WORK ORDER

ELASTOMERIC BEARINGS STATUS

W.O. NO DATED PROJECT/CUSTOMER

EB/20-21-17 29.05.20 SHREE MANGLAM BUILD.MP


EB/20-21-25 15.06.20 Y-TECH CONST. ENGG. MP.
EB/20-21-37 13.07.20 L.G. CHAUDHARY

EB/20-21-95 26.09.20 AMCON CONST. COMP. MP


EB/20-21-106 09.10.20 L.G. CHAUDHARY
EB/20-21-136 19.11.20 LONGJIAN - KEC JV 

EB/20-21-144 02.12.20 AYAAN CONSTRUCTION MH

EB/20-21-167 22.12.20 CEIGALL INDIA LTD. - HAR.


EB/20-21-192 02.12.20 SUBHASH  THAKKAR - M.P.
EB/20-21-222 01.03.21 NEEL MADHAV EARTH MP.
EB/20-21-242 26.03.21 PATEL CONST. COMP. M.P.
EB/21-22-22 22.06.21 SAM (INDIA) BUILD  P. LTD.
EB/21-22-43 22.07.21 L & T LTD. - WEST BENGAL
EB/21-22-48 07.08.21 SRC INFRA DEV. P. LTD. KAR.
EB/21-22-52 17.08.21 GAWAR CONST. LTD.-BIHAR

EB/21-22-65 16.09.21 JAGDISH PATHAK CONST.

EB/21-22-98 02.11.21 VKSC INFRA PROJ LTD - M.P.

EB/21-22-108 27.11.21 TIRUPATI BALAJI CIVILTECH

EB/21-22-121 11.12.21 M.G. CONTR. PVT. LTD. - JH


EB/21-22-122 16.12.21 DURGA CONST. CO. - HAR.
EB/21-22-127 24.12.21 PHULCHAND & SONS - HAR
EB/21-22-130 07.01.22 S. K.CHAUHAN - MP
EB/21-22-134 14.01.22 S.K. CHAUHAN -MP
EB/21-22-137 18.01.22 SALAHUDDIN & JK (JV) - BIHA
EB/21-22-152 2/17/2022 LARSEN & TOURBO LTD - W. B.
EB/21-22-155 19.02.22 U.P.S.B.C.L. - U.P.
EB/21-22-157 23.02.22 SAM (INDIA) BUILD WELL  P. LTD
EB/21-22-158 23.02.22 AFCONS INFRA. LTD - U.P.

EB/21-22-165 07.03.22 SAM (INDIA) BUILD WELL PVT LTD


EB/21-22-182 AYUSH PROCON PVT. LTD. - UP

EB/21-22-184 28.03.22 RAGHUKUL CONST. COMPANY - CG


EB/22-23-04 11.04.22 AFCONS INFRA. LTD. - MAH
EB/22-23-15 30.04.22 D.R.A. INFRACON PVT. LTD - M.P.
EB/22-23-18 09.05.22 D.R.A. INFRACON PVT. LTD - WB

EB/22-23-19 11.05.22 VKSC INFRA PROJ LTD - M.P.

EB/22-23-20 12.05.22 SONA-JK (JV)-BIHAR

EB/22-23-28 16.05.22 U.P.S.B.C.L. - U.P.

EB/22-23-34 18.05.22 AFCONS INFRA LTD. GUJARAT

EB/22-23-40 24.05.22 U.P.S.B.C.L. - U.P.


EB/22-23-44 04.06.22 AFCONS INFRA LTD. GUJARAT
EB/22-23-45 06.06.22 AGRAWAL INFRA BUILD PVT LTD - ORISSA
EB/22-23-49 09.06.22 U.P.S.B.C.L. - U.P.
EB/22-23-55 11.07.22 SLMI INFRAPROJECTS PVT LTD - TELANGANA

EB/22-23-56 13.07.22 U.P.S.B.C.L. - U.P.


EB/22-23-57 14.07.22 RISHU CONST. INFRATECH INDIA PVT LTD - U

EB/22-23-58 15.07.22 U.P.S.B.C.L. - U.P.


EB/22-23-59 16.07.22 U.P.S.B.C.L. - U.P.
EB/22-23-60 20.07.22 ANK CONSTRUCTION CO. PVT. LTD. Nepal
EB/22-23-62 02.08.22 U.P.S.B.C.L. - U.P.
EB/22-23-63 02.08.22 U.P.S.B.C.L. - U.P.
EB/22-23-67 09.08.22 V. K. GUPTA & ASSOCIATES

WORK ORDER
ELASTOMERIC BEARINGS STATUS

W.O. NO DATED PROJECT/CUSTOMER

EB/19-20-185 LARSEN & TOUBRO LTD - MAHARASHTRA

EB/19-20-256 GPT INFRA PROJECTS LIMITED - U.P.


EB/19-20-257 GPT INFRA PROJECTS LIMITED - U.P.
EB/21-22-164 PRAKASH ASPHALTINGS & TOLL HIGHWAYS (I) LTD
EB/22-23-10 GPT INFRA PROJECTS LIMITED - U.P.

