10-600000-4200000031-SAM-MEC-MST-000001 - 01 BEC-WTRAN-270769 WF-114807 Code C

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 34

NEOM - 10 SPINE INFRASTRUCTURE

Work Order No. 022

Work Order Title Enabling Works for Logistics Facilities(L3) – Coastal Desert East Region

Contract No. 4200000031

Contract Title SAMA-Site Preparation Framework 3

Document Title WO 022 Method Statement for Installation and Testing of


Reinforcement Pipes of Storm Water Piping

Document No. 10-600000-4200000031-SAM-MEC-MST-000001

Revision No. 01

Date 14/06/2023

Reason for Issue Issued for Approval

Revision History Revision Date Revision Description

01 14/06/2023 First Submission

Prepared By Reviewed By Approved By

Name TBA TBA Syed Iqbal Imam

Position Construction Manager Construction Project Manager


Manager

Date & Signature 14/06/2023 14/06/2023 14/06/2023

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 1 of 34
WO 022 Method Statement for
Storm Water Network System
10 -600000-4200000031-SAM -MEC-MST-000001– Rev. 01 ,

Date 14/06/2023

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 2 of 34
Document History

Revision code Description of changes Purpose of issue Date

01 First Submission Issued for Approval 14/06/2023

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 3 of 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

Table of Contents

Contents
1. Method Statement for Installation and Testing of Reinforcement Pipes of Storm Water Piping .......... 5

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 4 of 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

TABLE OF CONTENTS

Item Nº Descriptions Page

1 Location and Work Limits 5

2 Access / Egress 5

3 Protection and Isolation Arrangement 5

4 Task Specific Emergency Arrangements 5

5 Work Methodology 7

6 Resources 9

A. Site Key Personnel and Workforce 9

B. Plant and Equipment 10

C. Material and Tools 11

D. Chemicals Required 11

E. Task Specific PPE Required 12

Interfaces – Other Sites, Work Activities, General


7 12
Public Etc.

8 Permits 12

09 References Drawings / Specification / Other 13

10 Appendices 13

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 5 of 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

1. INTRODUCTION:
This document demonstrates the activities to be carried out for laying, installation,
jointing Concrete pipes for storm water network to service connection for the
construction activities in Enabling Works for Logistics Facilities (L3) – Coastal
Desert East Region as per the IFC/Shop Drawings and Project specifications

2 SCOPE OF WORK
The purpose of this method statement is to provide a safe sequence of activities for the
laying and installation of concrete pipes,frame and grate cover installation etc. on designated
location as shown on the latest revision of drawings. Ensure all pipe works shall be executed in
accordance with relevant drawings, approved shop drawings and NEOM contract agreement &
specifications

2. ACCESS/EGRESS:
Access/egress going into jobsite shall be as per NEOM approved TMP layout.

3. PROTECTION AND ISOLATION ARRANGEMENTS (e.g. 3rd Parties):

Area Protection/Isolation Measures

All existing utilities Existing Above ground & Underground utilities shall be
Protected with temporary barricades. (as applicable)
Contractor shall also protect existing benchmarks and
other existing properties.
Project Site Boundaries Contractor to provide boundary limit flag for identification
and if needed contractor will provide berm to ensure the
isolation on the work site.

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 6 of 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

4. TASK SPECIFIC EMERGENCY ARRANGEMENTS:

In the event of an accident, all activities shall be stopped immediately and the area where the
accident occurred shall be cleared of unauthorized persons. Injured personnel, if any, shall be
given first aid remedy as soon as possible and if required, taken to the nearest health care facility.
Emergency Evacuation:

 Evacuation of persons from affected areas and on-essential workers from adjacent areas
lowers the risk of casualties.
 Evacuation system testing and training.
 Control of access and exit points.
 Dead count requirements.

The project management and supervisor are responsible to familiarize with emergency evacuation
procedure, which can be apply to client areas where personnel are working.
Safety officer shall prepare Emergency Evacuation Procedure in graphical form and posted in
strategic locations within the Task Area. When emergency condition exists or upon hearing the
“Stop Work Alarm”.
The supervisor shall ensure:
That all work is immediately stopped and equipment is shut down.

That all workers are immediately evacuated to the designated “Assembly Point Area” in the working site.
Personnel shall not be allowed to return to work until a notification has been received from Operation
Department of from the Client Representative. Discipline Supervisor in conjunction with the site Engineer/
foreman shall be responsible for head counting to ensure all personnel are present at the assembly area.

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 7 of 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

In the event of emergency situation such as serious personnel injury, fire or any associated critical
situations, the nearest Clinic at site will be contacted for assistance and First-Aid Medical attention-
treatments will be given immediately to the injured workers without fail. When referring to the severe
and critical cases for which requires special medical treatments with facilities, our company ambulance
stationed at site will then mobilized the casualties to a nearest Hospital in town for carrying out suck
treatments.
The safety officer and project supervisor vehicle shall be equipped with VHF Mobile radio where the
nearest office can be reach and ask to dial for emergency assistance.
AMT will interface with Client representative in regards with emergency evacuation procedure by
communicating at the time of the event thru oral report.
This will be followed by detailed reports within 24 hours of the occurrence of the events.

EMERGENCY CONTACT NUMBERS


SN Name Category Contact Number
SAUDI GOVERNMENT EMERGENCIES
1 Saudi Government (NEOM) Civil Defense / Fire Department 998
2 Saudi Government (NEOM) Police 999
3 Saudi Government (NEOM) Traffic Accidents 993
4 Saudi Government (NEOM) Coastguard 994
5 Saudi Government (NEOM) Natural Disasters 966
6 Saudi Government (NEOM) Covid-19 Hotline 937
Abdul Mohsin Al Tamimi
1 Abdullah Ibrahim Project Manager 0503009446
2 Abdul Monhib Construction Manager 0507671998
3 Fawad Ali OSH Manager 0559081870
4 Shahid ullah Khan Environmental Manager 0594574265

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 8 of 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

5. WORK METHODOLOGY:
Nos. ACTIVITY DESCRIPTION AND SEQUENCING
PREPARATORY WORKS:

Conduct Safety induction to employees newly mobilized manpower for this job include QC
1. mechanical, pipe fitters, skilled workers, then the distribution of Personal Protective
Equipment (PPE).

