Trinity System M113 Spare Parts - 230731 - 220016
Trinity System M113 Spare Parts - 230731 - 220016
SPARE PARTS-M113
31 May 2021
Proposal number: TDG310521-02
This document de nes the spare parts for the M113 to the project mentioned below, our
understanding of your requirements
SPECIFICATIONS:
Set of elements with similar characteristics or that are manufactured under uniform production
conditions, which are subjected to inspection as a unitary set
1. Disassembly, disassembly, assembly and installation in the vehicle must be carried out,
application of a metrology system to each of the sub-assemblies and parts together,
crankshaft recti cation, change of connecting rod bushings, change of camshaft bushings,
changes of exhaust valve guides, change and recti cation of valve seats, hydrostatic test of
cylinder heads Veri cation of the bench circle, connecting rod circle, cylinder head and block
atness, maintenance and washing of injectors should be performed under laboratory tests,
Changed items must be original to this equipment keeping the engine capacity
2. Once this work is done, the motor must be painted and assembled. Contractor must
perform blowby test when hot engine repair, report measurement, and install on vehicle with
all new uids and consumables.
1. During the rst three years, the contractor must perform a blowby test on the hot engine
and present a report of the results obtained in each visit to the contract supervisor.
2. In the after-sales service, the contractor must guarantee engine reviews and periodic
assistance to maintenance carried out by the Army, in terms of oil changes, air lters, oil and
fuel.
3. The contractor must take the corresponding samples from each of the equipment and
present a laboratory report on the engine oil during the rst three years after the repair, at
least 4 times. This report should contain the state of the oil, analysis of the state of metal
wear, behavior of the cooling system and the function of the thermal wear of the oil.
4. Oil analysis should be done by an experienced and certi ed tribology professional.
5. At the end of the warranty and after-sales service, a nal report must be delivered taking into
account all the shots taken, with their respective recommendations and care to take into
account.
6. Along with the oil analysis periods, the quality of the refrigerant must be analyzed, in order to
guarantee the quality of this component, making the change, in case of not meeting the
quality standards.
7. The contractor company must deliver equipment certi cation
8. Turbocharger: Cleaning must be done, major maintenance at all costs, dents of exhaust
system components such as pipes, muf er, catalyst, fasteners, protectors and insulators.
The outside of all components must be painted.
9. Injectors: major maintenance at all costs, test bench calibration.
fl
fl
fi
fi
fi
fi
fl
fi
fi
fi
fi
fi
fi
Radiator:
1. Cleaning, maintenance, repair (probing, welding and painting) of the radiator and water tank
must be carried out. Change of additional components such as parts in rubber hoses and
clamps
2. Cleaning, maintenance and / or repair should be carried out for breaks, dents or missing
elements of the components of the exhaust system such as: pipes, muf er, catalyst,
fasteners, protectors and insulators. External painting of components must be carried out
3. Se debe realizar el mantenimiento mayor a todo costo donde se realice el desmontaje,
desarme, arme e instalación en el vehículo limpieza, mantenimiento, reparación,
puesta en funcionamiento de la torre de abanico caja angular y reemplazo de sus
componentes internos, reemplazo de toda la tornillería con sus respectivas arandelas de
presión empaquetadura y lubricantes nuevos
AUTOMATIC TRANSMISSION
SPECIFICATIONS:
1. Disassembly, disassembly, assembly and installation in the vehicle must be carried out,
carrying out a total update of this equipment, carrying out the corresponding repowering
with the total change of the internal parts, leaving it in the TX-100-1A version.
2. The update includes the replacement of the elements to allow the absorption of the power
generated by the engine.
3. This activity must include the test bench, certi cates for transmissions and be delivered with
the element to the contract supervisor.
4. The contractor must deliver the certi cates and results of the test benches for this type of
equipment.
5. The contractor must make it clear in the nal report, in what type of ATF technology the
servo transmission is left and the ATF change periods, which promote the durability and
ef ciency of the servo transmission; must carry out ATF monitoring through the used oil
analysis technique, to determine if the ATF change periods theoretically proposed are
effective and obey the reality of the servo transmission operation in the vehicle, or on the
contrary should make decisions about preventive maintenance, or reduce or increase
change intervals. Once the monitoring is completed, the contractor must deliver the new
preventive and corrective maintenance program.
6. The oil analysis must be done by an expert tribology professional and certi ed. 1 end of the
warranty and post-sale period, a nal report must be delivered taking into account all the
shots taken, with their respective recommendations and care
7. Once the study is concluded, if there is a unit or several that show atypical metal wear
levels, the contractor must dismantle and maintain under warranty, without this generating
any cost for the National Army and make a report on the condition of the elements of wear
and the possible root causes by which these wear are generated, to avoid massive failures
in the future or to provide the most appropriate preventive maintenance plan
fi
fi
fi
fi
fi
fi
fl
TRANSFER BOX
SPECIFICATIONS:
1. Major maintenance must be carried out at all costs, where the repair, assembly, assembly
and start-up of the transfer case must be carried out, replacement of its internal
components, replacement of all the hardware with their respective pin and pressure
washers.
