Professional Documents
Culture Documents
Part 2 - Sec 1.6.3 - 11 2010 K G RPT 2210 - Final
Part 2 - Sec 1.6.3 - 11 2010 K G RPT 2210 - Final
PART–2 : SECTION–1
(Part-2_Sec-1.6.3_11-2010-K-G-RPT-2210_Final.doc)
2x600 MW Long Phu 1 Technical Design Document
INDEX
1.00.00 INTRODUCTION
ANNEXURE
DRAWINGS
(Part-2_Sec-1.6.3_11-2010-K-G-RPT-2210_Final.doc)
2x600 MW Long Phu 1 Technical Design Document
1.00.00 INTRODUCTION
Long Phu, Phase-I project shall have two (2) units of 600 MW. It is also
envisaged to add another set of two (2) units of 600 MW each in Phase II and
finally, another set of two (2) units of 1000 MW each in Phase III. The station
shall ultimately consist of 6 units of total capacity of 4400 MW. This Design
Basis Report attempts to finalise the layout and various parameters of coal
handling plant required for Phase-I of the thermal power project.
Coal for the plant shall be received from 10000 DWT ship on the Ports in Hau
River located adjacent to Long Phu 1 power plant.
The system boundary shall start from the unloading of coal port upto the coal
bunker inlet of the boiler. This includes unloading, crushing, stacking at the
coal-yard & reclaiming from the yard and bunker filling. The ship link from
main source of coal however is not included in this report.
The system components of the coal handling plant are as mentioned in brief
below. Details of these items are discussed in subsequent clauses.
The various details of coal port is outside the scope of this Design Basis
Report (DBR). However, it has been considered that the coal port shall have
arrangement for handling the vessels of capacity maximum upto 10000 DWT.
The ship un-loaders which will unload the ship and feed the belt conveyors
are under the scope of this DBR.
These shall be used to carry and convey the coal from unloading points to the
various storage points or feed to crusher, coal bunker etc.
3.04.00 Crusher
Stacker Reclaimer are provided to stack the crushed coal as received from
Crusher House when coal is not conveyed for bunker feeding. Subsequently,
this stacker-cum-reclaimer shall be used to transfer the stacked crushed coal
to the boiler bunker as and when required.
Travelling trippers are provided on the top of the coal bunker to fill the
bunkers evenly along the length upto the desired level.
These shall be used to remove any magnetic/ferrous metal from the coal in
order to guard the crusher/pulveriser from damage.
3.08.00 Chutes & Hoppers
These shall be provided at various transfer points for transfer of coal from one
conveyor/equipment to the other conveyor/equipment.
3.09.00 Metal Detectors
These are needed to prevent fugitive coal dust flying out so as to maintain
clean environment in the vicinity.
3.11.00 Auxiliaries
The following data have been considered for the Power plant of capacity
2x600 mw units to arrive at coal requirement figure.
Long Phu 1
power plant
537.68 T/h 12904.38 T/day 4003582.57 T/year
(2x600MW)
The whole
power
- - 14679803 T/year
complex
Note: The coal consumption rates indicated above are as per the coal analysis for the
project is finalized. CHP has been designed based on design coal data as stated Rev-C
above.
Coal to Boiler Bunker (from thermal power station requirement point of view)
a. Coal requirement by boilers per hour for 2 units working : 537.7 TPH.
d. Average related capacity of CHP System, considering : 1075 x 1.15 =1236 TPH.
15% margin
b. Working day for coal unloading from Vessel : 365x0.8 = 292 days.
b. Ship un-loader capacity & number may be selected from any one of following 4
options :
It has been envisaged that fines in the coal will be controlled from mines as
per requirement. However, it is true that some dust will be generated in coal
unloading area especially when Grab Type unloader is unloading coal in a
hopper. Chain Bucket type unloader is a closed system which will generate
less dust nuisance but will have higher cost. Further, utilisation of this system
effectively for unloading of coal from vessel of 10,000 DWT is also available
for the purpose coal unloading to suit plant requirement.
Considering the fact that dust nuisance shall be limited during unloading of
coal, the use of continuous chain bucket type unloader will be a better choice
though it is relatively costly. In view of this, we recommend continuous chain
bucket type unloader.
Conclusion:
Coal Pile 2 Nos. : Covered storage yard for 15 days and open storage yard
for 15 days.
Coal yard machine : 2 nos. Reversible type Stacker / Reclaimer Machine, both
will work under covered yard as well as on open coal yard.
Stacking Capacity to suit capacity of ship un-loader
(1700TPH), average Reclaiming Capacity 1700 TPH.
Bunker Feeding Machine : 2 Nos. Motorised Traveller Tripper with 3 way/2 way coal
discharging facility to suit the available space on bunker
floor.
