TAKE OF SHEET

Desa : Mekarsari Bidang : PEMBANGUNAN DESA


Kecamatan : Cimerak Kegiatan : TPT & Gorong-gorog jembatan cikijing girang
Kabupaten : Pangandaran Lokasi : Dusun Citelu RT 03 RW 02
Provinsi : Jawa Barat Volume : Gorong-gorong =8 x 3 m, TPT=16 x 1,5 m

A. PEKERJAAN GORONG-GORONG

1. Pekerjaan galian tanah (1.7.1.a - hal. 183)

Volume = P x L x T
= 3.00 x 0.60 x 0.80
= 1.44 m3
Total volume = 1.44 x 5.00 unit
= 7.20 m3

Kebutuhan upah Vol x Koef


Pekerja = 7.2 x 0.7500 = 5.40 HOK
Mandor = 7.2 x 0.0250 = 0.18 HOK

2. Pekerjaan pasangan batu belah (2.1.2.a.3.b.(c) hal. 249)


0.50
Volume = P x L x T
= 3.00 x 0.50 x 2.32 x 2.32
= 3.48

Total volume = 3.48 x 5.00 unit


= 17.40 m3

Kebutuhan bahan dan upah Vol x Koef


Batu belah = 17.40 x 1.2000 = 20.88 m3
Pasir pasang = 17.40 x 0.5200 = 9.05 m3
Semen 40 kg/sak = 17.40 x 4.0750 = 70.91 sak
Pekerja = 17.40 x 1.5000 = 26.10 HOK
Tukang batu = 17.40 x 0.7500 = 13.05 HOK
Kepala tukang = 17.40 x 0.0750 = 1.31 HOK
Mandor = 17.40 x 0.0750 = 1.31 HOK

3. Pekerjaan plesteran (3.2.2.2.12.(c) hal. 306)

Luas = 3.00 + 1.52 + 1.52 0.50


= 6.04 m2
Total luas = 6.04 x 5.00 unit 1.52
= 30.20 m2

Kebutuhan bahan dan upah Vol x Koef


Semen 40 kg/sak = 30.20 x 0.1944 = 5.87 sak
Pasir pasang = 30.20 x 0.0230 = 0.69 m3
Pekerja = 30.20 x 0.3000 = 9.06 HOK
Tukang batu = 30.20 x 0.1500 = 4.53 HOK
Kepala tukang = 30.20 x 0.0150 = 0.45 HOK
Mandor = 30.20 x 0.0150 = 0.45 HOK

4. Pekerjaan acian (3.2.2.2.35.(a) - hal 318)

Luas = 3.00 + 1.60 + 1.60


= 6.20 m2
Total luas = 6.20 x 5.00 unit
= 31.00 m2

Kebutuhan bahan dan upah


Semen 40 kg/sak = 31.00 x 0.0813 = 2.52 sak
Pekerja = 31.00 x 0.1000 = 3.10 HOK
Tukang batu = 31.00 x 0.1000 = 3.10 HOK
Kepala tukang = 31.00 x 0.0100 = 0.31 HOK
Mandor = 31.00 x 0.0100 = 0.31 HOK

5. Pekerjaan pembesian (2.2.6.1.d.(a) Hal. 280)

Lantai memenajang
Diameter besi = 10.00 mm
Panjang besi = 8.00 m'
Jml besi memanjang = 15.00 btg
Total panjang = 120.00 m'
Berat besi per m = 0.62 kg
Total berat = 74.40 kg
Total besi = 10.00 btg
Lantai melintang
Diameter besi = 10.00 mm
Panjang besi = 3.00 m'
Jml besi melintang = 40.00 btg
Total panjang = 120.00 m'
Berat besi per m = 0.62 kg
Total berat = 74.40 kg
Total besi = 10.00 btg
Tiang sandaran
Diameter besi = 10.00 mm
Panjang besi = 4.00 m'
Jumlah batang = 20.00 btg
Total panjang = 80.00 m'
Berat besi per m = 0.62 kg
Total berat = 49.60 kg
Total besi = 6.67 btg

