Professional Documents
Culture Documents
Part 2 - Sec 1.6.4 - 11 2010 K G RPT 2210 - Final
Part 2 - Sec 1.6.4 - 11 2010 K G RPT 2210 - Final
Part 2 - Sec 1.6.4 - 11 2010 K G RPT 2210 - Final
PART-2 : SECTION-1
(Part-2_Sec-1.6.4_11-2010-K-G-RPT-2210_Final.doc)
2x600 MW Long Phu 1 Technical Design Document
INDEX
1.00.00 INTRODUCTION
REFERENCE DRAWINGS
(Part-2_Sec-1.6.4_11-2010-K-G-RPT-2210_Final.doc)
2x600 MW Long Phu 1 Technical Design Document
1.00.00 INTRODUCTION
Two numbers Steam Generators (2x600 MW) of Thermal Power Plant at Soc
Trang, Vietnam shall fire pulverized coal imported from Indonesia/Australia.
The power plant shall operate at supercritical condition of steam. In the
Steam Generating Plant, ash will be collected mainly in three areas and have
to be removed by mechanized means. These areas are
This report intends to establish the design philosophy of the Ash Handling
Plant covering collection, removal and disposal of all types of ash stated
above.
From the above information some overlapping may be noted in regards to the
total ash collection.
Design of the Ash Handling Plant shall, therefore, be carried out considering
following distribution rates (% of Total Ash):
b) Coarse Ash : 5%
It may be noted that both Bottom & Fly Ash Handling Systems and equipment
there of are independent of each other. Hence, even for higher collection of
ash in any collection point over the aforesaid figures, there shall be no
difficulty in removing it with the same equipment with longer duration of
operation only as long as the total ash generated by the plant remains within
design consideration.
b) Separate schemes for Bottom / Coarse Ash and that for Fly Ash
Handling have been envisaged. Accumulation of ash in stack hopper
being extremely nominal, only manual cleaning is envisaged and stack
hopper is not connected with the pneumatic system being envisaged
for other fly ash hoppers.
c) Operation of the Bottom Ash and Coarse ash Handling Plant for each
unit shall normally be continuous, whereas cleaning/removal of fly ash
shall be done periodically and sequentially.
d) Fly Ash of each boiler shall be evacuated by operating the plant six
hours in a shift including 10 minutes down times and purging time.
Capacity and equipment ratings have been decided accordingly.
in ESP third to last field and also second field in case first field is not
out and second field grain size is in acceptable range shall be taken
directly to fine ash silo. From the fine ash silo further removal of ash
shall be done in closed Trucks/browser. Both Coarse ash and fine ash
silo shall have arrangement of truck disposal as well as lean slurry
disposal system.
For Phase-I, one (1) remote Bottom ash silo, one (1) remote coarse
ash silo and one (1) fine ash silos have been envisaged.
EPC bidder will have the option to make an alternate proposal also
considering one number BA silo and one number FA silo without
Rev-C
classifier in FA system. A final decision on number of ash silo and
associated system will be taken subsequently.
h) Evacuation and transportation of both Fly ash & APH hopper ash shall
be two unit concept, i.e., Ash handling of two boiler units shall be
clubbed and shall have independent handling system.
Ash storage, slurry pumping and water supply system shall, however,
be common for all the units.
j) Both bottom ash and fly ash handling system normally being dry,
water requirement for the plant will be nominal except for ash
conditioning and delivering coarse fly ash/Bottom ash in lean slurry
form in emergency. Raw water shall be used as make up to the water
system. Clear water as necessary for equipment sealing shall be
tapped from station clarified water system. Sealing water for vacuum
pumps in fly ash system shall be taken through a settling unit and
clear water obtained shall be recirculated. Cooling water will be taken
from ACW system and will be returned to ACW return header.
k) Instrument air system and water supply system shall, also be common
for the two units.
l) Remote ash silos shall be located away from the main plant area up to
the extent possible keeping in view of maximum BA pneumatic Rev-C
pressure conveying distance possible.
consideration
Density of Bottom Ash For load 1600 Kg/Cu.M
consideration
Density of Fly Ash for ESP/APH/ECON 750 Kg/Cu.M
hopper volume and hopper outlet area
computation as well as volume for
intermediate surge hopper/buffer hopper.
