Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/292659614

But-for schedules - Analysis and defense

Article · August 2001

CITATIONS READS
39 1,559

1 author:

James Zack
Ankura Construction Forum
18 PUBLICATIONS   169 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Delivering Dispute Free Projects - Does Partnering Help Achieve This Goal? View project

Alternative Dispute Resolution - Your Key To Staying Out of Court View project

All content following this page was uploaded by James Zack on 09 November 2017.

The user has requested enhancement of the downloaded file.


T ECHNICAL A RTICLE

strate why the project was completed later


But-For Schedules—Analysis and than planned. Again, the selection of what
new activities are added to the schedule
Defense depends upon who is performing the
schedule analysis.

But-For Schedules
James G. Zack Jr. This technique is also referred to as the
collapsed as-built schedule analysis tech-
ABSTRACT: The purpose of this article is to discuss the use and abuse of but-for sched- nique. This technique attempts to create an
ules (sometimes called collapsed as-built schedules) in today’s claims oriented con- as-built schedule, identify “actual delays”
struction industry. This article also discusses ways to analyze but-for schedules when caused by two parties, and then remove
they are presented as evidence of either an excusable or a compensable delay. Finally, one party’s delays from the as-built sched-
the article discusses ways to defend against but-for schedules should the reader need to ule to “collapse” the schedule leaving in
do this in negotiation, litigation or some alternative dispute resolution forum (e.g., the schedule those delays caused solely by
mediation, arbitration, summary jury trial, etc.). the other party. The argument is, “but-for
the other party’s delays, this is when the
KEY WORDS: but-for schedules, claims, delay, dispute resolution, and mediation project would have been completed.” The
amount of delay and the resulting damage
ut-for schedules are usually used CPM Update Review

