Professional Documents
Culture Documents
First Successful Installation of A 4-12 Pre-Perforated Liner Through A 5-12 Solid Expandable Liner. Spe-182814-Ms
First Successful Installation of A 4-12 Pre-Perforated Liner Through A 5-12 Solid Expandable Liner. Spe-182814-Ms
This paper was prepared for presentation at the SPE Kingdom of Saudi Arabia Annual Technical Symposium and Exhibition held in Dammam, Saudi Arabia, 25–28
April 2016.
This paper was selected for presentation by an SPE program committee following review of information contained in an abstract submitted by the author(s). Contents
of the paper have not been reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material does not necessarily reflect
any position of the Society of Petroleum Engineers, its officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written
consent of the Society of Petroleum Engineers is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may
not be copied. The abstract must contain conspicuous acknowledgment of SPE copyright.
Abstract
Sustaining field proven technologies in mature fields and maximizing Return of Investment (ROI) is a
priority for operators worldwide. Financial constraints such as oil and gas prices, drilling cost, and any
intangibles must not burden the success of pushing limits to open new horizons, not just for the present
time but also for future generations. Parallel to reaching new limits, we must keep an eye on the safety
and engineering behind any step taken toward the limit to push the envelope successfully. Drilling team
recently used a a vendor product to maximize production, isolate a loss circulation zone, and push the
operating envelop by installing the first 4-1/2⬙ open hole completion (Pre-perforated liner) with inflatable
open hole isolation packers through a 5-1/2⬙ ⫻ 7⬙ open hole liner (OHL). The vendor product enabled
Saudi Aramco to install 5-1/2⬙ ⫻ 7⬙ solid expandable liner installation. The 5-½⬙ 18.24 lb/ft solid
expandable systems was utilized to isolate a loss zone and reactive shale section, sealing off the
problematic interval and allowing an extended lateral section to be drilled through the reservoir. The
expandable liner was run through a window cut through 7⬙ 26 lb/ft casing and subsequently installed
across part of the curve section to isolate the lost circulation zone. The use of the expandable liner enables
the ability to drill the remaining build section and horizontal section together with full circulation. This
paper describes the challenge and application.
Introduction
Maturing fields are a common challenge for drilling and workover operators around the world. Wells that
produce for long periods usually experience a variety of problems, which will ultimately require
workover. These workovers become essential to extending well life.
Four offshore areas have ongoing drilling and workover campaigns to maximize production. All four
areas show the same geologic structure and geological challenges. The casing design used is also identical,
which helps in unifying the solution and best practices. In these fields, severe losses typically occur in the
6-1/8 in. hole section, when drilling the buildup section and the horizontal section use high over-balanced
mud, due to limited hole size options. The losses cause difficulties running in hole to Total Depth (TD)
and are a major source of nonproductive time during both operations drilling and completion. Differential
2 SPE-182814-MS
stickings across the horizontal section is one major problem encountered and is a challenge because of
high overbalance.
Case Study
In one recent case, the Drilling Team planned to sidetrack a workover well below a known lost circulation
zone, drill the 6 1/8⬙ hole section and run a ICD completion. Because of the heavily corroded 7 in. casing,
the sidetrack whipstock was set just below the lost zone. The drilling team faced a challenge while drilling
to isolate the loss circulation zone, and maintain a hole size to run with a conventional 4-1/2 in. liner
string drill pipe. The safety subs were connected and the drill pipe picked up to pull the slips on the liner.
The liner was run to the bottom of the 7-3/8-in. open hole section.
Cementing the liner A cement job was conducted to set the expandable liner on bottom. The job
consisted of pumping 125 bbl of 118 pcf slurry with thickening time of at least 10 hours. Following the
cement job, the expansion initiation dart was dropped to displace the cement from the drillpipe. The dart
landed in the launcher with 85 bbl displacement as calculated.
Expanding the liner After landing the dart, the drillpipe was pressured-up to break the rupture disc. The
Figure 1—Schematic of the 4-1/2 Pre-Perforated Liner Installed below the 5-1/2 ⴛ 7 in. Expandable Liner
4 SPE-182814-MS
Equipment Details
Liner Data
The specifications for the expandable liner used in the well is described in the following set of tables:
Solid Expandable Tubular Data
Max Set down Weight 31,200 lbs Maximum Overpull on 50,000 lbs
in Open hole for ledge Drillpipe before Mechanical
or unstable wall; 80% Expansion; 80% of Launcher
of Guide nose initiation force
Compression Rating
Max Set down Weight 217,600 lbs Max Circulation Pressure; 80% 2,400 psi
in Open hole with of Rupture Disc Rating
Differential sticking; Max Set down Weight in 10,000 lbs
80% Connection Cased Hole or in Window
Minimum Parting Load
SPE-182814-MS 5
Workstring Data
Acknowledgements
The authors thank the management of Saudi Aramco for their support and approval to publish this paper
References
1. Dupal, K., Shell Deepwater Development, Inc.; Campo, D., Shell Exploration & Production Technology; Lofton, J.,
Chevron Petroleum Technology Company; Weisinger, D., BP; Cook, R., Bullock, M., Grant, T., and York, P.,
Enventure Global Technology, L.L.C., ⬙Solid Expandable Tubular Technology – A Year of Case Histories in the
Drilling Environment,⬙ at 2001 SPE/IADC Drilling Conference, Amsterdam, 27 February – 1 March.
2. Steven W. Sparling, Kerr-McGee Oil & Gas Corporation; Greg Noel, Enventure Global Technology; ⬙Expanding Oil
Field Tubulars Through a Window Demonstrates Value and Provides New Well Construction Option⬙ at 2004 SPE
Annual technical symposium & Exhibition, Dammam, April 25–28, 2016.