Conduct equipment inspection by Safety dept. for newly mobilized equipment intended for
2. the works to ensure in good working condition such as; to check that no oil & diesel
leakage, good tires, lights, reversing alarm, workable seat belt, foot brake, hand brake,
mirrors, available and workable fire extinguisher, as per inspection checklist.

3. Check to ensure have a valid driving license, Iqama’s, TUV for the operator, medical
insurance, safety passport to all employees. Consequently, to check and ensure
equipment documentation such as; MVPI, vehicle registration, insurance, are all updated.

4. Prior to starting the work will be obtained written permit from Contractor Safety/
Environmental Manager (if necessary).

Before starting the activity, Supervisor/Foreman shall lead a toolbox meeting with all
employees allocated to that activity in order to identify hazards associated with that activity
5. in that specific location and explain the necessary procedure to mitigate the risk of
accident associated with that task.

6. After the meeting employees will sign the attendance sheet and the Supervisor will keep
the records until the end of the day.

7. Establishment of control survey points, setting out and final survey works for this work of
Concrete culvert pipelines and installation as per latest revision of IFC drawings for
main water network and concrete culvert piping for service connection.

Superintendent to ensure concrete culvert pipes & Fittings will be transported to


8. designated area on-site will be conformed as per NEOM specifications and concrete
culvert pipes manufacturer's recommendation as well as the concrete culvert pipes
installation inside the chamber.

9. Ensure a copy of the approved method statement for this work is available to the
construction team.

10. Ensure availability of all approved materials such as; concrete culvert pipes & Fittings,
Warning Tape, etc. must be on site before actual installation will be done.

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 9 of 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

DELIVERY, STORAGE, AND HANDLING OF CONCRETE PIPES & FITTINGS

1. All concrete culvert pipes and fittings shall be handled and stored strictly according to the
instructions of the manufacturer.

2. Protect pipe, pipe fittings, and seals from dirt and damage.

3. Handle pipes and other structures according to the manufacturer's written instructions.

4. Manufacturer’s recommendations on handling, repairing, laying, jointing, anchoring, cutting


and other works for pipes and fittings are to be strictly followed.

5. The Contractor shall repair damaged coating, sheathing or lining in accordance with the
Specification and manufacturer's instructions. Material used for repair work shall be
compatible with that originally used. All repair works shall be approved by the Engineer
before incorporating materials into the work.
6. Pipes shall be stacked on horizontal surfaces. Pipes shall not be stored on their sockets or
jointing fairlings. End pipes in bottom row shall be secured by chocks. The allowable
height of stacks shall be to the manufacturer's instructions.

TRENCH EXCAVATION:

1. Prior to trenching all eventual services crossing or running close to the line of the trench
shall be identified and exposed.

2. Trenches shall provide sufficient room for laying, jointing and testing.

3. The trench bottom shall be composed of stable uniform sand with no protuberances that
might cause point loading of the pipe.

4. Trenches shall not excavate unless there is sufficient pipe to be installed in order to ensure
that trenches do not degrade with dirt and windblown debris.

5. Generally trenching at locations where the top soil has already spread shall not be
permitted, however if such trenching should occur, the 30cm top soil layer shall be
removed and placed on one side of the trench, the remaining sub-layer shall be excavated
to and shall be placed on the other side of the trench to avoid contamination when
backfilling.
6. During backfilling the sub-soil shall be filled into the level before the top soil emulating the
same condition found previous to trenching.

7. Structural excavation means excavation of pipes trench into the bottom of excavation in
which concrete culvert pipes with accessories required are to be laid and jointing
installation.
8. Ordinary or normal excavation of soil means all kinds of soil formed of clay, silt, sand,
gravel, volcanic ashes, cobbles, etc. which can be excavated and removed by ordinary
excavating machines and tools. However rock excavation - means any naturally occurring
solid mass of hard material of not less than one cubic meter (measured within the
excavation) which cannot be easily shattered or broken-up, and in the sole opinion of
NEOM requires the use of special rock breaking techniques such as wedges and
hammers, or compressed air drilling.
9. Ensure the line and level of excavation shall be as shown on the latest revision of IFC
drawings.

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 10 of 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

10. Ensure during excavation of the pipeline must be protected with barricades and other
safety devices as per NEOM HSE standards. It will be maintained until work is complete.
11. Prior to the commencement of any excavation, necessary official permits (if required) shall
be obtained with adherence to the time schedule for the completion of works. Also, permits
shall be obtained for the occupation of any part of the road by excavation works. Asphalt
layers over trenches shall be cut by the sewing machine and all the cracked surfaces shall
be removed.
12. Contractor shall erect at the excavation site a safety signboard containing
precaution and indicate emergency contact numbers.
13. In case the contractor is operating on public roads, he shall use and fix day and night
warning and lighting signals at the trench sides and shall provide an alternative for the
pedestrians and traffic routes in the areas of excavations. All the above mentioned shall be
with the coordination of the Traffic Department and according to their instructions.
14. Contractor shall excavate reasonable working space, proper sloping as per
specification. All excavations shall be made as nearly as possible to the required
dimensions so that the minimum backfilling will be needed afterwards.
15. Depending on trench depth and soil stability, the pipe may be placed near a planned
excavation to preclude damage to trench walls by heavy equipment. The supervisor or
foreman to ensure proper barricading to guard against damage to pipe and trench walls.
Excavation shall be performed as per NEOM specifications.
16. Contractor shall excavate a reasonable length of trenches in advance of pipe laying. No
length of trench excavation shall be started until the pipes to be laid in that length are
available on site.
17. All excavations shall be made as nearly as possible to the required dimensions so that the
minimum backfilling will be needed afterwards.