Total panjang besi = 320.00 x 2 = 640.00 m'


Total berat besi = 198.40 x 2 = 396.80 kg

Kebutuhan bahan dan upah


Besi D10 = 640.00 : 12 = 53.33 btg
Bendrat = 396.80 x 0.0280 = 11.11 kg
Pipa besi 3" 3mm = 2.50 x 2.0000 = 5.00 btg
Pekerja = 396.80 x 0.0160 = 6.35 HOK
Tukang besi = 396.80 x 0.0160 = 6.35 HOK
Kepala Tukang = 396.80 x 0.0016 = 0.63 HOK
Mandor = 396.80 x 0.0016 = 0.63 HOK

6. Pekerjaan bekisting (B.11.C - HAL. 632)

Volume = 8.00 x 3.00 + 4.40


= 28.40 m2
Kebutuhan bahan dan upah
Papan 2/20 = 28.40 x 0.0140 = 0.40 m3
Kaso 5/7 = 28.40 x 0.0030 = 0.09 m3
Paku 5 & 7 cm = 28.40 x 0.3000 = 8.52 kg
Minyak Bekisting = Dihilangkan karena pakai plastik
Pekerja = 28.40 0.3000 = 8.52 HOK
Tukang Kayu = 28.40 0.1500 = 4.26 HOK
Kepala Tukang = 28.40 0.0150 = 0.43 HOK
Mandor = 28.40 0.0300 = 0.85 HOK

7. Pekerjaan beton K125 (2.2.1.1.c.(c) - hal. 267)


Volume lantai = 8.00 x 3.00 x 0.20
= 4.80
Volume sandaran = 0.25 x 0.20 x 1.00
= 0.05 x 8 buah
= 0.40
Total volume = 5.20 m3
Kebutuhan bahan dan upah
Semen 40 kg/sak = 5.20 x 6.9000 = 35.88 sak
Pasir beton = 5.20 x 0.8280 = 4.31 m3
Split 2/3 = 5.20 x 1.0120 = 5.26 m3
Air (1 liter Air = 0,001 =m 5.20 x 0.2150 = 1.12 m3
Pekerja = 5.20 x 1.6500 = 8.58 HOK
Tukang Kayu = 5.20 x 0.2750 = 1.43 HOK
Kepala Tukang = 5.20 x 0.0275 = 0.14 HOK
Mandor = 5.20 x 0.1650 = 0.86 HOK

8. Angkut campuran beton (2.2.4.1.a.(a) - hal. 276)

Semen 40 kg/sak = 35.88 sak = 1.44 m3


Pasir beton = 4.31 m3 = 4.31 m3
Split 2/3 = 5.26 m3 = 5.26 m3
Air (1 liter Air = 0,001 =m 1.12 m3 = 1.12 m3
= 12.12 m3

Pekerja = 12.12 x 0.5037 = 6.11 HOK


Mandor = 12.12 0.0504 = 0.61 HOK
B. PEKERJAAN TPT

P 16.00 m
T 1.50 m
0.25

1.5

0.25

0.15 0.25

1. PEKERJAAN GALIAN TANAH BIASA (LAMP. PERMEN PUPR No. 1 2022 - Hal. 183)
Volume Galian = P x L x T
= 16 x 0.4 x 0.25
= 1.6 m³

Kebutuhan bahan dan upah


* Kebutuhan Upah : Vol x Koef
Pekerja = 1.6 x 0.75 = 1.2 HOK
Mandor = 1.6 x 0.025 = 0.04 HOK

