Professional Documents
Culture Documents
ButForSchedules AnalysisDefense ZackCostEngineering2001
ButForSchedules AnalysisDefense ZackCostEngineering2001
net/publication/292659614
CITATIONS READS
39 1,559
1 author:
James Zack
Ankura Construction Forum
18 PUBLICATIONS 169 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Delivering Dispute Free Projects - Does Partnering Help Achieve This Goal? View project
Alternative Dispute Resolution - Your Key To Staying Out of Court View project
All content following this page was uploaded by James Zack on 09 November 2017.
But-For Schedules
James G. Zack Jr. This technique is also referred to as the
collapsed as-built schedule analysis tech-
ABSTRACT: The purpose of this article is to discuss the use and abuse of but-for sched- nique. This technique attempts to create an
ules (sometimes called collapsed as-built schedules) in today’s claims oriented con- as-built schedule, identify “actual delays”
struction industry. This article also discusses ways to analyze but-for schedules when caused by two parties, and then remove
they are presented as evidence of either an excusable or a compensable delay. Finally, one party’s delays from the as-built sched-
the article discusses ways to defend against but-for schedules should the reader need to ule to “collapse” the schedule leaving in
do this in negotiation, litigation or some alternative dispute resolution forum (e.g., the schedule those delays caused solely by
mediation, arbitration, summary jury trial, etc.). the other party. The argument is, “but-for
the other party’s delays, this is when the
KEY WORDS: but-for schedules, claims, delay, dispute resolution, and mediation project would have been completed.” The
amount of delay and the resulting damage
ut-for schedules are usually used CPM Update Review
B
are then calculated.
to present delays and time This technique makes no attempt to
extension requests after a project create a separate delay analysis diagram.
is built. They are more reliable The technique examines each progress Windows Analysis
than several other delay analysis tech- schedule update submitted on the project This technique is occasionally referred
niques. They are, however, subject to abuse and explains what caused the delay on each to as contemporaneous period analysis [1].
and manipulation. Those faced with the update without performing any further The technique is to validate the as-planned
task of analyzing such delay analyses need analysis. Again, the explanation of delay or baseline schedule, and then, using con-
to be cautious. Reviewers must ascertain depends on whether the owner or the con- temporaneous project documentation,
that a but-for schedule presented in support tractor is doing the analysis. update the schedule one period at a time
of a claim has not been abused so badly as (monthly, quarterly, seasonally, etc.). The
to render it meaningless or dangerous. This technique builds one period analysis upon
article discusses ways to do this. As-Planned Versus As-Built Analysis the previous period’s analysis, examining
Like the bar chart analysis above, this each new period for delay, causation, and
technique simply compares the baseline or liability as the analysis proceeds. This
DELAY ANALYSIS TECHNIQUES as-planned schedule with the final or as- method puts delays in their proper time
built schedule. This analysis is similar to a frame within the overall context of the
There are, generally, seven analytical total cost claim analysis wherein one sub- project.
techniques used to perform schedule delay tracts the amount paid from the amount
analysis. expended to calculate the amount owed.
With respect to time, this type of analysis Linear Schedule Analysis
subtracts the time planned from the actual This technique is only used with linear
Bar Chart Analysis time expended to determine the time type projects (water mains, sewer lines,
This form of schedule analysis com- owed, thus presenting a “total time claim” highway construction, etc.). It is a form of
pares an as-planned bar chart with an as- with an explanation about why the time progress quantity charting applied to the
built bar chart. The concept portrayed is was extended and how it was the other progress of a specific construction project;
that the activities shown on the bar chart party’s “fault.” it plots construction activity progress over
would have been completed exactly as time. The delay analysis technique com-
planned, were it not for certain delays. The pares as-planned to actual linear progress
delays indicated in the analysis (that are Impacted As-Planned Analysis (similar to plotting as-planned versus actual
typically shown simply as extended bars) This technique is sometimes referred cash flow curves, for example). The analyst
are highly dependent upon whether the to as the as-planned plus delay technique. then offers an explanation of why the two
owner or the contractor is performing the In this technique, the scheduler simply lines diverged when they did (that is, cau-
analysis. The analysis is merely graphical, takes the as-planned schedule and adds sation and liability) in an effort to justify
and systematically ignores the lack of new activities that represent delays (gener- the delay requested.
underlying logic between the activities. ally caused by the other party) to demon-
Cost Engineering Vol. 43/No. 8 AUGUST 2001 13
BUT-FOR SCHEDULES contend that they should not be relied on rectness? There are, in my opinion, three
unless a great deal of independent research ways to accomplish this, as set forth below.
Why Are But-For Schedules So Popular? and analysis is done.