18. Minimum widths of trenches excavation shall be as set out in the trench detail of the
standard drawing.
19. Excavation shall be carried down to the depth required for laying the pipe bedding. The
bottom of the excavation shall whenever be required by NEOM/PMC be watered and
graded, before pouring any concrete base.
20. NEOM PMC may require the Contractor at any time during the period of the validity of the
Contract to excavate or cut open in any part of the works or uncover any part of the trench
that has been backfilled or covered. The Contractor shall abide by such request to such
extent as the Engineer may direct and shall reinstate the surface again all to the
satisfaction of the Engineer.
21. For foundation, as soon as the excavation reaches the required depth/elevation the
surface shall be leveled and shall be compacted to 90 % of maximum dry density.

22. Before the compaction starts, it shall make sure that the excavated level is free from
standing water or excessive moisture content. Water shall be prevented from entering or
standing in the excavated areas by dewatering system as per Neom specification.
23. Inspection would be conducted during compaction for checking and approval of the
Engineer.

24. The compaction test report shall be submitted to the Engineer for approval prior to proceed
for the work.

INSTALLATION, LAYING AND JOINTING FOR STORM DRAINAGE PIPE(RC PIPES):


1. Ensure Pipe Size as per the drawing and approval. The end of each pipe shall be a Socket
spigot end and suitable for the push-in joint. Pipe shall be class V.

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 11 of 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping
2. Concrete culvert Pipes shall comply with ASTM C76M, Class IV, with Wall Type [A] [B] [C].
Concrete for pipes and fittings shall be to the requirements of Division 3 of the specification
and shall be made using ordinary Portland cement.
3. The entire interior surfaces of pipes and fittings shall be lined with a concrete culvert
lining to the product requirements. concrete culvert lining should cover the entire
interior of the pipe.
4. The concrete culvert lining should be casted into the pipe at the time of manufacture of
the concrete pipes. Line the pipes entirely unless otherwise noted.

5. Concrete culvert Pipes End Connections should be Bell and spigot, Fittings to be
Reinforced concrete, Joint to be Rubber compression gasket and shall comply with ASTM
C443M and ASTM C361 or BS EN 681.
6. Concrete Compressive strength for concrete culvert pipes & fittings shall be minimum at
34.5mpa at 28 days as per ASTM C76 Class V and ASTM C497.

7. Reinforcement shall conform to ASTM A-615/1064, Cement used shall be sulfate resistant
type V conforming to ASTM C 150.

8. Trench width requirement for 600mm dia. Pipes shall be minimum of 1.20Meters;
for 800mm dia. Pipes shall be minimum of 1.50Meters.

9. Before handling the Pipes, check their mass and make sure the handling equipment/
crane is of adequate for lifting it. Crane Operator and Rigger must be certified.

10. Lifting Plan must be provided in each lifting activities during installation.

Pipe laying in an upstream direction with spigots pointing downstream having inserted into
11.
the socket, in this way restrains the joints from opening up as a result of pipeline and joint
surfaces are protected against entry of foreign matter.
12. To ensure pipes laid to correct grade, pipe bedding shall be levelled (taking pipe thickness
into consideration) and compacted prior to laying the pipes.
13. Rubber ring jointed pipe must be laid with joint gaps between the pipes to ensure that the
lines are able to deflect without damage to the pipes.
14. The ring must be assembled dry and without the use of lubricant.

15. Before jointing, the surface must be clean and free of foreign matters.
16. Place the rubber ring on the spigot and ensure the ring is free of kinks and twists and is
uniformly tensioned.
17. Then the pipe is pushed home and fit.
18. Installation, elevation, location and alignment must be check by the Quality personnel
with the client representative prior to backfilling
19. When work is not in progress, open ends of the pipe and fittings shall be securely closed
so that no substance will enter the pipes or fittings.
20.
Pipes shall be laid on a bed of stocked sand, this sand may be sourced from sieved
excavated material on site, but shall not contain any larger particles and shall have good
self-compacting properties.

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 12 of 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

Dd,K^ΘWZKhZ^INSTALLATION, LAYING AND JOINTING FOR uPVC


STORM DRAINAGE PIPE

^ŽůǀĞŶƚĞŵĞŶƚǁĞůĚŝŶŐ;^ͬͿ
ϭͲ DĞĂƐƵƌĞƚŚĞĚĞƉƚŚŽĨŝŶƐĞƌƚŝŽŶĂŶĚŵĂŬĞĂŵĂƌŬŽŶƐƉŝŐŽƚĞŶĚĂŶĚƵƐĞŝƚĂƐĂƌĞĨĞƌ
ĞŶĐĞ ĨŽƌƚŚĞŝŶƐĞƌƚŝŽŶ͘
ϮͲ ůĞĂŶďŽƚŚƉŝƉĞƐŽĐŬĞƚĂŶĚƐƉŝŐŽƚĞŶĚďLJƵƐŝŶŐĐůŽƚŚ͘
ϯͲ hƐĞĐůĞĂŶĞƌƚŽĐůĞĂŶďŽƚŚƉŝƉĞƐŽĐŬĞƚĂŶĚƉŝƉĞƐƉŝŐŽƚ͘
ϰͲ LJƵƐŝŶŐĐĞŵĞŶƚďƌƵƐŚƐƚŝƌƚŚĞƐŽůǀĞŶƚĐĞŵĞŶƚ͘
ϱͲ ƉƉůLJĂƚŚŝĐŬůĂLJĞƌŽĨĐĞŵĞŶƚƚŽƉŝƉĞƐƉŝŐŽƚ͕ĂƉƉůLJĂŶŽƚŚĞƌƚŚŝŶůĂLJĞƌ
KĨĐĞŵĞŶƚƚŽƉŝƉĞƐŽĐŬĞƚŽƌĨŝƚƚŝŶŐƐŽĐŬĞƚ͕ĂǀŽŝĚƉƵĚĚůŝŶŐŽĨĐĞŵĞŶƚ͘

