Concreting Barge BG.

Kiong Nguong 106


Rev-1
Unit Price (IDR) Total Price (IDR)
No Item Unit Q'ty Total Amount
Material Labour Material Labour

1 Cleaning deck 18x30 mtr m2 540,00 - 16.855,56 - 9.102.000,00 9.102.000,00

2 Install wire mesh M8 2 layer + stick weld to deck floor m2 540,00 353.937,92 136.251,79 191.126.478,57 73.575.964,29 264.702.442,86

3 Concreting Floor K300 200 mm thk m3 108,00 - 215.506,25 - 23.274.675,00 23.274.675,00

4 Formwork m2 19,20 405.387,50 108.137,50 7.783.440,00 2.076.240,00 9.859.680,00

Stopper plate 10 mm thk around concrete deck 200 mm high


5 m' 96,00 by owner 302.106,55 - 29.002.228,57 29.002.228,57
(cutting from stock material at Cita Sabut)

TOTAL PENJUMLAHAN HARGA DILUAR PPN & Pph ( A ) 198.909.918,57 137.031.107,86 335.941.026,43

Pph 5% ( B ) - 6.851.555,39

PPN 11% ( C ) 21.880.091,04 -

TOTAL PENJUMLAHAN HARGA KESELURUHAN ( D = A+B+C ) 220.790.009,61 143.882.663,25

TOTAL PENJUMLAHAN HARGA KESELURUHAN ( E ) 364.672.672,86