000,000.00 say 3,000,000.00

Preparation and Submission: Approval:

Prepared by: Checked by: Submitted by: Recommending Approval: Approved:

JONAMENE G. JUAYONG RIZA S. BENGALA CATHERINE A. TAMAYO MANOLITO S. FABIAN WILFREDO L. RACELIS
Engineer II Engineer II Chief, Maintenance Section Officer-In-Charge District Engineer
Office of the Asst. District Engineer
FORM POW-2015-01A-00
Repair/Maintenance of Tanay River Retvement 12 Brgy. Tandang Kutyo Tanay,Rizal

ITEMIZED BREAKDOWN OF WORKS

DIRECT COST TOTAL UNIT COST


QTY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
PART I FACILITIES FOR THE ENGINEER
Item A.1.1(8) Provision of Field office for the Engineer (Rental Basis) 2.86 mos. 35,691.50 12,500.00 14,437.50 Err:509
TOTAL OF PART I 35,691.50 Err:509
PART II OTHER GENERAL REQUIREMENTS
Item B.5 Project Billboard / Signboard 2.00 each 7,538.80 3,769.40 4,947.34 Err:509
Item B.7(2) Occupational Safety and Health Program 1.00 l.s. 237,468.30 237,468.30 274,275.87 Err:509
Item B.9 Mobilization / Demobilization 1.00 l.s. 23,430.89 23,430.89 24,602.44 Err:509
Item B.15(2) Detour/ Access Road 60.00 l.m. 40,223.82 670.40 670.40 Err:509
Item B.17 Temporary Diversion of Waterway 1.00 l.s. 25,664.14 25,664.14 33,684.18 Err:509
TOTAL OF PART II 334,325.94 Err:509
PART III CIVIL,MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORK
Item 101(1) Removal of Structures and Obstruction 1.00 l.s 20,673.70 20,673.70 27,134.24 Err:509
TOTAL OF PART A 20,673.70 Err:509
PART C FINISHING AND OTHER CIVIL WORK
Item 1027(1) Cement Plaster Finish 263.22 sq.m. 52,038.01 197.70 259.48 Err:509
TOTAL OF PART C 52,038.01 Err:509
PART J FLOOD CONTROL AND DRAINAGE
PART I-A EARTHWORK
Item 1700(1) Clearing and Grubbing 175.00 sq.m. 1,847.47 10.56 13.86 Err:509
Item 1701(1) Unsuitable Excavation 169.95 cu.m. 85,171.49 501.16 657.77 Err:509
Item 1704(1)a Embankment (From Roadway/Structure Excavation) 206.45 cu.m. 129,969.40 629.55 826.29 Err:509
Item 1704(1)b Embankment (From Borrow) #REF! cu.m. 68,409.59 #REF! 533.17 Err:509
TOTAL OF PART I-A 285,397.95 Err:509
PART I-B BANK AND SLOPE PROTECTION WORKS
Item 1711(1) Stone Masonry #REF! cu.m. 1,984,979.46 #REF! 5,890.12 Err:509
Item 1713(1) Rubble Concrete Err:509 cu.m. Err:509 Err:509 5,910.97 Err:509
TOTAL OF PART I-B Err:509 Err:509

GRAND TOTAL Err:509 Err:509


FORM POW-2015-01A-00

Repair/Maintenance of Tanay River Retvement 12 Brgy. Tandang Kutyo Tanay,Rizal

MINIMUM EQUIPMENT REQUIREMENT


Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Backhoe 0.30 cu.m 1.00
2 One Bagger Mixer 1.00
3 Water Truck 16,000 L 1.00
4 Water Pump 1.00
5
6
7
8
9
10
11
12
TOTAL 4.00
Rubble Concrete
***Slope Protection Details
Top Width 0.5 m
Height 4.80 m
Bottom Width 2.75 m
Length 41.00
Area 7.80 sq.m
Volume 319.80 cu.m

***Parapet
Width 0.5 m
Height 0.6 m
Length 41 m
Area 0.30 sq.m
Volume 12.30 cu.m

Total Volume 332.10 cu.m

Stone Masonry
Top Width 0.6 m
Heigth 5.10 m
Bottom Width 2.90 m
Length 9.00 (Actual)
Area 8.93 sq.m
Volume 80.33 cu.m

Clearing and Grubbing


***Rubble Concrete and Stone Masonry
Area (40.0m x 2.0m)
Area 129.15 cu.m

Embankment from Borrow (Volume to Fill)


Volume (40.0m x 2.0m x 1.8m)
Volume 291.10 cu.m

Removal of Structure and Obstruction

Volume (1/2 x (0.60m+2.60m) x 10m x 4.50m


Volume 72.00 cu.m

Embankment (From Roadway/Structure Excavation)


Volume Cut (1.50m x 2.75m x 41.0m)
Volume Cut 169.125 sq.m
Volume to Fill 144.0cu.m x 1.25
Volume to Fill 363.88 cu.m
Patrick
Hence; Volume to fill > Volume of Cut
175cu.m > 144.375cu.m

Embankment from Roadway = Volume of Cut / 1.25


Embankment from Roadway = 135.30 Volume to be use

Embankment from Borrow = Volume to fill - Vcut/1.25


Embankment from Borrow = 155.80 cu.m

Volume Cut
Volume to Fill
Hence; Volume to fill > Volume of Cut

Embankment (from roadway) = 135.30 cu.m


Embranment (From Borrow) = 228.58 cu.m

FOR ACCESS ROAD OF EQUIPMENT (RESTORATION)

TOP WIDTH 0.6


HEIGHT 3.8
BOTTOM WIDTH 2.2 2.2
LENGTH 3
VOLUME 15.96 cu.m

Removal of Structure and Obstruction


TOP WIDTH 0.6
HEIGHT 3.8
BOTTOM WIDTH 2.166 2.2
LENGTH 3
VOLUME 15.96 cu.m

Unsuitable Excavation
Volume 1.50m x 3.0m x 5.0m
Volume = cu.m

Embankment from Borrow


Volume cu.m
FORM POW-2015-01C-00
Repair/Maintenance of Tanay River Retvement 12 Brgy. Tandang Kutyo Tanay,Rizal