ϲͲ /ŵŵĞĚŝĂƚĞůLJƉƵƐŚƚŚĞƉŝƉĞŝŶƚŽƚŚĞƐŽĐŬĞƚƵƉƚŽƚŚĞ/ŶƐĞƌƚŝŽŶŵĂƌŬ͘
ϳͲ ĞƐƵƌĞƚŚĂƚĐĞŵĞŶƚŝƐĐƵƌĞĚďĞĨŽƌĞĂƉƉůLJŝŶŐƉƌĞƐƐƵƌĞ͘
ϴͲ fŽƌďŝŐƐŝnjĞƐŝƚŝƐƌĞĐŽŵŵĞŶĚĞĚƚŚĂƚƚǁŽƉĞƌƐŽŶƐƐŚŽƵůĚĐŽŶĚƵĐƚĐĞŵĞŶƚŝŶŐƉŝƉĞĂŶĚ
ƐŽĐŬĞƚĂƚƚŚĞƐĂŵĞƚŝŵĞ͘

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 13 of 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

5XEEHU-RLQW:HOGLQJ 5- 

ϭͲ ƐƐĞŵďůĞƚǁŽƉŝƉĞƐƚŽŐĞƚŚĞƌǁŝƚŚŽƵƚƉƵƚƚŝŶŐƌƵďďĞƌŐĂƐŬĞƚĂŶĚŵĂŬĞŵĂƌŬŽŶƐƉŝŐŽƚ
ĞŶĚĂŶĚƵƐĞŝƚĂƐĂƌĞĨĞƌĞŶĐĞĨŽƌƚŚĞŝŶƐĞƌƚŝŽŶ͘
ϮͲ ůĞĂŶďŽƚŚƉŝƉĞƐŽĐŬĞƚĂŶĚƐƉŝŐŽƚĞŶĚďLJƵƐŝŶŐĐůŽƚŚ͕WůĂĐĞƌƵďďĞƌŐĂƐŬĞƚŝŶƚŽŐƌŽŽǀĞ
ĂŶĚŵĂŬĞƐƵƌĞƚŚĂƚƚŚĞŐĂƐŬĞƚŝŶƚŚĞĐŽƌƌĞĐƚĚŝƌĞĐƚŝŽŶĂŶĚĐŽƌƌĞĐƚƉůĂĐĞ͕/ĨƚŚĞƌƵďďĞƌŐĂƐŬĞƚŝƐ
ĂůƌĞĂĚLJŝŶƐƚĂůůĞĚďLJŵĂŶƵĨĂĐƚƵƌĞƌƐ͕ĚŽŶŽƚƌĞŵŽǀĞŝƚ
ϯͲ ƉƉůLJůƵďƌŝĐĂŶƚƚŽƉŝƉĞƐƉŝŐŽƚŽŶůLJ͘
ϰͲ WƵƐŚůƵďƌŝĐĂƚĞĚĞŶĚŝŶƚŽƉŝƉĞďĞůůĞŶĚƵƉƚŽƚŚĞŝŶƐĞƌƚŝŽŶŵĂƌŬ͘


Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 14 of 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

CATCH BASIN & GRATED COVER INSTALLATION:


1. Catch basin installation will be as per the manufacturer's instruction or as per the
Engineer's recommendation.

2. Before Installation of the catch basins, the team will prepare the location

3. A lifting permit required as per the work and Safety rule must follow as per the NEOM
Safety requirement.

4. Catch basin shall be installed by using a boom truck or crane.

5. Level will be as per the approved drawing.

6. Prior to install the catch basin the bedding must be compacted to 90%.

7. Lean concrete should be done as per IFC drawings.

8. The roof should be constructed with the catch basin cover frame imbedded in it.

09. The catch basin cover must be installed after the installation of the pipe & fittings
inside the chamber.
GEOTEXTILE & GRAVEL INSTALLATION:
1. Install the seperation layer in the form of geotextile with these properties
Elongation not greater than 50 % .Thickness 1.2mm

2. After installtion of geotextile,Place a layer of pea gravels of thicknes of


150mm

3. Then place the perforated uPVC pipe

4. After instalaltion of uPVC Perforated Pipe,Place a layer of pea gravels


of thickness of 150mm

Install the seperation layer in the form of geotextile with these properties
5
Elongation not greater than 50 % .Thickness 1.2mm

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


14-159000-0000100201-MAH-MEC-MST-000003 REV.03 Page 14
Page 15ofof
30 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

FLUSHING & FLOWTEST


1. Clean the pipe as applicable until the water is clear and clean.

2.
Testing shall be in accordance with NEOM specification requirements and manufacturer
Recommendations.
3. Inspection and Test Plan /Checklist shall be submitted separately for review and
approval.

4. Prior to flow test, all safety requirements should have been complied with.

5. Once flow test has been successfully carried out. Submit WIR for consultation to witness
and for approval.
BACKFILLING:

1. After completion of the tests and acceptance by NEOM, backfilling shall commence using
similar excavated material.

2. Care shall be taken to remove bolder, vegetation’s and any other deleterious materials.

3. Minimum thickness required for backfilling as per IFC/Shop Drawings or Project


Specifications.
4. warning tape should be placed and then followed by the as per the standard drawing

5. Backfilled, compacted by layers to reach subgrade level.

7. RESOURCES

Title No. Required Task Specific Training Required (if applicable)

Project Manager
Construction Manager
QC Manager
Regular training is required during the
QC Engineers Project with refreshment;
Safety Manager 1. Safety Induction
Environmental Manager 2. Safety Training
3. Competent Operator Training
Site Engineer 4. Project Driving Rules
Chief Land Surveyor 5. Accident and Emergencies
Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01
Page 16 of 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

Safety Officers 6. Breakdown Procedure


7. Working at Height
Survey Team
Foreman
Operators
Skilled / Unskilledlabors
3rd Party Technician

B. PLANT AND EQUIPMENT:


Item Specific Requirements
Water Tankers ;
Excavator
1. Equipment Registration
Plate Compactor
2. Vehicle Insurance
Boom Truck 3. MVPI (Vehicles)
Diesel Tanker
Service Vehicle
Survey Equipment
NOTE: For all Equipment’s shall be complied all requirement as follows; Inspection Checklist,
Equipment Registration, Vehicle insurance, MVPI (vehicles), Driving License.

