1.1.0 RC SLAB-ON-FILL
1.1.1 PORTLAND CEMENT 40-KG BAG 147.00 245.00 36,015.00
1.1.2 SAND CU. M. 8.17 800.00 6,536.00
1.1.3 CRUSHED GRAVEL CU. M. 16.33 900.00 14,697.00
1.1.4 CRUSHED GRAVEL FOR FILL CU. M. 13.06 900.00 11,754.00
1.1.5 FORMWORKS/STAGING
A. LUMBER (5"X1"X12') PC. 11.00 360.00 3,960.00
B. LUMBER (2"X3"X12') PC. 13.00 180.00 2,340.00
1.4.0 SIDEWALK+CURB+GUTTER
1.4.1 PORTLAND CEMENT 40-KG BAG 37.00 245.00 9,065.00
1.4.2 SAND CU. M. 2.00 800.00 1,600.00
1.4.3 CRUSHED GRAVEL CU. M. 4.00 900.00 3,600.00
1.1.5 FORMWORKS/STAGING
A. LUMBER (5"X1"X12') PC. 6.00 360.00 2,160.00
B. LUMBER (2"X3"X12') PC. 7.00 180.00 1,260.00
2.0.0 STEELWORKS
2.1.0 RC SLAB-ON-FILL
2.1.1 D12MM REBARS (GRADE 60) KG 592.55 38.00 22,516.90
2.1.2 TIE WIRES (G.I. WIRE NO.16) KG 7.60 65.00 494.00
2.4.0 SIDEWALK+CURB+GUTTER
2.4.1 D10MM REBARS (GRADE 60) KG 133.58 38.00 5,076.04
2.4.2 TIE WIRES (G.I. WIRE NO.16) KG 3.55 65.00 230.75