Coal Conveying System : Conveyor belt in covered & un-covered gallery as per
system requirement capacity.
Coal Receiving equipment : Continuous Chan Bucket type ship un-loader. 2 nos. (850
from Vessel TPH).
Coal Unloading from Vessel : Rail mounted Continuous Chan Bucket type ship un-
loader complete with travelling hopper & vibrating feeder.
4.03.01 Coal for the thermal power station is envisaged to be received by 10000 DWT
vessel only and unloading shall be done on set of conveyors through hopper
at jetty dedicated for coal.
Coal from 10000 DWT Vessel shall be unloaded in belt conveyor by means of
ship un-loaders from where coal shall be carried to the boiler bunker through
crusher house & different transfer houses. Provision has been kept for
stacking crushed coal in coal stockyard from where coal shall be reclaimed as
and when the same shall be required in coal bunkers. In this respect, Dwg
No. 11/2010-K-M-DWG-2119 for Layout and Dwg No. 11/2010-K-M-DWG-
2036 for Flow Diagram of Coal Handling Plant shall be referred to.
1) The proposed layout has been made for coal unloading by Continuous
Chain bucket type ship un-loader.
2) The proposed layout has been developed in the specified area for the
plants.
First and topmost priority of the coal handling plant is to evacuate coal from
the ship when the same is available at port at any time in a day.
Considering two (2) units operation at 85% PLF & with average quality coal,
this quantity is thirty (30) days consumption of coal approximately.
Half of coal piles formed by both the machines, for storage of fifteen days,
shall be covered by structural shed with sufficient clearance so that Stacker-
Reclaimer machines shall be able to travel inside the shed.
There will be a 12 meter high wind shield fence beside coal pile on the Power
Plant side to arrest coal dust to move through wind towards Power house.
Since half of the pile length is covered by shed, the fence have considered on
the rest part of the pile which is uncovered.
Type of Machine : Orientation of the coal pile with respect to the direction of
coal flow from unloading point to Bunker suggests that reversible type
Stacker-Cum-Reclaimer would be the economical choice.
Reversible type rail mounted Stacker/ Reclaimer machine with tripper car and
Reversible Boom Conveyor on Turn table have considered for this Plant.
While comparing with the other machines like belt stacker or portal scraper
reclaimer such high capacity pile within the available land is not
recommended. In addition to that following points are being highlighted:-
1. By using belt stacker & portal scraper reclaimer space for installation of Rev-C
two machines is more compare to single stacker-cum-reclaimer.
For filling the Bunkers conventionally two methods are employed (a)
Travelling Tripper with side discharge chutes, (b) Reversible Shuttle
Conveyor System. Out of the two, it is proposed to provide 2x100%
Travelling Trippers with twin discharge chute on two sides from the following
considerations:
a) Travelling Trippers with twin discharge chutes gives best fill pattern in
bunker. In addition self discharge chutes with travelling tripper will be
provided for the system requirement. Hence travelling trippers with
triplet discharge chutes have been considered.
d) Bunker filling with reversible shuttle feeder invite more dust generation
in the Bunker Floor.
b) Space provision for maintenance and road beside jetty has been
considered.
d) Availability of land.
a) RCC potable water tank and RCC service water tank shall be located
near crusher house.
b) The air compressors for the DE system in Crusher House and Boiler
Bunker adjustment to the respective DE Units.
Rev-C
Conveyor
In general for bunker feeding 2x100% system has been adopted for
Conveyors considering standard practice. However, in case of emergency,
both streams can run simultaneously. Electrical design shall be so as to take
care of simultaneous two (2) streams operation. For building of stock pile &
receiving coal from stockpile, 2x100% conveyor system with 2 nos. of stacker
reclaimer machine, have been adopted.
Ship Unloader
In the jetty, on each of the two (2) parallel receiving conveyors, two (2) nos.
Ship Un-loader (2 x 50%) common for each conveyor have been provided.
Ring Granulator type Crushers shall be used for crushing coal from (-) 50 mm
to (-) 20 mm. Ring Granulator type Crusher gives much less fines compared
to that of Hammer Crusher. Replacements of Rings are also a simple job.
Type of screen has been considered as Grizzly type in order to reduce the
jamming problem with wet coal, particularly in monsoon period.
Provision of two (2) Nos. Stacker Cum Reclaimer (Reversible type) have
been proposed along with associated Boom, which shall reclaim coal from
crushed coal stock-pile and shall discharge on to trunk conveyor for carrying
coal for Boiler Bunkers.
Travelling Tripper
Air Compressor
The Coal Handling Plant is inherently a dusty place and a highly polluted
zone. Suitable ventilation and dust control systems are to be provided at
various places to minimize hazards due to such pollution. Dust suppression &
dust extraction would be used to handle the dust generated in the system. To
the extent possible, minimum water would be used for the purpose.
