PC-I,
JICA PROJECT
1 Name of Project UPGRADING OF MECHANICAL SYSTEM
FOR SEWERAGE AND DRAINAGE
SERVICES IN GUJRANWALA.
2 Location: Gujranwala is located at 63Km from
Provincial Capital Lahore at G.T Road
towards Federal Capital Islamabad.
i Name of District / Province Gujranwala, Punjab
ii Attach a map of the area, clearly Map of the area indicating the location is
indicating the project location. attached.
4 a) Plan Provision
Total Block Amount already Amount proposed for this Balance available
Provision committed Project
Not Applicable
iv. Provide technical parameters and The de-silting process of sewers and
discuss technology aspect of the drains is needs to be fully mechanized.
project The sludge suction and jetting
machines, traction type dewatering
pumps and other relevant equipment are
included in the project. With the use of
such machinery, the operational
performance of sanitation services will
be developed. The jetting and suction
technology is the latest and only
mechanical way to operate the
sewerage and drainage system.
v. Provide the detail of civil works, The component of the project are as
equipment, machinery and other given below:
physical facilities required for the Water Jet Cleaners
project. Suction Machines
Wheel type clamshell
Wheel type excavators
Winch Machines
Dump Trucks
Pickup trucks
Dewatering pumps
Safety Equipment
Drainage Pumps (Annex-H)
Generators (Annex-H)
vi. Indicate Governance issues of the The Govt. of the Punjab may ensure
sectors relevant to the projector provision of funds according to the
and strategy to resolve them. approved financial phasing.
vii. Indicate whether the proposed The proposed project is the upgrading, it
project is part of Master Plan, if is not provided in the Master Plan
so, provide detail. conducted during 2010. However, after
upgrading of Master Plan, it will become
a part.
Water Supply and Sewerage
i. Present and projected population Not Applicable
and water availability / demand.
ii. Indicate source and water Not Applicable
availability (mgd) during next 5,
10, 20 years.
iii. For wastewater / sewerage, Depletion of capacity of disposal
provide present and future stations, sewerage and drainage
disposal requirements, gap if any network will be overcome through
and proposed treatment methods project.
and capacity.
iv. Indicate present and proposed Not Applicable
per capita water supply in the
project area, comparison be
made with water supply in similar
localities.
v. Indicate whether the proposed The proposed project is the upgrading, it
project is a part of the Master is not provided in the Master Plan
Plan, if so, provide detail. conducted during 2010. However, after
upgrading of Master Plan, it will become
a part.
7 Capital Cost Estimates:
i. Indicate date of estimation of the February, 2014
project
ii. Basis of determining the capital The rates of JICA components are
cost be provided. It includes provided by JICA while the rates for
market survey, schedule rates, Pakistani components are based on
estimation on the basis of MRS as notified by the Govt. of the
previous work done etc. Punjab. For non MRS items, prevailing
market rates have been adopted.
iii. Provide year wise estimates of
physical activities by main
components
b) Project Analysis:
i Quantifiable output of the project As under
ii Unit Cost Analysis As under
Sub-Total 1012.395
Sub-Total 14.771
Total 1027.166
The Govt. of the Japan is expected a Grant Aid of JPY 1210 million to provide
equipment / machinery for upgrading of Sewerage and Drainage System in Gujranwala.
The allocation of funds is not involved in the purchase of such machinery. From
Pakistan side an amount of Rs. 16.100 Million will be provided by the Govt. of Punjab.
Tangible benefits
1. WASA shall minimize the work charge staff and save finances which otherwise is
spent on their wages, as the machinery shall be a replacement of most of the
manual labor.
2. The new machinery is expected to shake off the load from old ones, which at
present demand finance maintenance.
3. The old machinery shall be given a breather to get overhauled with genuine
parts, which shall work for longer period of time and thus save on frequent
breakdown and finances.
4. Choking of sewers and their overflowing result in inundation and consequent
damaging of roads. By deploying new machinery, the situation can be redressed
immediately resulting in saving road damage and its repair cost.
5. Less choking of sewers augments less cost on repair, replacement and their
renovations.
6. By means of new and efficient machinery, the digging out silt from drains has two
pronged benefits. The maintenance of undisturbed gravity flow and the retrieval
of site.
7. A lot of precious man hours are lost in case of machinery breakdown, which is
presently a common experienced. The idling time of operators and labor shall be
curtailed, as their duties shall be shifted over to the new and working machinery.
8. There shall be less POL consumption in proportion to the efficiency of the new
machinery.
9. In the absence of sewer cleaning equipment, the unhygienic conditions of the city
result in many epidemic diseases like cholera, typhoid, malaria and hepatitis. The
lesser the people getting sick, the lesser the burden on Govt. finances for
providing medicines and hospital facilities.
Intangible benefits