DIRECT COST TOTAL MARK-UP


ITEM NO. DESCRIPTION QTY. UNIT 5% VAT TOTAL COST
LABOR EQUIPMENT MATERIAL TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
Provision of Field Office for the Engineer AS EVALUATED
Item A.1.1(8) mos.
(Rental Basis) AS SUBMITTED 2.86 - - 35,691.50 35,691.50 10% 3,569.15 1,963.03 41,223.69
AS EVALUATED
TOTAL OF PART I
AS SUBMITTED - - 35,691.50 35,691.50 3,569.15 1,963.03 41,223.69
PART II OTHER GENERAL REQUIREMENTS
AS EVALUATED
Item B.5 Project Billboard / Signboard each
AS SUBMITTED 2.00 939.82 93.98 6,505.00 7,538.80 25% 1,884.70 471.18 9,894.68
Occupational Safety and AS EVALUATED
Item B.7(2) l.s
Health Program AS SUBMITTED 1.00 185,675.76 5,276.62 46,515.91 237,468.30 10% 23,746.83 13,060.76 274,275.87
Mobilization / AS EVALUATED
Item B.9 l.s
Demobilization AS SUBMITTED 1.00 - 23,430.89 - 23,430.89 0% - 1,171.54 24,602.44
AS EVALUATED
Item B.15(2) Detour/Access Road l.m.
AS SUBMITTED 60.00 771.93 29,874.79 - 30,646.72 7,661.68 1,915.42 40,223.82
AS EVALUATED
Item B.17 Temporary Diversion of Waterway l.s
AS SUBMITTED 1.00 1,048.64 3,572.50 21,043.00 25,664.14 25% 6,416.03 1,604.01 33,684.18
AS EVALUATED
TOTAL OF PART II
AS SUBMITTED 188,436.16 62,248.78 74,063.91 324,748.84 39,709.24 18,222.90 382,680.98
PART III CIVIL,MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORK
AS EVALUATED
Item 101(1) Removal of Structures and Obstruction
AS SUBMITTED 1.00 l.s 914.76 19,758.94 - 20,673.70 25% 5,168.43 1,292.11 27,134.24
AS EVALUATED
TOTAL OF PART A
AS SUBMITTED 914.76 19,758.94 - 20,673.70 5,168.43 1,292.11 27,134.24
PART C FINISHING AND OTHER CIVIL WORKS
AS EVALUATED
Item 1027 (1) Cement Plaster Finish sq.m.
AS SUBMITTED 263.22 20,537.81 2,053.78 29,446.42 52,038.01 25% 13,009.50 3,252.38 68,299.89
AS EVALUATED
TOTAL OF PART C
AS SUBMITTED 20,537.81 2,053.78 29,446.42 52,038.01 13,009.50 3,252.38 68,299.89
PART J FLOOD CONTROL AND DRAINAGE
PART I-A EARTHWORK
AS EVALUATED
Item 1700(1) Clearing and Grubbing sq.m.
AS SUBMITTED 175.00 1,679.51 167.95 - 1,847.47 25% 461.87 115.47 2,424.79
AS EVALUATED
Item 1700(1) Unsuitable Excavation cu.m.
AS SUBMITTED 169.95 2,339.54 82,831.94 - 85,171.49 25% 21,292.87 5,323.22 111,787.58
Embankment (From Roadway/Structure AS EVALUATED
Item 1704(1)a cu.m.
Excavation) AS SUBMITTED 206.45 8,562.56 121,406.84 - 129,969.40 25% 32,492.35 8,123.09 170,584.84
AS EVALUATED
Item 1704(1)b Embankment ( From Borrow) cu.m.
AS SUBMITTED 168.40 4,309.85 32,524.37 31,575.38 68,409.59 25% 17,102.40 4,275.60 89,787.59
AS EVALUATED
TOTAL OF PART I-A
AS SUBMITTED 16,891.46 236,931.11 31,575.38 285,397.95 71,349.49 17,837.37 374,584.80
PART I-B STONE MASONRY
AS EVALUATED
Item 1711(1) Stone Masonry cu.m.
AS SUBMITTED 423.96 373,394.34 165,268.77 1,446,316.36 1,984,979.46 25% 496,244.86 124,061.22 2,605,285.54
AS EVALUATED
TOTAL OF PART I-B
AS SUBMITTED 373,394.34 165,268.77 1,446,316.36 1,984,979.46 496,244.86 124,061.22 2,605,285.54
AS EVALUATED
GRAND TOTAL
AS SUBMITTED 600,174.51 486,261.38 1,617,093.56 2,703,529.46 629,050.67 166,629.03 3,499,209.13
SAY 3,500,000.00
Contract ID Number : N/A
Contract Name : Repair and Maintenance of Flood Control and Drainage Structure along
Tanay River (Flood Control ID No. F040074LZ) Tanay, Rizal
Contract Location : Tanay, Rizal

DETAILED ESTIMATE
PART A - FACILITIES FOR THE ENGINEER
Item A.1.1(8) - Provision of Field Office for the Engineer ( Rental Basis)
Quantity = 2.86 mos

PART B - OTHER GENERAL REQUIREMENTS


Item B.5 - Project Billboard / Signboard
Quantity = 2.00 each
Item B.7(2) - Occupational Safety and Health Program
Quantity = 1.00 l.s
Item B.9 - Mobilization / Demobilization
Quantity = 1.00 l.s
Item B.15(2) - Detour / Access Road
Quantity = 60.00 l.m.
Item B.17 - Temporary Diversion of Waterway
Quantity = 1.00 l.s

PART C - EARTHWORK
Item 101(1) - Removal of Structures and Obstruction
Quantity = 1.00 l.s

Part J - FLODD CONTROL AND DRAINAGE


Part I-A - EARTHWORK
Item 1700(1) - Clearing and Grubbing
Area = (15.00 m x 3.00 m)
Area = 175.00 sq.m.
Item 1701(1) - Unsuitable Excavation
Volume = (20.00 m x 2.90 m x cu.m.
Volume = 169.95 cu.m.
Item 1704(1)a - Embankment (From Roadway / Structure Excavation)
Volume (Cut) = (20.00 m x 2.90 m x 1.70 m)
Volume (Cut) = 258.06 cu.m.
Hence; VolumeFill > Volume Cut
Volume = Volume Cut / 1.25
Volume = 206.45 cu.m.

Item 1704(1)b - Embankment (From Borrow)


Volume (Fill) = (20.00 m x 3.00 m x 3.00 m)
Volume (Fill) = 374.85
Volume = Total Volume (Fill) - [Total Volume (Cut)/1.25]
Volume = 330.15 cu.m. - 207.80 cu.m.
Volume = 168.40 cu.m.
PART I-B - BANK AND SLOPE PROTECTION WORKS
Item 1711(1) - Stone Masonry
For Flood Control Structure:
Volume (FCS) = (length) x (area of flood control structure)
= 20.00 m x [ 0.50 x (0.70 m + 3.70 m) x 6.35 m]
Volume (FCS) = 423.95535 cu.m.
Volume 2 = 423.95535 cu.m.

For Parapet Wall:


Volume (FCS) = (length) x (area of flood control structure)
= 20.00 m x 0.70 m x 0.60 m
Volume (FCS) = 18.36 cu.m.
Volume 2 = 18.36 cu.m.

Total Volume = 442.32 cu.m.