B
are then calculated.
to present delays and time This technique makes no attempt to
extension requests after a project create a separate delay analysis diagram.
is built. They are more reliable The technique examines each progress Windows Analysis
than several other delay analysis tech- schedule update submitted on the project This technique is occasionally referred
niques. They are, however, subject to abuse and explains what caused the delay on each to as contemporaneous period analysis [1].
and manipulation. Those faced with the update without performing any further The technique is to validate the as-planned
task of analyzing such delay analyses need analysis. Again, the explanation of delay or baseline schedule, and then, using con-
to be cautious. Reviewers must ascertain depends on whether the owner or the con- temporaneous project documentation,
that a but-for schedule presented in support tractor is doing the analysis. update the schedule one period at a time
of a claim has not been abused so badly as (monthly, quarterly, seasonally, etc.). The
to render it meaningless or dangerous. This technique builds one period analysis upon
article discusses ways to do this. As-Planned Versus As-Built Analysis the previous period’s analysis, examining
Like the bar chart analysis above, this each new period for delay, causation, and
technique simply compares the baseline or liability as the analysis proceeds. This
DELAY ANALYSIS TECHNIQUES as-planned schedule with the final or as- method puts delays in their proper time
built schedule. This analysis is similar to a frame within the overall context of the
There are, generally, seven analytical total cost claim analysis wherein one sub- project.
techniques used to perform schedule delay tracts the amount paid from the amount
analysis. expended to calculate the amount owed.
With respect to time, this type of analysis Linear Schedule Analysis
subtracts the time planned from the actual This technique is only used with linear
Bar Chart Analysis time expended to determine the time type projects (water mains, sewer lines,
This form of schedule analysis com- owed, thus presenting a “total time claim” highway construction, etc.). It is a form of
pares an as-planned bar chart with an as- with an explanation about why the time progress quantity charting applied to the
built bar chart. The concept portrayed is was extended and how it was the other progress of a specific construction project;
that the activities shown on the bar chart party’s “fault.” it plots construction activity progress over
would have been completed exactly as time. The delay analysis technique com-
planned, were it not for certain delays. The pares as-planned to actual linear progress
delays indicated in the analysis (that are Impacted As-Planned Analysis (similar to plotting as-planned versus actual
typically shown simply as extended bars) This technique is sometimes referred cash flow curves, for example). The analyst
are highly dependent upon whether the to as the as-planned plus delay technique. then offers an explanation of why the two
owner or the contractor is performing the In this technique, the scheduler simply lines diverged when they did (that is, cau-
analysis. The analysis is merely graphical, takes the as-planned schedule and adds sation and liability) in an effort to justify
and systematically ignores the lack of new activities that represent delays (gener- the delay requested.
underlying logic between the activities. ally caused by the other party) to demon-
Cost Engineering Vol. 43/No. 8 AUGUST 2001 13
BUT-FOR SCHEDULES contend that they should not be relied on rectness? There are, in my opinion, three
unless a great deal of independent research ways to accomplish this, as set forth below.
Why Are But-For Schedules So Popular? and analysis is done.
Bar charts largely have been aban- • Challenge assumptions—as noted
doned in public works construction in the above, a series of assumptions have
US in favor of critical path method (CPM) But-For Schedules—Underlying been made by the scheduler preparing
scheduling, while linear scheduling, Assumptions the but-for schedule. Challenge these
because of its inherently narrow range of As with any methodology, there are a assumptions to test for accuracy in
applicability, is infrequently used. number of assumptions that underlie the each specific case.
Therefore, these two schedule analysis theory of the but-for schedule. These • Challenge theory—question the theo-
techniques are rare due to the infrequent assumptions are listed briefly below. ry concerning the but-for schedule to
use of the scheduling methodology they are see if it has been accurately applied to
applied to. As-planned versus as-built • While unstated, it is generally implied this specific delay analysis.
schedule analysis (the total time claim) and that an as-built critical path is readily • Challenge analysis—use the reviewer’s
the CPM update review method have a identifiable. The portrayal most fre- analysis of the project documentation
