Professional Documents
Culture Documents
Repair Rubble Concrete of FCD Tanay Revetment 30 FInal
Repair Rubble Concrete of FCD Tanay Revetment 30 FInal
Repair Rubble Concrete of FCD Tanay Revetment 30 FInal
JENI LOU B. ORACION PATRICK B. BALOT ROCHELLE V. ARMENDARES MANOLITO S. FABIAN WILFREDO L. RACELIS
Engineer II Engineer II Engineer II Officer-In-Charge District Engineer
Office of the Assistant District Engineer
DPWH Rizal 2nd District Engineering Office
#16 Westbank Road, Manggahan Floodway, Brgy. Rosario, Pasig City
FORM INFRA-03-2016
Repair/Maintenance of Tanay River Retvement 12 Brgy. Tandang Kutyo Tanay,Rizal
AS SUBMITTED 263.22 l.s 52,038.01 25% 13,009.50 3,252.38 16,261.88 68,299.89 259.48
Item 1027(1) Cement Plaster Finish
AS EVALUATED
AS SUBMITTED 52,038.01 13,009.50 3,252.38 16,261.88 68,299.89
TOTAL OF PART C
AS EVALUATED
PART J FLOOD CONTROL AND DRAINAGE
PART I-A EARTHWORK
AS SUBMITTED 175.00 sq.m 1,847.47 25% 461.87 115.47 577.33 2,424.79 13.86
Item 1700(1) Clearing and Grubbing
AS EVALUATED
Embankment (From Roadway/Structure AS SUBMITTED 206.45 cu.m. 129,969.40 25% 32,492.35 8,123.09 40,615.44 170,584.84 826.29
Item 1704(1)a
Excavation) AS EVALUATED
AS SUBMITTED 168.40 cu.m. 68,409.59 25% 17,102.40 4,275.60 21,378.00 89,787.59 533.17
Item 1704(1)b Embankment (From Burrow)
AS EVALUATED
AS SUBMITTED 285,397.95 71,349.49 17,837.37 89,186.86 374,584.80
TOTAL OF PART I-A
TOTAL OF PART I-A
AS EVALUATED
PART I-B BANK AND SLOPE PROTECTION WORKS
AS SUBMITTED 423.96 cu.m. 1,984,979.46 25% 496,244.86 124,061.22 620,306.08 2,605,285.54 5,890.12
Item 1711(1) Stone Masonry
AS EVALUATED
AS SUBMITTED 1,984,979.46 496,244.86 124,061.22 620,306.08 2,605,285.54
TOTAL OF PART I-B
AS EVALUATED
AS SUBMITTED 2,703,529.46 629,050.67 166,629.03 795,679.69 3,499,209.13
GRAND TOTAL
AS EVALUATED
say 2,000,000.00
Project : Repair/Maintenance of Tanay River Retvement 12 Brgy. Tandang Kutyo Tanay,Rizal Net Length : ( a ) Road N/A
( b ) Bridge N/A
Project ID : N/A ( c ) Others Flood Control and Drainage Structure 20.50 L.M
Location : Tanay, Rizal Target Start Date : Upon Release of NTP
Station Limits : N.A Total Project Duration : 66 Calendar Days
Appropriation : P 2,000,000.00 No. of Pre-determined
: 30 Calendar Days
Source of Fund : FY 2023 RA 11936 Regular 2023 CURRENT Unworkable Days
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I : Facilities for the Engineer 1.32% 35,691.50
Part II : Other General Requirements 12.01% 324,748.84
Civil,Mechanical Electrical, Sanitary/Plumbing
Part III :
Works
Part A : Earthwork 0.76% 20,673.70
Part C : Cement Plaster Finish 1.92% 52,038.01
Part J : Flood Control and Drainage
PLS. SEE FORM POW-2015-01C-00
Part I-A : Earthwork 10.56% 285,397.95
Part I-B : Bank and Slope Protection Works 73.42% 1,984,979.46
100.00% 2,703,529.46
JONAMENE G. JUAYONG RIZA S. BENGALA CATHERINE A. TAMAYO MANOLITO S. FABIAN WILFREDO L. RACELIS
Engineer II Engineer II Chief, Maintenance Section Officer-In-Charge District Engineer
Office of the Asst. District Engineer
FORM POW-2015-01A-00
Repair/Maintenance of Tanay River Retvement 12 Brgy. Tandang Kutyo Tanay,Rizal
***Parapet
Width 0.5 m
Height 0.6 m
Length 41 m
Area 0.30 sq.m
Volume 12.30 cu.m
Stone Masonry
Top Width 0.6 m
Heigth 5.10 m
Bottom Width 2.90 m
Length 9.00 (Actual)
Area 8.93 sq.m
Volume 80.33 cu.m
Volume Cut
Volume to Fill
Hence; Volume to fill > Volume of Cut
Unsuitable Excavation
Volume 1.50m x 3.0m x 5.0m
Volume = cu.m
DETAILED ESTIMATE
PART A - FACILITIES FOR THE ENGINEER
Item A.1.1(8) - Provision of Field Office for the Engineer ( Rental Basis)
Quantity = 2.86 mos
PART C - EARTHWORK
Item 101(1) - Removal of Structures and Obstruction
Quantity = 1.00 l.s
Approved by:
JULIANA D. VERGARA
District Engineer
Contract ID Number :
Contract Name : Repair and Maintenance of Flood Control and Drainage Structure along
Tanay River (Flood Control ID No. F040074LZ) Tanay, Rizal
Contract Location : Tanay, Rizal
BACK-UP COMPUTATION
Prepared by:
JONAMENE G. JUAYONG
Engineer II
Contract ID Number :N/A
Contract Name
#REF!