PART C - FINISHING AND OTHER CIVIL WORKS


ITEM 1027 - CEMENT PLASTER FINISH
Item 1027(1) - Cement Plaster Finish
For Flood Control Structure:
Surface Area = (5.84m x 20.50m)+(5.20m x 20.50m)
Surface Area = 226.32 sq.m

For Parapet Wall:


Surface Area = (0.60m x 20.50m x 3face)
Surface Area = 36.9 sq.m

Surface Area = 263.22 sq.m

Prepared by: Checked by:

JONAMENE G. JUAYONG ALVIN JOHN DC. FLORES


Engineer II Engineer II

Submitted by: Recommending Approval by:

CATHERINE A. TAMAYO RAMONITO S.M. PAZ


Chief, Maintenance Section Engineer III
Officer-In-Charge
Office of the Assistant District Engineer

Approved by:

JULIANA D. VERGARA
District Engineer
Contract ID Number :
Contract Name : Repair and Maintenance of Flood Control and Drainage Structure along
Tanay River (Flood Control ID No. F040074LZ) Tanay, Rizal
Contract Location : Tanay, Rizal

BACK-UP COMPUTATION

PART J - FLOOD CONTROL AND DRAINAGE


PART I-A - EARTHWORK
Item 1700(1) - Clearing and Grubbing
SECTION 1 -
Stone Masonry
Length = 50.00 m.
Ave. Width = 3.50 m.

Area = (15.00 m x 3.00 m)


Area = 175.00 sq.m.

Item 1701(1) -Unsuitable Excavation


SECTION 1 -
Length = 51.50 m.
Ave. Width = 2.20 m.
Ave. Height = 1.50 m.

Volume = (20.00 m x 2.90 m x 1.50 m)


Volume = 169.95 cu.m.

Item 1704(1)a - Embankment (From Roadway / Structure Excavation)


SECTION 1 -
Stone Masonry
Length = 51.00 m.
Ave. Width = 2.20 m.
Ave. Height = 2.30 m.

Volume (Cut) = (20.00 m x 2.90 m x 1.70 m)


Volume (Cut) = 258.06 cu.m.
Hence; VolumeFill > Volume Cut
Volume = Volume Cut / 1.25
Volume = 206.45 cu.m.

Item 1704(1)b - Embankment (from Borrow)


SECTION 1 -
Length = 51.00 m.
Ave. Width = 2.10 m.
Ave. Height = 3.50 m.

Volume (Fill) = (20.00 m x 3.00 m x 3.00 m)


Volume (Fill) = 374.85 cu.m.
Volume = Total Volume (Fill) - [Total Volume (Cut)/1.25]
Volume = 330.15 cu.m. - 207.80 cu.m.
Volume = 168.40 cu.m.

PART I-B - BANK AND SLOPE PROTECTION WORKS


Item 1711(1) - Stone Masonry

For Flood Control Structure:


Length = 51.00 m.
Top Width = 0.60 m.
Bottom Width = 2.79 m.
Height = 4.90 m.
Volume (FCS) = (length) x (area of flood control structure)
= 20.00 m x [ 0.50 x (0.70 m + 3.70 m) x 6.35 m]
Volume (FCS) = 423.96 cu.m.
Volume 2 = 423.96 cu.m.

For Parapet Wall:


Length = 51.00 m.
Top Width = 0.60 m.
Height = 0.60 m.
Volume (FCS) = (length) x (area of flood control structure)
= 20.00 m x 0.70 m x 0.60 m
Volume (FCS) = 18.36 cu.m.
Volume 2 = 18.36 cu.m.

Total Volume = 442.32 cu.m.


PART C - FINISHING AND OTHER CIVIL WORKS
ITEM 1027 - CEMENT PLASTER FINISH
Item 1027(1) - Cement Plaster Finish
Height = 4.90
Top Width = 0.60 m.
Slant Height = 5.37 m.
For Flood Control Structure:
Surface Area = (5.84m x 20.50m)+(5.20m x 20.50m)
Surface Area = 805.18 sq.m

For Parapet Wall:


Surface Area = (0.60m x 20.50m x 3 faces)
Surface Area = 55.08 sq.m

Surface Area = 860.26 sq.m

Prepared by:

JONAMENE G. JUAYONG
Engineer II
Contract ID Number :N/A
Contract Name
#REF!
Contract Location : Tanay, Rizal

COMPUTATION FOR PROJECT DURATION

Note : Estimated Mobilization / Demobilization for projects that ranges up to P 5M = 10 days


With given reference amount of P 1,769.002.74 within 34 days per 100 l.m. of Stone Masonry and

FOR COMPUTATION OF DURATION

For Stone Masonry


Calendar Days = (est. amount) x (ref. duration per km of road) Mobilization / Demobilization
+
Duration
given ref. amount
= (P 3,000,000.00) x (34 days)
+ 10days
P 1,769,002.74
Calendar Days = 68 C.D.

Pre-determined Unworkable Days on year 2023:


July 8 C.D.
August 10 C.D.
TOTAL = 18 C.D.

TOTAL ESTIMATED DURATION


= 48C.D. + 17 C.D.
= 86 C.D.
= 2.86 months

Prepared by:

JONAMENE G. JUAYONG
Engineer II
Contract ID Number :N/A
Contract Name
#REF!
Contract Location : Tanay, Rizal

COMPUTATION FOR PROJECT DURATION

Note : Estimated Mobilization / Demobilization for projects that ranges up to P 5M = 10 days


With given reference amount of P 1,769.002.74 within 34 days per 100 l.m. of Stone Masonry and

FOR COMPUTATION OF DURATION

5,000,000.00 - 3,000,000.00 88 - X
=
5,000,000.00 - 0 88 - 0

Calendar Days = 36 C.D


Total Estimated No. of 30 C.D Including Rainy Days
Unworkable Days =

Total Estimated Project Duration 66 C.D


=
= 2.20 Months

Prepared by:

JONAMENE G. JUAYONG
Engineer II
Embankment to Fill

Volume = (3.0m x 3.50m x 20.0m)


Volume = 210 cu.m

Embankment from Cut/Fill

Volume = (2.0m x 3.25m x 15.0m)


Volume = 97.5
Volume - 78 cu.m

VOLUME FILL > VOLUME CUT HENCE; EMBANKMENT FROM BORROW REQUIRED

Embankment From Borrow


Volume = (210.0Cu.m - 78.0Cu.m)
Volume = 132 Cu.m
DETAILED UNIT PRICE ANALYSIS (DUPA)

Project : #REF!
Location : Tanay, Rizal
Item No. : B.7(1)
Description : Occupational Safety and Health Program

Safety Safety Working Eye Amount


Item No. Manpower Rain Coat Dust Mask Ear Muff Days Man-days Unit Cost
Helmet Shoes Gloves Goggles (Pesos)