EB/22-23-12 28.04.22 THAKUR MHATRE JV


EB/22-23-14 29.04.22 KALPATARU POWER TRANSMISSION LTD. - M

EB/22-23-16 30.04.22 LARSEN & TOUBRO LTD - MP


EB/22-23-22 13.05.22 LARSEN & TOUBRO LTD - MAHARASHTRA
EB/22-23-36 20.05.22 GAWAR CONST. LTD.-BIHAR

EB/22-23-46 RAHEE INFRATECH LIMITED- MIZORAM


EB/22-23-48 09.06.22 GPT INFRA PROJECTS LIMITED - U.P.
EB/22-23-50 13.06.22 GPT INFRA PROJECTS LIMITED - U.P.

ELAST. BEARING BEARING SAMPLE & DIMENSION SHOW TO CLINT


S. NO. DR. NO. BEARING TYPE
1 EB/21-22-152 LARSEN & TOURBO LTD - W. B.

ELAST. BEARING BEARING AXIAL & COMPRESSIVE LOAD SHOW TO CLI


S. NO. DR. NO. BEARING TYPE
1 EB/21-22-152 LARSEN & TOURBO LTD - W. B.

ELAST. BEARING BEARING SEAR MODULAS AND BOND SHOW TO CLIN


S. NO. DR. NO. BEARING TYPE
1 EB/21-22-152 LARSEN & TOURBO LTD - W. B.

THANKS & REGARDS,


RISHI SAHU

EB/21-22-152 LARSEN & TOURBO LTD - W. B.


R DISPATCHED
DATE:23-08-2022
STATUS BALANCE

SIZE ORDER SUPPLIED BALANCE STOCK


QUANTITY QUANTITY

250X160X22 = 48 48 20 28 0
400X250X52 = 42+02 44 20 24 0
550X460X80 = 30 30 12 18 0
400X400X35 = 20 20 0 20 0
400X250X52 = 78 78 58 20 0
400X400X30 = 20 20 16 4 0
475X250X54 = 2800 2800 2478 322 322
475X250X54 = 930 930 852 78 7
500X320X64 = 66 66 0 66 0
400X250X39 = 44 44 0 44 0
200X160X22 = 44 44 0 44 0
550X500X96 = 20 20 0 20 0
400X250X33 = 16 16 0 16 16
500X250X52 = 08 8 0 8 0
250X160X22 = 16 16 0 16 0
475X250X54 = 1800 1800 1090 710 503
500X250X54 = 16 16 0 16 0
500X300X84 = 72+02 74 0 74 0
375X375X80 = 240 240 120 120 0
425X425X112 = 360 360 180 180 0
450X450X144 = 120 120 60 60 0
500X250X52 = 80+02 82 58 24 0

500X320X64 = 800+02 802 272 530 0

500X250X48 = 24+01 25 0 25 25
250X160X22 = 16 16 0 16 0
600X320X15 = 40 40 40 0 0
500X400X84 = 132+02 134 134 0 0
500X400X84 = 126+2 128 0 128 128
550X460X80 = 42+2 44 14 30 30
400X400X35 = 28+2 30 0 30 30
500X360X84 =184 184 128 56 0
500X300X52 = 420 420 250 170 170
500X320X56 = 60 60 0 60 0
400X375X80 = 500 500 140 360 360
540X540X150 = 8 8 0 8 8
450X250X52 = 8 8 0 8 8
400X400X80 = 405 405 100 305 305
400X400X106 = 12 12 0 12 12
 630X400X112 = 32 32 0 32 32
500X250X52 = 17 17 0 17 17
325X300X55 = 24 24 0 24 24
400X250X46 = 24 24 24 0 0
441X200X8 =48 48 0 48 48
552X200X8 =16 16 0 16 16
 938X425X8 = 8 8 0 8 8
700X350X8= 8 8 0 8 8
800X200X8  = 46 46 0 46 46
800X400X12  = 16 16 0 16 16
600X300X8  = 8 8 0 8 8
600X200X8  = 30 30 0 30 30
1100X150X40  = 12 12 0 12 12
600X150X40  = 8 8 0 8 8
400X200X8= 72 72 0 72 72
700X350X8= 8 8 0 8 8
600X200X8= 58 58 0 58 58
400X200X8= 104 104 0 104 104
400X280X52 = 40 40 0 40 40
450X350X52 =20 20 0 20 20
650X650X64 = 30 30 0 30 9
500X360X84= 64 64 56 8 0

