ID Task Task Name Duration Start August 2023 September 2023

Mode 25 30 4 9 14 19 24 29 3 8 13 18
1 Zimre Lift A 23 days Tue 8/8/23
Installation
2 Platform 2 days Tue 8/8/23 C & Team
Installation
3 Machine 2 days Thu 8/10/23 C& Team
Installation
4 Counter Weight 2 days Mon C & Team
Installation 8/14/23
5 Roping 2 days Wed 8/16/23 C & Team
6 Machine Auto Tune1 day Fri 8/18/23 TM
7 Demolitions 2 days Mon 8/21/23 Clovgate
8 Landing Doors 5 days Mon C & Team
Installation 8/21/23
9 Builders Work 2 days Mon 8/28/23 Builders
10 Car Door 1 day Wed C & Team
Installation 8/30/23
11 Doors Auto Tuning 1 day Thu 8/31/23 TM,C& Team
12 Wiring 2 days Thu 8/31/23 TM
13 Speed Run and 2 days Mon 9/4/23 Clovgate,C& Team,TM
Testing
14 Inspection & 2 days Wed 9/6/23 Inspector,C& Team,Clovgate
Commissioning

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Zimre
Summary Manual Summary Rollup Progress
Date: Tue 8/8/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1