Sr. No Date R.

D Description Remarks
1 2/1/2023 0+00 ~19+68 desmantling edging ok
2 4/1/2023 0+00 ~19+68 desmantling road pavement OK
3 16/1/2023 0+00 ~10+00 sub base fdt 1st OK
4 17/1/2023 10+00~15+00 sub base fdt 1st FAIL
5 19/1/2023 15+00~19+68 sub base fdt 1st OK
6 21/1/2023 10+00~15+00 sub base fdt 1st RETEST OK
7 21/1/2023 0+00~6+00 sub base fdt 2nd FAIL
8 22/1/2023 6+00~14+00 sub base fdt 2nd OK
9 23/1/2023 0+00~6+00 sub base fdt 2nd RETEST OK
10 23/1/2023 14+00~19+68 sub base fdt 2nd OK
11 23/1/2023 0+00~10+00 sub base fdt top OK
12 25/1/2023 10+00~15+00 sub base fdt top FAIL
13 26/1/2023 15+00~19+68 sub base fdt top OK
14 27/1/2023 10+00~15+00 sub base fdt top RETEST OK
15 28/1/2023 19+68~31+50 desmantling edging OK
16 28/1/2023 19+68~31+50 providing edging OK
17 29/1/2023 31+50~43+00 dismantling edging OK
18 30/1/2023 19+68~31+50 WBM FDT OVERLAY OK
19 30/1/2023 31+50~43+00 providing edging OK
20 31/1/2023 31+50~43+00 WBM FDT OVERLAY FAIL
21 31/1/2023 43+00~76+00 dismantling edging OK
22 1/2/2023 76+00~115+00 dismantling edging OK
23 1/2/2023 31+50~43+00 WBM FDT OVERLAY RETEST OK
24 2/2/2023 43+00~70+00 providing edging OK
25 3/2/2023 43+00~55+00 WBM FDT OVERLAY OK
26 4/2/2023 55+00~61+00 WBM FDT OVERLAY FAIL
27 4/2/2023 61+00~64+00 WBM FDT OVERLAY OK
28 5/2/2023 64+00~67+00 WBM FDT OVERLAY OK
29 6/2/2023 70+00~105+00 providing edging OK
30 7/2/2023 67+00~76+00 WBM FDT OVERLAY OK
31 8/2/2023 76+00~79+00 WBM FDT OVERLAY FAIL
32 8/2/2023 55+00~61+00 WBM FDT OVERLAY RETEST OK
33 9/2/2023 76+00~79+00 WBM FDT OVERLAY RETEST OK
34 9/2/2023 79+00~91+00 WBM FDT OVERLAY OK
35 10/2/2023 91+00~97+00 WBM FDT OVERLAY OK
36 10/2/2023 97+00~103+00 WBM FDT OVERLAY FAIL
37 11/2/2023 115+00~145+00 dismantling edging OK
38 12/2/2023 105+00~140+00 providing edging OK
39 12/2/2023 103+00~115+00 WBM FDT OVERLAY OK
40 13/2/2023 97+00~103+00 WBM FDT OVERLAY RETEST OK
41 14/2/2023 115+00~121+00 WBM FDT OVERLAY OK
42 15/2/2023 121+00~124+00 WBM FDT OVERLAY FAIL
43 16/2/2023 124+00~136+00 WBM FDT OVERLAY OK
44 18/2/2023 121+00~124+00 WBM FDT OVERLAY RETEST OK
45 20/2/2023 145+00~180+00 dismantling edging OK
46 22/2/2023 140+00~175+00 providing edging OK
47 25/2/2023 136+00~148+00 WBM FDT OVERLAY OK
48 26/2/2023 148+00~151+00 WBM FDT OVERLAY FAIL
49 1/3/2023 151+00~157+00 WBM FDT OVERLAY OK
50 2/3/2023 148+00~151+00 WBM FDT OVERLAY RETEST OK
51 5/3/2023 157+00~160+00 WBM FDT OVERLAY FAIL
52 7/3/2023 160+00~172+00 WBM FDT OVERLAY OK
53 10/3/2023 180+00~225+00 dismantling edging OK