B.15(2) 9 0.25 2.77 7.67 0.18 1.62 10.69 17.32


B.17 13 0.25 2.77 7.67 2.75 35.75 10.69 382.17
101(1) 3 0.25 2.77 7.67 0.45 1.36 10.69 14.58
1027(1) 7 0.25 2.77 7.67 4.62 32.33 10.69 345.56
1700(1) 5 0.25 2.77 7.67 0.55 2.73 10.69 29.23
1701(1) 4 0.25 2.77 7.67 1.06 4.25 10.69 45.42
1704(1)a 9 0.25 2.77 7.67 1.72 15.48 10.69 165.52
1704(1)b 5 0.25 2.77 7.67 1.40 7.02 10.69 75.01
1711(1) 11 0.25 2.77 7.67 34.56 380.11 10.69 4,063.43
TOTAL 5,120.91

Safety Safety Working Eye Body Rubber


Rain Coat Dust Mask Ear Muff Lanyard
Helmet Shoes Gloves Goggles Harness Boots
Service Life Days 730 365 3 730 1 60 730 740 730 365
Purchased Cost, Php 180.55 1,012.00 23.00 245.00 63.25 169.10 602.60 1,263.85 1,083.30 509.00
Unit Cost per man-day 0.25 2.77 7.67 0.34 63.25 2.82 0.83 1.71 1.48 1.39
UNIT COST ANALYSIS FOR HAULING COST

Item No. : Aggregates Terrain : Flat


Quantity : 1,000.00 Unit : cu.m.
Hauling Distance: 34.00 km (PAVED)
- km (UNPAVED)
34.00 km
Effective Working Hours : 8.00 hrs
Hauling : Using 10.00 cu.m. capacity Dumptruck
Weight of Dumptruck (cap. 10.00 cu.m) : 16,000.00 kgs.
Unit Weight of Fine Aggregates : 1,640.00 kg/cu.m.
Unit Weight of Coarse Aggregates : 1,534.00 kg/cu.m.
Maximum Volume to be Carried by DT: 11.57 cu.m.

Flat - Paved Speed when Unloaded : 35 kph


Speed when Loaded : 55 kph

Loaded running = 58.29 mins


Unloaded running = 37.09 mins

Loading and Unloading : 5.00 mins


Total Time : 100.38 mins

Flat - Paved Speed when Unloaded : 30


Speed when Loaded : 45

Loaded running = - mins


Unloaded running = - mins

Loading and Unloading : - mins


Total Time : - mins

Capacity of Dumptruck : 10.00 cu.m.


Total Cycle Time : 110.41 mins. (w/ 10% delay)
No. of Trips for Dumptruck per day : 4.35
Dumptruck daily output = 43.47 cu.m.
Using 4 dumptrucks = 173.89 cu.m.

No. of Days for Dumptrucks = 5.75 days

EQUIPMENT USED: (D.O 63 S2022)


4 dumptruck @ P 21,538.24 x 5.75 days = P 495,443.62
day
Estimated Quantity : 1,000.00 cu.m.

UNIT COST P 14.57 /cu.m./km say P 15.00 /cu.m./km

Source to Site Unit Cost/ Hauling Cost/ Unit Price Unit Cost /
(km) x cu.m./km cu.m. (Quarry) cu.m.
Cost of Fine Aggregates (Sand) 34.00 x 15.00 510.00 700.00 1,210.00
Cost of Coarse Aggregates (Gravel, G3/4) 34.00 x 15.00 510.00 750.00 1,260.00
Cost of Natural Gravel (Gravel Fill) 34.00 x 15.00 510.00 630.00 1,140.00
Cost of Class A Boulders 34.00 x 15.00 510.00 900.00 1,410.00
Note: P20/cu.m./km. as per supplier / 15km free hauling (Crownmix)

Prepared by:

JONAMENE G. JUAYONG
Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : B.5 - Project Billboard / Signboard


Unit of Measurement : each
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : -

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor

a. Construction Foreman 1 1.00 118.97 118.97


A.1
b. Skilled Labor 1 1.00 86.02 86.02
c. Laborer 4 1.00 66.23 264.92

Sub - Total for A.1 - As Submitted 469.91


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
Minor Tools (10% Labor) 46.99

Sub - Total for B.1 - As Submitted 46.99


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 516.90
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 516.90
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a.Tarpaulin 4' x 8' pc. 1.00 1,050.00 1,050.00


b.Marine Plywood 1/4" x 4' x 8' pc. 1.00 485.00 485.00
F.1
c. Coco Lumber 2" x 2" x 12' (C.S ) bd.ft. 12.00 28.00 336.00
d. Coco Lumber 2" x 4" x 12' (C.S ) bd.ft. 48.00 28.00 1,344.00
e. Assorted CWN kg. 0.50 75.00 37.50

Sub - Total for F.1 - As Submitted 3,252.50


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 3,769.40
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
Overhead, Contingencies & Miscellaneous (OCM)
H.1 15% of G.1 565.41
- As Submitted
Overhead, Contingencies & Miscellaneous (OCM)
H.2 of G.2 -
- As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 376.94
I.2 Contractor's Profit (CP) - As Evaluated of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 235.59
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 4,947.34
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

JONAMENE G. JUAYONG RIZA S. BENGALA


Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : A.1.1(8) - Provision of Field Office for the Engineer (Rental Basis)
Unit of Measurement : month
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : -

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor
A.1
Sub - Total for A.1 - As Submitted -
Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
Sub - Total for B.1 - As Submitted -
Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted -
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted -
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

F.1 a. Bunkhouse / House Rental mos. 1.00 12,500.00 12,500.00


(including Electric and Water Consumption)

Sub - Total for F.1 - As Submitted 12,500.00


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 12,500.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
Overhead, Contingencies & Miscellaneous (OCM)
H.1 0% of G.1 -
- As Submitted
Overhead, Contingencies & Miscellaneous (OCM)
H.2 of G.2 -
- As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 1,250.00
I.2 Contractor's Profit (CP) - As Evaluated of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 687.50
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 14,437.50
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

JONAMENE G. JUAYONG RIZA S. BENGALA


Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : B.7(2) - Occupational Safety and Health Program


Unit of Measurement : lump sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : -

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor

a. Safety Officer 1 685.28 118.90 81,479.42


A.1
b. Health Personnel (Full Time First Aider) 1 685.28 86.02 58,947.51
c. Sanitation Aide 1 685.28 66.03 45,248.83

Sub - Total for A.1 - As Submitted 185,675.76


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment

a. Portable Mist - Based Sanitation Tent 1 685.28 3.21 2,199.74


B.1
b. Thermal Scanner (w/ rechargeable battery) 1 685.28 0.35 239.85
c. Power Spray w/ complete accessories 1 685.28 4.14 2,837.05

