D.N.I.T.
Engineering Cell
Name of work:- Repair & renovation of Kitchen and Bath Intermediate Library in
Ganga Ram Building LCWU, Lahore. (Based on MRS 1st July, 2022 to
31st December, 2022)
Schedule Items
3. 55(ii)/Ch-4 Dismantling G.I./M.S. conduit/G.I. 100.00 Rft Per Rft 100.55 10055.00
flexible/PVC pipes or conduit
wiring, etc. of all sizes including
making good damaged surface
(building portion)
4. 48/Ch-4 Removing cement or lime plaster. 285.00 Sft 100 Sft 424.60 1210.00
5. 13/ Ch-11 Applying floating coat of cement 285.00 Sft 100.00 1876.70 5348.00
1/32" thick. Sft
6. 5(i)/Ch-7 Pacca brick work in ground floor, 15.00 Cft 100 Cft 37600.60 5640.00
cement, sand mortar 1:5.
7. 3(d)/Ch-6 Cement concrete brick or stone 45.00 Cft 100 Cft 22099.40 9945.00
ballast 1½ " to 2" gauge, in
foundation and plinth 1:6:12
8. 9(b)/Ch-11 Cement plaster 1:4 upto 20‟ height 450.00 Sft 100 Sft 3505.05 15773.00
½” thick.
10. 6(a3)/Ch-6 Reinforced cement concrete in 10.00 Cft Per Cft 559.20 5592.00
roof slab, beams, columns lintels,
girders and other structural
members laid in situ or precast
laid in position, or prestressed
members cast in situ, complete in
all respects Type C (nominal mix
1: 2: 4)
11. 5(f)/Ch-6 Cement concrete plain i/c placing 40.00 Cft 100 Cft 38747.00 15499.00
compacting finishing and curing
complete (i/c screening and
washing of stone aggregate) 1:2:4.
12. 49(b)/Ch-4 Scraping Ordinary distemper, oil 600.00 Sft 100 Sft 764.30 4589.00
bound distemper, or paint of wall.
13. 23(bi)/Ch-11 Distempering on old surface one 300.00 Sft 100 Sft 568.10 1704.00
coat (Ceiling).
14. 23(bii)/Ch-11 Distempering on old surface two 800.00 Sft 100 Sft 716.45 5732.00
coats (Walls).
15. 4©/Ch-13 Painting of door & windows i/c 1800.00 Sft 100 Sft 1694.65 30504.00
edges on old surface two coats.
16. 24(ii)/Ch-10 P/L superb quality Ceramic tile 140.00 Sft Per Sft 215.55 29897.00
floors of Master brand of specified
size, Glossy/Matt/ Texture of
approved Color and Shade as per
approved design with adhesive
bond, over 3/4" thick (1;2) cement
sand plaster i/c the cost of sealer
for finishing the joints i/c cutting
grinding complete in all respects
and as approved and directed by
the Engineer Incharge 10”x13”
17. 25(ii)/Ch-10 P/L superb quality Ceramic tile 290.00 Sft Per Sft 282.75 81998.00
dado of Master brand of specified
size, Glossy/Matt/ Texture of
approved Color and Shade as per
approved design with adhesive
bond, over 3/4" thick (1;2) cement
sand plaster i/c the cost of sealer
for finishing the joints i/c cutting
grinding complete in all respects
and as approved and directed by
the Engineer Incharge 10”x13”
18. 35(ii)/Ch-19 P/F “P” trap 4” dia glazed. 4.00 Nos. Each 289.10 1156.00
19. 1(i)/Ch-19 P/F glazed earthen ware water 1.00 Nos. Each 8242.40 8242.00
closet, squatter type, (Orisa
pattern) combined with foot rest,
White
20. 13(i)/Ch-19 P/F plastic made low down 1.00 Nos. Each 2669.10 2669.00
flushing cistern 1363 litter
(3gallons) capacity i/c bracket set
copper connection, complete
White.