C. MATERIAL AND TOOLS:


S.N Item

1 General tools(Measuring tape,Hammer,Sprit level)


2 Crane
3 Excavator
4 Safety Equipment(Signs,Cones,Warning Tape &PPE)

5 Vibrator Roller
6 Shovel
7 Powertools
8 Handtools

D. CHEMICALS REQUIRED:
Item MSDS Reason for Use

Lubricant Required For Joining of Pipes


Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01
Page 15
Page 17ofof
22 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

Solvent Required For Joining of Pipes

E. TASK SPICIFIC PPE REQUIRED: (Refer control measures from Risk Assessment)
Item Reason for use
Hard Hat Protection from falling object
Dust Mask (N95) Protection against dust and fumes
Safety Vest Visibility when working in the site
Goggles / Face Shield Eye protection during working in the site
Leather Gloves Hand protection during working in the site
Gum Boots with Steel Feet Protection
Toe
Ear Plug / Muff For ear protection
Welfare Facility Shelter, Drinking water, Portable toilet, etc.

“Note that all works require mandatory PPE as follows Hardhat, gloves, safety glasses, safety
boots, hi-visibility vest.”

8. INTERFACES – Other sites, work activities, general public etc.:


Interfacing party or activity Description of Interface

Governmental parties Coordinate to governmental parties before start of works for


existingutilities rerouting of existing cables & other Services. (if applicable)

9. PERMITS:
Permit Type Issued By Additional Information (Reference No. etc)

To conduct the topographical survey verification of


Notice to Proceed NEOM existing ground condition, and provide layout and
stacking.
Excavation / DigPermit NEOM If Necessary

10. REFERENCES DRAWINGS / SPECIFICATION / OTHER:


Permit Type Additional Information (Reference No. etc)

IFC Drawings 10-600000-4200000001-ESC-STR-DRG-009147-B

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 16
Page 18ofof
22 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

Section 334100 STORM UTILITY DRAINAGE PIPING


Section 312000 EARTH MOVING
Section 311000 SITE CLEARING

11. APPENDICES:
1.1. RISK ASSESSMENT

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 17
Page 19ofof
22 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

RISK ASSESSMENT

Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01


Page 18
Page 20ofof
22 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

RISK ASSESSMENT
RA # PROJECT Enabling Works for Logistics Facilities (L3) – Coastal Desert East Region

TASK Form Work, Reinforcement, Concrete Pouring


DATE 03 June 2023 ☒ New ☐ Revised Revision Date

☐ Cold Work ☒ Hot Work ☒ Excavation ☐ Confined Space ☐ Work at Height


1.0 Permit(s) Required:
☐ LOTO Permit ☐ Night Work ☐ Radiography ☒ Lifting Permit ☐ Road Closure Permit
☒ Hard Hat ☒ Fluorescent Reflective Vest ☐ Rain Suit ☐ Cut resistant gloves
☒ Clear Safety Glasses ☒ Dust Mask ☐ Disposable Coverall ☐ Leather Gloves
☒ Dark Safety Glasses ☐ Cartridge Respirator Mask ☐ Fire resistant coverall ☐ Rubber Gloves
2.0 PPE Required: ☒ Coverall ☐ Air supplied respirator ☐ Chemical Goggles ☐ Nitrile gloves
☒ Cotton Gloves ☐ SCBA ☐ Cutting Goggles ☐ Elect Insulated gloves
☒ Safety Shoes ☒ Ear Plugs ☐ Face Shield ☐ Welding Aprons
☐ Dielectric footwear ☐ Earmuffs ☐ Welding Hood ☒ Welding Leggings
Special Tools and ☐ Gas Badge ☒ Anemometer ☐ Lifeline ☒ Fire Extinguisher
3.0 Equipment ☐ Dosimeter ☐ Lux Meter ☐ Retrieval Line ☐ Ventilation Fans
Required:
☐ Multi-Gas Monitor ☒ Noise Meter ☒ Full body Harness ☐ Lighting
Foreman / Supervisors to secure work permit before commencing activity and conduct brief safety talk
(E.g. toolbox meeting, topics shall include heat stress awareness).
Additional Wear mandatory PPE’s (hard hats, safety glass, coverall, safety shoes, visibility vest)
4.0
Instructions Ensure availability of sufficient hydration and rest shade area.
Maintain adequate supervision.
Dangerous occurrence, near miss and other related incident shall be reported accordingly.

Document No. 10-600000-4200000031-SAM-MEC-MST-000001


10-600000-4200000031-SAM-CIV-MST-000002 – Rev. 01
Page 21
22 of 34
35
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

RISK ASSESSMENT
Basic Risk Calculation
Fire Risk Rating = Likelihood (L) X Severity (S)

5 5 10 15 20 25 R Unacceptable risk, Plan out or add additional controls

4 4 8 12 16 20 O Acceptable only if no other method viable and with high level control in place
Severity

3 3 6 9 12 15 Y Acceptable with suitable control measures

2 2 4 6 8 10 G Acceptable, no further action required

1 1 2 3 4 5

1 2 3 4 5

Likelihood

Calculation of Risk
A method is shown below for calculating the Risk, given the estimate Likelihood of occurrence (L), Severity (S).
Risk Level (RL) = Likelihood (L) X Severity (S)
Where:
a - L = Likelihood of fire occurrence i.e. probability of the event occurring because of the risk is measured on the likelihood of happening. (1, 2, 3, 4, 5)
b - S = The Severity (Outcome) are ranked on a scale from catastrophe to minor interruption. (1, 2, 3, 4, 5)
Residual Risk RR = is the amount of risk associated with an activity remaining after risks have been reduced by control measures.

10-600000-4200000031-SAM-CIV-MST-000002 – Rev. 01
Document No. 10-600000-4200000031-SAM-MEC-MST-000001
23 of 34
Page 22 35
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

RISK ASSESSMENT
SN Activity Potential Hazard L S RL Control Measures RR

1 Secure necessary Working without valid permit may 3 3 9 Secure necessary permit from authorized permit issuer. 2
permit cause harm Comply the requirement listed in the permit prior to start of any work.
2 Pre-task briefing Lack of communication between 3 3 9 Communicate with all workers of all the condition of work permit. 2
and inspection workers may cause harm Conduct Pre-task safety instructions prior to start of any work, ensure
that everyone understand its task.
3 Form work Damaged / Improper hand tools 3 3 9 All hand tools should be inspect daily prior to start the work and 2
preparation/ damaged hand tools shall be replaced or repair.
Fabrication Use of right tools for the appropriate job.
Exposed protruding nails during 3 3 9 Exposed nails shall be removed or bended. 4
dismantling of formwork. All un-nailed timber/plywood must be stacked in de-nailing area.
All workers shall wear gloves.
Slips, trips and falls due to uneven 3 4 12 Proper housekeeping should be kept. 4
surface and bad housekeeping Access free from obstructions.
Access marked properly and all areas barricaded.
Proper material arrangement shall be maintained.
Sharp edges, pinch points and 3 3 9 Use leather hand gloves. 2
damaged tools may result in Hand cut Use only the right tools for the job.
injury
Remove all damaged tools.
Inspect and color code all tools.