number of critical flaws, that are beyond quently offered is that one can “look to challenge the but-for schedule to
the scope of this article to discuss. backward” down the as-built critical test the objectivity of the scheduler
Therefore, they are rarely used today in lit- path to determine what events or activ- and the accuracy of the work.
igation. The impacted as-planned tech- ities actually caused the project to be
nique has so many flaws that most courts completed late. Once the reviewer has performed the
have widely discarded its use. • Also unstated is the implication that above tasks, a conclusion can be reached
This generally limits the scheduler to there was but a single, unchanging concerning the objectiveness of the sched-
the remaining two delay analysis tech- critical path that can be identified at uler preparing the but-for schedule, as well
niques. While windows analysis is probably the end of the project and analyzed for as the accuracy and reliability of the but-for
the more accurate of the two delay analysis delay and causation purposes for the schedule presented in support of a claim.
techniques, it is usually more expensive entire project duration.
due to the amount of time and effort need- • Another unstated assumption is that
ed to perform it. It also typically takes the project would have been built the CHALLENGE ASSUMPTIONS
longer to perform, due to the need to vali- exact same way if the various project
date all scheduling data used in the analy- delays had not arisen. The assumption The most fundamental assumption
sis. Thus, if the time and budget needed to is that the contractor made no attempt underlying an as-built schedule is that an
perform a delay analysis are limited, win- to change the schedule to mitigate the as-built critical path can be easily identi-
dows analysis may not be achievable within effect of delays. fied, reviewed, and analyzed to ascertain
the confines of these two constraints. • It is also assumed that accurate start delays, but can an as-built critical path
But-for schedules are frequently used and completion dates are available actually be calculated?
when performing a delay analysis. But-for from project records for every schedule By definition, the “critical path” is the
schedules generally require less time and activity. Thus, one need only find and longest uninterrupted chain of events
less effort. They can normally be done record these dates to fill out this analy- through the schedule network. The critical
more quickly and at less cost than a win- sis. path dictates the length of the project as it
dows analysis. But-for schedules are, how- • Once as-built start and complete dates is “ . . . the longest path into the last event,
ever, more easily manipulated, so the are determined, it is assumed that work since it establishes the latest event time for
scheduler is more likely to be able to on each activity is continuous for the that last event [2].” A project’s critical path
demonstrate the point trying to be made. entire time between the start and com- is computed by the forward and backward
Schedulers using this technique gener- pletion dates. passes that mathematically identify the
ally refer to the “as-built critical path,” • Yet another assumption is that as-built longest uninterrupted chain of events
which they say has been calculated from schedule logic can be entered easily through the network. These calculations
“as-built information.” The implication is once the as-built dates are found. are entirely dependent on the activity dura-
that this form of scheduling analysis is • Finally, it is assumed that the sched- tions and logic (or sequence of activities)
based solely on facts. Additionally, since uler has reviewed all project docu- input by the scheduler.
the scheduler constantly refers to “as-built mentation and interpreted the infor- The critical path is determined by a
dates,” it appears that this schedule analysis mation objectively and accurately. forward-looking set of calculations only! It
is highly accurate. The analysis resulting starts at a point in time and calculates how
from but-for schedules is easily understood, long it will take to reach the project’s end.
making them very popular with schedulers But-For Schedules—Analysis and Defense By definition then, an “as-built” critical
and claims consultants. Because of the If presented with a but-for schedule, path cannot be calculated as all activities
above reasons, most people reviewing a what analysis should be performed? How on an as-built schedule are completed.
but-for schedule will conclude that it is fac- can an owner or owner’s representative (Unless, of course, schedule activities have
tual, accurate, and correct. But-for sched- defend against a but-for schedule with its been left unstatused by the scheduler. If
ules are, however, deceptively simple. I implied factual basis, accuracy, and cor- they are unstatused, then the schedule is