Density of Fly Ash for Silo volume 750 Kg/Cu.M
computation
Density of Fly Ash for strength 1600 Kg/Cu.M
computation
Concentration of Ash in slurry 25%
Note: Crusher and vibrating screen shall be suitably provided so
that BA/CA particle size can be reduced less than 4mm to
ease pneumatic conveying
Note:
c) Each BA Hopper shall be sized for at least eight (8) hours storage
capacity. The bottom ash hopper shall have multiple bottom gates
operated by hydraulic power pack. The gates shall be adequately tight
shut off to enable maintenance of the conveyor with the boiler in
operation. The hopper is not envisaged to have any by pass to the
conveyor. However primary carrying conveyor / extractor mounted on
rails for removing the extractor away from furnace / hopper bottom
during maintenance may be provided. The supporting arrangement for
BA hopper shall be wide enough to enable such movement,
BA Secondary cooler conveyor, (if any common for two units) shall be
44 TPH dry ash (approx.) maximum and 22 T/Hr continuous and all
connected equipment like clinker grinder etc shall be suitable for this
load. For individual cooler conveyor capacity shall be matching with
primary conveyor/extractor and Eco ash carrying conveyor.
Two boiler units shall have intermediate bottom ash silo of 2 Hrs
capacity (in 1st stage) (44 Ton common silo in case of common cooler Rev-C
conveyor or individual silo for each unit with 22.0 Ton capacity).
equipments, etc. One (1) set of Vent Filter with all accessories for
venting within the stipulated limits of ash emission. BA silo shall also
be equipped with the following:-
Evacuation & transportation of Dry Fly ash shall be done in two stages, i.e.
from collection hoppers to the intermediate buffer hopper and from the buffer
hopper to remote storage silos. There shall also be a slurry disposal system,
taking feed from remote silos.
a) The fly ash removal from Air Heaters and Electrostatic Precipitators
shall be achieved in dry form by Vacuum Conveying System.
There shall be identical three (3) sets (2 W / 1 S for two units) of liquid
ring Vacuum pumps for VCS located in ESP area/fly ash equipment
building. For each vacuum stream/unit one set shall be in operation.
The two vacuum streams will have interconnection upstream of the
ash separators so that ash from any unit can be directed to any of the
ash separator/vacuum pump unit.
d) The vacuum conveying line emanating from each unit shall have ash
separator (bag filter with buffer hopper). Each ash separator shall be
connected with a vacuum pump. There will be an additional vacuum
pump installed as a common standby for the two streams. In normal
case ash from each unit shall be evacuated independently in 6Hrs
every shift. However with the interconnection of vacuum streams ash
from both the units can be evacuated sequentially in a shift with the
help of a single ash separator cum bag filter.
g) Vacuum ash conveying lines of each unit will be connected to the two
(2) nos. ash separators (one no. of ash separator connected to each
stream). The top of the ash separator shall be provided with bag filter
and at bottom there shall be pair of air lock vessels engaged in cyclic
tandem operation. The dust separator will separate ash continuously
and the separated ash discharges freely into airlock vessels below.
The conveying air after discharging most of the ash will further pass
through a bag filter to be cleaned before escaping to the vacuum
pump. The bag filter clearing will be reverse pulse jet type. The air
required for the pulse jet will be taken from the Instrument Air
Compressor system.
a) The air lock vessels below each buffer hopper shall be connected with
Pressure Conveying Stream (PCS). There shall be two (2) (1W / 1S)
pressure conveying streams common for two units
The pressure conveying line shall connect to both silo (course or fine
ash) via ash classifier
Two , 100% capacity oil free screw compressors (1W+1 S/B) shall be
provided to supply conveying air to air lock vessels for pneumatic
pressure conveying of dry ash up to the remote silos.
The PCS shall convey the total Fly Ash from the buffer hopper to
remote storage silos, which will be tentatively located as shown in plot
plan, the conveying capacity for pressure conveying lines shall be
around 120 T/Hr.
b) There shall be one (1) no fine fly ash silos, one (1) no coarse FA silo
and one (1) bottom ash silos for two units. Each CA storage silo shall
have capacity to store 48 hours of corresponding ash. Fine fly ash
silos each shall be capable of storing 48 hours of fine fly ash. The
bottom ash silo shall have capacity to store bottom ash generated in
48 hours. Each silo will be provided with pressure relief access door,
vent filter, fluidizing pad (for fly ash silos), unloading equipments, etc.
