Professional Documents
Culture Documents
Financial Energy Training
Financial Energy Training
❑The shorter the payback period, the more attractive the project
becomes. The length of the maximum permissible payback period is a
matter of company choice or established policy.
The cost of a new heat exchanger is N 150,000. What is the simple payback period
(SPP) in years considering annual savings of N 60,000 and annual maintenance cost
of N10,000?
Limitations:
• The payback period does not consider savings that are accrued after the
payback period has finished.
• Simple payback period does not consider the time value of money i.e.
money which is invested would accrue interest as time passes.
❑ ROI expresses the "annual return" expected from a project as a percentage of capital
cost or initial investment. ROI is an inverse of payback period.
❑ ROI must always be higher than cost of money (interest rate) so as to make the
project attractive; the greater the return on investment better is the investment.
Example
An outlay of N100,000 for equipment is expected to provide an after-tax cash flow of
N25,000 over a period of six years, without significant annual fluctuations. What is
the return on investment?
ROI = N25,000/N100,000 X 100 = 25%
❑ A dollar in hand today is more valuable than one to be received at some time in
the future. Money today is very valuable and future money is less valuable.
❑ Time value must be placed on all cash flows into and out of the company.
Present Value (PV)—the current value or principal amount.
Future Value (FV)—the future value of a current investment.
Annuity (A) - fixed payments at the end of a specified period
Interest/Discount Rate (i)—It is the expected rate of return from an alternative
investment. Interest rate (rate applied to PV to determine its FV) & Discount rate
(rate applied to determine PV of a future cash flow)
Term of Investment (N)—the number of years the investment is held.
Formula: FV = NPV (1 + i)n or NPV = FV / (1+i) n
❑ The net present value method considers the time value of money. This is done by
equating future cash flow to its current value today. The present value uses discount
rate.
❑ NPV may be defined as the difference between the total present value of the cash
inflows and the total present value of the cash outflows.
❑ NPV compares the value of the investment today versus the value of that same
investment in the future, after taking inflation and returns into account.
• If the NPV of a prospective project is positive then it should be accepted (i.e. NPV > 0)
• if the NPV of a prospective project is negative, then the project should be rejected
because cash flows are negative (i.e. NPV < 0)
• If the NPV of a prospective project is zero then it should probably be rejected as it
generates exactly the return that is expected (i.e. NPV = 0)
EXAMPLE
A lighting retrofit project cost N200,000 and the estimated Energy Cost Savings are N40,000
per year. The estimated life of lighting equipment 10 years and the discount factor is 10%.
Calculate the NPV?
SOLUTION
❑ The IRR will assist in determining and comparing with the rates you could earn by
investing your money in other projects or options.
❑ If the IRR is less than the cost of borrowing used to fund the project, investment is
not sound.
❑ IRR method is designed to assess whether or not a single project will achieve a
target rate of return.
Use interpolation method, to calculate the IRR using formula or graphical method
❑If this price is lower than the existing energy costs, the investment
should be made.
Where:
•Initial cost of investment expenditures (I)
•Maintenance and operations expenditures (M)
•Fuel expenditures (if applicable) (F)
•The sum of all electricity generated (E)
•The discount rate of the project (r)
•The life of the system (n)
Others include:
•Leasing / Renting
•Vendor Financing
•ESCO Financing
•Factoring / Forfeiting
1. Shared savings in which savings are shared between client and the ESCO at
an agreed percentage over an agreed duration. In this model, the ESCO finances
the cost of equipment (capital expenditure) through equity (own funds) or debt.
2. Guaranteed savings in which the ESCO assumes the project risk though
capital expenditure is borne by the client. Here, the ESCO guarantees the
quantum of energy and savings to be made. In the event of not meeting agreed
figures, the ESCO makes up for the difference.
3. Lease rental in which the ESCO is responsible for capital expenditure. The
client makes regular payments to cover capital expenditure and interest based on
verifiable energy and cost savings made. Usually at the end of the lease period,
ownership is transferred to the client.