2. PAS. BATU BELAH (LAMP. PERMEN PUPR No. 1 2022 - Hal. 248)
Volume I = P x L x T x 1/2
= 16 x 0.15 x 1.5 x 0.5
= 1.8 m³
Volume II = P x L x T
= 16 x 0.25 x 1.5
= 6 m³ I II
Volume III = P x L x T
= 16 x 0.4 x 0.25
= 1.6 m³ III

Total Volume = Vol I + Vol II + Vol III


= 1.8 + 6 + 1.6
= 9.4 m³

Kebutuhan bahan, alat dan upah


* Kebutuhan bahan : Vol x Koef
Batu Belah = 9.4 x 1.2 = 11.28 m³
Pasir Pasang = 9.4 x 0.52 = 4.888 m³
Semen 40 Kg/sak = 9.4 x 4.075 = 38.305 sak

* Kebutuhan Upah : Vol x Koef


Pekerja = 9.4 x 1.5 = 14.1 HOK
Tukang Batu = 9.4 x 0.5 = 4.7 HOK
Mandor = 9.4 x 0.15 = 1.41 HOK

3. TIMBUNAN TANAH ATAU URUGAN TANAH KEMBALI (LAMP. PERMEN PUPR No. 1 2022 - Hal. 184)
Volume = 1.8 m³

Kebutuhan bahan dan upah


* Kebutuhan Upah : Vol x Koef
Pekerja = 1.8 x 0.5 = 0.9 HOK
Mandor = 1.8 x 0.05 = 0.09 HOK
Plesteran tebal 1 cm, dengan mortar tipe N (LAMP. PERMEN PUPR No. 1 2022 - Hal. 302)
4.
Volume = P x (L + T) t = √(𝑎^2+𝑏^2
)
√(𝑎^2+𝑏^2
= 16 x 0.25 + 1.507481 = ) 1.507481343
= 28.119701 m2

Kebutuhan bahan, alat dan upah


* Kebutuhan bahan : Vol x Koef
Pasir Pasang = 28.119701 x 0.0167 = 0.4696 m³
Semen 40 Kg/sak = 28.119701 x 0.104 = 2.92445 sak

* Kebutuhan Upah : Vol x Koef


Pekerja = 28.119701 x 0.1 = 2.81197 HOK
Tukang Batu = 28.119701 x 0.1 = 2.81197 HOK
Kepala Tukang = 28.119701 x 0.01 = 0.2812 HOK
Mandor = 28.119701 x 0.01 = 0.2812 HOK

5. Pekerjaan Acian (LAMP. PERMEN PUPR No. 1 2022 - Hal. 318)


Volume = P x (L + T)
= 16 x 0.25 x 1.5
= 28 m2
Kebutuhan bahan, alat dan upah
* Kebutuhan bahan : Vol x Koef
Semen 40 Kg/sak = 28 x 0.08125 = 2.275 sak

* Kebutuhan Upah : Vol x Koef


Pekerja = 28 x 0.1 = 2.8 HOK
Tukang Batu = 28 x 0.1 = 2.8 HOK
Kepala Tukang = 28 x 0.01 = 0.28 HOK
Mandor = 28 x 0.01 = 0.28 HOK

6 PENGURUGAN DENGAN PASIR URUG (LAMP. PERMEN PUPR NOMOR 1 2022 - 1.7.2.d (c) - HAL 185)
Volume = P x L x T
= 8 x 3 x 1.5
= 36 m³

Kebutuhan bahan dan upah


* Kebutuhan bahan : Vol x Koef
Pasir Urug = 36 x 1.200 = 43.2 m³

* Kebutuhan Upah :
Pekerja = 36 x 0.300 = 10.8 HOK
Mandor = 36 x 0.010 = 0.36 HOK

C. Upah Angkut (1.7.15.1.k (a) - hal. 222)

Batu belah = 32.16 m3


Pasir = 19.41 m3
Split = 5.26 m3
Besi = 0.40 m3
Semen = 6.35 m3
Pasir urug = 43.20 m3 +
Jumlah = 106.77 m3