54 15/3/2023 175+00~220+00 providing edging OK
55 17/3/2023 172+00~181+00 WBM FDT OVERLAY OK
56 20/3/2023 157+00~160+00 WBM FDT OVERLAY RETEST OK
57 24/3/2023 181+00~184+00 WBM FDT OVERLAY FAIL
58 26/3/2023 184+00~196+00 WBM FDT OVERLAY OK
59 27/3/2023 181+00~184+00 WBM FDT OVERLAY RETEST OK
60 1/4/2023 196+00~202+00 WBM FDT OVERLAY OK
61 2/4/2023 202+00~208+00 WBM FDT OVERLAY FAIL
62 5/4/2023 208+00~220+00 WBM FDT OVERLAY OK
63 2/4/2023 225+00~264+00 dismantling edging OK
64 9/4/2023 202+00~208+00 WBM FDT OVERLAY RETEST OK
65 10/4/2023 220+00~264+00 providing edging OK
66 12/4/2023 220+00~232+00 WBM FDT OVERLAY OK
67 13/4/2023 232+00~244+00 WBM FDT OVERLAY OK
68 14/4/2023 244+00~253+00 WBM FDT OVERLAY FAIL
69 16/4/2023 253+00~264+00 WBM FDT OVERLAY OK
70 16/4/2023 244+00~253+00 WBM FDT OVERLAY RETEST OK
71 28/4/2023 19+68~40+00 SURFACE CLEANING OK
72 28/4/2023 19+68~40+00 PRIME COAT OK
73 29/4/2023 19+68~40+00 ASPHALT BASE COURSE OK
74 29/4/2023 40+00~73+00 SURFACE CLEANING OK
75 29/4/2023 40+00~73+00 PRIME COAT OK
76 30/4/2023 40+00~73+00 ASPHALT BASE COURSE OK
77 30/4/2023 73+00~80+00 SURFACE CLEANING OK
78 1/5/2023 73+00~80+00 PRIME COAT OK
79 2/5/2023 73+00~80+00 ASPHALT BASE COURSE OK
80 3/5/2023 73+00~80+00 SURFACE CLEANING OK
81 3/5/2023 73+00~80+00 PRIME COAT OK
82 3/5/2023 73+00~80+00 ASPHALT BASE COURSE OK
83 4/5/023 102+00~124+00 SURFACE CLEANING OK
84 04/5/023 102+00~124+00 PRIME COAT OK
85 04/5/023 102+00~124+00 ASPHALT BASE COURSE OK
86 5/5/2023 124+00~152+00 SURFACE CLEANING OK
87 5/5/2023 124+00~152+00 PRIME COAT OK
88 5/5/2023 124+00~152+00 ASPHALT BASE COURSE OK
89 6/5/2023 152+00~179+00 SURFACE CLEANING OK
90 6/5/2023 152+00~179+00 PRIME COAT OK
91 6/5/2023 152+00~179+00 ASPHALT BASE COURSE OK
92 7/5/2023 179+00~205+00 SURFACE CLEANING OK
93 7/5/2023 179+00~205+00 PRIME COAT OK
94 7/5/2023 179+00~205+00 ASPHALT BASE COURSE OK
95 8/5/2023 205+00~225+00 SURFACE CLEANING OK
96 8/5/2023 205+00~225+00 PRIME COAT OK
97 8/5/2023 205+00~225+00 ASPHALT BASE COURSE OK
98 10/5/2023 225+00~248+50 SURFACE CLEANING OK
99 10/5/2023 225+00~248+50 PRIME COAT OK
100 10/5/2023 225+00~248+50 ASPHALT BASE COURSE OK
101 10/5/2023 264+00~305+00 dismantling edging OK
102 12/5/2023 264+00~305+00 providing edging OK
103 12/5/2023 264+00~276+00 WBM FDT OVERLAY OK
104 12/5/2023 276+00~288+00 WBM FDT OVERLAY OK
105 13/5/2023 288+00~294+00 WBM FDT OVERLAY FAIL
106 14/5/2023 294+00~305+00 WBM FDT OVERLAY OK
107 14/5/2023 288+00~294+00 WBM FDT OVERLAY RETEST OK