Professional Documents
Culture Documents
GIS 31-011 7 December 2004
GIS 31-011 7 December 2004
GIS 31-011
Applicability Group
Date 7 December 2004
GIS 31-011
BP GROUP
ENGINEERING TECHNICAL PRACTICES
7 December 2004 GIS 31-011
Guidance on Industry Standard for Analyser Houses to IEC TR 61831
Foreword
This is the first issue of Engineering Technical Practice (ETP) GIS 31-011. This Guidance on Industry
Standard (GIS) is based on parts of heritage documents from the merged BP companies as follows:
Amoco (ACES)
A PC-PA-00-E Process Control—Process Analysers—Engineering Specification
A PC-PA-00-G Process Control—Process Analysers—Guide
A PC-PA-00-P Process Control—Process Analysers—Supply Specification
ARCO (APCES)
Std 312-92 Analysers
Copyright 2004,
2003, BP Group. All rights reserved. The information contained in this
document is subject to the terms and conditions of the agreement or contract under which
the document was supplied to the recipient’s organization. None of the information
contained in this document shall be disclosed outside the recipient’s own organization
without the prior written permission of Manager, Standards, BP Group, unless the terms of
such agreement or contract expressly allow.
Table of Contents
Page
Foreword .............................................................................................................................................. 2
Introduction .......................................................................................................................................... 5
2.6 Safety facilities ................................................................................................................ 6
2.7 Manual isolation of electrical and process supplies ....................................................... 6
2.9 Alarm indication............................................................................................................... 6
3 Housings ..................................................................................................................................... 6
3.3 Selection of housing........................................................................................................ 6
3.4 Area classification and toxic danger ............................................................................... 7
3.5 Construction and mounting ............................................................................................. 7
3.6 Analyser housing ventilation requirements..................................................................... 8
3.7 Design for natural ventilation .......................................................................................... 8
3.8 Design for forced ventilation ........................................................................................... 8
3.9 Analyser housing safety monitors and alarms................................................................ 9
4 Sampling systems ...................................................................................................................... 9
4.1 Introduction...................................................................................................................... 9
4.4 Sample point location...................................................................................................... 9
4.6 By-pass systems ............................................................................................................. 9
4.10 Construction .................................................................................................................... 9
4.11 Effluent disposal .............................................................................................................. 9
4.12 Calibration facilities ......................................................................................................... 9
4.13 Automatic calibration/validation ...................................................................................... 9
5 Analyser communications .......................................................................................................... 9
5.2 Signal transmission ......................................................................................................... 9
5.3 Safety .............................................................................................................................. 9
5.4 Cables ............................................................................................................................. 9
5.5 Linearisation .................................................................................................................... 9
5.6 Use of signal.................................................................................................................... 9
6 Drawings and data...................................................................................................................... 9
7 Inspection and testing................................................................................................................. 9
7.1 Factory acceptance testing (FAT)................................................................................... 9
7.2 Site acceptance testing (SAT) ........................................................................................ 9
8 System start-up and commissioning .......................................................................................... 9
9 Shipping and marking................................................................................................................. 9
10 Identification/Nameplates ........................................................................................................... 9
11 Responsibility.............................................................................................................................. 9
11.1 Analyzer system supplier ................................................................................................ 9
11.2 Purchaser ........................................................................................................................ 9
Introduction
a. Guidance for analyser houses is based on IEC TR 61831, On-line analyser systems –
Guide to design and installation, first edition July 1999.
b. Guidance statements of this GIS are modifications to IEC TR 61831.
c. Modifications to IEC TR 61831 are identified as Add, Modify to Read, or Delete.
d. Section numbers in this GIS correspond to IEC TR 61831.
e. Sections of IEC TR 61831 that are not revised remain applicable.
1 General
3 Housings
practice to operate at an over pressure of 2 mbar to 5 mbar which meets the primary requirement
with a good factor of safety without causing discomfort to personnel and undue stress on the
house structure.
3.9.1 General
Modify Second Paragraph to Read
The primary safeguard for the analyser installations is the design of the equipment to the
required standards (e.g. zones 1 and 2). Flammable gas, toxic gas and oxygen deficiency
detectors shall be fitted as an additional safeguard, the detecting heads being located at key
points within the AH, cabinet or shelter. The detector heads and associated electronics shall be
suitable for continued operation during the period of hazard they are detecting, e.g. certified for
zone 1 hazardous area for flammable materials.