Kebutuhan upah
Pekerja = 106.77 x 1.3777 = 147.10 HOK
Mandor = 106.77 x 0.0688 = 7.35 HOK

REKAP BAHAN DAN UPAH


Semen 40 kg/sak = 158.68 = 159.00 sak
Batu belah = 32.16 = 32.00 m3
Pasir = 19.41 = 19.00 m3
Split = 5.26 = 5.00 m3
Papan 2/20 = 0.40 = 0.40 m3
Kaso 5/7 = 0.09 = 0.10 m3
Paku = 8.52 = 9.00 kg
Besi D10 = 53.33 = 53.00 btg
Bendrat = 11.11 = 11.00 kg
Pipa besi 3" 3mm = 5.00 = 5.00 btg
Pasir urug = 43.20 = 43.00 m3

Pekerja = 252.93 = 253.00 HOK


Tukang = 40.41 = 40.00 HOK
Kepala Tukang = 3.83 = 4.00 HOK
Mandor = 15.01 = 15.00 HOK
PEMERINTAH KABUPATEN PANGANDARAN
KECAMATAN CIMERAK
DESA MEKARSARI
Jln. Mekarsari No. 333 Desa Mekarsari Kec. Cimerak Kab. Pangandaran

RENCANA ANGGARAN BIAYA (RAB)

DESA : MEKARSARI No.RAB : 010


KECAMATAN : CIMERAK Bidang : PEMBANGUNAN DESA
KABUPATEN : PANGANDARAN Kegiatan : TPT & Gorong-gorog jembatan cikijing girang
PROVINSI : JAWA BARAT Lokasi : Dusun Citelu RT 03 RW 02
Volume : Gorong-gorong =8 x 3 m, TPT=16 x 1,5 m

HARGA SATUAN
NO URAIAN VOLUME SATUAN JUMLAH (Rp.)
(Rp.)
I BAHAN
1 Semen 40 kg/sak 159.00 sak 65,500 10,414,500
2 Batu belah 32.00 m3 305,000 9,760,000
3 Pasir 19.00 m3 305,000 5,795,000
4 Split 5.00 m3 350,000 1,750,000
5 Papan 2/20 0.40 m3 2,025,000 810,000
6 Kaso 5/7 0.10 m3 2,025,000 202,500
7 Paku 9.00 kg 29,000 261,000
8 Besi D10 53.00 btg 81,000 4,293,000
9 Bendrat 11.00 kg 29,500 324,500
10 Pipa besi 3" 3mm 5.00 btg 505,000 2,525,000
11 Pasir urug 43.00 m3 222,500 9,567,500

SUB TOTAL 1 45,703,000


II ALAT
1 Papan Proyek 1 buah 150,000 150,000
2 Ember 10 buah 13,500 135,000
3 Benang 2 buah 5,500 11,000
4 -
5 -
SUB TOTAL 2 296,000
III UPAH
1 Pekerja 253 HOK 85,000 21,505,000
2 Tukang 40 HOK 100,000 4,000,000
3 Kepala Tukang HOK 100,000 -
4 Mandor HOK 120,000 -
SUB TOTAL 3 25,505,000
IV HONOR TPK
1 Honorarium Ketua 1 OK 185,000 185,000
2 Honorarium Sekretaris 1 OK 170,000 170,000
3 Honorarium Anggota 1 OK 141,000 141,000
SUB TOTAL 4 496,000
JUMLAH TOTAL ( Rp. ) 72,000,000

Disetujui, Telah Diverifikasi Mekarsari, 30 Desember 2022


Kepala Desa Mekarsari PDTI Pelaksana Kegiatan

AAN ANDRES SATRIAJI, S.IP ___________________ MAMAN SUDIAMAN


GAMBAR RENCANA PRASARANA

Catatan : Gambar dibuat secara manual


GAMBAR RENCANA PRASARANA

Catatan : Gambar dibuat secara manual


GAMBAR RENCANA PRASARANA

PIPA
BES
I 3"
PIPA
BES
I 3"