Fall of personnel and material from 3 5 15 Competent and experienced workers shall be deployed and personnel 4
height may cause serious injury working at height shall wear full body harness with shock absorber
type double lanyard.
100% tie-off policy implementation shall be followed.
Anchorage point must be provided with minimum capacity 5000 LBS.

Document No. 10-600000-4200000031-SAM-MEC-MST-000001


10-600000-4200000031-SAM-CIV-MST-000002 – Rev. 01
Page 23
24 of 34
35
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping
RISK ASSESSMENT
SN Activity Potential Hazard L S RL Control Measures RR
Inspected and certified scaffold and access ladder shall be erected and
working platform shall be provided with adequate top, mid rail and toe
board to be installed.
Scaffold Tag System to be followed and maintained.
All personnel working at height must use tool lanyard to secure their
tools to prevent fall from height.
All personnel involved in the crew shall be properly trained for working
at heights.
Proper access and egress or to be maintained at all times.
Area shall be barricaded with relevant warning signs to prevent
unauthorized entry.
Avoiding overlapping jobs and/or position in the line of fire of
accidental fall of materials.
All works in elevated area shall be stopped if the wind speed exceeds
32 km per hour.
Canvas tool bags used for tools transfer.
No alternation/modification of working platform/Scaffolds unless by
competent scaffolders and under the supervision of certified
supervisor.
4 Formworks Back injury due to Manual handling 3 4 12 All work force to be trained for manual handling. 4
Installation. (by Works should be carried out under competent supervision.
hand)
Feet and hand injury due to Exposed 3 3 9 Exposed nails shall be removed or bended. 4
protruding nail All un-nailed timber/plywood must be stacked in de-nailing area.
All workers shall wear gloves.
Document No. 10-600000-4200000031-SAM-MEC-MST-000001 – Rev. 01
Page 24 of 34
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping
RISK ASSESSMENT
SN Activity Potential Hazard L S RL Control Measures RR

Slips, trips and falls due to uneven 3 4 12 Proper housekeeping should be kept. 4
surface and bad housekeeping Access free from obstructions.
Access marked properly and all areas barricaded.
Proper material arrangement shall be maintained.
Sharp edges, pinch points and 3 3 9 Use leather hand gloves. 2
damaged tools may result in Hand cut Use only the right tools for the job.
injury
Remove all damaged tools.
Inspect and color code all tools.
5 Steel bar bending, Equipment failure, cut and injury due 3 4 12 Equipment and power tools shall be inspected by competent person 4
fixing / to splashing of metal parts and color-coded.
reinforcement Equipment shall be fitted with appropriate machine guard to protect
from moving parts.
Experienced and competent workers shall be deployed with adequate
and appropriate tools.
Store the steel in segregation at the designated places with proper
barricading and signage.
Back injury due to Manual handling 3 4 12 All the persons involved in manual handling shall be trained. 4
Supervisor will assess the weight, center of gravity etc. and determine
the number of persons required to carry out safely.
Use of appropriate hand gloves by personnel engaged in material
handling in addition to other PPE.
Slips, trips and falls due to uneven 3 4 12 Rebar off-cuts, tie wires etc. shall be removed in order to alleviate 4
surface and bad housekeeping slip, trip and falls.
Prevent noninvolved employees from entering the area.
No loose material shall be kept in elevated work areas and all tools
and materials shall be secured and stored properly.
Document No. 10-600000-4200000031-SAM-MEC-MST-000001
10-600000-4200000031-SAM-CIV-MST-000002 – Rev. 01
Page 25
26 of 34
35
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping
RISK ASSESSMENT
SN Activity Potential Hazard L S RL Control Measures RR

Body punctured due to Exposed 3 4 12 Rebar caps / Wooden block shall be installed or bend the exposed 4
vertical rebar. protruding vertical rebar.

Fall of personnel and material from 3 5 15 Competent and experienced workers shall be deployed and personnel 4
height may cause serious injury working at height shall wear full body harness with shock absorber
type double lanyard.
100% tie-off policy implementation shall be followed.
Anchorage point must be provided with minimum capacity 5000 LBS.
Inspected and certified scaffold and access ladder shall be erected and
working platform shall be provided with adequate top, mid rail and toe
board to be installed.
Scaffold Tag System to be followed and maintained.
All personnel working at height must use tool lanyard to secure their
tools to prevent fall from height.
All personnel involved in the crew shall be properly trained for working
at heights.
Proper access and egress or to be maintained at all times.
Area shall be barricaded with relevant warning signs to prevent
unauthorized entry.
Avoiding overlapping jobs and/or position in the line of fire of
accidental fall of materials.
All works in elevated area shall be stopped if the wind speed exceeds
32 km per hour.
Canvas tool bags used for tools transfer.

