PROJECT DURATION & MASTER SCHEDULE

PT. TRIGUNA INTERNUSA PRATAMA


JASA SEWA GAS PROCESSING FACILITY KAPASITAS 45 MMSCFD - LHOKSUKON, ACEH
NO. TENDER : 5188-369-PGE
ID WBS Task Name Duration M12 M13 M14 M15
W49 W50 W51 W52 W53 W54 W55 W56 W57 W58 W59 W60 W61 W62
1 1 PROJECT MASTER SCHEDULE 420 days
2 1.1 CONTRACT AWARD 0 days
3 1.2 PREPARATION FACILITIES 30 days
4 1.3 DETAIL ENGINEERING DESIGN 105 days
1210 1.4 PROCUREMENT 280 days
2512 1.5 CONSTRUCTION 249 days
2708 1.6 INSTALLATION 244 days
2861 1.7 COMMISSIONING 127 days
2862 1.7.1 MDR (incld. As Built Drawing) 60 days
2863 1.7.2 Start-Up & Commissioning 62 days
2864 1.7.2.1 Electrical System 13 days
2865 1.7.2.1.1 Grounding 2 days
2866 1.7.2.1.2 Emergency Diesel Generator 1 day
2867 1.7.2.1.3 Power Transformers 1 day
2868 1.7.2.1.4 MV Switchgear 1 day
2869 1.7.2.1.5 LV Switchgear and MCC 2 days
2870 1.7.2.1.6 Variable Frequency Drive (VFD) 1 day
2871 1.7.2.1.7 Lighting & Small Power Panel 3 days
2872 1.7.2.1.8 UPS System 2 days
2873 1.7.2.1.9 Cathodic Protection 1 day
2874 1.7.2.2 Instrument Control System 13 days
2875 1.7.2.2.1 Integrated Control and Safety System3(ICSS)
days
2876 1.7.2.2.2 Field Instrument 7 days
2877 1.7.2.2.3 Metering System 2 days
2878 1.7.2.2.4 Electrical Power System Interface 3 days
2879 1.7.2.2.5 Telecommunication System 2 days
2880 1.7.2.2.5.1 CCTV System 1 day
2881 1.7.2.2.5.2 GA System 1 day
2882 1.7.2.3 Utilities 7 days
2883 1.7.2.3.1 Fire Water System 2 days
2884 1.7.2.3.2 Instrument Air And Utility Air System1 day
2885 1.7.2.3.3 Nitrogen Generation 1 day
2886 1.7.2.3.4 Water Treatment Package 1 day
2887 1.7.2.3.5 Open Drain And Waste Water Treatment 1 day
2888 1.7.2.3.6 Closed Drain System 1 day
2889 1.7.2.4 Gas Processing 29 days

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Project Duration & Mas
Milestone Inactive Summary Start-only Critical
Date: 17 April 2023
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

ISSUED FOR TENDER Page 1 of 2