National Highways Authority of India
(Ministry of Road Transport and Highways) February 27, 2023
HS Ud 6, RaCLAO, areaT, AE RS-1 10075 Important
G5 & 6, Sector 10, Dwarka, New Delhi ~ 110075
File. No 13057/01/2021/IT
Office Memorandum
Sub.: Functionality for Time and Cost Management in NH Projects through Data Lake.
The existing functionalities under EoT and CoS modules in Data Lake have been
further upgraded to cater to various provisions in the existing policy guidelines of
NHAT on the subject.
2. Revised SoP on its use has been made available on Data Lake under the concerned
modules. To facilitate the users, in addition to SoP a training video shall also be
provided shortly. The key features of the revised module are enclosed and ready
reference.
3. All PDs, ROs and the Technical Divisions are advised to take note of above and also
issue directions to their contractors and consultants in the field for compliance.
Encl:
Annex-A EoT Module
Annex-B CoS Module
(Deepak Saxena)
GM (IT) / Data Lake
To,
1, AIL ROs & All PDs
2. AllCGMs/ GMs
Copy to:
1. PPS toall Members / CVO
2. PPS to Chairman, NHAI
Copy also for necessary action to:
1 Data Lake Team - Project Manager - Kind Att. Sh Ram Singh
2. GMC Team - Project Manager ~ Kind Att. Ms Chinmayee PradhanAnnex-A
Key features of new Time Management (EOT) Module — Ensuring conformity to NHAI Policy
Guidelines no. 9.2.25/2019 dated 24.07.2019 and adherence thereof:
1. The new Time Management Module is divided into two parts:
i. EOT Notice: For notification of Delay Events by the Contractor as per Clause 10.5(ii)
of EPC Agreement.
ji, EOT Proposal: For submission of the detailed EOT proposal by the Contractor.
2. The Contractor cannot submit a new EOT proposal until the previous EOT is concluded
(Only one EOT proposal will be in review pipeline at a time)
3. Facility for the system-generated letter has been provided at all PIU/RO/HQ levels with
digital signature. Alternatively existing feature to upload offline letter has also been
continued:
4, To capture the remarks/comments by each concerned officer/stakeholder during
proposal processing through chronologically captured and digitally signed comments at
each stage has been enabled.
5. Visibility the current stage of the File/Proposal is enabled until itis concluded (approved
or rejected)
6. The revised project milestones for completion will be updated by the AE once the EOT
is approved.
7. Alerts and reminders have been imposed as per the provisions of Mode! Contract
Agreements and NHAI Policy Guideline no. 9.2.25/2019 dated 24.07.2019.
8 Auto pull file facility has been enabled at RO, GM, CGM and Member levels to pull file
in case it is pending at a lower level beyond a reasonable time limit.
in addition to the above, for faster communication of the decisions, the following optional
features have been added in the new Module:
i. _ Incase the EOT claimed by the Contractor is less than 2 months and there is no financial
claim by the Contractor (Damages from the Authority or any Prolongation Cost), PD may
grant provisional approval for the EOT pending the regular approval process at the
higher levels.
ii. Incase the EOT claimed by the Contractor is between 2 to 6 months and there is no
financial claim by the Contractor (Damages from the Authority or any Prolongation
Cost), RO may grant provisional approval for the EOT pending the regular approval
process at the higher levels.
ili, ‘The above approvals may be conveyed as per the prevailing Delegation of Powers.
% 41Annex-B
Key features of the new Change of Scope (COS) Module, Ensuring conformity to NHAI Policy
Guidelines and adherence thereof:
No, 11.46/2023 dated 21.02.2023.
No. 8.3.41/2021 dated 24.08.2021.
No. 8.3.34/202 dated 10.06.2020.
No. 9.2.27/2019 dated 23.09.2019.
No. 9.2.24/2019 dated 29.04.2019.
The new COS Module is divided into two major workflows:
a. COS In Principle and issuance of COS Order.
b. Regular COS and issuance of COS Order.
The COS proposal can be initiated by either the Contractor or the Authority as under:
‘a. The COS canbe initiated by the Contractor within 90 days from AD (in EPC Contracts
as per the MCA) and within 180 days from AD. (in HAM & BOT Agreements as per
NHAI Policy Circular no. 9.2.24/2019/2019 dated 29.04.2019)
b. Authority can initiate the COS process at any time during construction. However, in
case the COS is initiated after 6 months from AD, justification has to be submitted
‘along with the COS proposal for the delay in identifying the COS. (as per NHAI Policy
Circular no. 9.2.24/2019/2019 dated 29.04.2019)
Facility for the system-generated letter has been provided at all PIU/RO/HQ levels with
the digital signature. Alternatively, the existing feature to upload offline letters has also
been continued
To capture the remarks/comments by each concerned officer/stakeholder during
proposal processing through chronologically captured and digitally signed comments at
each stage has been enabled.
Visibility the current stage of the
or rejected).
./Proposal is enabled until itis concluded (approved
Alerts and reminders have been imposed as per the provisions of Model Contract
‘Agreements and NHAI Policy Guideline no. 9.2.27/2019 dated 23.09.2019.
Auto pull file facility has been enabled at RO, GM, CGM and Member levels to pull a file
in case it is pending at a lower level beyond a reasonable time limit.