Sub - Total for B.1 - As Submitted 5,276.62


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 190,952.38
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 190,952.38
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

A. PPE's l.s. 1.00 5,120.91 5,120.91

B. First Aid Kit:


a. Sanitizing Solution lit 83.00 220.00 18,260.00
F.1
b. Ethyl Alcohol lit 29.00 215.00 6,235.00
c. Disinfectant Spray can 15.00 540.00 8,100.00
d. Liquid Hand Soap lit 15.00 110.00 1,650.00

C. COVID-19 Rapid Antibody Test each 11.00 650.00 7,150.00

Sub - Total for F.1 - As Submitted 46,515.91


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 237,468.30
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
Overhead, Contingencies & Miscellaneous (OCM)
H.1 0% of G.1 -
- As Submitted
Overhead, Contingencies & Miscellaneous (OCM)
H.2 of G.2 -
- As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 23,746.83
I.2 Contractor's Profit (CP) - As Evaluated of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 13,060.76
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Evaluated (G.1 + H.1 + I.1 + J.1) 274,275.87
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

JONAMENE G. JUAYONG RIZA S. BENGALA


Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : B.9 - Mobilization / Demobilization


Unit of Measurement : lump sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : -

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor
A.1
Sub - Total for A.1 - As Submitted -
Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment

B.1 a. Backhoe (0.80 cu.m.) 1 2.57768131969 2,474.46 6,378.37


b. Dump Truck 1 2.57768131969 2,696.28 6,950.15
c. Water Truck (16 000 L) 1 2.57768131969 3,919.17 10,102.37

Sub - Total for B.1 - As Submitted 23,430.89


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 23,430.89
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 23,430.89
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials
F.1
Sub - Total for F.1 - As Submitted -
Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 23,430.89
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
Overhead, Contingencies & Miscellaneous (OCM)
H.1 0% of G.1 -
- As Submitted
Overhead, Contingencies & Miscellaneous (OCM)
H.2 of G.2 -
- As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 0% of G.1 -
I.2 Contractor's Profit (CP) - As Evaluated of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 1,171.54
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Evaluated (G.1 + H.1 + I.1 + J.1) 24,602.44
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

JONAMENE G. JUAYONG RIZA S. BENGALA


Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS

Item No. / Description : B.15(2) - Detour/Access Road

Unit of Measurement : l.m.


Output per hour - As Submitted : 41.67
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor

Construction and Maintenance


For Stockpiling
a. Construction Foreman 1 0.83 103.15 85.61
b. Labor 2 0.83 57.39 95.27

A.1 For Spreading and Compaction


a. Construction Foreman 1 1.00 103.15 103.15
b. Labor 2 1.00 57.39 114.78

For Removal
a. Construction Foreman 1 0.63 103.15 64.98
b. Labor 2 0.63 57.39 72.31

Sub - Total for A.1 - As Submitted 536.11


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment

Construction and Maintenance


For Stockpiling
a. Payloader (1.50 cu.m.) 1 0.83 1,733.00 1,438.39
b. Dumptruck (12 yd3) 2 0.83 1,420.00 2,357.20

For Spreading and Compaction


B.1
a. Motorized Grader, G710A 1 1.00 2,173.00 2,173.00
b. Vibratory Roller, SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck (16,000 L) 1 0.25 2,450.00 612.50

Removal
a. Dumptruck (12 yd3) 3 0.63 1,420.00 2,683.80
b. Backhoe (0.80 cu.m.) 1 0.63 1,537.00 968.31

Sub - Total for B.1 - As Submitted 12,079.20


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 12,615.31
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 41.67
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 302.74
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials
F.1

Sub - Total for F.1 - As Submitted -


Materials
F.2
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 302.74
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM) - 15% of G.1 45.41
H.2 Overhead, Contingencies & Miscellaneous (OCM) - of G.2
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 30.27
I.2 Contractor's Profit (CP) - As Evaluated of G.2
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 18.92
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2)
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 397.35
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2)

Prepared by:

ALVIN JOHN DC. FLORES


Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : B.15(2) - Detour/Access Road

Unit of Measurement : l.m.


Output per hour - As Submitted : 41.67
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor

Construction and Maintenance


For Stockpiling
a. Construction Foreman 1 0.83 103.15 85.61
b. Labor 2 0.83 57.39 95.27

A.1 For Spreading and Compaction


a. Construction Foreman 1 1.00 103.15 103.15
b. Labor 2 1.00 57.39 114.78

For Removal
a. Construction Foreman 1 0.63 103.15 64.98
b. Labor 2 0.63 57.39 72.31

Sub - Total for A.1 - As Submitted 536.11


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment

Construction and Maintenance


For Stockpiling
a. Payloader (1.50 cu.m.) 1 0.83 2,274.00 1,887.42
b. Dumptruck (12 yd3) 2 0.83 3,352.19 5,564.64

For Spreading and Compaction


B.1
a. Motorized Grader, G710A 1 1.00 2,173.00 2,173.00
b. Vibratory Roller, SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck (16,000 L) 1 0.25 4,738.38 1,184.60

Removal
a. Dumptruck (12 yd3) 3 0.63 3,352.19 6,335.64
b. Backhoe (0.80 cu.m.) 1 0.63 2,788.49 1,756.75

Sub - Total for B.1 - As Submitted 20,748.04


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 21,284.15
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 41.67
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 510.78
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials
F.1

Sub - Total for F.1 - As Submitted -


Materials
F.2
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 510.78
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 76.62
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated of G.2
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 51.08
I.2 Contractor's Profit (CP) - As Evaluated of G.2
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 31.92
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2)
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 670.40
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2)

Prepared by: Checked/Reviewed by:

JONAMENE G. JUAYONG ALVIN JOHN DC. FLORES


Engineer II Engineer II
Output per No. of Safety Working Eye Body Rubber
Item No. Quantity Workers Days Man- Days Safety Shoes Safety Vest Rain Coat Face Mask Ear Muff Lanyard Face Shield
Hour Personnel Helmet Gloves Goggles Harness Boots