Bottom ash storage silo is not expected to require any fluidizing
arrangement. The bottom of bottom ash silo shall be adequately
sloped (around 70 deg.) and lined with SS to ensure proper material
flow.
c) After classifier conveying stream carrying fine fly ash shall be taken to
fine ash silos under normal mode of operation. Under normal mode of
operation, conveying streams below classifier carrying coarse ash
shall be taken to coarse ash silo. There will be two (2) classifier units
(100% capacity each) installed above coarse ash silo (1 working +1
stand by). If coarse ash is passed through classifier then classifier will
separate ash particles larger than a specified particle size (normally
45-50 micron) which will accumulate in the coarse ash silo below. The
smaller particles shall be conveyed to the adjacent fine ash silo and
arrested in bag filter thereafter accumulating in fly ash silo below. Both
the pressure conveying headers (coarse and fine together) shall have
connection with both the fine ash silos & coarse ash silo to enable
storage of ash without segregating in emergency.
The silo shall also be provided with one (1) opening dedicated for
slurry system and one connection will be left blank for future use.
e) Each coarse FA, fine fly ash and bottom ash silo shall be provided
with following:
ii) Telescopic chute with scavenger fan (as indicated in the flow
diagram) also be provided at the bottom of the silo for
unloading ash into closed road tankers at minimum 150 T/Hr
discharge capacity. There shall be rotary feeder on ash
discharge line from silo.
iii) One outlet provided with manual valve and pneumatic isolation
valve for delivering ash to pneumatic ash transporter vessel.
vii) Bottom ash silo shall have conical bottom provided with SS
liner.
viii) One (1) set of Vent Filter with all accessories for venting within
the stipulated limits of ash emission.
xii) All silos will be provided with at least 8.5 m clear head room
below the operating floor of silo (from bottom of beam to top of
road/grade).
EPC bidder will have the option to make an alternate proposal also
considering one number FA silo without classifier in FA system. A final
decision on number of ash silo and associated system will be taken Rev-C
subsequently.
Slurry disposal system is envisaged for emergency situation when dry ash
unloading from silos through trucks / tankers is not possible.
Each of the fly ash and bottom ash silos shall have a wetting arrangement
called feeder ejector below silo where high pressure water will be
administered. The vacuum created within it will draw ash which will be mixed
with water in the combination tube at discharge to form slurry and discharge
in the collector tank (acting as a surge hopper) below. The slurry from the
collector tank shall be delivered to slurry sump either by gravity flow or with a
jet pump in case slurry sump is located distant.
Two chains of slurry pumps (one working) have been envisaged to convey
the ash slurry to ash dump area.
Ash disposal area will be located approximately 3 KM away from power block
area (considering the farthest slurry outlet on ash dyke). Rev-C
Single discharge pipe for each pump series with interconnection will be
routed up to the proposed ash dumping area. Provision of suitable discharge
spouts (adequate numbers) with slurry duty valves is considered.
Necessary water required for slurry system (HP & LP) shall be provided by
two (1W and one stand by) sets of HP & LP Water Pumps”. These pumps will
take their suction from a water sump near slurry system. Two nos. (1W +1
stand by) conditioning water pump shall also take its feed from this sump.
Make up Water input for the said sump will be from raw water and recyle
water.
Ash slurry will be disposed in the ash pond area. The head of slurry pump
shall be designed to enable discharge at furthest point in the dyke area up to
ultimate dyke height. Provision of additional pump stage shall be there to take
care of future expansion of ash pond/rise of dyke height
The slurry pond will gradually get filled up with deposited ash and provisions
shall be there to shift the slurry discharge point(s) from time to time such that
an efficient filling of the entire ash pond is ensured. Proper garlanding on the
ash dyke shall be made.
Ash pond shall be provided with suitable collecting well which will collect
water from top surface of accumulated slurry. Suitable launders provided with
sluice gate shall guide the collected water to a stilling pond for precipitation of
ash carry-over. The stilling pond will be connected with RCC water recovery
sump through pipes and valves. Two nos recovery water pumps (one
working) shall deliver the water to a clarifier unit located near main plant.
