This document summarizes excavation work for Project Ditch Pit Selatan. It involves 4 segments with total excavation volumes of 6,446.55 cubic meters. Segment 1 involves excavation of 3,055.80 cubic meters of material from an elevation of 60.22 meters to 55 meters. Segment 2 involves excavating 3,416.44 cubic meters of material from an elevation of 62.58 meters to 55 meters. Segment 3 involves excavating 623.31 cubic meters of material with a top elevation of 56.67 meters and bottom elevation of 55 meters. Segment 4 involves excavating 1,350 cubic meters of material to a depth of 3 meters. The schedule shows work being done over 8 days in shifts.
This document summarizes excavation work for Project Ditch Pit Selatan. It involves 4 segments with total excavation volumes of 6,446.55 cubic meters. Segment 1 involves excavation of 3,055.80 cubic meters of material from an elevation of 60.22 meters to 55 meters. Segment 2 involves excavating 3,416.44 cubic meters of material from an elevation of 62.58 meters to 55 meters. Segment 3 involves excavating 623.31 cubic meters of material with a top elevation of 56.67 meters and bottom elevation of 55 meters. Segment 4 involves excavating 1,350 cubic meters of material to a depth of 3 meters. The schedule shows work being done over 8 days in shifts.
This document summarizes excavation work for Project Ditch Pit Selatan. It involves 4 segments with total excavation volumes of 6,446.55 cubic meters. Segment 1 involves excavation of 3,055.80 cubic meters of material from an elevation of 60.22 meters to 55 meters. Segment 2 involves excavating 3,416.44 cubic meters of material from an elevation of 62.58 meters to 55 meters. Segment 3 involves excavating 623.31 cubic meters of material with a top elevation of 56.67 meters and bottom elevation of 55 meters. Segment 4 involves excavating 1,350 cubic meters of material to a depth of 3 meters. The schedule shows work being done over 8 days in shifts.
Dimensi 10 x 10 m Kedalaman 3 m Jarak 5 m Segment 3
Volume 623.31 BCM
Top El. 56.67 m Bottom El. 55 m Cut +- 2 m Side Cast Top Soil
Batas IPPKH Volume 1771 LCM
01 = 727.3 LCM 02 = 795.9 LCM 03 = 140 LCM 04 = 107.8 LCM 04 Segment 2 03 Volume 3,416.44 BCM Segment 1 Top El. 62.58 m 02 Volume 3,055.80 BCM Bottom El. 55 m Cut +- 7.5 m Top El. 60.22 m Bottom El. 55 m 01 Cut +- 5 m Hari ke- No Aktifitas Alat Segmen Volume Satuan Remark 1 2 3 4 5 6 7 8 SOUTH PIT ACTIVITIES P 1 1 1 Side Cast Top Soil EX 1318 1-2 1,771.00 Lcm A P 1 1 EX 1318 1 3,055.80 Bcm A P 1 1 2 Pembuatan Ditch EX 1318 2 3416.44 Bcm A P 0.5 EX 1318 3 623.31 Bcm A P 0.5 1 3 Pembuatan Settling Pond EX 1318 4 1350.00 Bcm A
2 Ortho Update : 15 July 2023
1 1 1 1 1 1 1 1 8 Noted : Operasional hanya dilakukan pada shift siang 1 2 3 4 5 6 7 8 13% 25% 38% 50% 63% 75% 88% 100% THANK YOU