Foreman 3 0.18 0.54 1.62 1.62 1.62 1.62 1.62 1.62 1.62 1.62 1.62 1.62
B.15(2) 60.00 41.67
Skilled Laborer 6 0.18 1.08 6.48 6.48 6.48 6.48 6.48 6.48 6.48 6.48 6.48 6.48
Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
B.17 1.00 1.00 Skilled Laborer 2 0.13 0.25 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
Unskilled Laborer 10 0.13 1.25 12.50 12.50 12.50 12.50 12.50 12.50 12.50 12.50 12.50 12.50
Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
101(1) 1.00 1.00
Skilled Laborer 2 0.13 0.25 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
Foreman 1 4.62 4.62 4.62 4.62 4.62 4.62 4.62 4.62 4.62
1027(1) 263.22 7.13 Skilled Laborer 2 4.62 9.24 18.47 18.47 18.47 18.47 18.47 18.47 18.47
Unskilled Laborer 4 4.62 18.47 73.89 73.89 73.89 73.89 73.89 73.89 73.89
Foreman 1 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55
1700(1) 175.00 40.00
Skilled Laborer 4 0.55 2.19 8.75 8.75 8.75 8.75 8.75 8.75 8.75
Foreman 1 1.06 1.06 1.06 1.06 1.06 1.06 1.06 1.06 1.06
1701(1) 169.95 20.00
Skilled Laborer 3 1.06 3.19 9.56 9.56 9.56 9.56 9.56 9.56 9.56
Foreman 2 1.72 3.44 6.88 6.88 6.88 6.88 6.88 6.88 6.88
1704(1)a 206.45 15.00
Skilled Laborer 7 1.72 12.04 84.30 84.30 84.30 84.30 84.30 84.30 84.30
Foreman 1 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40
1704(1)b 168.40 15.00
Skilled Laborer 4 1.40 5.61 5.61 22.45 22.45 22.45 22.45 22.45 22.45 22.45 22.45 22.45
Foreman 1 34.56 34.56 34.56 34.56 34.56 34.56 34.56 34.56 34.56 34.56
1711(1) 442.32 1.60 Skilled Laborer 2 34.56 69.11 69.11 138.22 138.22 138.22 138.22 138.22 138.22 138.22
Unskilled Laborer 8 34.56 276.45 276.45 2,211.58 2,211.58 2,211.58 2,211.58 2,211.58 2,211.58 2,211.58
A. TOTAL, PERSONNEL/
66 447.54 619.06 2,640.14 2,640.14 2,640.14 2.00 2,640.14 2,432.06 2.00 47.71 47.71 2,640.14 2,640.14
MAN-DAYS
B. SERVICE LIFE, DAYS 730 365 180 3 730 1 60 730 730 730 365 60
C. PURCHASE COST, Pph 250.00 1500.00 400.00 23.00 245.00 5.00 300.00 612.60 1263.85 1083.30 506.00 500.00
D. UNIT COST/ MAN-DAYS (C/B) 0.34 4.11 2.22 7.67 0.34 5.00 5.00 0.84 1.73 1.48 1.39 8.33
E. DIRECT COST FOR PPE'S (D x A (Man-Days) 210.48 10,850.97 5,861.11 20,249.26 0.68 13,200.69 ### 1.68 82.53 70.61 3,669.79 21,992.35 88,350.46
TOTAL
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : B.17 - Temporary Diversion of Waterway


Unit of Measurement : lump sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : -

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor

a. Construction Foreman 1 1.10 118.97 130.87


A.1
b. Skilled Labor 2 1.10 86.02 189.24
c. Laborer 10 1.10 66.23 728.53

Sub - Total for A.1 - As Submitted 1,048.64


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment

a. Water Pump 2 1.10 338.97 745.73


B.1
b. Backhoe (0.80 cu.m) 1 1.10 2,474.46 2,721.91
Minor Tools (10% of Labor) 104.86

Sub - Total for B.1 - As Submitted 3,572.50


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 4,621.14
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 4,621.14
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. Sand cu.m. 14.30 1,210.00 17,303.00


F.1
b. Sack bd.ft. 748.00 5.00 3,740.00

Sub - Total for F.1 - As Submitted 21,043.00


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 25,664.14
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
Overhead, Contingencies & Miscellaneous (OCM)
H.1 15% of G.1 3,849.62
- As Submitted
Overhead, Contingencies & Miscellaneous (OCM)
H.2 of G.2 -
- As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 2,566.41
I.2 Contractor's Profit (CP) - As Evaluated of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 1,604.01
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 33,684.18
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

JONAMENE G. JUAYONG RIZA S. BENGALA


Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 1027(1) - Cement Plaster Finish


Unit of Measurement : sq.m.
Output per hour - As Submitted : 7.125
Output per hour - As Evaluated : -

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor

a. Construction Foreman 1 1.00 118.97 118.97


A.1
b. Skilled Laborer 2 1.00 86.02 172.04
c. Laborer 4 1.00 66.23 264.92

Sub - Total for A.1 - As Submitted 555.93


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
Minor Tools (10% of Labor) 55.59

Sub - Total for B.1 - As Submitted 55.59


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 611.52
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 7.125
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 85.83
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

F.1 a. Cement bags 0.330 240.00 79.20


b. Sand cu.m. 0.027 1210.00 32.67

Sub - Total for F.1 - As Submitted 111.87


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 197.70
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
Overhead, Contingencies & Miscellaneous (OCM)
H.1 15% of G.1 29.65
- As Submitted
Overhead, Contingencies & Miscellaneous (OCM)
H.2 of G.2 -
- As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 19.77
I.2 Contractor's Profit (CP) - As Evaluated of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 12.36
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 259.48
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:


JONAMENE G. JUAYONG RIZA. S BENGALA
Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 101(1) - Removal of Structures and Obstruction


Unit of Measurement : lump sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : -

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor

A.1 a. Construction Foreman 1 3.64 118.97 432.84


b. Laborer 2 3.64 66.23 481.92

Sub - Total for A.1 - As Submitted 914.76


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment

a. Backhoe w/ Breaker 0.80 cu.m 1 1.82 3,002.76 5,462.40


B.1 b. Backhoe 0.80 cu.m 1 1.82 2,474.46 4,501.35
c. Dump Truck (12 cu.yd.) 1 3.64 2,692.28 9,795.19
Hauling Distance - within three (3) km.

Sub - Total for B.1 - As Submitted 19,758.94


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 20,673.70
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 20,673.70
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials
F.1
Sub - Total for F.1 - As Submitted -
Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 20,673.70
G.2 Direct Unit Contingencies
Overhead, Cost (E.2 + F.2)& -Miscellaneous
As Evaluated -
H.1 (OCM)
Overhead, Contingencies & Miscellaneous 15% of G.1 3,101.06
H.2 - As Submitted
(OCM) of G.2 -
I.1 -Contractor's
As EvaluatedProfit (CP) - As Submitted 10% of G.1 2,067.37
I.2 Contractor's Profit (CP) - As Evaluated of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1 1,292.11
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2 -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 27,134.24
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

JONAMENE G. JUAYONG RIZA S. BENGALA


Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 1700(1) - Clearing and Grubbing


Unit of Measurement : sq.m.
Output per hour - As Submitted : 40.00
Output per hour - As Evaluated : -