Catatan : Gambar dibuat secara manual


ARANA

GAMBAR RENCANA

KABUPATEN
PANGANDARAN
KECAMATAN
CIMERAK
DESA
MEKARSARI
JENIS PRASARANA
PEMBANGUNAN GORONG-GORONG
LOKASI
DUSUN CITELU RT 03 RW 02
JUDUL GAMBAR
PASANGAN BATU
Digambar Oleh
Pelaksana Kegiatan
(Kader Teknik)
Diperiksa dan Disetujui oleh :
Dinas/Instansi terkait dan/atau Tenaga Profesional
(jika tersedia)

Lembar Dari Lembar


ARANA

GAMBAR RENCANA

KABUPATEN
PANGANDARAN
KECAMATAN
CIMERAK
DESA
MEKARSARI
JENIS PRASARANA
PEMBANGUNAN GORONG-GORONG
LOKASI
DUSUN CITELU RT 03 RW 02
JUDUL GAMBAR
PENULANGAN LANTAI
Digambar Oleh
Pelaksana Kegiatan
(Kader Teknik)
Diperiksa dan Disetujui oleh :
Dinas/Instansi terkait dan/atau Tenaga Profesional
(jika tersedia)

Lembar Dari Lembar


ARANA

GAMBAR RENCANA

KABUPATEN
PANGANDARAN
KECAMATAN
CIMERAK
DESA
MEKARSARI
JENIS PRASARANA
PEMBANGUNAN GORONG-GORONG
LOKASI
DUSUN CITELU RT 03 RW 02
JUDUL GAMBAR
TIANG SANDARAN
Digambar Oleh
Pelaksana Kegiatan
(Kader Teknik)
Diperiksa dan Disetujui oleh :
Dinas/Instansi terkait dan/atau Tenaga Profesional
(jika tersedia)

Lembar Dari Lembar


HASIL SURVEI HARGA BAHAN DAN ALAT
TAHUN ANGGARAN 2023

Bidang : PEMBANGUNAN DESA


Kegiatan : TPT & Gorong-gorog jembatan cikijing girang
Lokasi : Dusun Citelu RT 03 RW 02
Volume : Gorong-gorong =8 x 3 m, TPT=16 x 1,5 m

NO JENIS BAHAN/MATERIAL/ALAT SATUAN


1 Semen 40 kg/sak sak
2 Batu belah m3
3 Pasir m3
4 Split m3
5 Papan 2/20 m3
6 Kaso 5/7 m3
7 Paku kg
8 Besi D10 btg
9 Bendrat kg
10 Pipa besi 3" 3mm btg
11 Pasir urug m3
12 Papan Proyek bh
13 Ember bh
14 Benang bh

Mengetahui, Toko/Suplier
Kepala Desa Mekarsari TB. INDO BETON

AAN ANDTRES SATRIAJI, S.IP ADE IMRAN


HASIL SURVEI HARGA BAHAN DAN ALAT
TAHUN ANGGARAN 2023

Bidang : PEMBANGUNAN DESA


Kegiatan : TPT & Gorong-gorog jembatan cikijing girang
Lokasi : Dusun Citelu RT 03 RW 02
Volume : Gorong-gorong =8 x 3 m, TPT=16 x 1,5 m

NO JENIS BAHAN/MATERIAL/ALAT SATUAN


1 Semen 40 kg/sak sak
2 Batu belah m3
3 Pasir m3
4 Split m3
5 Papan 2/20 m3
6 Kaso 5/7 m3
7 Paku kg
8 Besi D10 btg
9 Bendrat kg
10 Pipa besi 3" 3mm btg
11 Pasir urug m3
12 Papan Proyek bh
13 Ember bh
14 Benang bh

