PE01 MMG Perú Las Bambas Mine
PE01 MMG Perú Las Bambas Mine
Operations Overview
Duration
Operation Description Work Centre People
HRS
0040 REPUESTOS WONG - LUBRICACION MDAU-MEC 0 0
Overview of Materials
Store
Material Description Qty Unit Unloading Point
Locn
80003502 MANGUERA,1/4IN,SAE100R2AT,T24A,RYCO 370 CM 1001
Work Summary
REPUESTOS WONG - VARIOS
08.06.2023 10:40:32 AUSVIC Roberto Carlos Rocha Cordova (ROCHACOR)
Job Description
Materials Required
General Data
Description : REPUESTOS WONG - VARIOS Priority : On the Day
Required Start : Wednesday, 07/06/2023 8:15:38 PM
Technical Object : PE01-10-25-16-DZTR011.HYSM Hydraulic System
System Condition : Offline - PU
Sort field : DZ011
Process Area : PE01-10-25 Auxiliary Equip
Measuring Point :
Equipment :
Serial Number :
Task Type :
Operations Overview
Duration
Operation Description Work Center People
HRS
0040 REPUESTOS WONG - LUBRICACION MDAU-MEC 0 0
Overview of Materials
Store Item
Material Description Qty Unit Unloading Point Resv No
Locn no
80003502 MANGUERA,1/4IN,SAE100R2AT,T24A,RYCO 370 CM 1001 2453594 32
Work Summary