Mazari Technical Works LLC

Fairway 139 Villa + 140 Villa , Dubai Period Highlight: 1 Plan Actual % Complete Actual (beyond plan)

PLAN PLAN ACTUAL ACTUAL PERCENT

ACTIVITY START DURATION START DURATION COMPLETE PERIODS

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Site Mobilization, CAR insurance, Tools, 1 2 1 2 0%


Material & Scaffolding delivery

Demolition of inter-tenancy partition walls, 3 15 3 15 0%


Corridor protection and carting away debris
Removal of existing DB, ONT, IFU and roll up
armored cable and fiber optic cable to soffit 4 3 4 3 0%
slab

SMDB Installation Works 5 5 5 5 0%

CT Meter Installation Works 5 5 5 5 0%

Armored cable installation, glanding and 5 10 5 10 0%


termination 150mm, 4C & 70mm, 1C

Modification of existing SMDB-RT1 6 3 6 3 0%

Reinstatement of existing wall and ceiling 15 5 15 5 0%


finishes as per site requirement

Testing and Commissioning Works 15 3 15 3 0%

Trakhees, DCD and Dewa drawings approvals


and final site inspections
1 25 1 25 0%

Project Handover 25 2 25 2 0%