630X400X70 = 64 64 64 0 0

300X250X67 = 640 640 0 640 418

410X410X128 = 264 264 0 264 264


600X450X90 = 150 150 150 0 0
480X240X67 = 200 200 0 200 0
450X300X48 = 48 48 0 48 45
630X400X70 = 33 33 33 0 0
720X220X75 = 50 50 0 50 0
650X250X60 = 30 30 0 30 0
630X400X70 = 60 60 0 60 29
450X450X111 = 18 18 0 18 0
450X450X120 = 32 32 0 32 0
630X400X70 = 32 32 0 32 0
640X460X96 = 80 80 0 80 0
430X425X44 = 4 4 0 4 4
630X400X96 = 93 93 0 93 0
630X400X96 = 114 114 0 114 0
500X320X54 = 200 200 0 200 0
TOTAL  12497 6351 6146 3286

DATE:23-08-2022
STATUS
ORDER SUPPLIED
SIZE QUANTITY QUANTITY BALANCE STOCK

1005X1005X451 30 0
1150X1150X341 84 52
750X550X106 = 24 24 0 24 24
750X550X106 = 24 24 0 24 24
550X300X74 = 20 20 0 20 0
545X280X65 = 12 12 0 12 0

680X490X96 = 48 48 0 48 8

835X835X183 = 12 12 0 12 12
545X280X65 = 14 14 14 0 0
650X370X65 = 8 8 0 8 0
760X500X106 = 200 200 0 200 0
760X760X170 = 11 11 11 0 0
870X870X177 = 8 8 8 0 0
655X655X163 = 4 4 4 0 0
950X950X167 = 2 2 2 0 0
400X300X74 = 40 40 0 40 0
450X300X74 = 40 40 0 40 0
550X300X74 = 20 20 0 20 0
850X650X128 =48 48 0 48 0
680X490X96 = 28 28 0 28 0
750X550X106 = 116 116 0 116 0
TOTAL  679 39 754 120

DIMENSION SHOW TO CLINT


SIZE QUANTITY
500X300X52 8

RESSIVE LOAD SHOW TO CLINT


SIZE QUANTITY
500X300X52 5

AS AND BOND SHOW TO CLINT


SIZE QUANTITY
500X300X52 2

500X300X52 = 420 420


NCR
STOCK
CONCERN
REMARKS ED
PERSON

STOCK ADJUST S.M./A.J.


S.M./A.J.
S.M./A.J.
S.M./A.J.
S.M./A.J.
DISPATCHED 29.04.22 S.M./A.J.
OK N.M.
7NCR 06.08.22 N.M.
ADJUST EB-158 , EB-84   S.M./A.J.
ADJUST TO EB/10 & 11 S.M./A.J.
ADJUST IN EB-158  S.M./A.J.
V.V.
M/22-23/746 08.06.22 S.M./A.J.
ADJUSTED IN EB - 135 S.M./A.J.
ADJUSTED IN EB-177 S.M./A.J.
RECEIVED 29.07.22 OK N.M.
A.A.
V.V.
S.M./A.J.
S.M./A.J.
S.M./A.J.
DISPATCHED 20.12.21 S.M./A.J.

DISPATCHED 13.08.22
S.M./A.J.
TO BE ADJUST S.M./A.J.
ADJUST IN EB-143 S.M./A.J.
DISPATCHED 12.08.22 S.M./A.J.
dispatched 18.08.22 S.S.R.
RECEIVED 26.03.22 OK S.S.R.
M/22-23/747 08.06.22 S.M./A.J.
SIL/MFG/21-22/3191 11.03.22 S.M./A.J.
ADJUST IN EB/22-23-20 56NOS
RECEIVED 07.07.22 OK
T.T.
RECEIVED 20.05.22 OK
RECEIVED 17.05.22 OK T.T.
RECEIVED 17.05.22 OK T.T.
RECEIVED 21.05.22 OK
M/22-23/744 08.06.22 T.T.
M/22-23/744 08.06.22 T.T.
M/22-23/572 25.05.22
RECEIVED 15.06.22 OK S.M./A.J.
dispatched 20.08.22 S.M./A.J.

M/22-23/1206 23.07.22

RECEIVED 29.07.22 OK S.M./A.J.


received 25.07.22 OK S.M./A.J.
3 NCR 30.07.22 S.M./A.J.
dispatched 21.05.22

DISPATCHED 01.08.22 ADJUST


IN EB-31 18NOS , EB-185 18 T.T.
NOS, EB-31 24NOS

7 NCR 13.08.55 RECEIVED


S.M./A.J.
09.08.22 U/I

RECEIVED 23.07.22 OK S.M./A.J.


DISPATCHED 16.08.22 T.T.
3 NCR 06.08.22 OK
DISPATCHED 04.08.22 T.T.

1 NCR 06.08.22 OK
T.T.
T.T.
T.T.
T.T.
M/22-23/EXP/19 10.08.22
T.T.
T.T.

3-08-2022

CONCERN
REMARKS ED
PERSON

RECEIVED 20.08.22
24 NCR 01.08.22
24 NCR 01.08.22
20 NCR 02.08.22
12 NCR 30.07.22

RECEIVED 13.08.22, 5NOS OK,


2 NOS U/I, 1 NCR 12.08.22

6 NCR 06.08.22
dispatched 17.08.22

dispatched 17.08.22
dispatched 17.08.22