(b) Natural ventilation for crusher floor of crusher house, over ground
portions of transfer points.
(d) Air cooled Precision type air conditioner (with one stand-by module)
for control room of CHP main control building and Split type air
conditioners (with 100% stand-by units) for other control rooms.
The dust extraction systems shall be provided at the boiler bunker area and
the crusher house. The DE systems envisaged is dry type with the captured
dust being fed back to the system.
Plain water dust suppression system shall be used for crushed coal stock pile
and receiving points at coal jetty.
Dry fog type dust suppression system shall be provided for all other transfer
points.
Dust suppression with plain water shall be done at crushed coal stock piles
and receiving points at coal jetty.
Dry fog system shall be used in all other areas except above areas and areas
covered under DE system.
4.12.01 Ventilation systems shall be provided for electrical rooms. Natural ventilation
shall be provided to all over ground buildings through open able windows or
louvres. Continuous opening in conveyor gallery of the order of 500mm at the
top shall be provided for ventilation as well as natural light. In Shed,
continuous opening shall be provided for the same purpose.
All rooms for electrical items, viz. MCC/Switchgear Rooms shall have dry
type pressurised ventilation system by providing Fan–Filter Units for air
supply and back draft dampers for air exhaust to maintain dust free
environment inside these rooms. A minimum air change rate of 15 per hour
shall be maintained. Electric Fuse link type fire dampers shall be incorporated
with the Fan-Filter units supplying air to the electrical rooms.
For underground Tunnels, if any, fresh filtered air shall be supplied by means
of Fan–filter unit/s (located overground) through ducting and supply air grilles
and the air will be exhausted through wall mounted exhaust fans (located on
the pent house wall ) and short ducting. A minimum air change rate of 10 per
hour shall be maintained inside the tunnels.
Service water network throughout the entire Coal Handling Plant shall be fed
by 2x100% Dust Suppression Pumps. The service water shall be used for
floor washing cleaning, etc. One (1) service water tapping point shall be
provided at each RCC floor of Transfer Points and Crusher House.
Additionally Service Water tapping points shall be provided throughout the
conveyor gallery/tunnel at maximum span of 30.0 meters. Consumption of
service water per outlet for floor washing shall be considered as 3 Cu.m/Hr
and assuming maximum six points operating simultaneously in the entire
CHP for design purposes, the service water system shall be designed.
Like service water, potable water shall also be pumped from the storage tank
beside pump house. Water shall be pumped to tank located at suitable
altitude (preferably on roof of each building) to distribute water at all CHP
Buildings. Water shall be distributed by gravity to all buildings and Control
Rooms from the over head tank.
Service water disposal throughout the entire Coal Handling Plant shall be
collected in pit at suitable location. 2x100% disposal pumps shall be used for
disposing the water from the pit.
5.01.00 The Electrical Power Distribution system is envisaged at 3.0kV & 400V, 3-
phase; and 230V, 1-phase, voltage levels for supplying power to the drives
and other electrical equipment/system of the CHP to ensure smooth operation
of the plant and to maintain the operating parameters of various equipment/
devices within allowable limits. Suitable sequence controlling facilities are
provided in the Control room of Main CHP Substation Building near Crusher
House for proper control of the entire CHP including Electrical System
Operation in addition to the process.
5.02.00 CHP drives are scattered over a large area. Power supply to the drives/
equipments above 160 KW including distribution transformers will be derived
from two (2) Nos. 3.0 KV Switchgears to be located at the Main CHP
Substation cum Control Room Building near Crusher House. Each of these
Switchgears will be fed through 2 X 100 % rated feeders from 3.0 kV Station
Switchgears located in Power House building. 3.0 kV power supply from
these 3.0 KV Switchgears will be distributed to various 3.0 kV motors (except
bunker area including TP-4) and to Stacker/Reclaimer through central land
mounted junction box, flexible trailing cable with cable reeling drum,
transformer along with machine electrical of mobile equipment.
5.03.00 All LT loads from Crusher House up to TP-4 will receive power from one (1)
no. 400V Power Cum Motor Control Centre (PMCC) installed in Main CHP
Substation Building. This PMCC will receive power from 3.0 KV Switchgear -1
via 2 X 100 percent of suitably rated LT Auxiliary Distribution Transformers
5.04.00 One (1) no. 3.0 KV Switchgear located at TP-4 near bunker area will cater to
all HT Drives in the vicinity of Bunker floor including TP-4. This Switchgear
will be fed through 2 X 100 % rated feeders from 3.0 kV Station Switchgear
located in Power House building. One (1) no. 400V Power Cum Motor Control
Center (PMCC) located in TP-4 near bunker area will cater to CHP LT loads
adjacent to Bunker area including TP-4. Illumination of above building
including the associated areas except bunker floor shall also be catered from
this PMCC. This PMCC will receive power from two (2) nos. 100% rating
3.0/0.420 KV LT Dry Type Auxiliary transformers through non-segregated
phase bus-duct. These transformers will receive power from aforesaid 3.0 KV
Switchgear at TP-4.