Document No. 10-600000-4200000031-SAM-MEC-MST-000001


10-600000-4200000031-SAM-CIV-MST-000002 – Rev. 01
Page 26
27 of 34
35
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping
RISK ASSESSMENT
SN Activity Potential Hazard L S RL Control Measures RR
No alternation/modification of working platform/Scaffolds unless by
competent scaffolders and under the supervision of certified
supervisor.
6 Clean the reinforced Bodily Injury due to air stream 3 4 12 Do not direct air stream to the body. 4
steel using air Compressor air shall not be used to clean dirt and dust on clothes
compressor
Use eye protection.
Do not touch moving parts.
Keep all guards or covers in place or do not use if guards or covers are
broken.
Barricade the area and restrict unauthorized entry.
Nozzle and valve shall be provided to the other end of the hose.
Risk of Bursting and Equipment / 3 4 12 Ensure that the daily checklist is in place and filled properly. 4
Hoses damage Ensure that all part of the equipment are in good working condition,
no diesel or oil leakage is observed.
Do not operate without proper safety valve in place.
Do not adjust a regulator to result in output pressure greater than
marked maximum pressure.
Whip checks shall be provided for all hose’s connections.
Only use tools or attachments rated at 200 PSI or higher.
Do not weld on or repair the air tank.
Replace damaged tank immediately.
Drip tray shall and checklist shall be provided.
Electrical Shock due to damage 3 4 12 Do not expose to rain. 4
equipment or unauthorized repair Use properly grounded electrical connections.
Do not use grounding adaptors.

Document No. 10-600000-4200000031-SAM-MEC-MST-000001


10-600000-4200000031-SAM-CIV-MST-000002 – Rev. 01
Page 27
28 of 34
35
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

RISK ASSESSMENT
SN Activity Potential Hazard L S RL Control Measures RR

Inhalation of Dust from the air stream 4 3 12 Provide Dust Mask for all workers during this activity. 4
Reduce the exposure of the employees as much as practicable.
Exposure to high level Noise 4 3 12 All workers in the vicinity and affected by the high noise level shall 2
have proper hearing protection.
Chemical spills (oil, diesel) to ground 3 3 9 Ensure that the Air Compressor is inspected and free from leaks and 3
from the Air Compressor in good condition prior starting work.
Remove Air Compressor leaking or showing any damage in the hoses,
pipes or tanks (oil, diesel) immediately from site.
Spill kit available and used by trained personnel when spills are
identified.
All contaminated material found among the excavated soil shall be
removed, assessed and stored as Hazardous waste or non-hazardous
waste in the designated areas for disposal.
Emissions of black smoke from Air 2 3 6 Ensure that the Air Compressor is inspected not emitting any black 2
Compressor smoke and in good condition prior starting work.
Air Compressor emitting black smoke shall be stopped and
checked/repaired before continue to use or removed from site if not
repairable.
7 Concreting Injury to personnel / Equipment failure 3 3 9 All works shall be carried out under competent supervision. 2
Concrete Pouring Proper work plat forms or scaffolding shall be erected for safe pouring
using transit mixer when required.
and Concrete Pump.
Proper barricades and warning sign shall be installed and maintained.
All equipment shall be operated by experienced persons and proper
guards shall be provided.
Concreting shall not be done when adverse weather condition prevails.
Dust inhalation / Eye irritation due to 3 4 12 Ensure all personnel engaged in concrete pouring are using dust mask. 2
cement Ensure that all personnel are using eye protection.

Document No. 10-600000-4200000031-SAM-MEC-MST-000001


10-600000-4200000031-SAM-CIV-MST-000002 – Rev. 01
Page 28
29 of 34
35
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping
RISK ASSESSMENT
SN Activity Potential Hazard L S RL Control Measures RR

The workers involved directly with concrete pouring shall wear full-
face shield.
Exposure to vibration by the concrete 3 3 9 Workers shall be rotated suitably to avoid prolonged exposure to 2
vibrator vibration.
Caught-in, by or between moving 3 5 15 Concrete pump and transit mixers shall be equipped with reverse 4
heavy equipment. alarm and inspected prior to entry.
Spotter and Flagman must be placed to control traffic / equipment
movement.
Competent concrete pump operator shall be used.
Burns and skin irritation due to 3 4 12 Disposable coverall shall be wear by all workers exposed to concrete. 2
concrete Rubber gloves shall be wear by workers.
Rubber boots shall be wear by workers involved directly in concrete
pouring activity.
Any burn / injury shall be treated by the nurse provided full time at
site.
MSDS shall be available at site and in the clinic to be used in case of
emergency.
Eyewash shall be available at site to be used in case of emergency.
Collapse or settlement of pump due to 3 4 12 Sole plates are provided for placement below outrigger feet to support 2
ground conditions/ inadequate ground the pumps outriggers/ reduce surface damage these are designed for
bearing use on firm, level standing
The Machines Maximum possible loading is displayed on its outriggers
Provide sufficient extra support (timbers, steel sheets, etc.) as required
It is the responsibility of the engineer to ensure ground conditions at
set-up position are adequate for the imposed load of pump

Document No. 10-600000-4200000031-SAM-MEC-MST-000001


10-600000-4200000031-SAM-CIV-MST-000002 – Rev. 01
Page 29
30 of 34
35
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

RISK ASSESSMENT
SN Activity Potential Hazard L S RL Control Measures RR

overturning of pump/ collapse of boom 3 3 9 The concrete pump operator shall ensure that outriggers are extended 2
due to insufficient stability to the appropriate position
Ensure adequate space is available for the pump, and for the full
deployment of its outriggers

structural failure of pump/ boom 3 3 9 All pumps are inspected and certified by an approved third party. 2
All Pumps shall be inspected by Nesma HSE and have a valid color-code
sticker.

collapse of placing boom due to failure 3 4 12 All hydraulic rams are fitted with lock valves to limit movement should 4
of hydraulics failure occur

vehicle movements (reversing) - 3 4 12 All mobile concrete pumps are fitted with a backup alarm, which is 4
crushing or trapping of persons when activated when reverse gear is selected.
moving pump to work position on site
Mobile concrete pumps are fitted with appropriate mirrors.
Flagman to be provided for reversing concrete pump for assistance.
Where possible, the concrete pump operator will assist the flagman to
direct the mixer truck during the reversing maneuver onto the
concrete pump.
Limit access for persons to area of vehicle movement.

crush or impact by boom, or struck by 3 5 15 Every pump is provided with a remote-control unit (RCU) allowing the 4
placing hose, during initial or operator to operate the pump/ boom from a position of safety/
subsequent positioning, or during ‘off improved visibility.
the boom’ placement of concrete
The operator shall visually monitor the unfolding/ folding, and
positioning of the boom, and ensure no person is placed at risk by any
movements
The operator shall ensure that during movement to position, the
placing hose is not allowed to swing in the vicinity of any person
Document No. 10-600000-4200000031-SAM-MEC-MST-000001
10-600000-4200000031-SAM-CIV-MST-000002 – Rev. 01
Page 30
31 of 34
35
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

