visitwww.DeepL.com/profor more information. ACTIVITY REPORT
February 2021
WEEKLY MAN-HOURS
DATE 7 JANURAY TO 13 FEBRUARY 2022
NUM COMPANY WORK-FORCE MAN-HOURS
1 PROYECTO MAGISTRAL 4 280
WEEK TOTAL 4 280
MAN-HOURS ACCUMULATED W/O ANY LDA 17170
TY MAN-HOURS
DATE 7 JAN 2021 TO 13 FEBRUARY 2022
NUM COMPANY MAN-HOURS
1 PROYECTO MAGISTRAL 11690
2 BYLSA 840
3 GREEN & GEOLOGY - GEOLOGIA-TARACHI GOLD 730
4 GREEN & GEOLOGY - ECOLOGIA 185
5 GREEN & GEOLOGY- TOPOGRAFIA 400
6 SINDICATO RETRO 49
7 TOPMIR 120
8 MERCY & BENEZRA 2934
9 LABORATORIO GUADIANA 24
10 MINERALES DE TARACHI CONSTRUCCION. 198
MAN-HOURS ACCUMULATED W/O LDA 17170
page1desde5
Juan Gurrola
ACTIVITY REPORT
February 2021
o Bio German Gonzalez, makes ETJ review, due to the need to make modifications or
proceed with the clearing and stripping works, it will be necessary to make and authorize a
new ETJ for the pending areas that were not impacted.
o Ramon Amaya, an expert in safety, environmental, maintenance and health issues, who is
awaiting authorization to begin the operation and emergency attention procedure for the
tailings dam, which is requested in one of the conditions requested by the government
agencies.
CAPEX.
page2desde5
Juan Gurrola
ACTIVITY REPORT
February 2021
6. CAPEX concepts are being developed based on the field needs and projections of
AUSENCO's preliminary study.
$ - $ - $ - $ 11,131,318.97
Vendors estimated costs
Juan Gurrola
ACTIVITY REPORT
February 2021
7. A table of machinery and equipment for rental and financing is made for the
development of plant operation activities. Quotations for these equipment and
services will be required.
8. Gonzalo Cortez of FIMSA, based on Skecht the concept of the jal transportation plan to
the mill. The specifications of the haulage ramp are added.
9. Adrian Gonzales from STS is confirmed to visit on February 24, the plan is to take them
from Durango to the Magistral Project and return them to Durango the same day.
02-11-22
A) You receive drawings for a 30-kilogram melting furnace for reheating, you want to know
how many degrees centigrade it plans to melt at and the heating rate.
B) Smelting furnace does not have a burner and needs to be rehabilitated.
C) Research in Hermosillo who can repair the furnace and have an estimated cost.
D) Meeting with German Gonzalez, to follow up on MIA, ETJ, and tailings dam operating
procedures.
E) We continue to study, review and consult PEA for CAPEX development.
page4desde5
Juan Gurrola
ACTIVITY REPORT
February 2021
F) Meeting with Joel Carrasco via telephone to request his support to share with us a CAD file
required for the development of the curtain and to georeferenced the initiator board and
see what would be the development of the curtain of the tailings dam and identify
possible areas outside the authorized ETJ.
G)
10-02-22
9-02-22
A) Fabian from Green Geology and Jose Roberto Comptroller from Minerales Tarachi to
continue developing the CAPEX concepts.
B) It begins with a Database for potential service and material providers.
C) Fabian Duarte from Green & Geology, related to the progress and planning of the activities
to be carried out in Durango, procedures, to present the action plan that will be proposed,
continues in review delivered by Camarón for the integration to the documents of the
permits the information received.
D) Results of the laboratory sample in the torreon. (9 days approx)
E) Ing. Joel Carrasco, pending authorization to start the tailings pond engineering and the
necessary studies for tailings compaction.
8-02-22
7-02-22
page5desde5
Juan Gurrola