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor

A.1 a. Construction Foreman 1 1.00 118.97 118.97


b. Laborer 4 1.00 66.23 264.92

Sub - Total for A.1 - As Submitted 383.89


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment
B.1
Minor Tools (10% Labor) 38.39

Sub - Total for B.1 - As Submitted 38.39


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 422.28
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 40.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 10.56
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials
F.1
Sub - Total for F.1 - As Submitted -
Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 10.56
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
Overhead, Contingencies & Miscellaneous (OCM)
H.1 15% of G.1 1.58
- As Submitted
Overhead, Contingencies & Miscellaneous (OCM)
H.2 of G.2
- As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 1.06
I.2 Contractor's Profit (CP) - As Evaluated of G.2
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 0.66
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 13.86
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2)

Prepared by: Checked/Reviewed by:

JONAMENE G. JUAYONG RIZA S. BENGALA


Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 1700(3)a4 - Individual Removal of Trees


Unit of Measurement : each
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : -

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor

A.1 a. Construction Foreman 1 6.67 118.97 793.53


b. Skilled 1 6.67 86.02 573.75
c. labor 2 6.67 66.23
Sub - Total for A.1 - As Submitted 1,367.28
Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment

a. Backhoe (0.80 cu.m) 1 5.00 2,351.85 11,759.25


B.1 b. Dump Truck (12cu.yd) 1 3.33 2,434.64 8,107.35
c. Chain Saw 1 3.33 2,343.86 7,805.05
Minor Tools (5% Labor) 136.73

Sub - Total for B.1 - As Submitted 27,808.38


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 29,175.67
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 29,175.67
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

F.1 a. Rope, 1" dia. - 5 uses m 20.00 35.00 700.00

Sub - Total for F.1 - As Submitted 700.00


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 29,875.67
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
Overhead, Contingencies & Miscellaneous (OCM)
H.1 15% of G.1 4,481.35
- As Submitted

Overhead, Contingencies & Miscellaneous (OCM)


H.2 of G.2
- As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 2,987.57
I.2 Contractor's Profit (CP) - As Evaluated of G.2
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 1,867.23
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 39,211.81
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2)
Prepared by: Checked/Reviewed by:

JONAMENE G. JUAYONG RIZA S. BENGALA


Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 1701 (1) - Unsuitable Excavation

Unit of Measurement : cu.m.


Output per hour - As Submitted : 20.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor

For Excavation Work:


a. Construction Foreman 1 1.00 103.15 103.15
b. Laborer 3 1.00 57.39 172.17
A.1

Sub - Total for A.1 - As Submitted 275.32


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment

a. Dumptruck (12 cu.yd.) 2 1.00 3,352.19 6,704.38


b. Backhoe( 0.80 cu.m) 1 1.00 2,788.49 2,788.49
c. Payloader 1 0.10 2,274.00 227.40
B.1
Minor Tools (10% of Labor) 27.53

Sub - Total for B.1 - As Submitted 9,747.80


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 10,023.12
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 20.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 501.16
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials
F.1

Sub - Total for F.1 - As Submitted -


Materials
F.2
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 501.16
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (O 15% of G.1 75.17
H.2 Overhead, Contingencies & Miscellaneous (OC of G.2
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 50.12
I.2 Contractor's Profit (CP) - As Evaluated of G.2
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 31.32
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2)
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 657.77
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2)

Prepared by: Cheked/ Reviewed by:

JONAMENE G. JUAYONG ALVIN JOHN D.C FLORES


Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 1701 (1) - Unsuitable Excavation

Unit of Measurement : cu.m.


Output per hour - As Submitted : 20.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor

For Excavation Work:


a. Construction Foreman 1 1.00 103.15 103.15
b. Laborer 3 1.00 57.39 172.17
A.1

Sub - Total for A.1 - As Submitted 275.32


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment

a. Dumptruck (12 cu.yd.) 2 1.00 3,352.19 6,704.38


b. Backhoe( 0.80 cu.m) 1 1.00 2,788.49 2,788.49
c. Payloader 1 0.10 2,274.00 227.40
B.1
Minor Tools (10% of Labor) 27.53

Sub - Total for B.1 - As Submitted 9,747.80


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 10,023.12
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 20.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 501.16
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials
F.1
Sub - Total for F.1 - As Submitted -
Materials
F.2
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 501.16
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As 15% of G.1 75.17
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As of G.2
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 50.12
I.2 Contractor's Profit (CP) - As Evaluated of G.2
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 31.32
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2)
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 657.77
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2)

Prepared by: Checked/Reviewed by:

JONAMENE G. JUAYONG ALVIN JOHN DC. FLORES


Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 1704(1)a - Embankment (from Roadway / Structure Excavation)


Unit of Measurement : cu.m.
Output per hour - As Submitted : 15.00
Output per hour - As Evaluated : -

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor

For Excavation Work:


a. Construction Foreman 1 0.75 118.97 89.23
b. Laborer 3 0.75 66.23 149.02
A.1
For Spreading and Compaction:
a. Construction Foreman 1 1.00 118.97 118.97
b. Laborer 4 1.00 66.23 264.92

Sub - Total for A.1 - As Submitted 622.14


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment

For Excavation Work:


a. Dump Truck (12 cu.yd.) 2 0.75 2,696.28 4,044.42
b. Backhoe 0.80 cu.m 1 0.75 2,474.46 1,855.85
B.1
For Spreading and Compaction:
a. Walk Behind Roller 1 1.00 344.99 344.99
b. Water Truck (16000 L) 1 0.01 3,919.17 39.19
c. Backhoe (0.80 cu.m.) 1 1.00 2,474.46 2,474.46
Minor Tools (10% Labor) 62.21

Sub - Total for B.1 - As Submitted 8,821.12


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 9,443.26
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 15.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 629.55
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

F.1

Sub - Total for F.1 - As Submitted -


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 629.55
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
Overhead, Contingencies & Miscellaneous (OCM)
H.1 15% of G.1 94.43
- As Submitted
Overhead, Contingencies & Miscellaneous (OCM)
H.2 of G.2
- As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 62.96
I.2 Contractor's Profit (CP) - As Evaluated of G.2
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 39.35
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 826.29
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2)

Prepared by: Checked/Reviewed by:

JONAMENE G. JUAYONG RIZA S. BENGALA


Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 1704(1)b - Embankment (from Borrow)


Unit of Measurement : cu.m.
Output per hour - As Submitted : 15.00
Output per hour - As Evaluated : -

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor

A.1 a. Construction Foreman 1 1.00 118.97 118.97


b. Laborer 4 1.00 66.23 264.92

Sub - Total for A.1 - As Submitted 383.89


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment

a. Walk Behind Roller 1 1.00 344.99 344.99


B.1 b. Water Truck (16000 L) 1 0.01 3,919.17 39.19
c. Backhoe 0.80 cu.m 1 1.00 2,474.46 2,474.46
Minor Tools (10% Labor) 38.39

