PCC Works -Post Checks

Company Godrej Properties Project Nurture


Tower Floor Ground Floor
Unit(s) Activity PCC Works -Post Checks
WIR Created By WIR Status
WIR Created Date WIR Closed Date
Contractor Nurture- Adiraj Enterprises Phase Hardscape

TASKS HISTORY

SI # Location Task Applicant Status Scheduled Date Closed Date


1 PCC Works -Post Checks

SI # Checkpoint Client Comments Contractor Comments Last Status Photos


1 Check after concreting pouring, ensure the surface
of PCC is finished as per requirements.
2 Check Curing must be done using the hessian cloth
/ ponding for 10 Days

Adiraj Enterprises FABS Godrej Properties


Contractor Representative MEP Representative Client Representative