SUSPENSION SYSTEM
SPECIFICATIONS:
1. Major maintenance must be carried out at all costs with the disassembly, inspection,
cleaning, repair, assembly, assembly and commissioning of the suspension system such as
tracks, suspension arms, wheel hubs, idler wheels, road wheels , sprockets, idler arms
torsion bars
ELECTRIC SYSTEM
SPECIFICATIONS:
1. Major maintenance must be carried out at all costs by dismantling, inspecting, cleaning,
repairing, assembling, assembling and putting into operation the components of the
electrical system in its entirety, including the high lines, connections, alternator, lights,
batteries, panels. control, gauges, starter motor
HYDRAULIC SYSTEM
SPECIFICATIONS:
1. Major maintenance must be carried out at all costs where the disassembly, inspection,
cleaning, maintenance, repair, assembly, assembly and commissioning of the components
of the hydraulic system are carried out in their entirety.
SPECIFICATIONS:
1. Major maintenance must be carried out at all costs where the disassembly, inspection,
cleaning, maintenance, repair, assembly, assembly and start-up of the components of the
control and steering system are carried out, which includes levers, controlled differential and
nal drives, cardan , spreaders.
fi
FUEL SYSTEM
SPECIFICATIONS:
1. Major maintenance must be carried out at all costs, where the disassembly, inspection,
cleaning, maintenance, repair, assembly, assembly and commissioning of the components
of the fuel system including water traps, tanks, fuel lines, valves are carried out. He passed
2. In the same way, the entire 0306 group must be changed according to the fuel lines vehicle
parts manual
MONOBLOCK SYSTEM
SPECIFICATIONS:
1. Major maintenance must be carried out at all costs, where the complete stripping of the
barge coating must be carried out under the sandblating technique or application of remover
for special military paint, in order to expose all imperfections or damage to the metal The
contractor must make the corresponding corrections, guaranteeing not to affect the
shielding and leaving it 100% in such a way that the barge is ready for the tinwork and
painting process.The contractor must certify that the primer and the applied color layer
correspond to speci cations. military, in permanent directive No. 00193 of 2017 annex H.
This certi cation must be issued by the contractor company, it must submit a report with the
work carried out before, during and after the infrared trace produced by the vehicle, in the
internal part a painting process must be carried out in the entire cabin and engine
compartment
2. Military external paint with low infra-red radiation: green and / or monochromatic desert.
3. Vehicle identi cation must be carried out by placing notices on black self-adhesive vinyl (Two
notices 1. With the identi cation of the unit and 2. With the identi cation of the vehicle on the
front, one on each side. exact locations according to the current directive.
SPECIFICATIONS:
1. Major maintenance must be performed at all costs where disassembly, cleaning, inspection,
maintenance, repair, assembly, assembly and commissioning are carried out. The elements
that make up the upholstery of the vehicle must be new.
2. Cleaning, inspection, repairing, painting, assembly, assembly and operation of the supports
or bases, cushions of the operator's chairs, commander, gun aimer and the ri emen's chairs
must be carried out.
3. The replacement of everything related to the rubber and gaskets that the vehicle has must
be carried out since, due to the time of use, these present wear and tear and loss of
properties due to the climatic conditions where the vehicles are located.
fi
fi
fi
fi
fi
fl
SPECIFICATIONS:
1. Carry out major maintenance at all costs where the disassembly, cleaning, inspection,
maintenance, repair, assembly, assembly and commissioning of the elements that make up
the re control system are carried out.
2. Recharge
3. 2.3 KG CO2 Portable in troop compartment
4. 2.3 KG CO2 In engine compartment
SPECIFICATIONS:
1. The new fuels, uids, greases and lubricants must be applied and the necessary quantities
in the different systems for the start-up and correct operation of the vehicle, since it is a
major maintenance, where the vehicle is being placed on point and once removed from the
vehicle they can be contaminated and will not be reused.
fi
fl
Table 1
QTY PER
Nº NSN No. PART DENOMINATION Price USD TOTAL
VEHÍCLE
ENGINE
TRANSMITION
1
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
QTY PER
Nº NSN No. PART DENOMINATION Price USD TOTAL
VEHÍCLE
TRANSFER CASE
CONTROLLED DIFERENTIAL
FINAL CONTROLS
89 2530-01-496-4444 12474844-1 Track Shoe Assy Ls, T150 Track 63 US 458.33 US 28,875.00
2
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
QTY PER
Nº NSN No. PART DENOMINATION Price USD TOTAL
VEHÍCLE
90 2530-01-496-4444 12474844-1 Track Shoe Assy Rs, T150 Track 64 US 458.33 US 29,333.33
128 5305-00-916-2345 MS90727-187 Tension Wheel Bracket Hex Bolt 16 US 3.33 US 53.33
3
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
QTY PER
Nº NSN No. PART DENOMINATION Price USD TOTAL
VEHÍCLE
ELECTRIC SYSTEM
HIDRAULIC SYSTEM
4
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
QTY PER
Nº NSN No. PART DENOMINATION Price USD TOTAL
VEHÍCLE
REFRIGERATION SYSTEM
226
5
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
QTY PER
Nº NSN No. PART DENOMINATION Price USD TOTAL
VEHÍCLE
6
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
QTY PER
Nº NSN No. PART DENOMINATION Price USD TOTAL
VEHÍCLE
7
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
QTY PER
Nº NSN No. PART DENOMINATION Price USD TOTAL
VEHÍCLE
OPERATOR CHAIR
8
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
QTY PER
Nº NSN No. PART DENOMINATION Price USD TOTAL
VEHÍCLE
397 5340-01-083-5674 12316370 Opening the Fuel Fill Cap 1 US 66.67 US 66.67
9
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
QTY PER
Nº NSN No. PART DENOMINATION Price USD TOTAL
VEHÍCLE
LUBRICATION SYSTEM
Total US 174,418.51
Packing 3% US 5,232.56
10
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$