RISK ASSESSMENT
SN Activity Potential Hazard L S RL Control Measures RR
Provide sufficient set-up space, and height for unfolding/ folding/
moving the boom
Ensure persons remain clear during boom and hose movements
Operator controlling the position of the placing hose should hold it at
arm’s length.
Person(s) shall be nominated to converse with and signal the operator,
for minor boom positioning during concrete placement if the operator
cannot see the area.
Ensure adequate illumination and visibility is available where the boom
has to be unfolded/ folded/ moved during the hours of darkness or in
low light environments

contact with moving pump 4 4 16 All moving components upon the concrete pump are fully guarded 4
components either by virtue of its manufacture, by mechanical guard, or by
automatic interlock systems.
Do not allow workers to come close to the pump when in operation.

injury to persons in vicinity of pumping 3 3 9 The operator shall follow the site HSE rules as advised during induction. 2
operation
Demarcate area of pump operation.
Limit access to persons, especially below boom, or in vicinity of
pipeline or placing hose.
Appropriate PPE shall be work by all workers at all times.

Potential blockages at start or restart 3 4 12 The operator shall request that all persons shall remain clear of the 4
of the pump – use of suspended hose suspended hose at each start or restart of the pump.
‘off the boom’.
Persons shall only be permitted to approach the suspended hose once
‘smooth flow’ has been achieved

Document No. 10-600000-4200000031-SAM-MEC-MST-000001


10-600000-4200000031-SAM-CIV-MST-000002 – Rev. 01
Page 31
32 of 34
35
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

RISK ASSESSMENT
SN Activity Potential Hazard L S RL Control Measures RR
Ensure ALL persons shall remain at a safe distance (at least twice the
length of the suspended delivery hose) of the hose at EVERY start or
restart of the pump.

Bursting of pipelines/ hoses under 3 4 12 Only pipes, hoses, clips, of sufficient safety rating shall be used. 2
pressure
Wear and damage shall be monitored by the operator, and checked
during scheduled services.
Excessively damaged/ worn components shall be changed
immediately, or the pump shall be put Idle.
Concrete leaking to the ground or
4 3 12 Polyethylene sheet shall be provided to avoid the leak of concrete to 3
Inappropriate wash out facility
the ground.
The operator shall only wash out in areas available in the batch plant
for such purpose.
Batch plant management shall provide adequate wash out facilities for
concrete residues, etc.

Chemical spills (oil, diesel) to ground 3 3 9 Ensure that the Concrete pump and trucks are inspected and free 3
from the Concrete pump and trucks from leaks and in good condition prior starting work.
Remove Concrete pump and trucks leaking or showing any damage in
the hoses, pipes or tanks (oil, diesel) immediately from site.
Spill kit available and used to contain/absorb fuel/oil spillage by
trained personnel when spills are identified.
All contaminated material found among the excavated soil shall be
removed, assessed and stored as Hazardous waste or non-hazardous
waste in the designated areas for disposal.
Emissions of black smoke from the 2 3 6 Ensure that the Concrete pump and trucks are inspected not emitting 2
Concrete pump and trucks any black smoke and in good condition prior starting work.

Document No. 10-600000-4200000031-SAM-MEC-MST-000001


10-600000-4200000031-SAM-CIV-MST-000002 – Rev. 01
Page 32
33 of 34
35
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

RISK ASSESSMENT
SN Activity Potential Hazard L S RL Control Measures RR
Concrete pump and trucks emitting black smoke shall be stopped and
checked/repaired before continue to use or removed from site if not
repairable.
8 Formworks removal Back injury due Manual handling 3 3 9 All work force to be trained for manual handling. 2
by hand Works should be carried out under competent supervision.
Use of all required PPE
Feet and hand punctured due to 3 4 12 Exposed nails shall be removed or bended. 4
Exposed protruding nail All un-nailed timber or plywood must be stacked in de-nailing area.
All workers shall wear gloves.
Slips, trips and falls due to uneven 3 4 12 Ensure proper access such as ladder for up & down to truck. 4
surface and bad housekeeping Proper housekeeping should be kept.
Access free from obstructions.
Access marked properly and all areas barricaded.
Proper material arrangement shall be maintained.
Sharp edges, pinch points and 3 3 9 Use leather hand gloves. 2
damaged tools may result in Hand cut Use only the right tools for the job.
injury
Remove all damaged tools.
Inspect and color code all tools.
Collapse of concrete and Formwork 3 3 9 Ensure the formwork is not removed until the concrete has been 2
properly cured and ready for removal.
Consent from quality/engineering section.
9 Housekeeping Tripping hazard due excess/unwanted 3 2 6 Keeping waste segregated at all times in accordance with waste 2
materials handling requirements
All trash and job spoils will be picked up and monitored to prevent
slips, trips and falls and to clear walkways.
Excess materials/ garbage shall collect properly at daily basis
Document No. 10-600000-4200000031-SAM-MEC-MST-000001
10-600000-4200000031-SAM-CIV-MST-000002 – Rev. 01
Page 33
34 of 34
35
NEOM - 10 SPINE INFRASTRUCTURE
Contract No. 4200000031
Contract Name SAMA-Site Preparation Framework 3
WO 022 Enabling Works for Logistics Facilities(L3) – Coastal Desert East
Region_Method Statement for Installation and Testing of
Reinforcement Pipes of Storm Water Piping

RISK ASSESSMENT
Prepared By Reviewed By Approved By
Name Atiq Ullah Atiq Ullah Iqbal Imam
Position Safety Manager Safety Manager Project Manager
Date 03-06-2023 03-06-2023 03-06-2023

Signature

Document No. 10-600000-4200000031-SAM-MEC-MST-000001


10-600000-4200000031-SAM-CIV-MST-000002 – Rev. 01
Page 34
35 of 34
35

You might also like