Bar charts largely have been aban- • Challenge assumptions—as noted
doned in public works construction in the above, a series of assumptions have
US in favor of critical path method (CPM) But-For Schedules—Underlying been made by the scheduler preparing
scheduling, while linear scheduling, Assumptions the but-for schedule. Challenge these
because of its inherently narrow range of As with any methodology, there are a assumptions to test for accuracy in
applicability, is infrequently used. number of assumptions that underlie the each specific case.
Therefore, these two schedule analysis theory of the but-for schedule. These • Challenge theory—question the theo-
techniques are rare due to the infrequent assumptions are listed briefly below. ry concerning the but-for schedule to
use of the scheduling methodology they are see if it has been accurately applied to
applied to. As-planned versus as-built • While unstated, it is generally implied this specific delay analysis.
schedule analysis (the total time claim) and that an as-built critical path is readily • Challenge analysis—use the reviewer’s
the CPM update review method have a identifiable. The portrayal most fre- analysis of the project documentation
number of critical flaws, that are beyond quently offered is that one can “look to challenge the but-for schedule to
the scope of this article to discuss. backward” down the as-built critical test the objectivity of the scheduler
Therefore, they are rarely used today in lit- path to determine what events or activ- and the accuracy of the work.
igation. The impacted as-planned tech- ities actually caused the project to be
nique has so many flaws that most courts completed late. Once the reviewer has performed the
have widely discarded its use. • Also unstated is the implication that above tasks, a conclusion can be reached
This generally limits the scheduler to there was but a single, unchanging concerning the objectiveness of the sched-
the remaining two delay analysis tech- critical path that can be identified at uler preparing the but-for schedule, as well
niques. While windows analysis is probably the end of the project and analyzed for as the accuracy and reliability of the but-for
the more accurate of the two delay analysis delay and causation purposes for the schedule presented in support of a claim.
techniques, it is usually more expensive entire project duration.
due to the amount of time and effort need- • Another unstated assumption is that
ed to perform it. It also typically takes the project would have been built the CHALLENGE ASSUMPTIONS
longer to perform, due to the need to vali- exact same way if the various project
date all scheduling data used in the analy- delays had not arisen. The assumption The most fundamental assumption
sis. Thus, if the time and budget needed to is that the contractor made no attempt underlying an as-built schedule is that an
perform a delay analysis are limited, win- to change the schedule to mitigate the as-built critical path can be easily identi-
dows analysis may not be achievable within effect of delays. fied, reviewed, and analyzed to ascertain
the confines of these two constraints. • It is also assumed that accurate start delays, but can an as-built critical path
But-for schedules are frequently used and completion dates are available actually be calculated?
when performing a delay analysis. But-for from project records for every schedule By definition, the “critical path” is the
schedules generally require less time and activity. Thus, one need only find and longest uninterrupted chain of events
less effort. They can normally be done record these dates to fill out this analy- through the schedule network. The critical
more quickly and at less cost than a win- sis. path dictates the length of the project as it
dows analysis. But-for schedules are, how- • Once as-built start and complete dates is “ . . . the longest path into the last event,
ever, more easily manipulated, so the are determined, it is assumed that work since it establishes the latest event time for
scheduler is more likely to be able to on each activity is continuous for the that last event [2].” A project’s critical path
demonstrate the point trying to be made. entire time between the start and com- is computed by the forward and backward
Schedulers using this technique gener- pletion dates. passes that mathematically identify the
ally refer to the “as-built critical path,” • Yet another assumption is that as-built longest uninterrupted chain of events
which they say has been calculated from schedule logic can be entered easily through the network. These calculations
“as-built information.” The implication is once the as-built dates are found. are entirely dependent on the activity dura-
that this form of scheduling analysis is • Finally, it is assumed that the sched- tions and logic (or sequence of activities)
based solely on facts. Additionally, since uler has reviewed all project docu- input by the scheduler.
the scheduler constantly refers to “as-built mentation and interpreted the infor- The critical path is determined by a
dates,” it appears that this schedule analysis mation objectively and accurately. forward-looking set of calculations only! It
is highly accurate. The analysis resulting starts at a point in time and calculates how
from but-for schedules is easily understood, long it will take to reach the project’s end.
making them very popular with schedulers But-For Schedules—Analysis and Defense By definition then, an “as-built” critical
and claims consultants. Because of the If presented with a but-for schedule, path cannot be calculated as all activities
above reasons, most people reviewing a what analysis should be performed? How on an as-built schedule are completed.
but-for schedule will conclude that it is fac- can an owner or owner’s representative (Unless, of course, schedule activities have
tual, accurate, and correct. But-for sched- defend against a but-for schedule with its been left unstatused by the scheduler. If
ules are, however, deceptively simple. I implied factual basis, accuracy, and cor- they are unstatused, then the schedule is