14 Cost Engineering Vol. 43/No. 8 AUGUST 2001


not an “as-built schedule.”) While com- project and can be analyzed for delay at the If they were, then this theory has been
pleted activities are identifiable and actual end of the job. This assumption ignores shown to be unsupported, at least insofar as
durations perhaps known, the schedule reality and thus is subject to serious chal- this specific analysis is concerned. If “pac-
logic no longer comes into play in the cal- lenge. ing delays” [3] can be demonstrated by the
culation process. One cannot therefore reviewer, then this is proof that the speed of
“calculate” an as-built critical path. “As- the project would not have been the same.
built” critical paths can be identified, per- CHALLENGE THEORY The third theory subject to challenge is
haps, but a great deal of judgment goes into perhaps the most important of all. Were the
such an effort, and manipulation of the There are three aspects of the theory of activities on the but-for schedule prosecuted
schedule is accomplished. This is consider- but-for schedules that are subject to attack. continuously from start to finish? This is the
ably different than “calculating” a critical First, would the work of the project way most schedulers show an activity on the
path! have been done in the same manner had but-for schedule. The scheduler will show
Equally open to challenge is the the delays not occurred? It is my experi- “install conduit, basin 1” with an actual
assumption that there was a single, ence that contractors faced with delays start of June 1, 1998, and an actual comple-
unchanging critical path throughout the (both critical and noncritical) will rese- tion of June 30, 1998. The unstated impli-
life of a project. It is my experience that a quence activities in order to compensate. cation, of course, is that this activity actual-
schedule and its critical path are dynamic Contractors do this to mitigate potential ly took 30 calendar days, or 22 work days,
in nature. They are subject to change for a effect or damage. Sometimes, schedule and was prosecuted continuously—work
wide variety of valid reasons (late equip- resequencing is done for other reasons. was performed on this activity every day for
ment deliveries, adverse weather, late Thus, the but-for schedule should be criti- all 22 work days. If the reviewer can docu-
responses to submittals, issuance of change cally examined to find logic or sequence ment, through a review of contemporane-
orders, subcontractor defaults, etc.). changes when compared to the as-planned ous project records, that a number of activi-
Further, the critical path may change schedule. Assuming such sequence ties shown on the but-for schedule were not
monthly, or even more frequently, on a changes are found, the reviewer should try prosecuted continuously, as shown, then
project with a myriad of problems. to determine if any of the changes were substantial doubt can be cast on this theo-
Thus, schedule activities that have a “preferential”—not an unavoidable conse- retical aspect of the methodology. Since it
great deal of float in the early portion of a quence of the delay. For example, were demonstrates that the but-for schedule is
project may end up on the critical path activities resequenced simply to mask con- not as accurate as it was held out to be.
during the middle of the project and then current contractor or subcontractor-caused
be returned to a noncritical status with float delays? If resequencing of this nature can
time at the end of a project. Assuming this be demonstrated, then this is a strong indi- CHALLENGE ANALYSIS
is an accurate portrayal of the dynamics of cator the project probably would have been
project scheduling, to find a single critical built differently, absent the delays. If this The largest part of the effort in chal-
path and analyze the effect to it, at the end can be shown, the reviewer can assert that lenging a but-for schedule analysis is in
of the job, ignores these dynamics. For this part of the theory is false with respect to examining the details. As the old saying
example, at the end of a project, looking at this particular delay analysis. That is, the goes, “The devil is in the details!” Likewise,
the as-built critical path, a change order reviewer will have shown that schedule the most substantial challenge to a but-for
that caused a demonstrable time effect in logic was modified by the contractor during schedule lies in challenging the details of
June 1997 (at the time of issuance) may the project, thus proving that the project the analysis presented to determine accura-
have 100 days of float when the as-built would not have been built the same way cy, reliability, and correctness.
critical path is determined in December without the delays.
1998. Should the owner take back the pre- Second, would the project have been
viously approved time extension that was built at the same speed in the absence of Challenge the Manner in Which the As-
valid in mid-1997, but that has been proven these delays? Again, it is my experience that Built Schedule Was Derived
not to be critical by the end of 1998? Or, in when faced with a project delay, contrac- Questions to be asked include the fol-
light of this scheduling methodology, tors tend to slow down other noncritical lowing. What are the sources of the as-built
should owners refuse to grant any time work. They tend to take the position “Why dates used in the but-for schedule? How
extensions until the project is totally com- should I hurry up and later have to wait due did the scheduler ascertain logic between
pleted and the as-built critical path identi- to an owner’s delay?” Such extension of the as-built activities? What was the source
fied? Neither is reasonable, and both fly in activity durations effects or distorts the proj- of the information for the as-built logic?
the face of good contract management ect schedule. Activity duration extensions The point here is that a but-for schedule
practices, in my opinion. of this nature tend to exacerbate schedule analysis places a heavy burden on a sched-
The assumption used in the but-for effects. Therefore, the reviewer should uler to ferret out all of the facts and make
schedule methodology fails to put delays in compare the but-for schedule to the as- the series of discretionary choices necessary
their proper context. The methodology planned schedule to find activity durations when employing this analytical technique.
denies the dynamics of project scheduling that took significantly longer than planned There are so many choices that the temp-
in the real world. The methodology but that were not affected by any identifi- tation to skew the schedule analysis in favor
assumes the existence of a single critical able delays. The reviewer should ascertain of one’s client is all too real.
path that was unchanging throughout the whether these were simply “pacing delays.”