Modify Fourth Paragraph to Read
If suitably certified zone 1 or zone 2 analysers are not available then they shall be fitted with an
air purge system designed to CENELEC EN 50016, IEC 60079-2, or NFPA 496. Otherwise the
analyzer shall be considered general purpose equipment. Each purged analyser shall have its
own individual purge system.
Add to Fifth Paragraph
Shutdown and alarms indications specified as critical shall be transmitted to a continuously
manned control room.
A visual indication of the pressure differential between the analyser house and the external
atmosphere should be provided at the primary entrance point to the analyzer house.
The above trip functions shall operate independently of any house ventilation and/or toxic
exhaust extraction system failures.
Toxic gas detection is to be considered an added safeguard and shall not substitute for
ventilation trips other than allowing either limited continued operation (24 hr maximum) of
analysers handling high toxic concentrations on failure of associated exhaust extraction systems,
or continued operation of analysers handling diluted samples upon main house ventilation
failure.
Consideration can be given to providing back-up ventilation to increase dilution rates in the
event of a toxic gas detection. If this is provided then the trip functions above will depend on
whether the gas concentration is reduced or not. However this shall not delay alarms and any
actions to investigate and correct for the original hazard detection.
The design of fire detection and protection systems shall be in accordance with GP 30-85.
3.9.8 Alarms
Modify to Read
The following analyser house related local alarms/indicators shall be generated and displayed:
a) ventilation flow or house purge pressure low*;
b) combustibles present (>20 % LEL)*;
c) fan 1 failure;
d) fan 2 failure;
e) oxygen deficiency*;
f). exhaust system failure – if applicable;
g) toxic gas present (< long term OEL) – if applicable*;
h) fire detected – if applicable*;
i) extinguishant released – if applicable*;
j) common shutdown/alarm bypass in operation*.
4 Sampling systems
4.1 Introduction
Delete Last Paragraph
Add
Sample systems shall be assembled and tested in accordance with GIS 31-002.
4.10 Construction
4.10.1 General
Modify to Read
The line size(s) of circulation loops can be determined from annex C with due regard to the
response time required.
Piping up to and including the first isolation valve shall be to the process piping specifications.
Fast circulating loops should be considered as part of the process system and as such due regard
should be paid to the relevant piping specifications.
For other sampling systems it is common practice to meet the process piping specification up to
devices which will restrict the flow, e.g. pressure regulators, restrictors or small bore tubing.
The number of joints in sample lines shall be kept to a minimum. The method of jointing shall
conform to the relevant piping specifications.
Sample lines shall be provided with drains and vents as necessary. Piping layouts which would
create traps shall be avoided. Piping shall be sloped towards drain and vent points as
appropriate.
Provision shall be made for depressurising and safe disposal of the process fluid on plant or
analyser shutdown.
Liquid samples which have been vapourised shall be heat-traced, thermally insulated and clad as
necessary to ensure that sample flow rates are maintained under all weather conditions.
4.10.8 Instrumentation
Modify to Read
Fast loop flows, the sample stream flow to each analyser and any by-pass stream flows, shall be
indicated locally.
Glass tube variable area flow meters may be used with the approval of the user as local
indicators for low risk service such as clean and non-corrosive samples under conditions of near
ambient temperature, low pressure and low flow. If used they shall be mechanically protected
and shrouded to prevent injury in case of tube failure. For high-risk service generally stainless
steel variable area meters shall be used or an alternative approved method (e.g. variable area
orifice, turbine meter or differential pressure cell).
The sample pressure and, if necessary, the temperature shall be indicated at the analyzer inlet.
Downloaded Date: 6/17/2008 10:41:39 PM
The latest update of this document is located in the BP ETP and Projects Library
Page 15 of 26
7 December 2004 GIS 31-011
Guidance on Industry Standard for Analyser Houses to IEC TR 61831
Pressures shall be indicated at appropriate points in the sample system, e.g. upstream and
downstream of regulators, upstream and downstream of filters, suction and discharge from
pumps, at relief valves, etc. However care shall be taken to minimise dead legs/volumes by
close coupling, especially in the relatively low flow rate sections delivering the final sample to
the analyser.
Temperature shall be indicated at appropriate points in the sample system, e.g. after heat
exchangers, at inlet and outlet of heat traced sections, etc.