Suitable chemical house having arrangement for chemical dosing shall be
provided for required treatment of the water. Water duly treated / clarified will
be taken to the ash water sump by gravity flow or by another pumping
arrangement if ash water sump can not be located adjacent.
4.02.04 Ash pond area : With lean slurry (assuming 1.1 T/CuM effective design
density) the selected area of 35 He for ash storage will be able to store cent
percent ash 2m height/year with 85% plf and 85% filling capacity. Thus with
10m height of ash dyke it will be able to store cent percent ash for 5 years.
The storing time will increase depending upon ash utilization in other
avenues. Proper ash management may enable rising ash dyke even further
which will increase the effective ash storage.
The layout and arrangement of the Ash Dyke is shown in attached dwg. No.
11/2010-K-M-DWG-2131. Rev-C
For transporting dry ash (both Bottom ash as well as fly ash) barge (upto
capacity 300 dwt ) shall be used and a dedicated berth shall be constructed
on Hau river adjacent to plant area. The ash silos (bottom ash as well as fly
ash) shall have a pneumatic ash transport vessel below the silo. In the ash
port an ash silo approximately 150 Ton capacity shall be erected on a jetty.
The silo shall have a bag filter on top which will be connected with ash Rev-C
transport line emanating from the ash transporter vessels at main plant silos.
Dry ash from main plant silos shall be pneumatically pressure conveyed to
the bag filter on jetty silo. Two numbers conveying air compressors (one
operating and one standby) shall be provided alongwith all accessories to
supply compressed air for transportation of ash to the jetty silo from plant
silos. The ash collected in bag filter shall be accumulated at silo which will Rev-C
have an extended boom screw conveyor for loading ash onto barge. The
discharge of screw conveyor shall pass through a cascading chute to enable
ash loading onto the barge in a dustless manner. The beam supporting the
discharge screw conveyor shall have flexibility in mounting for slewing and
luffing to enable maneuver loading ash on barge. Two such units each having
capacity to handle ash 150 T/Hr shall be installed with proper distance in
between so that both the units can simultaneously load the barge.
The barge loading units shall have provision for receiving ash from future
units also.
a) Water Requirement For Ash Handling System (Both Bottom ash and
Fly ash system being dry type water requirement in normal operation
is envisaged to be very nominal.)
The raw water and the supply of water from clarified water will be the
net consumption of water. There shall also be extensive re-cycling of
water in the plant. Re-use of the sealing water for sealing duties and
re-use of miscellaneous drains for ash slurry make-up will be effected.
The plant shall be sized for the maximum drawal of water during
start-up and occasional surge operation.
ii) Clarified water required for Ash Handling plant shall be tapped
from clarified water and discharged to a sump in vacuum pump
area for sealing pumps to take suction from this sump.
iii) There shall be two (2) number Seal Water pumps (one working
and one stand by for 2x600 MW units) for sealing of slurry
pumps, vacuum pumps, sealing of drain pumps and other
miscellaneous uses. The desalinated raw water will be
discharged to a sump provided in Silo area. HP, LP ash water
pumps will take suction from this sump. This sump will also
supply water for pumps spraying water to rotary ash
conditioners. These pumps will also supply water for
occasional floor washing.
The compressed air requirement (Instrument Air Quality) of the Ash Handling
Plant shall be met from the Screw type (non-lubricated) compressors installed
in the Ash Handling plant specifically for this purpose. The air shall be
required to operate pneumatically operated cylinders, diaphragms associated
with valves and gates of the plant.
2x100% duty compressors with all accessories and 2x100% duty refrigeration
type Air Drying Plants with all accessories shall be provided
4.04.03 Sump Pumps, Hoisting Equipment, Air Conditioning and Ventilation system
The same shall be provided, as required, in the plant. However the following
minimum requirement shall be fulfilled:
Bottom Ash Hopper area of each unit shall be provided with two nos. drain
pumps and shall discharge into clarifier.
Semi EOT crane (hand operated LT, pendant operated CT and hoist) of
capacity 3.5 ton (approx) shall be provided for fly ash compressor building
(containing compressor, vacuum pumps etc.) and silo utility building.
Selection of crane capacity shall be guided by 110% of heaviest load to be
handled. Slurry pump house crane capacity shall be 5.0 ton (approx).