Cost Engineering Vol. 43/No. 8 AUGUST 2001 15


Challenge the Dates Shown on the But- uler whether the owner should be “credit- • Deleted activities: were any activities
For Schedule ed” with these time extensions since the as- from the as-planned schedule deleted
Check the accuracy of the dates shown built critical path analysis demonstrates that in the as-built schedule? If so, why?
on the but-for schedule against contempo- they were not critical, in the end? What project records document the
raneous project records. Look in the proj- reasons for activity deletion?
ect records to see if conflicting information • Changed activities: were any activities
can be found. Reviewers should look for Challenge the Assumption of changed? For example, were two activ-
conflicting information concerning start Continuous Work on Schedule Activities ities merged or hammocked into a sin-
and completion dates in project documents As noted earlier, an activity on the but- gle activity or was one activity split into
such as weekly or monthly meeting min- for schedule may be shown as 22 work days. two or three? If so, how and why?
utes, project correspondence, RFI and The implication, of course, is that the con- What project records document such a
change order logs, schedule updates, pay- tractor worked on this activity for each of change?
ment applications, daily inspection records, the 22 days shown on the but-for schedule. • Differing activity durations: were any
daily diaries, project photographs, and Take the example given above, “install con- activity durations changed? What
monthly status reports. If contradictory duit, basin 1” with actual start and comple- project records document these
information can be found, challenge the tion dates of June 1 and June 30, 1998. changes?
scheduler’s use of that information. If the Let’s say it can be shown (through analysis • Differing lag times: were the lead and
reviewer can document that information of the contractor’s labor distribution lag time between activities changed? If
exists that the scheduler failed to use or reports) that the contractor employed an 8- so, how and why? What project records
ignored, or can find project documentation person crew on this activity from June 1 to document these changes?
that contradicts the dates contained in the June 5, then no work was performed on the • Differing activity relationships: were
but-for schedule, then substantial doubt activity again until June 29, when there was relationships between activities from
concerning the validity and accuracy of the a 2-person crew who completed the work the as-planned schedule changed
but-for schedule can be raised. on June 29 and 30, 1998. If this were the when put into the as-built schedule? If
case, the reviewer could certainly show that so, how and why? What project records
Challenge the But-For Schedule’s this was not an activity with a 22-work day document such changes?
Critical Path duration, but actually had a duration of 7
Look especially at start and completion work days over a 30-calendar day period Given the above research, the reviewer
dates for activities on the critical path. and one that accomplished approximately should be in a good position to critique the
Challenge the scheduler’s starting dates. 91 percent (40/44 worker days) of the work but-for schedule and to challenge the
What, exactly, constitutes “start work” for in the first 5 work days (320 mh/352 mh). scheduler concerning schedule manipula-
each activity identified? Let’s look at an This is hardly the same picture as the but-tion. It is my experience that but-for sched-
activity identified as “install conduit, basin for schedule indicates, which is work by a ules are frequently manipulated to pro-
1.” Does work start when the conduit is full crew every day for 22 work days. duce exact dates desired to support a claim.
delivered to basin 1? Is it when the first If schedule manipulation can be demon-
hanger is installed? Is it when the first strated by the reviewer, then the sched-
piece of conduit is hung? What constitutes Challenge the But-For Schedule Logic uler’s objectivity and the But-For
“work complete”? Do all of the hangers and Diagram Schedule’s accuracy can be seriously called
conduit have to be painted before it’s com- A careful review of the as-planned into question.
plete, for example? Challenge the sched- schedule compared to the as-built schedule
uler to define precisely the scope of work should be performed. The reviewer should
for each activity on the but-for schedule’s look for and question the following items. SUMMARY OF CHALLENGES
critical path. Compare this information to
contemporaneous project documentation • Added delay activities: have new activ- A reviewer tasked with responsibility
to determine whether it is accurate. ities been added to represent delays? If for analyzing, critiquing, and defending
so, what delays were added? Why were against a but-for schedule should focus
they added with these dates? What most effort on the critical path activities
Challenge the Premise That There Was a project records document these activi- shown on the as-planned schedule and the
Single, Unchanging Project Critical Path ties and their recorded dates? Why but-for schedule.
Examine the project records to see if were they added in this particular
any time extensions were requested by the sequence? What project record docu- • Find conflicting information from
contractor for events that are not shown on ments this logic? contemporaneous project documenta-
the critical path in the but-for schedule. • Added change order activities: have tion. Challenge the scheduler to see
Question the scheduler on why such time new activities been added to represent how the critical path would change if
extension requests were made. Examine the change orders? If so, what change conflicting dates were used.
project records to determine whether any orders were added and in what man- • Challenge the scheduler as to why the
time extensions were granted for activities ner? What project records document dates used are more reliable or accu-
or events that are not on the as-built critical the logic and duration of the added rate than the conflicting dates found in
path in the but-for schedule. Ask the sched- change orders? project records by the reviewer.

