Method Statement For The Block Glass Curved Ceiling Installation
Method Statement For The Block Glass Curved Ceiling Installation
Method Statement For The Block Glass Curved Ceiling Installation
Document Title MST for the Block Glass Curved Ceiling Installation Date 14.03. 2022
Document No. KH-PK4b(i)-a-HBK-MST-A-0061 Rev. No. 0
Revision History
Review &
KH-PK4b(i)-a-HBK-MST-A-0061 0 14/03/22
Approval
Purpose of Reviewe
Re Prepared Approve
Document No. Date Submissio d by
v by CM d by PM
n QA/QC
KH-PK4b(i)-a-HBK-MST-A-0061 Page 1 of 14
Project Name: Lusail Katara Twin Tower Hotel
Document Title MST for the Block Glass Curved Ceiling Installation Date 14.03. 2022
Document No. KH-PK4b(i)-a-HBK-MST-A-0061 Rev. No. 0
1. INTRODUCTION...................................................................................................................................3
1.1. Purpose............................................................................................................................................... 3
1.2. Scope.................................................................................................................................................. 3
2. REFERENCES......................................................................................................................................3
3. ABBREVIATIONS.................................................................................................................................3
4. RESOURCES........................................................................................................................................4
4.1. Equipment & Machineries.................................................................................................................... 4
4.2. Manpower............................................................................................................................................ 4
4.3. Materials.............................................................................................................................................. 5
5. RESPONSIBILITIES.............................................................................................................................5
5.1. Project Manager.................................................................................................................................. 5
5.2. Construction Manager......................................................................................................................... 5
5.3. Project Engineer/ Site Engineer.......................................................................................................... 5
5.4. QAQC Engineer.................................................................................................................................. 5
5.5. HSE Engineer/Officer.......................................................................................................................... 6
5.6. PERMITS AND LICENSES................................................................................................................. 6
6. DESCRIPTION OF WORKS................................................................................................................6
6.1. Locations............................................................................................................................................. 6
6.2. Sequence of Works............................................................................................................................. 6
7. METHODOLOGY..................................................................................................................................7
7.1. Preparatory Works............................................................................................................................... 7
7.2. Examination......................................................................................................................................... 7
7.3. Fabrication........................................................................................................................................... 7
7.4. Steel Framing Installation.................................................................................................................... 7
7.5. Formworks........................................................................................................................................... 8
7.6. Mockup................................................................................................................................................ 8
7.7. Placement of Glass-Blocks.................................................................................................................. 9
7.8. Cleaning and Protection.................................................................................................................... 10
8. QUALITY..............................................................................................................................................10
8.1. Inspection and Testing...................................................................................................................... 10
8.2. Documentation.................................................................................................................................. 11
10. ATTACHMENTS.................................................................................................................................11
KH-PK4b(i)-a-HBK-MST-A-0061 Page 2 of 14
Project Name: Lusail Katara Twin Tower Hotel
Document Title MST for the Block Glass Curved Ceiling Installation Date 14.03. 2022
Document No. KH-PK4b(i)-a-HBK-MST-A-0061 Rev. No. 0
1. INTRODUCTION
1.1. Purpose
1.1.1. The purpose of this Method Statement is to describe methodology and activities for the
installation of the curved ceiling using the GL14A - Glass Block for the All-Day Dining,
Level 1, 5 Star Katara Hotel Project, Lusail, Doha. The installation shall be in
accordance with the approved shop drawing, project specification, QCS 2014 and the
deliverables under the KH-PK4b(i) Fit-out package.
1.1.2. This document will be distributed to the site team for guidance and compliance to the
procedures which to be executed by IMAR.
1.2. Scope
1.2.1. This method statement covers the main activities such as the construction of the steel
sub-framing structure, reinforcement, and masonry works for the GL-14a- glass block as
indicated in the approved shop drawing, material approval and project specification. This
includes the testing and quality control activities during the execution works.
1.2.2. This document consists of the references, materials, responsibilities, activities involved,
best practices, project specification requirements, HSE requirements, resources,
methodology, checklist, and inspection & testing plan.
