Project Management Processes-Practice Exam

Practice Exam-Question
1. In which project management process group is the detailed project budget
created?

A. Initiating
B. Before the project management process
C. Planning
D. Executing
2. The Project Charter is created in which project management process group?
A. Executing
B. Planning
C. Closing
D. Initiating
3. The project team has just completed the initial project schedule and budget. The
NEXT thing to do is:

A. begin risk identification


B. begin iterations
C. determine communication requirements
D. create a bar (Gannt) charts

4. A detailed project schedule can be created only after creating the:


A. project manager
B. work breakdown structure
C. project management plan
D. detailed risk assessment
5. The person who should be in control of the project during project management
Planning is the:
A. Project manager
B. Team leader
C. Functional manager
D. Sponsor
6. Which of the following is NOT an input to the initiating process group?
A. Company processes
B. The company culture
C. Historical WBSs
D. Project scopestatement
7. The project sponsor has just provided the preliminary project scope statement.
What is the NEXT thing to do?

1
Project Management Processes-Practice Exam
A. Begin to complete work packages
B. Complete scope verification
C. Start integrated change control
D. Start to create management plans
8. The high-level project schedule constraints have just been determined. What
Project management process group are you in?

A. Initiating
B. Planning
C. Executing
D. Monitoring & controlling
9. The WBS and WBS dictionary are completed. The project team has begun
working on identifying risks. The sponsor contacts the project manager,
requesting that the responsibility assignment matrix be issued. The project has a
budget of U.S.$100,000 and is taking place in three countries using 14 human
resources. There is little risk expected for project and the projects similar to this
one. what is the next thing to do?
A. Understanding the experience of the sponsor on similar projects
B. Create an activity list
C. Make sure the project scope is defined
D. Complete risk management and issue the responsibility assignment
matrix
10. A project manager does not have much time to spend planning before the
Mandatory start date arrives. He therefore wants to move through planning as
effectively as possible. Which of the following would you recommend?
A. Make sure you have a completed preliminary project scope statement and
then start the WBS
B. Create an activity list before creating a network diagram
C. Document all the known risks before you document the high-level
assumption
D. Finalize the quality management plan before you determine quality
metrics