Contract Location : Tanay, Rizal
Prepared by:
JONAMENE G. JUAYONG
Engineer II
Contract ID Number :N/A
Contract Name
#REF!
Contract Location : Tanay, Rizal
5,000,000.00 - 3,000,000.00 88 - X
=
5,000,000.00 - 0 88 - 0
Prepared by:
JONAMENE G. JUAYONG
Engineer II
Embankment to Fill
VOLUME FILL > VOLUME CUT HENCE; EMBANKMENT FROM BORROW REQUIRED
Project : #REF!
Location : Tanay, Rizal
Item No. : B.7(1)
Description : Occupational Safety and Health Program
Source to Site Unit Cost/ Hauling Cost/ Unit Price Unit Cost /
(km) x cu.m./km cu.m. (Quarry) cu.m.
Cost of Fine Aggregates (Sand) 34.00 x 15.00 510.00 700.00 1,210.00
Cost of Coarse Aggregates (Gravel, G3/4) 34.00 x 15.00 510.00 750.00 1,260.00
Cost of Natural Gravel (Gravel Fill) 34.00 x 15.00 510.00 630.00 1,140.00
Cost of Class A Boulders 34.00 x 15.00 510.00 900.00 1,410.00
Note: P20/cu.m./km. as per supplier / 15km free hauling (Crownmix)
Prepared by:
JONAMENE G. JUAYONG
Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. / Description : A.1.1(8) - Provision of Field Office for the Engineer (Rental Basis)
Unit of Measurement : month
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : -
For Removal
a. Construction Foreman 1 0.63 103.15 64.98
b. Labor 2 0.63 57.39 72.31
Removal
a. Dumptruck (12 yd3) 3 0.63 1,420.00 2,683.80
b. Backhoe (0.80 cu.m.) 1 0.63 1,537.00 968.31
Prepared by:
For Removal
a. Construction Foreman 1 0.63 103.15 64.98
b. Labor 2 0.63 57.39 72.31
Removal
a. Dumptruck (12 yd3) 3 0.63 3,352.19 6,335.64
b. Backhoe (0.80 cu.m.) 1 0.63 2,788.49 1,756.75
Foreman 3 0.18 0.54 1.62 1.62 1.62 1.62 1.62 1.62 1.62 1.62 1.62 1.62
B.15(2) 60.00 41.67
Skilled Laborer 6 0.18 1.08 6.48 6.48 6.48 6.48 6.48 6.48 6.48 6.48 6.48 6.48
Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
B.17 1.00 1.00 Skilled Laborer 2 0.13 0.25 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
Unskilled Laborer 10 0.13 1.25 12.50 12.50 12.50 12.50 12.50 12.50 12.50 12.50 12.50 12.50
Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
101(1) 1.00 1.00
Skilled Laborer 2 0.13 0.25 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
Foreman 1 4.62 4.62 4.62 4.62 4.62 4.62 4.62 4.62 4.62
1027(1) 263.22 7.13 Skilled Laborer 2 4.62 9.24 18.47 18.47 18.47 18.47 18.47 18.47 18.47
Unskilled Laborer 4 4.62 18.47 73.89 73.89 73.89 73.89 73.89 73.89 73.89
Foreman 1 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55
1700(1) 175.00 40.00
Skilled Laborer 4 0.55 2.19 8.75 8.75 8.75 8.75 8.75 8.75 8.75
Foreman 1 1.06 1.06 1.06 1.06 1.06 1.06 1.06 1.06 1.06
1701(1) 169.95 20.00
Skilled Laborer 3 1.06 3.19 9.56 9.56 9.56 9.56 9.56 9.56 9.56
Foreman 2 1.72 3.44 6.88 6.88 6.88 6.88 6.88 6.88 6.88
1704(1)a 206.45 15.00
Skilled Laborer 7 1.72 12.04 84.30 84.30 84.30 84.30 84.30 84.30 84.30
Foreman 1 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40
1704(1)b 168.40 15.00
Skilled Laborer 4 1.40 5.61 5.61 22.45 22.45 22.45 22.45 22.45 22.45 22.45 22.45 22.45
Foreman 1 34.56 34.56 34.56 34.56 34.56 34.56 34.56 34.56 34.56 34.56
1711(1) 442.32 1.60 Skilled Laborer 2 34.56 69.11 69.11 138.22 138.22 138.22 138.22 138.22 138.22 138.22
Unskilled Laborer 8 34.56 276.45 276.45 2,211.58 2,211.58 2,211.58 2,211.58 2,211.58 2,211.58 2,211.58
A. TOTAL, PERSONNEL/
66 447.54 619.06 2,640.14 2,640.14 2,640.14 2.00 2,640.14 2,432.06 2.00 47.71 47.71 2,640.14 2,640.14
MAN-DAYS
B. SERVICE LIFE, DAYS 730 365 180 3 730 1 60 730 730 730 365 60
C. PURCHASE COST, Pph 250.00 1500.00 400.00 23.00 245.00 5.00 300.00 612.60 1263.85 1083.30 506.00 500.00
D. UNIT COST/ MAN-DAYS (C/B) 0.34 4.11 2.22 7.67 0.34 5.00 5.00 0.84 1.73 1.48 1.39 8.33
E. DIRECT COST FOR PPE'S (D x A (Man-Days) 210.48 10,850.97 5,861.11 20,249.26 0.68 13,200.69 ### 1.68 82.53 70.61 3,669.79 21,992.35 88,350.46
TOTAL
DETAILED UNIT PRICE ANALYSIS (DUPA)
F.1
Handling of Materials
a. Laborer 8 1.00 57.39 459.12
Handling of Materials
a. Laborer 8 1.00 57.39 459.12