2. REFERENCES
2.1.1. Issue for Construction Drawings (IFC) & Approved Shop Drawing
2.1.2. Project Quality Plan: KH-PK4b(i)-A-IMR-PQP-G-0001-02
2.1.3. Project Architectural Specification: Q17017-0100D-PK4b(i)-a-TD-SPC-AR-01-REV 00
2.1.4. Material Submittal: KH-PK4b(i)-a-HBK-MAT-A-0220
2.1.5. Project Construction Health & Safety Plan
2.1.6. Project Construction Environmental Plan
2.1.7. British Standards and other applicable standards
2.1.8. Qatar Construction Standards (QCS 2014)
2.1.9. Applicable Products and Industry Standards
3. ABBREVIATIONS
1 KH Katara Hospitality (Contract Administrator on behalf of Abraj
Katara Lidartulfnadq W.L.L)
2 QPM Qatar Project Management (Project & Construction
Management Consultant)
3 DAR Dar Al Handasah (Project Design & Construction Supervision
Service Consultant)
KH-PK4b(i)-a-HBK-MST-A-0061 Page 3 of 14
Project Name: Lusail Katara Twin Tower Hotel
Document Title MST for the Block Glass Curved Ceiling Installation Date 14.03. 2022
Document No. KH-PK4b(i)-a-HBK-MST-A-0061 Rev. No. 0
4. RESOURCES
KH-PK4b(i)-a-HBK-MST-A-0061 Page 4 of 14
Project Name: Lusail Katara Twin Tower Hotel
Document Title MST for the Block Glass Curved Ceiling Installation Date 14.03. 2022
Document No. KH-PK4b(i)-a-HBK-MST-A-0061 Rev. No. 0
4.2. Manpower
Site Engineer Carpenters/Installers
QA/QC Engineer 0 laborers
Surveyor Technicians
Supervisors Helpers
4.3. Materials
Sn Type Description
1. GL-14A Glass Block
2. Steel Tubular Sections Sub-structure framing
3. Grout mortar For the fixation of the glass blocks
4. Steel re-bars Reinforcement
5 Fasteners Anchors, screws, through bolts etc.
6 Welding rods Welding of steel joints
7 Zinc Paints Protective Coating
4.3.1. Note: The above list of material provided is for general overview but are not limited to
above.
4.3.2. Additional materials or alternative materials may be used if required with respect to
approved shop drawings, material approvals and project specifications.
5. RESPONSIBILITIES
KH-PK4b(i)-a-HBK-MST-A-0061 Page 5 of 14
Project Name: Lusail Katara Twin Tower Hotel
Document Title MST for the Block Glass Curved Ceiling Installation Date 14.03. 2022
Document No. KH-PK4b(i)-a-HBK-MST-A-0061 Rev. No. 0
6. DESCRIPTION OF WORKS
6.1. Locations
6.1.1. Level 1, Gridlines: G to F: 12 to 16
KH-PK4b(i)-a-HBK-MST-A-0061 Page 6 of 14
Project Name: Lusail Katara Twin Tower Hotel
Document Title MST for the Block Glass Curved Ceiling Installation Date 14.03. 2022
Document No. KH-PK4b(i)-a-HBK-MST-A-0061 Rev. No. 0
7. METHODOLOGY
7.2. Examination
7.2.1. Examine openings, substrates, structural support, anchorage, and conditions, with
Installer present, for compliance with requirements for installation tolerances and other
conditions affecting the performance of Work.
7.2.2. Verify rough opening dimensions, levelness of threshold substrate, and operational
clearances.
7.2.3. Examine all adjacent works are completed and no hindrances are present.
7.2.4. Examine the surface of the substrate, make sure that the surface is free from any
protrusion, and lose materials or dust. This will optimize the bonding of the metal panel
to the substrate.
7.2.5. Proceed with installation only after unsatisfactory conditions have been corrected.
7.3. Fabrication
7.3.1. When actual site measurements have been taken, fabrication of steel structure can
proceed based on the cutting list generated as per the approved shop drawing.
KH-PK4b(i)-a-HBK-MST-A-0061 Page 7 of 14
Project Name: Lusail Katara Twin Tower Hotel
Document Title MST for the Block Glass Curved Ceiling Installation Date 14.03. 2022
Document No. KH-PK4b(i)-a-HBK-MST-A-0061 Rev. No. 0
7.3.2. Manufacturing /fabrication of frames and allied accessories for glass blocks installation
will take place in line with the approved design calculations, material submittal, and shop
drawing
Figure 1
7.4.4. Install the reinforcement bars between glass blocks as per the layout indicated in the
approved shop drawing
7.4.5. Arrange the 3rd party laboratory to perform the pullout test and welding test
7.4.6. Apply the protective zinc coats to the exposed steel and welding joints to ensure the rust
proofing of the sub-structure
7.5. Formworks
KH-PK4b(i)-a-HBK-MST-A-0061 Page 8 of 14
Project Name: Lusail Katara Twin Tower Hotel
Document Title MST for the Block Glass Curved Ceiling Installation Date 14.03. 2022