Sub - Total for B.1 - As Submitted 2,897.03


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 3,280.92
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 15.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 218.73
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

F.1 a. Common Borrow cu.m. 1.25 150.00 187.50


(w/ 25% Shrinkage Factor)

Sub - Total for F.1 - As Submitted 187.50


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 406.23
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
Overhead, Contingencies & Miscellaneous (OCM)
H.1 15% of G.1 60.93
- As Submitted
Overhead, Contingencies & Miscellaneous (OCM)
H.2 of G.2
- As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 40.62
I.2 Contractor's Profit (CP) - As Evaluated of G.2
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 25.39
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 533.17
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2)

Prepared by: Checked/Reviewed by:

JONAMENE G. JUAYONG RIZA S. BENGALA


Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 1713(1) - Rubble Concrete


Unit of Measurement : cu.m.
Output per hour - As Submitted : 1.40
Output per hour - As Evaluated : -

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor

a. Construction Foreman 1 1.00 103.15 103.15


b. Skilled labor 2 1.00 74.52 149.04
A.1 c. Laborer 8 1.00 57.39 459.12

Handling of Materials
a. Laborer 8 1.00 57.39 459.12

Sub - Total for A.1 - As Submitted 1,170.43


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment

a. One Bagger Mixer 1 1.00 927.50 927.50


B.1 b. Water Truck (16,000 L) 1 0.05 4,540.66 227.03
c. Backhoe 0.80 cu.m 1 0.10 2,712.70 271.27
Minor Tools (10% of Labor) 117.04

Sub - Total for B.1 - As Submitted 1,542.85


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 2,713.28
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 1.40
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 1,938.05
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. Portland Cement bag 4.200 220.00 924.00


b. Sand cu.m. 0.263 1,210.00 317.63
c. Gravel Fill cu.m. 0.020 1,140.00 22.80
F.1 d. Weepholes (PVC) l.m 0.300 150.00 45.00
e. Filter Cloth sq.m. 0.015 280.00 4.20
f. Stones cu.m. 0.630 1,410.00 888.30
g. Gravel, G - 3/4 cu.m. 0.525 1,260.00 661.50
Miscellaneous (2% of Materials) 57.2685

Sub - Total for F.1 - As Submitted 2,920.69


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 4,858.75
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -

H.1 Overhead, Contingencies & Miscellaneous (OCM) 15% of G.1 728.81


- As Submitted

H.2 Overhead, Contingencies & Miscellaneous (OCM) of G.2 -


- As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 485.87
I.2 Contractor's Profit (CP) - As Evaluated of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 303.67
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 6,377.11
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

JONAMENE G. JUAYONG RIZA S. BENGALA


Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 1711(1) - Stone Masonry


Unit of Measurement : cu.m.
Output per hour - As Submitted : 1.60
Output per hour - As Evaluated : -

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor

a. Construction Foreman 1 1.00 118.97 118.97


A.1 b. Skilled Laborer 2 1.00 86.02 172.04
c. Laborer 8 1.00 66.23 529.84
Handling of Materials
a. Laborer 8 1 66.23 529.84
Sub - Total for A.1 - As Submitted 1,350.69
Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment

a. One Bagger Mixer 1 1.00 144.00 144.00


B.1 b. Water Truck (16000 L) 1 0.05 3,919.17 195.96
c. Backhoe (0.30 cu.m.) 1 0.10 1,228.04 122.80
Minor Tools (10% Labor) 135.07

Sub - Total for B.1 - As Submitted 597.83


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 1,948.52
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 1.60
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 1,217.83
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. Portland Cement bag 5.50 240.00 1320.00


b. Sand cu.m. 0.30 1,210.00 363.00
c. Gravel Fill cu.m. 0.02 1,140.00 22.80
F.1
d. Weepholes (PVC) l.m. 0.30 156.67 47.00
e. Filter Cloth sq.m. 0.015 280.00 4.20
f. Boulders cu.m. 1.05 1,410.00 1480.50
Miscellaneous (1% of Materials) 32.38

Sub - Total for F.1 - As Submitted 3,269.88


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 4,487.71
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
Overhead, Contingencies & Miscellaneous (OCM)
H.1 15% of G.1 673.16
- As Submitted

Overhead, Contingencies & Miscellaneous (OCM)


H.2 of G.2
- As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 448.77
I.2 Contractor's Profit (CP) - As Evaluated of G.2
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 280.48
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 5,890.12
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2)
Prepared by: Checked/Reviewed by:

JONAMENE G. JUAYONG RIZA S. BENGALA


Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 1713(1) - Rubble Concrete


Unit of Measurement : cu.m.
Output per hour - As Submitted : 1.40
Output per hour - As Evaluated : -

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


Labor

a. Construction Foreman 1 1.00 103.15 103.15


b. Skilled labor 2 1.00 74.52 149.04
A.1 c. Laborer 8 1.00 57.39 459.12

Handling of Materials
a. Laborer 8 1.00 57.39 459.12

Sub - Total for A.1 - As Submitted 1,170.43


Labor
A.2
Sub - Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment

a. One Bagger Mixer 1 1.00 927.50 927.50


B.1 b. Water Truck (16,000 L) 1 0.05 4,540.66 227.03
c. Backhoe 0.80 cu.m 1 0.10 2,712.70 271.27
Minor Tools (10% of Labor) 117.04

Sub - Total for B.1 - As Submitted 1,542.85


Equipment
B.2
Sub - Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 2,713.28
C.2 Total (A.2 + B.2) - Evaluated -
D.1 Output per hour - As Submitted 1.40
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 1,938.05
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. Portland Cement bag 4.200 220.00 924.00


b. Sand cu.m. 0.263 835.00 219.19
c. Gravel Fill cu.m. 0.020 990.00 19.80
F.1 d. Weepholes (PVC) l.m 0.300 150.00 45.00
e. Filter Cloth sq.m. 0.015 280.00 4.20
f. Stones cu.m. 0.630 1,060.00 667.80
g. Gravel, G - 3/4 cu.m. 0.525 1,210.00 635.25
Miscellaneous (2% of Materials) 50.30475

Sub - Total for F.1 - As Submitted 2,565.54


Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 4,503.60
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
Overhead, Contingencies & Miscellaneous (OCM)
H.1 15% of G.1 675.54
- As Submitted
Overhead, Contingencies & Miscellaneous (OCM)
H.2 of G.2 -
- As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 450.36
I.2 Contractor's Profit (CP) - As Evaluated of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 281.47
J.2 Value Added Tax (VAT) - As Evaluated of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 5,910.97
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

JONAMENE G. JUAYONG ALVIN JOHN DC. FLORES


Engineer II Engineer II

You might also like