Abs - CE
Abs - CE
Project Management Consultancy Services For UP Gradation To 4 Lane Configuration of Newly Declared NH 167AG From Its Junction With NH-
167A Near Kondamodu Connecting Rajupalem, Reddigudem, Sattenapalli, Medikonduru And Terminating At Its Junction With NH-544D Near
Perecherla In The State of Andhra Pradesh Total 49.917Km.
Stretches (Km) Length = 49.917 Cost
Part "A" - Road Works Km Per Km
TCS 1 - 4 Lane Divided Highway without Service Roads and with Raised Median (Open Country - Plain / Rolling Terrain) - Concentric
3202.57 Lacs 536.07 Lacs
Widening
TCS 2 - 4 Lane Divided Highway without Service Roads and with Raised Median (Open Country - Plain / Rolling Terrain) - Ecentric
5639.46 Lacs 516.56 Lacs
Widening-LHS
TCS 3 - 4 Lane Divided Highway without Service Roads and with Raised Median (Open Country - Plain / Rolling Terrain) - Ecentric
3812.92 Lacs 516.56 Lacs
Widening- Right
TCS 5 - 4 Lane Divided Highway with Service Road and with Raised Median (Concentric-Widening) - Widening - Builtup Plain/Rolling
Terrain 2557.67 Lacs 608.71 Lacs
TCS 6 - Cross Section of Grade Separator Approach with Slip Road- (New Construction)
2067.94 Lacs 581.70 Lacs
TCS 4 - 4 Lane Divided Highway without Service Roads and with Raised Median (Open Country - Plain / Rolling Terrain) - New
7761.77 Lacs 577.01 Lacs
Construction (REALIGNMENT / BYPASS)
TCS (16 & 17)- Typical cross section of Ramp 1 & Ramp 2 170.14 Lacs 144.19 Lacs
Total cutting & Filling (Exculding approach TCS) 4740.70 Lacs 94.97 Lacs
TCS : Flaring of Carriageway From Built-up & Structures section to Rural Sections 69.61 Lacs
Total (Part "A" - Road Works) 31508.94 Lacs 631.23 Lacs
Maintenance Charges for 5 years @ 2.5% of Civil Construction Cost (B) (For 1st year -, 2nd year-0.5%,3rd year-0.5%,4th year-0.5%
1891.92 Lacs
& 5th Year-1%)
Sub Total of Other Charges (C) 1891.92 Lacs
Total Project Cost (B+C) 77568.76 Lacs 1553.955 Lacs
D) Non Civil Works
Environment Cost 184.05 Lacs
LA compensation cost 15000.00 Lacs
Cost of shifting utilities 4119.00 Lacs
Sub Total of Non Civil Works (D) 19303.05 Lacs
Total Project Cost (B+C+D) 96871.80 Lacs 1940.658 Lacs