Project N Project MaProject StaTask NamePlanned StPlanned FiPlanned DuPercent CoPerson Linked Fro

Buying of aMalefane TOpen Allocation ### ### 9 days 0


WATERMELMalefane TOpen Buying of a 9/4/2023 9/7/2023 4 days 0
WATERMELMalefane TOpen Change of 9/8/2023 9/8/2023 1 day 0
WATERMELMalefane TOpen Setting Up ### ### 4 days 0
WATERMELMalefane TOpen Soil Prepar 9/1/2023 9/7/2023 5 days 0
WATERMELMalefane TOpen Buying Manu ### ### 1 day 0
WATERMELMalefane TOpen Hiring or L 9/7/2023 ### 8 days 0
WATERMELMalefane TOpen Irrigation ### ### 16 days 0
WATERMELMalefane TOpen Routine Pla ### ### 30 days 0
WATERMELMalefane TOpen De-Weeding ### ### 7 days 0
WATERMELMalefane TOpen Hiring of B ### ### 14 days 0
WATERMELMalefane TOpen Mounting a ### ### 3 days 0
WATERMELMalefane TOpen Hiring of S ### ### 30 days 0
WATERMELMalefane TOpen Harvesting ### ### 40 days 0
WATERMELMalefane TOpen Banking of ### 3/8/2024 7 days 0
Actual CosActual ResPriority WBS
### Critical 1
### Critical 2
Very High 3
Critical 4
Critical 5
Very High 6
Critical 7
Very High 8
Very High 9
High 10
Medium 11
Medium 12
Medium 13
Critical 14
Low 15