Document No. KH-PK4b(i)-a-HBK-MST-A-0061 Rev. No. 0
7.5.1. Install the formworks that will support the placement of glass blocks following the curved
shape of the ceiling
7.5.2. Ensure the formworks are clean, watertight aligned and properly supported.
7.6. Mockup
7.6.1. Prepare and agree with DAR for the glass block mockup at one portion of the works,
7.6.2. Obtain approval of the mock before proceeding to complete the entire system
7.6.3. The approved mockup shall be considered as part of the permanent works.
7.6.4. Upon completion of installation of framing supports, the installation of glass blocks
begins.
7.7.7. Place the reinforcement at the joints, between the glass blocks and along the perimeter
with steel bars that are shorter than the sides of the panel itself (to prevent them from
coming out and oxidizing).
7.7.8. If the panel must be laid on the supporting structure with two sides only, first insert the
rods perpendicular to the support and then the others.
KH-PK4b(i)-a-HBK-MST-A-0061 Page 9 of 14
Project Name: Lusail Katara Twin Tower Hotel
Document Title MST for the Block Glass Curved Ceiling Installation Date 14.03. 2022
Document No. KH-PK4b(i)-a-HBK-MST-A-0061 Rev. No. 0
7.7.9. Make sure that the bars are positioned in the middle of the space to prevent them from
touching the glass blocks. Refer to the following images:
7.7.10. Compact the mortar well and fill all spaces to make it impermeable.
7.7.11. Allow the mortar to cure and gain the designed strength as per the manufacturer’s
recommendation before the removal of the formworks
8. QUALITY
KH-PK4b(i)-a-HBK-MST-A-0061 Page 10 of 14
Project Name: Lusail Katara Twin Tower Hotel
Document Title MST for the Block Glass Curved Ceiling Installation Date 14.03. 2022
Document No. KH-PK4b(i)-a-HBK-MST-A-0061 Rev. No. 0
8.2. Documentation
8.2.1. Inspection Request (IR) Form will be submitted for various activities of blockwork with
adequate notice. Consultant Inspection Request (IR) shall be followed for all site work
activities and will be the verification documents for meeting the requirements of the
project.
8.2.2. The QA/QC Inspector will be responsible for completing Inspection Requests for these
activities and recording all checked items in the related Checklist for Block Works (Refer
to Attachment- 2)
10. ATTACHMENTS
10.1.1. Attachment 1 - ITP of Execution of Block Work
10.1.2. Attachment 2 - Checklist
10.1.3. Attachment 3 - Risk Assessment and Hazard Analysis
KH-PK4b(i)-a-HBK-MST-A-0061 Page 11 of 14
Project Name: Lusail Katara Twin Tower Hotel
Document Title MST for the Block Glass Curved Ceiling Installation Date 14.03. 2022
Document No. KH-PK4b(i)-a-HBK-MST-A-0061 Rev. No. 0
1.1.29.
1.1.30.
1.1.31.
1.1.32.
1.1.33.
1.1.34.
1.1.35.
1.1.36.
1.1.37.
1.1.38.
1.1.39.
1.1.40.
1.1.41.
1.1.42.
1.1.43.
1.1.44. Attachment 1
1.1.45. Inspection Checklist
KH-PK4b(i)-a-HBK-MST-A-0061 Page 12 of 14
Project Name: Lusail Katara Twin Tower Hotel
Document Title MST for the Block Glass Curved Ceiling Installation Date 14.03. 2022
Document No. KH-PK4b(i)-a-HBK-MST-A-0061 Rev. No. 0
1.1.46. Attachment 2
1.1.47. ITP
KH-PK4b(i)-a-HBK-MST-A-0061 Page 13 of 14
Project Name: Lusail Katara Twin Tower Hotel
Document Title MST for the Block Glass Curved Ceiling Installation Date 14.03. 2022
Document No. KH-PK4b(i)-a-HBK-MST-A-0061 Rev. No. 0
1.1.48. Attachment 3
1.1.49. Risk Assessment
KH-PK4b(i)-a-HBK-MST-A-0061 Page 14 of 14