Monorail with chain pulley block shall be provided on top of silo.
Control room shall be air conditioned with window / package air conditioners.
Electrical room for MCC shall be pressurized ventilated
a) Material Selection
b) Conveying Equipment
c) Slurry pump, Vacuum pump seal water pumps, Clarified / Seal water
pumps, HP, LP Water Pumps, FA/BA dust conditioning water pumps
d) Velocity consideration for air, water and slurry line selection shall be
limited to
Velocity, M/Sec
Sl Pipe size Pipe sizes of
Service Pipe sizes of
No below 50 200 mm and
50 to 150 mm
mm above
a) Water pump
0.6-0.9 1.2-1.5 1.2-1.5
suction
b) Water pump
0.9-1.8 1.5-2.4 1.8-2.8
discharge
c) Compressed air
below 2kg/cm2 15-20 20-30 25-35
(g)
d) Compressed air
2 kg/cm2 (g) 20-30 25-40 35-45
and above
e) Min/Max Velocity in Ash Slurry lines (lean slurry) 1.8/2.8 m/sec
f)
Rev-C
Since the system design is such, a large surface area (provided in the Ash
Dump) shall adequately cool the ash and the stipulation of thermal pollution
shall therefore be met.
At Dry Ash unloading point, special water spray dust suppression equipment
shall be provided. For all dust collection points, the system adopted for Ash
Handling shall be "Vacuum" system, which precludes any chance of
particulate emission. Besides, Vent filters, Air scrubbers shall be provided at
logistic locations to take care of pollution.
Control & Operation of Ash Handling Plants (AHP) including Slurry Disposal
systems shall be integrated in Station Control & Monitoring System (SCMS)
through VDU based Man Machine Interface (MMI) located in respective unit
AHP Control Room as well as in Central Control Room (CCR). All Electrical
System monitoring & operation shall also be achieved in SCMS.
Ash disposal system from Silos shall be operated manually from local.
8.01.01 The Electrical Power Distribution System for the Ash handling plant (AHP)
has been envisaged at 3000V, 400V & 230V level to supply the drives & other
electrical equipment/systems. 220V DC power & 230V AC uninterrupted
supplies have also been envisaged for control and monitoring of the Ash
Handling Plant equipment/system. The voltage levels are selected and the
distribution network is designed to ensure smooth operation of the plant and
to maintain the operating parameters of various equipment/devices within
allowable limits.
8.01.02 Power supply to electrical equipment in AHP shall be provided from 3000V
switchgears located at AHP electrical room & slurry pump house. Each of
these switchgears shall be powered from 3000V station switchgears, in power
house, through duplicate (2x100%) supplies. 3000V switchgear shall feed
3000V motor loads and shall also act as power source to 400V loads through
3000/420V oil filled step down service transformers, located outside AHP
electrical room and slurry pump house. At 400V level the distribution shall be
through 400V PMCCs. They will be located at AHP electrical room and slurry
pump house and shall feed power to 400V motors, distribution boards, local
starter panels, distributed over the ash handling plant. 220V DC power shall
be made available at 220V DCDB (through duplicate supplies) located at AHP
electrical room and slurry pump house, for further distribution to various
loads. 230V AC uninterrupted supply required for control, monitoring of AHP
equipment shall be derived from UPS, located in AHP control room and slurry
pump area.
Power supply to remote Ash Pond area earmarked for Ash storage mound
having no major equipment drive will require nominal power for lighting and
occasional constructional activities and will be arranged through a separate
overhead line to be originated from main plant area and routed along
proposed ash pipe corridor.
a. Two (2) nos. incomers and bus coupler each rated to carry the entire
load of 3000 bus (2x100%) shall be provided for 3000V AHP
Switchgear.
b. In case of 400V system each 400V PMCC shall be provided with two
(2) incomers and a bus coupler. Power supply to the incomer
(2x100%) shall be derived from upstream LT service transformer rated
for 100 % load of the entire bus.
d. Spare feeders of each type and rating shall be provided in 3000V and
400V PMCC / MCC / DBs for future use.
8.02.02 The electrical installation shall meet the requirement of Vietnam Electricity
Rules as amended up to date. In addition, other rules and regulations
applicable to the work shall be followed.