Mengetahui, Toko/Suplier
Kepala Desa Mekarsari MK. AMANAH

AAN ANDTRES SATRIAJI, S.IP EPI SAPEIN


HASIL SURVEI HARGA BAHAN DAN ALAT
TAHUN ANGGARAN 2023

Bidang : PEMBANGUNAN DESA


Kegiatan : TPT & Gorong-gorog jembatan cikijing girang
Lokasi : Dusun Citelu RT 03 RW 02
Volume : Gorong-gorong =8 x 3 m, TPT=16 x 1,5 m

NO JENIS BAHAN/MATERIAL/ALAT SATUAN


1 Semen 40 kg/sak sak
2 Batu belah m3
3 Pasir m3
4 Split m3
5 Papan 2/20 m3
6 Kaso 5/7 m3
7 Paku kg
8 Besi D10 btg
9 Bendrat kg
10 Pipa besi 3" 3mm m3
11 Pasir urug btg
12 Papan Proyek bh
13 Ember bh
14 Benang bh

Mengetahui, Toko/Suplier
Kepala Desa Mekarsari TB. MAMAN

AAN ANDTRES SATRIAJI, S.IP H. MAMAN


HASIL SURVEI HARGA BAHAN DAN ALAT
TAHUN ANGGARAN 2023

Bidang : PEMBANGUNAN DESA


Kegiatan : TPT & Gorong-gorog jembatan cikijing girang
Lokasi : Dusun Citelu RT 03 RW 02
Volume : Gorong-gorong =8 x 3 m, TPT=16 x 1,5 m

NO JENIS BAHAN/MATERIAL/ALAT SATUAN


1 Semen 40 kg/sak sak
2 Batu belah m3
3 Pasir m3
4 Split m3
5 Papan 2/20 m3
6 Kaso 5/7 m3
7 Paku kg
8 Besi D10 btg
9 Bendrat kg
10 Pipa besi 3" 3mm btg
11 Pasir urug
12 Papan Proyek bh
13 Ember bh
14 Benang bh

Mengetahui,
Pj. Kepala Desa Mekarsari

UTIS SUTISNA, S.Kep., Ners


NIP. 19870427 201001 1 002
N ALAT

embatan cikijing girang

3 m, TPT=16 x 1,5 m

HARGA SATUAN SAMPAI DI


LOKASI KEGIATAN (RP)
65,000
300,000
300,000
345,000
2,000,000
2,000,000
28,000
80,000
29,000
500,000
220,000
150,000
13,000
5,000

Mekarsari, 14 Desember 2022


Disurvey Oleh

MAMAN SUDIAMAN
N ALAT

embatan cikijing girang

3 m, TPT=16 x 1,5 m

HARGA SATUAN SAMPAI DI


LOKASI KEGIATAN (RP)
65,500
305,000
305,000
350,000
2,025,000
2,025,000
29,000
81,000
29,500
505,000
222,500
150,000
13,500
5,500

Mekarsari, 14 Desember 2022


Disurvey Oleh

MAMAN SUDIAMAN
N ALAT

embatan cikijing girang

3 m, TPT=16 x 1,5 m

HARGA SATUAN SAMPAI DI


LOKASI KEGIATAN (RP)
66,000
310,000
310,000
355,000
2,050,000
2,050,000
30,000
82,000
30,000
510,000
225,000
150,000
14,000
6,000

Mekarsari, 14 Desember 2022


Disurvey Oleh

MAMAN SUDIAMAN
N ALAT

embatan cikijing girang

3 m, TPT=16 x 1,5 m

HARGA SATUAN SAMPAI DI


LOKASI KEGIATAN (RP)
65,500
305,000
305,000
350,000
2,025,000
2,025,000
29,000
81,000
29,500
505,000
222,500
150,000
13,500
5,500

Mekarsari, 2 September 2022


Pelaksana Kegiatan Anggaran

MAMAN SUDIAMAN