Professional Documents
Culture Documents
Precast Box Culvert Methodology
Precast Box Culvert Methodology
CLIENT
SUPERVISION CONSULTANT
CONTRACTOR:
Page 1 of 8
TABLE OF CONTENTS
S. No. Description of Title Page No.
1.0 Purpose 3
2.0 Scope 3
3.0 Definitions 3
4.0 Code References 3
5.0 Responsibilities 4
6.0 Details of Plant, Equipment and 5
Machinery
7.0 Material 5-6
7.1 Reinforcement steel
7.2 Cement
7.3 Course Aggregate
7.4 Fine aggregate
7.5 Others Material
8.0 Segment Constructions 6-8
Methodology
9.0 Segment Inspections & Testing 8
Process.
10.0 Segment Documentation 8
Requirements:
11.0 Segment Safety & Environmental 8
Requirements:
WORK METHODOLOGY
For (Precast) Box Culvert
1.0 PURPOSE:
The purpose of this Segment Quality Plan for Box Culvert is to provide
details of the Construction Methodology, Quality Control System,
Procedures and Safety & Environment Management Plans to be adopted
by BSCPL INFRASTRUCTURE LIMITED.
Page 2 of 8
3.0 DEFINITIONS:
The words like contract, Contractor, Engineer, Drawing, Employer,
Government, Works, Worksite used in this Work Methodology shall be
considered to have the same meaning as understood from the definitions
of these terms given in the General conditions of the contract.
5.0 RESPONSIBILITIES:
Page 3 of 8
7.0 Materials:
7.1. Reinforcement Steel
The Reinforcement Steel (HYSD-Fe 500 Grade) shall be procured from
manufacturers directly. The Reinforcement bars shall be subject to all
necessary tests. The bars shall be procured and stacked in central stack
yard. The stacking shall be done in such a way that bars do not come in
contact with soil.
7.2 Cement
Page 4 of 8
a. The Fine Aggregate shall consist of clean, hard, strong and durable pieces
o crushed stone or natural sand from river bed. It shall be tested for
Fineness Modulus, Silt Content, etc.before using in the works.
8.2 Well before proposed start for RCC works, Mix Design for M-30 grades
of concrete to be used in works shall be conducted in Field Laboratory
as per approved Technical Specifications. The Mix Design shall be
conducted in the presence of Consultant/Client’s representatives. The
Design Mix results shall be submitted to Consultant for approval.
8.3 Bar Bending schedule shall be prepared for each Segment structure and
reinforcement, steel shall be cut bent at centralized reinforcement yard
and shall conform to the dimensions and shapes as given in the approved
Bar Bending schedules.
8.4 The bars shall be placed in accordance with the drawings and cross bars
shall be tied together with binding wires at every intersection.
8.5 Appropriate cover between the formwork and bars shall be provided as
per the requirement by placing cover blocks. Necessary spacer bars,
chairs, etc shall be provided to fix the reinforcement firmly to its correct
position.
8.7 The Form work shall be made of Structural Steel with standardized plates
& other formworks. The scaffolding material shall be of standard in
nature and shall be of MS pipes, jacks etc.
8.8 Placement of shuttering shall be done manually or with help of crane and
care shall be taken that there are no weak joints from where the concrete
slurry can leak.
8.13 The production of concrete shall be done with Concrete Batching and
Mixing plant of 30 cum/hour and shall be transported though transit
mixers and placed at the casting yard work site.
All the Inspection and Testing requirements for various activities in the
present segment will be carried out as per relevant NHAI Specification &
Article-11 of Contract Agreement.
Page 8 of 8