5.05.00 220 V DC supply required at Main CHP Sub-station Building near Crusher
House shall be obtained through (1) no. 100% rating 220 V Battery & Battery
Charger located at Main CHP Substation Building.
5.06.00 DCDB installed at Track Hopper Substation Building shall receive power
through two (2) nos. feeder of 100% rating from 220V DCDB installed at Main
CHP Substation Building.
5.07.00 DCDB installed at TP-4 shall receive power through two (2) nos. feeder of
100% rating from 220 V DCDB at powerhouse building.
5.09.00 Illumination is provided for indoors and outdoor areas with non-explosion
proof lighting fixtures. Lighting fixtures are supplied power from a number of
local lighting panels, which are in turn supplied from the main lighting
distribution boards in the Substation and PMCC/MCC room.
5.10.00 All material and accessories including cable trays, and its supports are hot dip
galvanized.
The complete CHP is operated from this building located near Crusher
House. This is a two (2) storied building. The ground floor is cable
spreader room. The first floor accommodates 3.0 KV SWGR s, 400V
PMCC, 3.0/0.420 KV LT Dry type Transformers, Main Lighting
Distribution Board (MLDB), lighting panel, D.C. Distribution Board
(DCDB), Battery, Battery Charger, A. C. Distribution Board (ACDB)
etc. A separate Control Room is provided for installation of PLC,
Control Panel, Operating Station, Engineering Station, UPS, Fire
Alarm Panels including intercom panels, etc.
Cable spreader room is provided below the floor where the electrical
equipment is installed. The floor for the equipment accommodates 3.0
KV Switchgear, 3.0/0.420 KV LT Dry Type Transformers, 400V Power
cum MCC, MLDB, ELDB, Lighting Panel, PLC remote I/O Rack, UPS,
DCDB, ACDB and any other Control Panel. A separate control room
shall be provided for installation of Remote I/O.
6.01.00 Control & Operation of Coal Handling Plants (CHP) shall be integrated in
Station Control & Monitoring System (SCMS) through VDU based Man
6.02.00 Control operation of the Stacker / Reclaimer is operated from the operator’s
cabin mounted on the machine and to be implemented through a proprietary
Programmable Logic Control (PLC) system.
6.03.00 Following Equipment shall come under interlock scheme and shall be
controlled & monitored from operator workstation in Main CHP substation
building cum Control Room Building with fault annunciation facility:
b) Crushers.
c) Flap Gates
e) Magnetic Separator
f) Metal Detector.
However, all the above mentioned equipment has its local control panels /
station for start & stop and / or any other function required with suitable
lockable type local / remote selector switch (to be housed in local panel /
station and placed near drives).
6.04.00 Following equipment shall not generally be under interlock scheme and shall
be started / stopped / controlled from their respective MCC / local panel with
status indication on Operating Station:
6.05.00 Following equipment shall not come under interlock Scheme and shall be
operated from its respective local panel without any indication in operator
workstation.
a. Electric Hoist
b. Ventilation System
7.01.00 The design of I&C system is such that isolation of any piece of defective
equipment would be possible without shutting down the main equipment or
disturbing the operation of associated instrument and accessories.
a) Vibration pads on the Crushers and crusher motors for mounting the
vibration probes and measurement.
7.04.00 For further details ref. Part-2 Section-3 of Technical Design Document.
Rev-C
Air pollution in the vicinity of CHP area through windage of coal dust shall be
suitably arrested by providing adequate green belt through planting of trees in
the periphery of CHP area. However, adequate measures shall be taken to
control local generation of dust by providing dust extraction and dust
suppression systems.
Only possibility of water pollution from CHP area is through drainage water,
which may carry coal dust particles and fines. To control the same the
drainage water from the main CHP area shall be taken up to a coal dust
disposal settling pond to bring down the turbidity of drainage water within
acceptable limits stipulated in relevant pollution control standards.
Crusher House
Transfer Points
Coal Jetty
Control Room
Bunker House
Pump/Compressor Houses
ANNEXURE–I
Ship un-loader
Crusher
Stacker-Cum-Reclaimer
Traveling Tripper
Belt Conveyors
Magnetic Separator
Hopper Lining : SS
Number : 2 x 100%.
Capacity : To suit.