8.03.01 The equipment shall be installed in hot, humid and tropical atmosphere highly
polluted at places by coal dust / fly ash. Electrical equipment shall be capable
of continuous full load operation under the following conditions:
8.03.02 Where the equipment are to operate in the vicinity of high temperature zone
or installed outside and exposed to direct sun rays, suitable de-rating shall be
taken into consideration for higher ambient temperature and rigorous weather
conditions, as applicable.
Sl.
System Volt. & Frequency Fault Level Grounding
No.
a) 3000V ±10%, 3Ph, 3 wire, 50 Hz ±5% 40 KA (1 sec) Non effectively
earthed
b) 400V ±10%, 3Ph, 4 wire, 50 Hz ±5% 50 KA (1 sec) Solidly earthed
Combined voltage and frequency variation 10% (absolute sum)
c) 220V DC (-)15% to (+)10%, 2 wire 25 KA Unearthed
8.04.02 During starting of large equipment the voltage may drop by a maximum of
20% for a period of 60 seconds depending upon the driven equipment
characteristic. All electrical equipment, while running, shall successfully ride
over such period without affecting system performance.
No. of
Voltage
Energy network apparatus phases & Grounding
(V)
frequency
AC motors (rated above 160 3000V ± 10% 3 Ph, 50 Hz, Non effectively
KW) ±5% earthed
AC motors (rated up to and 400V ± 10% 3 Ph, 50 Hz, Solidly earthed
including 160 KW), power ±5%
receptacles and three phase
AC loads
DC Motors 220V (+) 10% 2 wire DC Unearthed
to (-) 15%
Control, indication & 220V (+) 10% 2 wire DC Unearthed
protection circuits of circuit to (-) 15%
breakers
Control & indication for 230V ± 10% 1 Ph, 50 Hz, Solidly earthed
contactor operated 400 V ±5%
motor feeders
No. of
Voltage
Energy network apparatus phases & Grounding
(V)
frequency
Space heaters rated up to 230V ± 10% 1 Ph, 50 Hz, Solidly earthed
and including 1200 watt ±5%.
Space heaters rated above 400V ± 10% 3 Ph, 50 Hz, Solidly earthed
1200 watt ±5%.
Panel interior lighting, 230V ± 10% 1 Ph, 50 Hz, Solidly earthed
receptacles and general ±5%.
power
9.01.00 The Instrumentation and Control System envisaged shall be complete in all
respect and adequate for safe, reliable, efficient and commercial operation of
the Ash handling Plants under normal and worst service and environmental
conditions specified.
9.02.00 The design of I & C system shall be such that isolation of any piece of
defective equipment would be possible without shutting down the main
equipment or disturbing the operation of associated instrument & accessories.
9.04.00 All instruments shall be compatible for hook up to Station Control &
Monitoring System (SCMS).
9.05.00 For further details refer Part-2, Section-3 of the Technical Design Document.
Rev-C
ATTACHMENT-I
Bottom Ash generation @20% = 8.87 T/Hr Economiser ash @5% = 2.22, Total 11.09
Bottom ash metallic conveyor capacity 11.0 T/Hr Continuous basis and 22.0 T/Hr maximum
to cater emergency
Capacity of pneumatic conveying stream of bottom ash with margin =25 T/Hr. In case of
emergency both the streams will run.
Capacity of pressure conveying stream connected with two units 120 T/Hr
Bottom Ash (48 Hrs storage) silo capacity one silo for two units.2X 48X11.0=1056 T
With BA density for volume consideration 0.65 T/CuM = 1625 CuM app
Fly Ash (48 Hrs storage) silo capacity two silo for two units, each 44.43X48=2132 Ton
With FA density for volume consideration 0.75 T/CuM = 2843CuM app 2850 CuM
Capacity of slurry system. Total ash generation form two units 88.7 T/Hr
Considering 8 Hrs ash generation to be cleaned in 6 Hrs , capacity 118 T/Hr = app 120 T/Hr
Generation of ash from two boilers with 85% plf= 88.7X24X.85X365= 6604602 T per year
With effective density 1.1 T/CuM for ash volume 600418 CuM
With 85% utilization pond area available for ash storage 35X10000X.85=297500 SqM
Ash such with an elevation of ash pond dyke as 10m the area can accumulate total ash
generation of two units for five years.