16 Cost Engineering Vol. 43/No. 8 AUGUST 2001


• Challenge the scheduler to justify the to determine when the project would have REFERENCES
logic relationships used in the but-for finished but-for the actions of . . . .” As has 1. Schumacher, Lee. Quantifying and
schedule. As noted earlier, it is not pos- been shown, most but-for schedules should Apportioning Delay on Construction
sible to “calculate” an as-built critical be challenged and perhaps rejected for the Projects, Cost Engineering 37, no. 2
path, and in my experience, it is rare following reasons. (February 1995).
that contractors or owners keep suffi-
ciently detailed daily records to recon- • But-for schedules assume that the 2. O’Brien, James J. CPM in
struct a completely accurate record of project would have been constructed Construction Management. 3rd ed.
all logic relationships on an as-built in exactly the same manner even with- New York: McGraw-Hill, 1984.
schedule. Therefore, a considerable out the delays.
amount of judgment must be exercised • But-for schedules assume that non- 3. Zack, James G. Jr. Pacing Delays, the
in identifying an as-built critical path. delayed activities would have been Practical Effect, 1999 AACE
Test the scheduler’s judgment. constructed at exactly the same speed International Transcations.
• Challenge the scheduler to determine or pace without the delays. Morgantown, WV: AACE
whether the critical path in the but-for • But-for schedules assume that an as- International, 1999.
schedule differs from the evolutions of built critical path can be calculated
the critical path shown on contempo- and analyzed.
raneous project schedule updates. If • But-for schedules assume the existence James G. Zack Jr. is
so, in what way? Are the differences of a single, static, unchanging critical Executive Director of
due to unexpected events during the path on the project which can be ana- Corporate Claims
project or manipulation of the sched- lyzed. Management at Fluor
ule (either during the project or during • But-for schedules assume that accurate Daniel, One Enterprise
the but-for schedule analysis)? Why is start and complete dates for all activi- Drive, S3-148 Aliso
the but-for schedule more believable ties can be found in the project records Viejo, CA 92656-2606.
than the contemporaneous schedules and recorded on the as-built schedule. He previously was a vice
prepared and submitted by the con- • But-for schedules assume that logic president of PinnacleOne and the director of
tractor during the project? between all activities can be deter- the PinnacleOne Institute, an educational
• Challenge the scheduler on whether mined from the project records and organization established to provide profes-
the but-for schedule was manipulated recorded on the as-built schedule. sional development seminars in project man-
to arrive at the work product pro- • Finally, but-for schedules assume that agement, claims mitigation, and claims
duced? Was conflicting information the scheduler preparing them is, at all management. Mr. Zack also was the project
found? If so, why use the information times, both thorough and objective. manager for the company’s on-call construc-
presented and not the conflicting tion claims support services contract with
information? Did the But-For ut-for schedules are very popular the California Department of
Schedule come out this exact way on
the first run as the document submit-
ted? (This is almost a practical impos-
sibility.) If not, why not? What did the
scheduler do to “fix it”?
B in claim presentations. They
appear to be accurate, correct,
and reliable, and the outcome
of a but-for schedule analysis is easily
understood by a trier-of-fact. However, as
Transportation and was a senior claims con-
sultant for a similar contract with the
California Department of Corrections. For
30 years, he has worked on government con-
tract and grant projects. He has worked for
• Challenge the scheduler concerning has been shown, but-for schedules are public clients throughout the US and in
various changes in logical relation- deceptively simple. The assumptions and Alexandria and Cairo, Egypt. Mr. Zack has
ships, lead times, lag times, etc. theories underlying them are all subject to been involved in more than 2,500 claims
Ascertain whether the scheduler challenge. But-for schedules are all too eas- and has been designated as an expert wit-
inserted certain relationships simply to ily manipulated. While this is a valid form ness in mediation, arbitration, and litiga-
“force fit” the but-for schedule with of delay analysis and is still acceptable in a tion. Mr. Zack is a member of AACE Inter-
the claim. claim or dispute situation, but-for sched- national, is the Region 6 Director, and is a
ules need to be reviewed and analyzed with well-recognized speaker, author, and trainer.
a great deal of care. Both the but-for sched- He can be reached at jim.zack@fluor.com◆
REASONS FOR REJECTING ule and the scheduler must be challenged
BUT-FOR SCHEDULES to determine whether the but-for schedule
is accurate or skewed.
As noted earlier, but-for schedules are
commonly used to support delay damage
and disruption claims. At first glance, most
but-for schedules look impressive, as they
are meant to. Most schedulers will tell the
reviewer that “We rebuilt the as-built
schedule exactly the way the project was
built and then simply removed the delays

Cost Engineering Vol. 43/No. 8 AUGUST 2001 17

View publication stats

You might also like