Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

CHECK LIST REINFORCEMENT WORKS - PRE, DURING & POST CHECK

Company Godrej Properties Project Nurture


Tower Floor Ground Floor
Unit(s) Activity REINFORCEMENT WORKS
- PRE, DURING & POST
CHECK
WIR Created By WIR Status
WIR Created Date WIR Closed Date
Contractor Nurture- Adiraj Enterprises Phase Hardscape

TASKS HISTORY

SI # Location Task applicant Status Scheduled Date Closed Date


1 REINFORCEMENT WORKS
- PRE, DURING & POST
CHECK

SI # Checkpoint Client Comments Contractor Comments Last Status Photos


1 Name, date and number of the GFC drawing
2 Is the area prepared for starting reinforcement
(shuttering complete, cleaned, oiled, taped &
required safety measures has been taken)
3 Aproved bar bending schedule available and the area
to be reinforced compatible with the approved
drawings?
4 Are the required tools available at site to ensure
correct work?
5 Is the reinforcement stacked on wooden runners and
free from oil, mud, grease and other forms of
contamination?
6 Is the overlapping of rebar for correct length and the
laps are staggered?
7 Are the development length provided for
Beams/Columns as per drawing/BBS?
8 Are the dowels for columns, beams and slabs in
place checked for proper length as per the bar
bending plan or schedule?
9 Are the required hooks fixed and is the chainheight
or the upper layer of reinforcement correct? Can
the chair support the construction load without
displacement of rebar?
10 Is the reinforcement done as per specification and
drawing [numbers, spacing, shape]?(Tolerance
10mm for effective depth 200mm &15mm for depth
above 200mm)
11 Are cover blocks provided and fixed as per
specifications,have beam and column joints
checked for sufficient cover bIocks?(Tolerance to
Cover+5mm)
12 Is the rebar assembly well tied and able to take
construction loads & forces?
13 Is the binding wire of correct size 16 to 22 gauge
black annealed steel wire used? Are the ends of the
binding wire turned away from the surface?
14 Has the consultant inspected the reinforcement
before the concreting has started?
15 Check for support system for reinforcement
works as per technical specification
requirements
16 Check the top level of the reinforcement (
excluding cover ) as per approved GFC drawing

Adiraj Enterprises FABS Godrej Properties


Contractor Representative MEP Representative Client Representative

You might also like