4.10.9 Identification
Modify to Read
Sample take-off and return points, isolating valves and sampling lines shall be identified and
permanently labeled.
4.11.1 General
Modify to Read
Flammable and toxic materials shall be disposed of in a safe manner
4.11.2 Vapour
Modify to Read
Effluents shall be disposed of to approved closed vent systems. Direct independent discharges to
atmosphere from local vents shall be avoided.
Many cyclic analysers, such as chromatographs, sample and operate at atmospheric pressure and
cannot tolerate discharge to closed systems. To minimise sample discharge to atmosphere, use
shall be made of what are termed "minimum pollution sample systems".
These allow sample flows through the analyser sample valve to a closed vent system or even
back to the process whilst letting the analyser still perform its sampling at atmospheric pressure
by isolation of the small section containing the sample valve, opening it to an atmospheric vent
and giving time to stabilise at atmospheric pressure before sample injection (see Annex 1).
Regardless of allowing sampling at atmospheric pressure, there is still a requirement for
atmospheric vents from chromatograph columns, detectors and other systems where back
pressure variations and/or back contamination may have a significant effect on operation. These
vents should be completely independent.
The atmospheric vent line shall be sized to comply with manufacturer'
s limits for back pressure,
preferably not smaller than 10 mm I.D.
The tops of all vent lines shall be arranged to prevent entry of rainwater and, where necessary,
to prevent wind effects on the analyser. Each vent shall have a water/ condensate pot with a
drain valve or alternative (e.g. goose neck) at the lowest point.
Flame arrestors shall be fitted on vents with flammable vapours.
4.11.3 Liquid
Modify to Read
Liquid hydrocarbon samples shall be returned directly to the process or discharged to the plant
slops system, the method of disposal being dependent on the value or difficult nature (e.g.
waxy) of the sample and the quantities involved.
In accordance with appropriate environmental practices the disposal of hydrocarbon to oily
water drain or open sewer systems shall be avoided.
Downloaded Date: 6/17/2008 10:41:39 PM
The latest update of this document is located in the BP ETP and Projects Library
Page 16 of 26
7 December 2004 GIS 31-011
Guidance on Industry Standard for Analyser Houses to IEC TR 61831
Where direct return of the sample to the process is required, this may be by either a pump
associated with each analyser system or via sample recovery systems, e.g. a common sump tank
with controlled pump-out.
Sump tanks shall be provided with:
a) automatic pump-out;
b) high and low level alarms;
c) atmospheric vent which may need a flame arrestor if samples have vapour pressures
above atmospheric pressure;
d) manual drain valve.
e) A level switch should be fitted and configured to isolate the sample recovery unit on hi-hi
level.
Analysers shall be located such that their outlets are at a sufficient elevation in respect to drain
headers. Drain lines from the analysers shall be routed directly to the drain header without
valves.
Drain lines shall be of sufficient size to prevent back-pressure on the analyser systems and shall
slope and be vented as necessary to prevent air locks.
When disposing of materials to drain, care must be taken to ensure the drain system is suitable
particularly where toxic, flammable, corrosive or waxy fluids are concerned.
Modify to Read
5 Analyser communications
5.3 Safety
Modify Last Paragraph to Read
When analysers are shut down/isolated either for maintenance or as a result of hazard initiated
trips (ventilation failure/gas detection, etc.) special attention shall be paid to parts of the
electrical circuits within the analyser remaining powered via the external transmission lines
which could present ignition and/or electrical shock hazards. Digital contacts which may have
non-intrinsically safe voltages applied, digital highways, and other circuits which may be
electrically uncertified, shall be fitted with special isolation relays mounted in safe areas or in
certified enclosures to provide a means of automatic isolation.
5.4 Cables
Modify Last Sentence to Read
Optical fibre cables should be in accordance with GIS 12-157 or GIS 12-158.
5.5 Linearisation
Delete
Add
In addition to the information furnished in the quotation, as a supplier, the supplier shall
expeditiously submit any drawings or test data required by purchaser for planning, layout,
installation, maintenance, and record purposes. The number of copies and the format shall be
specified in the purchase order.
The supplier shall identify all drawings and data with purchaser job number, complete purchase
order number, client's name, job location, item number and service description. The supplier' s
drawings and data sheets shall include revisions boxes to describe the latest revisions in full
detail.