21. 3/Ch-19 P/F one piece Europeon Coupled 1.00 Nos. Each 20022.90 20023.00
set of Water Closet (WC) and
flushing Cistern of PORTA brand
(full size) i/c the cost of CP/rubber
connection, thimble, normal seat
cover and rawal bolts complete in
all respects as approved and
directed by the Engineer Incharge.
22. 30/Ch-19 P/F chromium plated mixing 1.00 Nos. Each 2231.50 2231.00
valve, for wash hand basin, sink or
shower.
23. 7(i)/Ch-19 P/F glazed earthen ware wash 1.00 Nos. Each 5187.45 5187.00
hand basin /vanity 22"x16" i/c
bracket set, waste pipe and waste
coupling, etc white with pedestal.
24. 28/Ch-19 P/F chromium plated tee stop cock 7.00 Nos. Each 957.20 6700.00
½” dia
26. 38(ib)/Ch-23 Providing and installing P.V.C. 2.00 Nos. Each 546.30 1093.00
bends, of B.S.S. Class `B' working
pressure 4” dia
27. 39(ib)/Ch-23 Providing and installing P.V.C. 2.00 Nos. Each 1590.20 3180.00
tees, of B.S.S Class `B' working
pressure 4” dia
28. 16/Ch-19 P/F chromium plated soap dish 1.00 No. Each 280.40 280.00
29. 19(i)/Ch-19 P/F chromium plated towel rail 1.00 No. Each 551.50 552.00
24" long, and ¾" dia
30. 20/Ch-19 P/F looking glass 22"x16" size and 1.00 No. Each 642.30 642.00
5 mm thick, first quality.
31. 27(ii)/Ch-19 P/F chromium plated bib cock. ½” 2.00 Nos. Each 777.20 1544.00
dia
32. P/F CP bath Room Set made of
Sonex/ Master/ Faisal comprising
of 3-No Tee stop cocks, lever type
Basin Mixer, double Bib Cock,
open wall shower, Muslim shower,
waste coupling and bottle trap etc.
complete in all respect as approved
and directed by the Engineer
incharge.
A 52(ii)/Ch-19 Lever Type Basin Mixer. 1.00 Nos. Each 6539.00 6539.00
B 52(iii)/Ch-19 Double Bib Cock made of Sonex/ 2.00 Nos. Each 1739.00 3478.00
Master/ Faisal.
33. 8/Ch-19 P/F stainless steel sink with drain 1.00 No. Each 6423.95 6424.00
board, size (48"x24") i/c bracket
set, waste pipe and waste coupling
34. 47(cii)/Ch-23 P/L testing and commissioning of 100.00 Rft Per Rft 76.00 7600.00
POLYPROPYLENE RANDOM
COPOLYMER (PPRC) water
supply pipe (Dadex /Popular/
Beta or equivalent) with specified
pressure rating PN (PRESSURE
NOMINAL)and conforming to
DIN 077-8078 code i/c cost of
solvent, specials, making jharries
complete in all respect as approved
and directed by Engineer Incharge.
(Internal/External Diameters
mentioned). PN-25 pipe 25 mm
Total Amount Rs. 339673.00
Rate quoted percentage above or below on Schedule Items Rs.
Total Amount Rs.
LAHORE COLLEGE FOR WOMEN UNIVERSITY, LAHORE
D.N.I.T.
Engineering Cell
Name of work:- Repair & renovation of Kitchen and Bath Intermediate Library in
Ganga Ram Building LCWU, Lahore. (Based on MRS 1st July, 2022 to
31st December, 2022)
Non- Schedule Items
2. N.S. P/F floor trap grating of stainless 4.00 Nos. Each 445.00 1780.00
steel 6”x6” complete in all respects
as directed by the Engineer-in-
Charge.
Total Amount Rs. 17140.00
Rate quoted percentage above or below on Non Schedule Items Rs.
Total Amount Rs.