Date Activity

9 Oct 2017,
Reading and analyzing Auto CAD drawings of the Project.
Monday

10 Oct 2017, Attending Construction Skills training which function likely as CIDB
Tuesday which is set by GAMUDA to allow us entering site afterwards.

11 Oct 2017, Working at Headquarters due to incident happened earlier on. Thus,
Wednesday getting chances to know the operation of each department in HQ.

Renaming the photos that were taken during the construction and
12 Oct 2017,
regrouping them into each category, such as catch pit, sedimentation
Thursday
tank, drainage, fences, capping beam, etc.

13 Oct 2017, Attending department meeting discussing about the progression of


Friday construction.

14 Oct 2017, Categorizing photos of secant bored pile structure into each step and
Saturday renaming the paperwork of SBP structure based on the data given.