The supplier shall furnish certified "as built" drawings in the form specified on the purchase
order. The drawings shall show as a minimum:
a) All dimensions.
b) The size, type, location, and identification of all electrical field connections. (Terminal
boxes)
c) The size, type, location, and identification of all utility connections.
d) Wiring diagrams for the complete system identifying all termination. These drawings shall
include wiring type, size, and shielding; also these diagrams shall clearly identify each
connection to be made by purchaser.
e) The drawings and documents shall be in English.
The following engineering drawings and documents shall be submitted for approval:
a) Drawing Index, Shelter
b) Substructure (Skid) Detail
c) Door and Wall-Panel Location
d) Front and Left Elevation
e) Rear and Right Elevation
f) Plan View, Shelter
g) Floor Plan, Shelter Interior
h) Electrical Arrangement Diagram
supplied by the Supplier shall be pressurized to 1.5 times working pressure with
Helium/nitrogen. Maximum leakage through the bubbler shall be one bubble or less in
60 seconds. If pressurized higher than 50 psig (345 kPag) with Helium/nitrogen, the maximum
permissible leakage rates are as follows:
1. Gas systems - 5 percent change per hour of the specified design pressure.
2. Liquid Systems - No visible leakage.
c) Dimensions shall be checked against the final approved drawings.
d) The complete analyzer system(s) shall be tested and set up to verify the correct functioning of
the supplied equipment using certified calibration samples provided by the supplier. The test
samples shall be at the conditions and of the composition specified by the purchaser. A
minimum of two unique gases shall be used for system checkout to prove linearity/accuracy
through out the range of expected results. A continuous operational test shall be conducted for
each analyzer for a minimum of 24 hours. This 24 hours operational test may be waived by
purchaser and/or client if such test has already been performed at the analyzer factory. All
recordings shall be submitted together with a copy of the test report to the purchaser for
approval. Costs for the above operation tests shall be listed separately in the Supplier's quoted
price. Data collected during the 24 hour operational test shall be subjected to statistical analysis.
e) Alarms or alarm functions, safety systems, and other devices required by the order shall be
demonstrated for proper function.
f) Full hook-up, functional test and documentation of the local network including fiber-optic and
related communication package is required.
g) If the factory test is not run at the specified voltage and frequency, the suitability of the
equipment for the specified voltage and frequency shall be established by nameplate data of
equipment components or certified by the equipment components'manufacturers.
h) Hydrostatic testing on pipe, excluding analyzer piping and sample system piping, shall be
done as follows:
1. All piping shall be hydrostatically tested at 1 1/2 times the design pressure.
2. Piping systems in vacuum service shall be tested for full vacuum.
3. Austenitic stainless steel piping shall be tested and flushed with water having less than
500 ppm (500 mg/L) chlorides. Potable water should meet this requirement. The piping
and tubing shall be drained immediately after flushing and dried by blowing with clean
filtered air.
i) On gas chromatographs, where background components in the sample may interfere with the
measured components, the concentration of these components shall be varied to demonstrate
that measurement is free of any interference.
Inspections and testing shall be documented in writing by the supplier and submitted to the
purchaser for approval. Shipment cannot be made without written approval from the purchaser.
Costs associated with inspection and customer witness testing shall be included in the supplier'
s
quoted price for the analyzer systems.
The process analyzer supplier shall provide a start-up service proposal to include a competent
applications engineer for review of the installation, to supervise calibration and provide initial
plant-site start-up. Proposal shall state terms of this service. The person shall be competent,
familiar with project requirements and experienced in trouble shooting, diagnosing the problems
and bringing the analyzer system on line. In any case, the process analyzer' s physical and
performance warranties shall be preserved for client.
Seller shall furnish a master shipping list, in advance of the shipment, listing total quantities of
each section, subassembly, or piece required for the complete shipment.
Seller shall include a packing list in each shipment, listing the contents by assembly piece mark,
individual instrument tag number and piece mark, or by item number of each box, crate, bag,
and skid. The list shall state whether the contents are complete or partial.
Seller shall include, on all shipments, a copy of each instruction manual, all drawings required
for assembly, installation, or erection; and one extra copy of all data required under
Paragraph 1.3.1. These documents preferably shall be attached to the inside of the largest crate
in the shipment and this crate shall be marked accordingly. (Copies are independent of SDR,
Supplier Data Requirements.)
Openings shall be plugged or blanketed to keep out foreign matter. Threaded connections shall
be fitted with a plug for the female end, and a thread protector for the male end.
Analyzer shelter and equipment supplied shall be packaged properly for shipment. The supplier
shall supply the purchaser with shipment details.
10 Identification/Nameplates
The process analyzer shelter supplier shall permanently affix nameplates to both sides of each
wall penetration, clearly identifying source and/or service of that line.
The shelter itself shall have a permanently affixed nameplate indicating project number, P. O.
number, date of order, and analyzers that are mounted inside. Nameplates shall be white
laminated plastic with letters engraved into the black core. Tags shall be fixed in place with
RTV sealant on interior locations and with stainless steel screws on exterior locations.
Analyzers and related equipment shall have the following identifying information on their
nameplate permanently fastened to the analyzer:
a) Equipment identification number.
b) Manufacturer's name, model, serial number, operating range, output signal and range, and
supply voltage and frequency.
c) Pressure rating of supplied components.
d) Materials of parts exposed to process fluids.
e) Electrical area classification for which analyser is suitable.
11 Responsibility
Materials and system design shall meet or exceed specifications described in this document.
Material selection and system design are subject to client and/or purchaser'
s acceptance.
Supplier shall comply with any local rules or regulations which are specified by the purchaser.
Supplier shall be responsible for all wiring and piping from the analyzer system to well-defined
junctions outside the analyzer shelter.
The analyzer system shall include all required sample conditioning and handling equipment and
peripherals described in this requisition and the reference documents.
Supplier shall provide sizing of sample line to calculate the transport time to meet the sample
analysis time requirements.
Supplier shall be responsible for informing the purchaser of all services, equipment and utilities
required at the analyzer shelter.
Supplier shall provide drawings and documents the purchaser will require for connecting
utilities and sample lines to the analyzer house.
Supplier shall be responsible for the commissioning and testing of the analyzer system and shall
make available technical assistance during the guarantee period.
Supplier shall be responsible for providing on site training, as required, by the client for the
operation, maintenance and repair of all the equipment in the analyzer system.
Supplier shall be responsible for providing all test equipment, carrier gases and related
equipment for the FAT test.
Supplier shall specify any required gases at the time of initial offering or proposal.
Supplier shall submit a monthly progress report on all phases of engineering including the
analyzer delivery, drawing review, material purchases, construction, factory testing, on-site
installation, onsite testing and start-up.
Supplier shall inform the Purchaser immediately of any delivery slippages greater than two
weeks that is related to any component within the Supplier'
s scope of work.
Supplier shall provide details of tie-down attachments, dimensions and construction notes of
foundation pads.
Supplier shall provide any special tools and hardware for assembly.
Supplier shall recommend and quote any additional equipment required for the calibration,
programming and operation of the analyzer systems.
Supplier shall respond in his proposal to each paragraph of this specification. Any exceptions
taken shall be noted on a paragraph by paragraph basis.
Supplier shall provide in his quotation a complete list of utilities required, such as cooling
water, instrument air, steam and electrical power. The list shall include quantities, flow rates,
pressures, voltage and other defining parameters for the utilities to be supplied by the owner,
including minimum quality and maximum pressure rating for all required utilities.
Supplier shall identify all consumables, such as calibration and carrier gases, and provide
anticipated rates of consumption for the analyzer systems proposed.
Sample system shall be designed with personnel safety in mind. Suitable precautions shall be
taken for toxicity, burns from exposure to hot spots and venting to safe locations.
Supplier shall provide pressure relief valve to prevent overpressure.
Venting to flare header is not permitted, unless approved by the Purchaser.
Supplier shall meet government regulations such as EPA and OSHA.
11.2 Purchaser
Purchaser shall provide analyzer data sheets with appropriate stream composition data and
physical conditions.
Purchaser shall be responsible for providing the utilities to the analyzer house in the field. These
shall include air, water, steam, electricity, etc., along with any other service required in writing
by the Supplier.
Purchaser shall review and comment on supplier'
s specification and design of the analyzer
sample systems and the analyzer house.
Annex L
d) Process Conditions
Pressure (barg)
Max Min Typical
Temperature ºC
Max Min Typical
.......... ....................
.......... ....................
.......... ....................
The house(s) will each contain ...........................analysers identified by the following tag numbers:
Provision for installation of .................................................. is to be made. These have the following reserved
tag numbers.